GUIDANCE ON CERTIFICATION “Technical Integrity Management” Western Hemisphere Edition Revision 1 à Guidance On Certification http://houston.bpweb.bp.com/gocmancon/ GOC © BP Exploration 1989 - 2001 All Rights Reserved COMMISSIONING MANAGEMENT PROCESS GUIDANCE ON CERTIFICATION SECTIONS 1 TO 10 This guidance document has been requested by BP Assets to provide a collective Asset statement of shared good practice on the minimum acceptable level of documentation required to demonstrate that Technical Integrity has been acceptably achieved, and/or reinstated following the completion of project and/or maintenance activities. The document has been assembled by seeking the collective knowledge and experience of BP Engineers having responsibility for Technical Integrity. The compilation of this Asset knowledge has been compiled, organised and managed by Upstream Technology Group (UTG) and any revision to this document should, in the first © © instance, be directed to Mike Matula, GOC /MANCON Co-ordinator, Operations Excellence & Operations Integrity. John P. Platt Commissioning Management Process System Custodian Project Leader, Commissioning (Houston) Upstream Technology Group (UTG) [email protected] +1 281-366-3002 John M. Johnson Team Leader Operations Excellence (Houston) Upstream Technology Group (UTG) [email protected] +1 281-366-2799 GOC© & MANCON© Services Western Hemisphere Edition Mike Matula (Houston) System Development Co-ordinator [email protected] +1 281-366-2298 For more Information, visit the BP Intranet Site @ http://houston.bpweb.bp.com/gocmancon Issue Date: Rev 1 May 2001 GOC© BP Exploration 1989 - 2001 All Rights Reserved Western Hemisphere REV. 1 UPSTREAM TECHNOLOGY BP America Inc. DISTRIBUTION GUIDANCE ON CERTIFICATION Copy 1.1 Copy 1.2 Copy 1.3 Copy 1.4 J. P. Platt - Commissioning Management Process (Custodian Consultant) M. K. Matula - Commissioning Management Co-ordinator (Houston) J. R. Douglas - Commissioning Management Co-ordinator (Aberdeen) Alan Dean - GOC Consultant (Aberdeen) SUPPORT / SERVICE GROUPS ASSETS ASSET PARTNERS TO BE FINALIZED GOC© BP Exploration 1989 - 2001 All Rights Reserved Americas REV. 1 GUIDANCE ON CERTIFICATION GOC © AMERICAS EDITION SUBJECT: CONTENTS - SECTIONS 1 to SECTION 10 CONTENTS REVISION: 1 PAGE: i CONTENTS SECTION DESCRIPTION 1.0 SYSTEM PRINCIPLES 1 1.1 INTRODUCTION 3 1.2 SYSTEM OVERVIEW 5 1.2.1 Purpose 1.2.2 Objective 1.2.3 Execution 5 5 6 1.2.4 Certification Management Database 6 1.2.5 Definitions 7 1.3 1.4 PAGE FUNCTIONAL SYSTEMIZATION 1.3.1 General 1.3.2 Scope 1.3.3 Philosophy 8 8 8 1.3.4 System Schematics 1.3.5 Generic Examples 1.3.6 Specific Examples 1.3.7 Isolations 1.3.8 Controls and Cables 10 16 17 25 26 SYSTEM MECHANICS 1.4.1 Limits of System Handover 1.4.2 Data Input Sheets 1.4.3 Inspection and Test Plan 1.4.4 Handover Certification Packs (HCP) 1.4.5 System Safe Certificate (SS1) 1.4.6 Mechanical Completion Certificate (MC1) 1.4.7 System Handover Certificate (SH1) 1.4.8 Plant Performance Certificate (PP1) 1.4.9 Punch List (PL1) 33 33 34 35 35 36 37 38 40 41 GOC© BP Exploration 1989 – 2001 All Rights Reserved GUIDANCE ON CERTIFICATION GOC © AMERICAS EDITION SUBJECT: CONTENTS - SECTIONS 1 to SECTION 10 CONTENTS REVISION: 1 PAGE: ii CONTENTS (cont.) SECTION DESCRIPTION 1.0 1.5 1.6 1.7 PAGE KEY PERSONNEL 43 1.5.1 Nomination of Authorities 43 1.5.2 Design/Maintenance Planning Authority 43 1.5.3 Construction/Maintenance Authority 1.5.4 Commissioning Authority 44 44 1.5.5 Certification Administrator 1.5.6 Handover Management 1.5.7 Operating Authority 44 44 45 CHANGE CONTROL 1.6.1 Requirement for Change 45 45 1.6.2 Handover Change Request 45 1.6.3 MANCON Change 46 SYSTEM FLOW 47 1.7.1 Sequence of Events 1.7.2 Flowcharts 1.7.3 Handover Sequence of Events (Off-Site) 47 50 51 1.7.4. Handover Sequence of Events (On-Site) 1.7.5 Handover Change Request (HCR) 52 53 EXHIBIT 1 1. List of Standard Forms GOC© BP Exploration 1989 – 2001 All Rights Reserved 54 GUIDANCE ON CERTIFICATION GOC © AMERICAS EDITION SUBJECT: CONTENTS - SECTIONS 1 to SECTION 10 CONTENTS REVISION: 1 PAGE: iii CONTENTS (cont.) PAGE APPENDIX 1 1.0 Examples of an Operations System Mnemonics Matrices i 1.1 Examples of System Limits. ii 1.2 GOC "Carrier" Certificate Example iii Technical Integrity Assurance Flowcharts Functional Certification Flowchart 1.3 Example Basis of Design Contents iv 1.4 Asset Nomination of Authorities v 1.5 Glossary of Terms iv GOC© BP Exploration 1989 – 2001 All Rights Reserved GUIDANCE ON CERTIFICATION GOC © AMERICAS EDITION SUBJECT: CONTENTS - SECTIONS 1 to SECTION 10 CONTENTS REVISION: 1 PAGE: iv CONTENTS (cont.) SECTION DESCRIPTION 2.0 WELDING AND NDE 1 2.1 ACTIONS 2 2.1.1 General 2 2.1.2 Welders Qualifications 2.1.3 Prior Qualifications 3 3 2.1.4 NDE Qualiications 3 WELD INSPECTION 2.2.1. General 2.2.2 Use of Forms 4 4 8 2.2 PAGE FLOWCHART 2 1. Welding Flowchart 13 List Of Standard Forms 14 EXHIBIT 2 1. GOC© BP Exploration 1989 – 2001 All Rights Reserved GUIDANCE ON CERTIFICATION GOC © AMERICAS EDITION SUBJECT: CONTENTS - SECTIONS 1 to SECTION 10 CONTENTS REVISION: 1 PAGE: v CONTENTS (cont.) SECTION DESCRIPTION PAGE 3.0 PIPE TESTING 1 3.1 ACTIONS 3.1.1 General 2 2 3.1.2 Use of Forms 3 3.1.3 Calibration 8 INSTALLATION 10 Pressure Test Procedure 3.1 3.1.1 - Joint Integrity Installation 11 11 3.1.2 - Piping Pre-test Inspection 3.1.3 - Hydrotest Cleaning & Flushing 3.1.4 - Hydrostatic Testing 15 19 21 3.1.5 - Pneumatic Testing 3.1.6 - Piping Completion 3.1.7 - Fire & Gas Piping Completion 25 27 30 3.1.8 - Certification 31 OPERABILITY 32 Leak Test Procedure 3.2 3.2.1 - System Flushing Procedure 3.2.2 - Leak Test Procedure 3.2.3 - Critical Joint Installation 3.2.4 - Service Test Procedure 32 32 34 40 41 3.2.5 - Certification 43 PROCEDURES FLOWCHART 3 1. Pipe Testing Certification Flowchart 44 EXHIBIT 3 1. List of Standard Forms GOC© BP Exploration 1989 – 2001 All Rights Reserved 45 GUIDANCE ON CERTIFICATION GOC © AMERICAS EDITION SUBJECT: CONTENTS - SECTIONS 1 to SECTION 10 CONTENTS REVISION: 1 PAGE: vi CONTENTS (cont.) SECTION DESCRIPTION 4.0 MECHANICAL EQUIPMENT 1 4.1 ACTIONS 4.1.1 General 4.1.2 Pumps and Compressors 4.1.3 Skid Mounted Units 4.1.4 Vessels and Tanks 4.1.5 Mechanical Handling 4.1.6 Use of Forms 2 2 2 2 3 3 7 INSTALLATION & OPERABILITY 9 Machinery 4.1 - Pump/Compressor/Skid Mounted Unit Inst. 4.2 - Machinery Alignment 10 13 PROCEDURES PAGE Vessels 4.3 - General Requirements & Pressure Safety Relief Devices 17 4.4 - Vessel & Tanks Fabricated (Off-Site) 4.5 - Vessel & Tanks Modified (On-Site) 24 26 Mechanical Handling 4.6 - Cranes 4.7 - Hoists, Trolleys and Gantries 4.8 - Trolley Beams and Pad Eyes 4.9 - Lifeboat Davits and Lifeboat 28 31 33 36 FLOWCHARTS 4 1. Certification Flowchart 1 - Mechanical Equipment 2. Certification Flowchart 2 - Vessels And Tanks 3. Certification Flowchart 3 - Mechanical Handling 39 40 41 EXHIBIT 4 1. List of Standard Forms GOC© 42 BP Exploration 1989 – 2001 All Rights Reserved GUIDANCE ON CERTIFICATION GOC © AMERICAS EDITION SUBJECT: CONTENTS - SECTIONS 1 to SECTION 10 CONTENTS REVISION: 1 PAGE: vii CONTENTS (cont.) SECTION DESCRIPTION PAGE 5.0 STRUCTURAL 1 5.1 ACTIONS 5.1.1 General 5.1.2 Installation 5.1.3 Use of Forms 2 2 3 3 Structural Certification Flowchart 5 List Of Standard Forms 6 FLOWCHART 5 1. EXHIBIT 5 1. GOC© BP Exploration 1989 – 2001 All Rights Reserved GUIDANCE ON CERTIFICATION GOC © AMERICAS EDITION SUBJECT: CONTENTS - SECTIONS 1 to SECTION 10 CONTENTS REVISION: 1 PAGE: viii CONTENTS (cont.) SECTION DESCRIPTION 6.0 HVAC 6.1 PROCEDURES PAGE 1 ACTIONS 6.1.1 General 6.1.2 Installation 6.1.3 Use of Forms 6.1.4 Calibration 2 2 2 3 7 INSTALLATION & OPERABILITY 8 6.1 - General Requirements 6.2 - Dampers 6.3 - Filtration 6.4 - Heating and Cooling Coils 6.5 - Centrifugal Fans and Drivers 6.6 - Humidifiers 6.7 - Terminal Unit, Grills & Diffusers 6.8 - Air Conditioning Units 6.9 - Air Handling Unit 6.10 - Ductwork 6.11 - Sound Attenuators 6.12 - Cooling Towers 6.13 - Areas Receiving HVAC Supply 9 11 14 16 18 21 23 25 27 29 32 34 36 FLOWCHART 6 1. HVAC Certification Flowchart 38 List Of Standard Forms 39 EXHIBIT 6 1. GOC© BP Exploration 1989 – 2001 All Rights Reserved GUIDANCE ON CERTIFICATION GOC © AMERICAS EDITION SUBJECT: CONTENTS - SECTIONS 1 to SECTION 10 CONTENTS REVISION: 1 PAGE: ix CONTENTS (cont.) SECTION DESCRIPTION PAGE 7.0 ARCHITECTURAL SERVICES 1 7.1 ACTIONS 7.1.1 General 7.1.2 Use of Forms 2 2 2 Architectural Services Flowchart 4 List of Standard Forms 5 FLOWCHART 7 1. EXHIBIT 7 1. GOC© BP Exploration 1989 – 2001 All Rights Reserved GUIDANCE ON CERTIFICATION GOC © AMERICAS EDITION SUBJECT: CONTENTS - SECTIONS 1 to SECTION 10 CONTENTS REVISION: 1 PAGE: x CONTENTS (cont.) SECTION DESCRIPTION 8.0 CONTROL 1 8.1 ACTIONS 8.1.1 General 8.1.2 Use of Forms 2 2 4 INSTALLATION & OPERABILITY 7 8.1 - Impulse line Pressure Testing 8 8.2 - Control Cable & Fiber Optic Cable Testing 12 8.3 - General/Calibration/Installation and Cold Loop Checking 17 8.4 - Powered Up Loop and Function Testing 30 8.5 - System Control (Function) Testing 36 8.6 - System Performance "HIPS" (High Integrity Performance System) Tests 37 PROCEDURES PAGE 8.7 - Programmable Logic Controller Panels (PLCP) 41 FLOWCHART 8 1. Control Certification Flowchart 45 List of Standard Forms 46 EXHIBIT 8 1. GOC© BP Exploration 1989 – 2001 All Rights Reserved GUIDANCE ON CERTIFICATION GOC © AMERICAS EDITION SUBJECT: CONTENTS - SECTIONS 1 to SECTION 10 CONTENTS REVISION: 1 PAGE: xi CONTENTS (cont.) SECTION DESCRIPTION 9.0 ELECTRICAL 1 9.1 2 2 3 4 7 8 9 PROCEDURES ACTIONS 9.1.1 General 9.1.2 Installation 9.1.3 Pre-Acceptance Procedure 9.1.4 Energization and Commissioning 9.1.5 Permit to Work Procedures 9.1.6 Safety Precautions INSTALLATION & OPERABILITY PAGE 10 9.1 - Power and Control Cables and Instrument Cables 11 9.2 - Switch Gear, Motor Control Centers and Metal Enclosed Bus Duct 23 9.3 - Circuit Breakers - Air, Molded Case and Oil Immersed 32 9.4 - Contactor Starters and Variable Frequency Drives 42 9.5 - Medium Voltage Air Switches 48 9.6 - Power Transformers; Oil Filled and Dry Type 51 9.7 - Motors 62 9.8 - Batteries and Battery Chargers 69 9.9 - U.P.S. 76 9.10 - Lighting and Small Power Distribution System 78 9.11 - Navigation Aids (Nav-aids) 84 9.12 - Neutral Grounding Resistors 87 9.13 - Heat Trace Cables and Circuits 90 9.14 - Grounding/Bonding 95 9.15 - Equipment for use in Hazardous Locations 97 9.16 - Oil Insulation Tests 102 9.17 - Drying of Electrical Rotating Machinery 103 9.18 - Instrument Transformer Verifications 106 9.19 - Junction Box Inspection 109 9.20 - Protective Relay Testing and Metering Circuits 111 9.21 - A.C. Generators 113 FLOWCHART 9 1. Electrical Certification Flowchart 120 List of Standard Forms 121 EXHIBIT 9 1. GOC© BP Exploration 1989 – 2001 All Rights Reserved GUIDANCE ON CERTIFICATION GOC © AMERICAS EDITION SUBJECT: CONTENTS - SECTIONS 1 to SECTION 10 CONTENTS REVISION: 1 PAGE: xii CONTENTS (cont.) SECTION DESCRIPTION 10.0 Civil Construction 1 10.1 2 2 ACTIONS 10.1.1 General PAGE 10.2 Civil Work 10.2.1 Scope 10.2.2 General 10.2.3 Soils and Earthwork 10.2.4 Piling Operations 10.2.5 Concrete 3 3 3 5 5 5 10.3 Steel Construction 10.3.1 General 7 7 10.4 Piping 10.4.1 General 7 7 10.5 Use of Forms 8 10.6 Buildings, Fittings and Furnishings (Architectural) 10.6.1 General 10.6.2 Inspection Requirements 10.6.3 Surface Finishes 10.6.4 Windows and Doors 10.6.5 Fittings 10.6.6 Safety Items 10.6.7 Soft Furnishings 10.6.8 Buildings, Fittings and Furnishings Certificate (Architectural) 11 11 12 12 13 13 14 15 15 FLOWCHART 10 1. Civil Construction Certification Flowchart 16 Civil Buildings Certification Flowchart 17 List of Standard Forms 18 FLOWCHART 11 1. EXHIBIT 10 1. GOC© BP Exploration 1989 – 2001 All Rights Reserved SUBJECT: GUIDANCE ON CERTIFICATION SECTION 1.0 GOC © AMERICAS EDITION REVISION: 1 SYSTEM PRINCIPLES SECTION 1.0 SYSTEM PRINCIPLES GOC© BP Exploration 1989 - 2001 All Rights Reserved PAGE: 1 SUBJECT: GUIDANCE ON CERTIFICATION SECTION 1.0 GOC© AMERICAS EDITION REVISION: 1 SYSTEM PRINCIPLES PAGE: 2 REVISION RECORD NOTE: Revisions are denoted in one of two ways: i. By a line in the right hand margin for narrative sections with the revision number on the right. ii. By the symbol 2 with the revision number denoted within. REV. DESCRIPTION OF REVISION Date 0 1 Draft – Milne Point Pilot First Issue March 1998 May 2001 GOC© BP Exploration 1989 - 2001 All Rights Reserved SUBJECT: 1.1 GUIDANCE ON CERTIFICATION SECTION 1.0 GOC© AMERICAS EDITION REVISION: 1 SYSTEM PRINCIPLES PAGE: 3 INTRODUCTION The BP Exploration Guidance On Certification© (GOC©) has been developed and updated, with input from the users, over a considerable period, improving the efficiency of the Certification process by reducing certificates to a minimum level that achieves the demonstrability of Operational Technical Integrity. The GOC© is an integrated process that incorporates commissioning, system turnover procedure and an enhanced documentation procedure. BP has attempted to keep the text to a minimum by use of flow charts/examples where possible, and provide a "user-friendly" document. The Certificates and associated procedures provide the basis for Inspection and Test (I&T) requirements, and can be applied to all new projects, existing operational/maintenance activities and third party fabrication. Use of the principles embodied in the GOC© enables Assets to demonstrably achieve compliance with BP - “Getting HSE Right.” The GOC© has been developed together with an associated computerized certification management database (MANCON©), which provides an electronic means to record, track and manage the I&T activities. It should be noted that Assets can choose the certificates and associated procedures contained in the GOC© without the MANCON© database by substituting their chosen method of recording, tracking and managing I&T activities. In this case, Assets should demonstrate compliance to the above Performance Standards in the manner described in their Safety Case. BP Upstream Technology Group is the custodian of the GOC© and MANCON©. Procedures will be developed to enable individual assets to propose changes and maintain the continuous improvement process that has been embodied in the current form of the GOC©/MANCON©. GOC© BP Exploration 1989 - 2001 All Rights Reserved GUIDANCE ON CERTIFICATION SECTION 1.0 GOC© AMERICAS EDITION REVISION: 1 SUBJECT: SYSTEM PRINCIPLES © The GOC PAGE: 4 is sub-divided to assist easy access to the relevant information. Section 1: System Principles Section 2: Section 3: Welding and NDE Piping Section 4: Mechanical Section 5: Section 6: Structural HVAC Section 7: Architectural Section 8: Control Section 9: Section 10: Electrical Civil Within the individual discipline sections are contained the specific procedures relevant to that discipline, plus the associated certificate proforma's. GOC© BP Exploration 1989 - 2001 All Rights Reserved SUBJECT: GUIDANCE ON CERTIFICATION SECTION 1.0 GOC© AMERICAS EDITION REVISION: 1 PAGE: 5 SYSTEM PRINCIPLES 1.2 SYSTEM OVERVIEW 1.2.1 Purpose The intent of this document is to provide guidance on a management control system for inspection and test (I&T) activities associated with fabrication, construction, pre-commissioning, commissioning and maintenance of systems being worked upon and handed over for operation. Given the different character of individual assets and the correspondingly different management structures in operation, it is intended that this document merely forms the basis from which detailed, step-by-step, individual asset based management procedures would be developed. 1.2.2 Objective To provide a system that, for a given new project, maintenance routine or modification change, fulfills the following: (a) Identification of the limits of the system to be maintained/modified and then handed over for operation. (b) For the identified limits, identifies the minimum inspection and test (I&T) requirements for the given maintenance or modification activity. (c) Identification of I&T authorities. (d) Standard methods of measurement for both the performance of I&T activities and recording of requisite data. (e) Establishes those I&T requirements satisfactorily achieved. (f) Identification of the key personnel involved in the preparation and acceptance of handover documentation, in readiness for the next stage of activities. GOC© BP Exploration 1989 - 2001 All Rights Reserved GUIDANCE ON CERTIFICATION SECTION 1.0 GOC© AMERICAS EDITION REVISION: 1 SUBJECT: (g) SYSTEM PRINCIPLES PAGE: 6 Definition of the mechanisms for handover of the system identified above, from the design/maintenance planning stage, through the principal authorities, and finally to the operational stage. (h) Monitoring of the ongoing status of I&T activities. (i) A recording and tracking mechanism for works outstanding after handover. 1.2.3 Execution The following sections detail the fundamental components of the system: Section 1.3 - explains limit identification philosophy for functional system breaks. Section 1.4 - describes the principal elements employed in the execution of the system. Section 1.5 - details the key personnel (and their roles and responsibilities). Section 1.6 - details the change control procedures to be followed where changes are required to either the original systems limits or associated I&T requirements. Section 1.7 - describes the sequence of events. 1.2.4 Commissioning Certification Management System A number of the certification recording/tracking objectives, can be met by the BP PC-based, Certification Management Database, known as MANCON©. Individual discipline I&T requirements, once identified, can be inputed into the system database and the system enables an I&T plan (per discipline) to be generated. The database is available, for updating as Engineering Queries (EQ’s) are raised, original requirements re-defined, I&T activities are completed, handover(s) and "as-built" requirements are achieved, thereby allowing the status to be continually assessed (as required). GOC© BP Exploration 1989 - 2001 All Rights Reserved SUBJECT: GUIDANCE ON CERTIFICATION SECTION 1.0 GOC© AMERICAS EDITION REVISION: 1 SYSTEM PRINCIPLES PAGE: 7 At the handover stage, outstanding work (punch lists and "as-built" requirements, etc.) can also be recorded. The database may then be accessed for the control, storage and retrieval of I&T records. © This document makes many references to MANCON , a typical certification management system available and in use within BP. This is used as an example only, to illustrate where certification and the control of it, are interlinked. Individual assets may have their own alternative systems, in which case their system name/procedures should replace the word "MANCON©." Detailed operational data for MANCON© is contained within a MANCON© user manual. 1.2.5 Definitions Inspection and Test Summary (ITS): The Inspection and Test Summary is a document that details the minimum Inspection and Test Requirements for specified activities. Delegated Authority: Resource Organization appointed by BP to carry out Engineering and/or Construction activities on their behalf, for example via a Partnering or Alliance Contract. GOC© BP Exploration 1989 - 2001 All Rights Reserved SUBJECT: 1.3 1.3.1 GUIDANCE ON CERTIFICATION SECTION 1.0 GOC© AMERICAS EDITION REVISION: 1 SYSTEM PRINCIPLES PAGE: 8 FUNCTIONAL SYSTEMIZATION General Within the Whole Life Cycle context the maintenance of a consistent and coherent philosophy for functional system limits is fundamentally important. This allows information to be developed, transferred, modified etc. throughout the asset life, since it is based on identifying functional system limits that are relevant during both the project and operational phases. 1.3.2 Scope This section details the philosophy to be applied when defining functional system limits, in order that this may be linked to, and consistent with, the document numbering system and the content of critical operational drawings, in particular P & ID’s and E & ID’s. Examples are included for clarification. 1.3.3 Philosophy It is recognized that the approach currently used during the project phase to develop PFD’s and P & ID’s is largely done by using “design orientated” experience, and this section attempts to describe a process to achieve a consistent approach, during all the phases of the asset. A functional approach is different in that emphasis is placed upon what the system does, not what the system is. As a result system limits are not constructed from equipment packages, but rather from a strict analysis of how the various functions needed of a facility are provided. Also, as the facility design is developed, some decisions about equipment selection may be undecided, this approach centres upon the intended function of the facility equipment rather than the equipment units themselves. This function is top down, with a single function at the apex, describing at the highest level why the installation exists. All other functions are GOC© BP Exploration 1989 - 2001 All Rights Reserved SUBJECT: GUIDANCE ON CERTIFICATION SECTION 1.0 GOC© AMERICAS EDITION REVISION: 1 SYSTEM PRINCIPLES PAGE: 9 arranged as sub-functions, supporting the main function(s), at various levels. The level of a function does not represent a measure of its importance or criticality, merely that the function cannot be adequately described without decomposing it into a number of sub-functions. The primary principle should be that all valves, equipment, control rooms/panels and/or cabling etc. that can be uniquely identified as supporting a single function should be categorized within that system. A secondary principle, is that for each uniquely quantifiable functional component, the actual functional system boundary, in the absence of an alternative operational need, shall “normally” exist, at the upstream connection point of the first unique isolating device on the feed side and the downstream connection point of the final unique isolating device on the outlet side, as defined by the forward flow direction. The BP Andrew Functional Relationships are included to illustrate these points. Each P & ID should, ideally, contain a single principle system, which, by definition, contains a function by its boundaries. This then allows each P & ID to be numbered in a way that reflects the system it represents, as detailed in the Document Numbering System document (ETAP-PCMEN-902). The BP Andrew Potable Water Utility P & ID is included to illustrate this and how this relates to Functional Block A326 in the BP Andrew Functional Relationships. Drawing number (ADP-PR-PID-0569-001) illustrates how the P & ID boundary, functional system boundary and function relate at the Accommodation Interface. In practice, to aid comprehension and avoid the potential for errors occurring, the size of a system may need more than one drawing to fully describe its functionality. In this case, the individual drawing numbers should be so structured to have consistency with each of the drawings describing the total functional system. GOC© BP Exploration 1989 - 2001 All Rights Reserved SUBJECT: 1.3.4 GUIDANCE ON CERTIFICATION SECTION 1.0 GOC© AMERICAS EDITION REVISION: 1 SYSTEM PRINCIPLES PAGE: 10 System Schematics The guide to viewing the attached figures is summarized as follows : Figure 1: Typical North Sea platform PFD (Andrew) Figure 2: Primary System breakdown i.e Wells (100 series), Oil Processing (200 series), Gas Processing (300 series) and Flares (500 series) Figure 3: Breakdown of Oil Processing (200 series) into sub-systems Figure 4: Breakdown of Gas Processing (300 series) into sub-systems Figure 5: Figures 3 and 4 combined Figure 6: Actual systems used on Andrew, with each color representing a different system - note anomoloies such as suction scrubber on 2nd stage of HP compressor in different system to compressor itself Figure 7: Figures 5 and 6 combined Figure 8: Typical use of integration of Tagging Philosophy with FunctionalSystemization to improve clarity for everyone: projects, commissioning, operations, etc. Figure 9: Example of application throughout the facility - mainly to show E&I GOC© BP Exploration 1989 - 2001 All Rights Reserved GUIDANCE ON CERTIFICATION SECTION 1.0 GOC© AMERICAS EDITION REVISION: 1 SUBJECT: PAGE: 11 SYSTEM PRINCIPLES HP FLARE GAS LIFT GAS EXPORT ASC ASC GAS INJ. TEG PLANT HP FLARE ASC HP FLARE LP FLARE LIQUID EXPORT TEST SEPARATOR Figure 1: Typical North Sea platform PFD (Andrew) HP FLARE GAS LIFT GAS EXPORT ASC ASC GAS INJ. TEG PLANT HP FLARE ASC HP FLARE LP FLARE LIQUID EXPORT TEST SEPARATOR Figure 2: Primary System breakdown i.e Wells (100 series), Oil Processing (200 series), Gas Processing (300 series) and Flares (500 series) GOC© BP Exploration 1989 - 2001 All Rights Reserved GUIDANCE ON CERTIFICATION SECTION 1.0 GOC© AMERICAS EDITION REVISION: 1 SUBJECT: PAGE: 12 SYSTEM PRINCIPLES HP FLARE GAS LIFT GAS EXPORT ASC ASC GAS INJ. TEG PLANT HP FLARE ASC HP [200] FLARE [510] [1xx] [210] LP [520] FLARE LIQUID EXPORT [220] TEST SEPARATOR [260] [250] [240] [230] Figure 3: Breakdown of Oil Processing (200 series) into sub-systems [510] HP FLARE [350] [340] GAS LIFT [1xx] [360] GAS EXPORT [370] ASC [380] [330] [320] ASC GAS INJ. [1xx] TEG PLANT HP FLARE [510] [310] ASC HP FLARE LP FLARE LIQUID EXPORT TEST SEPARATOR Figure 4: Breakdown of Gas Processing (300 series) into sub-systems GOC© BP Exploration 1989 - 2001 All Rights Reserved GUIDANCE ON CERTIFICATION SECTION 1.0 GOC© AMERICAS EDITION REVISION: 1 SUBJECT: PAGE: 13 SYSTEM PRINCIPLES HP FLARE [350] [340] GAS LIFT [1xx] [360] GAS EXPORT [370] ASC [380] [330] [320] ASC GAS INJ. TEG PLANT HP FLARE [510] ASC [310] HP [200] FLARE [510] [1xx] [210] LP [520] FLARE LIQUID EXPORT [220] TEST SEPARATOR [260] Figure 5: [230] [250] [240] Figures 3 and 4 combined HP FLARE GAS LIFT GAS EXPORT ASC ASC GAS INJ. TEG PLANT HP FLARE ASC HP FLARE LP FLARE LIQUID EXPORT TEST SEPARATOR Figure 6: Actual systems used on Andrew, with each color representing a different system - note anomoloies such as suction scrubber on 2nd stage of HP compressor in different system to compressor itself GOC© BP Exploration 1989 - 2001 All Rights Reserved GUIDANCE ON CERTIFICATION SECTION 1.0 GOC© AMERICAS EDITION REVISION: 1 SUBJECT: PAGE: 14 SYSTEM PRINCIPLES HP FLARE GAS LIFT GAS EXPORT ASC ASC GAS INJ. TEG PLANT HP FLARE ASC HP FLARE LP FLARE LIQUID EXPORT TEST SEPARATOR Figure 7: Figures 5 and 6 combined HP FLARE [510] [330] [320] PCV-33001 PIC-33001 ASCV-32001 ASC-32001 [340] ASC V-33001 V-32001 X-32001 TEG PLANT X-33001 LCV-33001 Z-33001 K-32001 [211] [211] [310] [210] Figure 8: Typical use of integration of Tagging Philosophy with Functional Systemization to improve clarity for projects, commissioning, operations, etc. GOC© BP Exploration 1989 - 2001 All Rights Reserved GUIDANCE ON CERTIFICATION SECTION 1.0 GOC© AMERICAS EDITION REVISION: 1 SUBJECT: PACKAGE 1 ECP3003 U.P.S. SUITE A.C. DIST SECTION PAGE: 15 SYSTEM PRINCIPLES 11 KV SUPPLY CB 4 EMERGENCY STOP PB 1 PACKAGE IX RED SHUTDOWN SYSTEM V.S.D. TRANSFORMER T 3008 EMERGENCY STOP PB 2 V.S.D. CUBICLES K 3000 VSD - CP REMOTE EMERGENCY STOP HEAT EXCHANGE FAN K 3000 & K 3001 INTERPOSING RELAY PANEL COMPRESSOR CONTROL PANEL AUX. MCC 12 NGL CONTROL ROOM SOUTH WEST CANTILEVER MB-AL-E-006 TRACE HEATING PANEL ‘D’ TO GAS LIFT MANIFOLD COMPRESSOR SKID MOTOR PROCESS SKID FROM SOURCE GAS SUPPLY PACKAGE LIMITS SYSTEM LIMITS Figure 9: Example of application throughout the facility - mainly to show E&I GOC© BP Exploration 1989 - 2001 All Rights Reserved GUIDANCE ON CERTIFICATION SECTION 1.0 GOC© AMERICAS EDITION REVISION: 1 SUBJECT: 1.3.5 PAGE: 16 SYSTEM PRINCIPLES Generic Examples Traditionally, some P & ID’s have contained more than one system e.g. the production manifold and test manifold are commonly shown on the same drawing. Using the philosophy described over; as they clearly have different functions and hence are in different systems they should be represented on different drawings. Some items have to be shown in a line that is part of a function that the item is not supporting directly. L System “C” System “A” L S F System “B” B A B Distributed systems are sometimes difficult i.e. where the generation and distribution are traditionally in one system. However, from the primary isolation point providing a supply into another function should be shown on that system. See cooling water supply example illustrated below. GOC© BP Exploration 1989 - 2001 All Rights Reserved SUBJECT: 1.3.6 GUIDANCE ON CERTIFICATION SECTION 1.0 GOC© AMERICAS EDITION REVISION: 1 SYSTEM PRINCIPLES PAGE: 17 Specific Examples Utility headers and connection to equipment e.g. Cooling water. The system break will be upstream of the inlet block valve and downstream of the outlet block valve. System “B” System “A” System “B” GOC© BP Exploration 1989 - 2001 All Rights Reserved SUBJECT: GUIDANCE ON CERTIFICATION SECTION 1.0 GOC© AMERICAS EDITION REVISION: 1 PAGE: 18 SYSTEM PRINCIPLES 1.3.6.1 Relief valves and connection to vent header System “B” System “A” 1.3.6.2 Tank on level control System “B” System “A” GOC© System “C” BP Exploration 1989 - 2001 All Rights Reserved SUBJECT: GUIDANCE ON CERTIFICATION SECTION 1.0 GOC© AMERICAS EDITION REVISION: 1 PAGE: 19 SYSTEM PRINCIPLES 1.3.6.3 Wells and Manifolds WELL System “D” System “A” System “B” System “F” System “C” System “E” 1.3.6.4 Chemical Injection System “A” GOC© DU System “B” BP Exploration 1989 - 2001 All Rights Reserved GUIDANCE ON CERTIFICATION SECTION 1.0 GOC© AMERICAS EDITION REVISION: 1 SUBJECT: PAGE: 20 SYSTEM PRINCIPLES 1.3.6.5 System Total Bypass System “B” System “A” 1.3.6.6 Pig Receiver System “B” System “A” GOC© BP Exploration 1989 - 2001 All Rights Reserved GUIDANCE ON CERTIFICATION SECTION 1.0 GOC© AMERICAS EDITION REVISION: 1 SUBJECT: 1.3.6.7 PAGE: 21 SYSTEM PRINCIPLES Metering (Test and Allocation). P F L L F F ALLOCATION METERING SYSTEM “C” System “A” P F L L F F System “B” GOC© SEPARATION METERING SYSTEM “A” BP Exploration 1989 - 2001 All Rights Reserved SEPARATION METERING SYSTEM “B” SUBJECT: GUIDANCE ON CERTIFICATION SECTION 1.0 GOC© AMERICAS EDITION REVISION: 1 PAGE: 22 SYSTEM PRINCIPLES 1.3.6.8 Double Barrier Isolation System “A” PI System “B” 1.3.6.9 Cascaded Instrumentation F System “A” L F GOC© P L F BP Exploration 1989 - 2001 All Rights Reserved GUIDANCE ON CERTIFICATION SECTION 1.0 GOC© AMERICAS EDITION REVISION: 1 SUBJECT: PAGE: 23 SYSTEM PRINCIPLES 1.3.6.10 Power and Control Connections System “A” 11 KV System “E” LOGIC 3.3 KV P System “D” C C System “B” GOC© 415 V System “C” T OCR BP Exploration 1989 - 2001 All Rights Reserved A SUBJECT: GUIDANCE ON CERTIFICATION SECTION 1.0 GOC© AMERICAS EDITION REVISION: 1 PAGE: 24 SYSTEM PRINCIPLES 1.3.6.11 Control Interconnections PIC PT System “A” FQI TT FT WV UMV System “B” LMV LMV GOC© BP Exploration 1989 - 2001 All Rights Reserved SUBJECT: 1.3.7 GUIDANCE ON CERTIFICATION SECTION 1.0 GOC© AMERICAS EDITION REVISION: 1 PAGE: 25 SYSTEM PRINCIPLES Isolations An understanding of where and why the equipment is isolated, will aid where the boundaries are and which side of valves they occur. As detailed in section 1.3.3, the actual functional system boundary shall “normally” exist at the upstream and downstream connections of the initial and final unique isolating devices, as defined by the forward flow direction. 1.3.7.1 On-line Maintenance Where a specific system may be isolated for maintenance without affecting the capability to achieve the primary functionality of that section of plant, then the level of isolation and acceptable leakage criteria is extremely important. System “A” PI PI System “B” In the illustration above, the pressure and flow in the main line (system “A”) are fully operational while system “B” is isolated for maintenance. 1.3.7.2 Off-line Maintenance When a specific system, necessary to support achievement of the primary functionality of that section of plant, such as the HP separator in GOC© BP Exploration 1989 - 2001 All Rights Reserved SUBJECT: GUIDANCE ON CERTIFICATION SECTION 1.0 GOC© AMERICAS EDITION REVISION: 1 SYSTEM PRINCIPLES PAGE: 26 a single train operation i.e. no sparing, is de-commissioned for maintenance, it is normal practice to depressurise adjacent systems. In this case the level of isolation and the leakage criteria are less severe. These isolations and understanding which side of the valve would require to be hydrocarbon free should be the system boundaries. 1.3.8 Controls and Cables General Each process primary system contains a sub-system for control panels (96), and multicore cables (97), associated with that primary system. Systemization of these configurations is straightforward, provided all cables and equipment associated with that configuration resides in just one primary system. The examples shown in section 1.3.8.1 demonstrate systemization of such configurations. The introduction of Integrated Process Control Systems into our industry changes our approach to systemization of control panels and their multicore cables. These high technology panels perform complete process control, ESD and in some cases fire and gas monitoring and detection, and cannot be categorized into any one of the process primary systems. Therefore, these ICS panels and their associated multicore cables have been allocated their own secondary number in primary system 6 (Safety). The examples shown in section 1.3.8.3 demonstrate systemization of such configurations. GOC© BP Exploration 1989 - 2001 All Rights Reserved SUBJECT: GUIDANCE ON CERTIFICATION SECTION 1.0 GOC© AMERICAS EDITION REVISION: 1 PAGE: 27 SYSTEM PRINCIPLES 1.3.8.1 Local Control Panel Systemization The following examples show a variety of different hook ups to control panels, which serve only one primary system. It is important to remember that all cables and equipment must reside in that primary system. In the majority of cases stand alone control panels, their multicore cables, junction boxes and field devices, naturally fall into only one primary system, due to the location of field junction boxes and field devices. The systemization of this equipment and their cables are straightforward, in that they are all part of the same system. A local control panel serving system A would be systematized as follows: Local Control Panel JB Multicore Cable 1 Cable 2 FT.. PT.. Cable 3 System A96… TT.. System AXY… All three field devices (FT, PT, TT) are in primary system ‘A’, and secondary system ‘XY’. Therefore cables 1,2 and 3 become part of the same primary and secondary system, as does the multicore cable. The control panel only serves primary system A . The system limits for the above example would be: Control panel and its power supplies A96 Multicore cable, JB, Cables 1,2 &3 and Field equipment AXY (where XY is the secondary number) GOC© BP Exploration 1989 - 2001 All Rights Reserved GUIDANCE ON CERTIFICATION SECTION 1.0 GOC© AMERICAS EDITION REVISION: 1 SUBJECT: 1.3.8.2 PAGE: 28 SYSTEM PRINCIPLES In this example, the control panel serves more than one subsystem of primary system A. System AXY… Control Panel JB1 Multicores Cable 1 Cable 2 Cable 3 JB2 JB3 Cable 4 Cable 5 FT PT TT LT PT System A96… Cable 6 JB4 ZS System A97… System AXZ… In the case where there are multiple multicore cables leaving the control panel each to a different main junction box in the same primary system, then systemization would be as follows: Control panel and its power supplies A96 Multicore cables and JBs A97 Field devices and their cables would come under their respective secondary system number, in this case AXY and AXZ In this instance, the multicores have been separated from their respective secondary system and given a separate number (A97). This is to ensure that all multicores are installed and tested before any system is commissioned, and furthermore to reduce to amount of cable work such as glanding and terminating that has to be carried out when the panel is ‘live’ and partly operational. GOC© BP Exploration 1989 - 2001 All Rights Reserved SUBJECT: 1.3.8.3 GUIDANCE ON CERTIFICATION SECTION 1.0 GOC© AMERICAS EDITION REVISION: 1 PAGE: 29 SYSTEM PRINCIPLES Integrated Control Panel Systemization Integrated Control Systems and their multicores are covered in the safety primary system number (6). System AXY… ICS Panel Cable 1 JB1 FT Cable 2 Multicores PT Cable 3 TT Cable 4 LT JB2 JB3 Cable 5 PT System 690… JB4 Cable 6 System 697… 1.3.8.4 ZS System BXZ… Typical Integrated system field hook-up The example above, shows field equipment located in two primary systems AXY… and BXZ… Because the multicores between the control panel and its JBs cover two primary systems, systemization would be as shown. As an integrated control network, the control panel and its multicore cables would reside in the safety primary system No 6. The multicores and JBs have a separate secondary number for the same reason as described in example 1.3.8.2. Which is to ensure that all multicores are installed and tested before any system is commissioned, and furthermore to reduce to amount of cable work such as glanding and terminating that has to be carried out inside a ‘live’ panel. GOC© BP Exploration 1989 - 2001 All Rights Reserved SUBJECT: GUIDANCE ON CERTIFICATION SECTION 1.0 GOC© AMERICAS EDITION REVISION: 1 PAGE: 30 SYSTEM PRINCIPLES 1.3.8.5 The following example shows two subsystems of primary system A entering a single junction box JB1, and a single multicore cable to ICS panel. System AXY… ICS Panel JB1 Multicores Cable 1 Cable 2 Cable 3 FT PT TT System AZZ… JB2 Cable 4 JB3 Cable 5 LT PT System 690… JB4 Cable 6 ZS System 697… System BXZ… The system limits for this type of configuration would be as shown in the above example, but additional handover information would be required to show the relationship between the common multicore and the two subsystem loops. This additional information would be an electrical schematic drawing of the junction box JB1, systematized as shown in 1.3.8.6. GOC© BP Exploration 1989 - 2001 All Rights Reserved SUBJECT: GUIDANCE ON CERTIFICATION SECTION 1.0 GOC© AMERICAS EDITION REVISION: 1 PAGE: 31 SYSTEM PRINCIPLES 1.3.8.6 Junction Box Details Junction Box 1 TB1 1 2 System AXY.. Cable 1 3 4 5 Cable 2 6 7 System AZZ.. 8 9 10 Cable 3 11 12 13 System 697… A schematic of JB1 would be highlighted to show the cable core and termination details for each of the subsystems involved. The installation and testing of the multicore can only be carried out under one subsystem. Where a multicore cable is shared between more than one subsystem, references to multicore cable number and its cores are made in each of the applicable subsystems. For completeness, a suitably marked up drawing of the control panel terminations of the multicore could also be included to show demarcation between subsystems involved. With this data recorded and logged in a database future tracability of control equipment and their loops is accessible. GOC© BP Exploration 1989 - 2001 All Rights Reserved SUBJECT: GUIDANCE ON CERTIFICATION SECTION 1.0 GOC© AMERICAS EDITION REVISION: 1 PAGE: 32 SYSTEM PRINCIPLES 1.3.8.7 A typical Integrated System Network System 690 System 692… Radio Tx/Rx Operator Display Station Operator Display Station Server Data Highway System 691 PLC B PLC A PLC C System 690… Primary system 6 has a sub system number 90 which is allocated to these types of integrated controls. Other applicable sub systems within 6 are: Integrated Controls 90 Networks 91 Communications 92 The above simplified integrated control system, shows how the network would be systematized. GOC© BP Exploration 1989 - 2001 All Rights Reserved SUBJECT: 1.4 1.4.1 GUIDANCE ON CERTIFICATION SECTION 1.0 GOC© AMERICAS EDITION REVISION: 1 SYSTEM PRINCIPLES PAGE: 33 SYSTEM MECHANICS Limits of System Handover (LOSH) When the design or maintenance process has reached a "high" level of definition, limits of system handover (LOSH) can be established by the Construction/Maintenance Authority, in conjunction with the Commissioning Authority. Unique handover identifying number(s), issued by the Commissioning Authority, using the asset system mnemonics matrix, should then be allocated, covering the work scope to the agreed limit(s). An example of one of the system mnemonics matrix, used within BP, is shown in Appendix 1.0. System limit definition is achieved by dividing the workscope into "standalone functional systems" e.g. Produced Crude, Produced Water, Lift Gas, etc., that perform specific, quantifiable duties, and identifying the associated interfaces, piping specification changes and isolation boundaries between these systems and other connected systems. These stand-alone systems may be further sub-divided into smaller defined scopes of work (system handover limits), which may have single or multiple-discipline content, to aid constructability, maintainability, commissionability and transfer of plant/equipment to the operator. For compilation of system handover limits, the most current P&ID drawings should be marked up to identify limit boundaries and discipline content. The Handover Authority may further sub-divide the handover limit to detail Pre-Shutdown scope, Shutdown scope and Post-Shutdown scope as appropriate; Appendix 1 details an example of a LOSH Legend. Other discipline drawings may be added to define detail. There are exceptions when P&ID drawings are not applicable, e.g. HVAC (part), structural, architectural, etc. GOC© BP Exploration 1989 - 2001 All Rights Reserved SUBJECT: GUIDANCE ON CERTIFICATION SECTION 1.0 GOC© AMERICAS EDITION REVISION: 1 SYSTEM PRINCIPLES PAGE: 34 The term "black-box" is used with respect to system limit boundary compilation. That is to say, an outlined stand-alone scope, defining the interfaces and isolations/termination points with other systems. For an example, see Appendix 1.1. 1.4.2 Data Input Sheets (DIS's) Data input sheets (DIS's), detail the minimum inspection and test (I&T) requirements for each system handover limit, usually stipulated according to discipline by the Construction/Maintenance and/or Engineering Authority and accepted by the Commissioning Authority. The DIS’s should be developed using the work schedule, together with an assessment of the risk involved, in conjunction with individual discipline procedures contained in sections 2 to 10 of the GOC©. To assist in this risk assessment, and thus the documentation required, Technical Integrity Assurance flowcharts (and functional certification flowchart) are included in Appendix 1.2. Nominated personnel who carry out these activities and those who witness them (where appropriate) should also be identified. Discipline/functional certification requirements should be annotated on DIS's, prior to the data being entered into the asset specific certification management system e.g. MANCON©, to provide a certification recording/tracking capability. The DIS categories are as follows: DIS No. Discipline/Function 1 Mechanical - Piping 2 " - Machinery, Vessels and Handling Equipment 3 " - Structural 4 " - HVAC 5 Control - Instruments, Fire & Gas & Telecoms 6 Electrical - Cables 7 " - Equipment 8 Civil - Roads & Pads, Foundations, Piling & Backfill Refer to the appropriate GOC© discipline section for the above DIS forms. GOC© BP Exploration 1989 - 2001 All Rights Reserved SUBJECT: 1.4.3 GUIDANCE ON CERTIFICATION SECTION 1.0 GOC© AMERICAS EDITION REVISION: 1 SYSTEM PRINCIPLES PAGE: 35 Inspection and Test Summary (ITS) The Inspection and Test summary (ITS), generated on an individual discipline basis, for a given System Handover Certificate (SH1) system handover, is a summary of all the certification requirements for that particular handover and forms the basis of BP Certification Management Database (MANCON©). The discipline procedures, DIS's and associated I&T plan(s), provide standardization of the certification system and identification of the various authorities involved in the execution of the plan. 1.4.4 Handover Certification Pack (HCP) Once system handover limits and associated DIS / I&T plans have been defined and approved, the Handover Certification Pack (HCP) may be compiled. This pack should contain the DIS's or certification requirements matrix i.e. I&T plan (as appropriate), P&ID's (marked up with the system limits) and preferably the relevant certificates (called up in the applicable DIS's or I&T plans), which detail the testing procedures. As work progresses, the certificates should be completed, inserted in the HCP and the appropriate DIS or I&T plan updated accordingly. The pack should be handed over from one performing authority to another until final handover to the operator is achieved. The HCP should then be returned, as soon as possible, to the appropriate asset engineering group for document/drawing "as-built", close-out, auditing (where appropriate) and archiving. In certain cases, the required certification may be raised by a third party, using their own certificates and, for contractual/legal reasons, the originals need to be retained by the third party. Provided the third party © certificates embody the requirements of the corresponding GOC certificate, the GOC© certificate shall be merely used as a "carrier" certificate. GOC© BP Exploration 1989 - 2001 All Rights Reserved SUBJECT: GUIDANCE ON CERTIFICATION SECTION 1.0 GOC© AMERICAS EDITION REVISION: 1 SYSTEM PRINCIPLES © In this case, the GOC PAGE: 36 certificate should reference the third party certificate identifier and a copy of the authorized third party original should be attached to it. An example of the GOC© "carrier" certificate is contained in Appendix 1.2. System limits, DIS's, I&T plan and HCP may be generated either on-site or off-site. Generation on-site being particularly valid for "in-house" activities: e.g. operational maintenance works that require "recertification" for retention of License to Operate, e.g. breaking of containment or involving the facilities Emergency Shut Down (ESD) systems. Though the principles of minimum certification requirements, as contained in section 2 to 10 of the GOC© may be followed, because of the very nature of the activity itself; i.e. one individual carrying out the whole process, as one activity, at one time, instead of a number of disciplines being involved over a prolonged period, as is often the case in a modification, the number of certificates necessary in maintenance activities may be lower than normal modification activities. In this case, the corresponding degree of certification, agreed by the operational authority, shall however ensure that a true I&T requirement is maintained and that integrity of the plant/equipment is not impaired, before being brought back into service. HCP's in this category should be kept, for a suitable period determined by the asset, as "hard copy only" for auditability. It is recommended that, in such cases, the unique system handover number(s) and general brief activity descriptions should be added to the asset specific certification management system, for record and tracking purposes only. 1.4.5 System Safe Certificate (SS1) The System Safe Certificate (SS1) facilitates the handover of the system from the Operating Authority to the Construction Authority to confirm the system(s) as defined by the System Handover (SH1) is isolated and all necessary tests and precautions have been carried out in readiness for safe work with the defined limits of isolation. GOC© BP Exploration 1989 - 2001 All Rights Reserved SUBJECT: GUIDANCE ON CERTIFICATION SECTION 1.0 GOC© AMERICAS EDITION REVISION: 1 PAGE: 37 SYSTEM PRINCIPLES The SS1 is only applicable when a Project or Modification is being carried out on an existing facility (brown field site) and is not normally applicable on a new build (green field site). However, there maybe occasions on a new build (green field site) when a system has been handed over and is being operated by the Operating Authority, where Construction and/or Commission Authority may be required to carry out the requirements of an Engineering Query (EQ) or a Technical Query (TQ), then in cases like this, the SS1 would be applicable and appropriate on a green field site. 1.4.6 Mechanical Completion Certificate (MC1) The Mechanical Completion Certificate (MC1) facilitates the handover of the system from the Construction/Maintenance Authority to the Commissioning Authority. While during the final construction stages, some commissioning activities (e.g. flushing, leak testing and certain function tests, etc.) are possible, with the approval of the construction performing body and without MC1 handover, all construction and pre-commissioning activities must have been completed and MC1 handover taken place, before "powering-up", introduction of actual working fluids/chemicals on the danger list or where danger to other systems may exist. To aid constructability/maintainability/commission ability, the system handover limits may be sub-divided into more than one "black box"/subsystem. This would occur when an advantage can be gained by having early access to a section of plant/equipment and handover, via the mechanical completion certificate (MC1), to the Commissioning Authority. Each MC1 carries the same identification number as the system handover number but with the addition of +01, +02, etc., depending upon the number of MC1's. Each MC1 must be capable of isolation / termination from other sections, ensuring safety is not impaired. GOC© BP Exploration 1989 - 2001 All Rights Reserved SUBJECT: GUIDANCE ON CERTIFICATION SECTION 1.0 GOC© AMERICAS EDITION REVISION: 1 SYSTEM PRINCIPLES PAGE: 38 Occasions occur when certain activities, requiring certification, are performed outside the site location i.e. vendors fabrication/assembly facilities, module yards etc. In this particular case, the same GOC© principles should be applied in the generation of separate MC1's; i.e. system handover limits established, I&T requirements determined etc., such that on completion, the works can be "punched" in the normal way and prepared for handover to the Commissioning Authority. If the completed work and associated MC1 pack are agreeable to the Commissioning Authority, the MC1 should be accepted, the asset certification management system updated and the MC1 pack retained at the asset's central certification control point, rather than dispatching to the site. Subsequent on-site hook-up works should then form the basis of additional independent MC1's (as appropriate), which would be managed in the normal way. Once again vendor certification can be utilized by using the GOC© "carrier" certificate methodology, detailed above. Where the Construction/Maintenance performing body and commissioning performing body come under the same management authority, the MC1 may be omitted and approval authorization undertaken via the SH1. 1.4.7 System Handover Certificate (SH1) The System Handover Certificate (SH1) facilitates the handover of the system from the Commissioning Authority to the Operating Authority. At this stage, commissioning activities should have been completed. At SH1 approval / acceptance, the following restrictions/limitations apply: (a) No category ‘A’ Punch List items shall remain. (b) Engineering queries (EQs) raised shall have been answered, assessed for its impact and where possible subsequent GOC© BP Exploration 1989 - 2001 All Rights Reserved SUBJECT: GUIDANCE ON CERTIFICATION SECTION 1.0 GOC© AMERICAS EDITION REVISION: 1 SYSTEM PRINCIPLES PAGE: 39 construction/ commissioning works implemented. Only outstanding EQ’s that do not impair the safety of plant and/or personnel and have the approval of the operating authority shall remain (Punch List Item category B). (c) The Integrity Authority shall have witnessed any I&T activities specifically requested by them. (d) Any I&T activities required for obtaining or retaining of certificate of fitness e.g. containment confirmation, PSV/Cat 1 protection system, ESD system testing, Life support systems etc. shall have been completed in full. (e) The operator should have been provided with all technical and operations/maintenance information i.e. equipment specifications and data, operating and maintenance procedures etc. necessary for Operations to safely operate the plant being handed over. When commissioning activities require hydrocarbons introduced, to complete the certification, e.g. gas compressor or crude pump test runs etc., the SH1 must be handed over and accepted by the operating authority before commencement. In this particular case, any outstanding activities should be entered in the "exclusions" section of the SH1 and included on the punch list, prior to handover. Further commissioning should then proceed under operations authority control with appropriate certification/running logs/as-built drawings etc. added to the HCP on completion, and copied to the operating authority (where appropriate). Certain circumstances arise when non-essential plant/equipment, which fall within the SH1 limits and is not immediately required for operations to continue, e.g. a chemical injection pump used intermittently etc., is not available when the main system requires to be made operational. Provided the plant/equipment can be isolated to the satisfaction of all performing authorities, such that no impairment to safety of the plant GOC© BP Exploration 1989 - 2001 All Rights Reserved SUBJECT: GUIDANCE ON CERTIFICATION SECTION 1.0 GOC© AMERICAS EDITION REVISION: 1 SYSTEM PRINCIPLES PAGE: 40 and/or personnel exists, the outstanding plant/equipment and associated certification may be entered into the "exclusions" section of the SH1 and included on the punch list prior to handover. Once again, appropriate certification, as-built drawings etc. should be added to the HCP on completion, and copied to the operating authority (where appropriate). Situations also arise where additional work to that originally planned, needs to be undertaken in order to achieve the aims of the modification/maintenance activity e.g. pipework re-routing due to a "conflict” etc. The normal implementation method, for capturing the additional man-hours involved, is the raising of an site instruction (S.I.). To capture the change in system limit and/or I&T data requirements (refer to 1.6 - Change Control), an on-site HCR should be raised and included in the HCP and at SH1 handover, specifically brought to the notification of the operating authority. 1.4.8 Plant Performance Certificate (PP1) The Plant Performance Certificate (PP1) facilitates the realization of design integrity and expectations and that the facility is performing to those expectations for the agreed period of time, post SH1 Handover. The Engineering & Commissioning Authority confirms that the plant performance tests as defined are in accordance with design and vendor requirements, specifications and drawings, and that the plant meets the expectations of design criteria and intended purpose, provided a NonPerformance report (NP1) is not raised. If a Non-Performance report (NP1) is raised, the Operating Authority may not accept the PP1 until the detail of the NP1 or any subsequent Engineering Queries (EQ) and/or Technical Queries (TQ) have been satisfactory resolved. Upon completion of the NP1, EQ and/or TQ process to the satisfaction of the Operating Authority, the Operating Authority will sign the PP1 accepting GOC© BP Exploration 1989 - 2001 All Rights Reserved SUBJECT: GUIDANCE ON CERTIFICATION SECTION 1.0 GOC© AMERICAS EDITION REVISION: 1 SYSTEM PRINCIPLES PAGE: 41 that plant performance tests have demonstrated that the design expectations have been achieved. 1.4.9 Punch List (PL1) The punch list form (PL1) shall detail all outstanding items of work, according to the original work scope, at the point of handover of both MC1 and SH1. Prior to offering the MC1/SH1 for acceptance, the work content shall be reviewed (punched) to ensure work has been constructed/maintained as per design/maintenance routine and that the plant/equipment integrity is valid or has not been impaired during maintenance. To record these items, a PL1 shall be raised (normally by the construction/maintenance performing authority), listing all defects found outside design/original operating capability. At MC1 handover stage, the punch (punch-list walk-through inspection) shall be carried out by the Construction/Maintenance performing body together with the commissioning performing body with operations invited to participate. At SH1 handover stage, the punch (punch-list walk-through inspection) shall be carried out by the Commissioning performing body together with Operations with the Construction/Maintenance performing body invited to participate. Wherever possible, the PL1 should be accompanied with attached marked-up P&ID(s) showing location of defect items. To assist detail, other types of drawings may be added, i.e. piping isometrics, E&I line diagrams, etc. The P&ID, having been HAZOPed, remains the primary drawing. There should be only one uniquely identified, discipline specific, punch list per HCP (as many pages as required). The same PL1 shall be carried forward from MC1 to SH1, items being signed off and/or added, as required. GOC© BP Exploration 1989 - 2001 All Rights Reserved SUBJECT: GUIDANCE ON CERTIFICATION SECTION 1.0 GOC© AMERICAS EDITION REVISION: 1 SYSTEM PRINCIPLES PAGE: 42 Each item on the list shall be categorized as priority ‘A’ & ‘B’. ‘A’ denoting major items which must be completed before a handover is acceptable and priority ‘B’ denoting minor items which, provided they are not excessive in number and with the agreement of the accepting authority, can be completed after the handover is accepted. The responsibility for clearing PL1 items shall, unless agreed otherwise, rest with the Construction/Maintenance Authority, except where the commissioning performing body/operations have requested something, within the scope, to be left out to assist their progress, etc., e.g. a spectacle blind left in the closed position at MC1 acceptance, to assist commissioning leak test. This would be cleared by turning the spectacle blind to the run position (open), prior to offering the SH1 to the operator, for acceptance. In this particular case this would have appeared as a "B" item at MC1 offer stage, but an "‘A’" item (commissioning to clear) at SH1 offer stage. The PL1 shall remain live and tracked until all items are completed and signed off. Where the handover is of considerable size, it is recommended that a pre-punch is carried out in order to reduce the number of items being entered on the official PL1, and the certification management system. Punch list items must be restricted to "as per design/maintenance routine" and not include "nice to have" or "preferential engineering" items. GOC© BP Exploration 1989 - 2001 All Rights Reserved SUBJECT: GUIDANCE ON CERTIFICATION SECTION 1.0 GOC© AMERICAS EDITION REVISION: 1 SYSTEM PRINCIPLES 1.5 KEY PERSONNEL 1.5.1 Nomination of Authorities PAGE: 43 Dependent on the scope of the works to be completed using the GOC©, the various performing bodies and authorities should be nominated at the outset. Clearly a major project will involve large discrete departments to fulfill the required roles (both performing and authorization) and normally the handover authorized by the head of those departments or his nominated deputy by signature on the requisite forms. Nomination of performing bodies and authorities is particularly important where the projects are smaller, such as repair orders on the plant, and all work will be carried out on site. Then, the performing bodies and authorities defined below may be the same signatory and the provision of information at each stage will be correspondingly less (e.g. basis of designs (BOD's) referenced in 1.5.2 below, will not necessarily be required). The following defines the roles of the various authorities in so far as they apply to the Certification System. Appendix 1.4 details the relevant performing bodies and authorities normally applicable. It is incumbent upon the relevant Asset to fill in or delete as applicable, the requisite names/job titles applicable to their Asset. 1.5.2 Design/Maintenance Planning Authority The design/maintenance planning authority shall provide the Basis of Design (BOD) which will include, but not be limited to, detailed drawings (PFD's, P&ID's, Isometrics, etc.), material specifications, system parameters and proposed methods of construction, maintenance, commissioning and operation. For smaller modifications or maintenance activity the BOD may be replaced by a scope of work (SOW). A typical BOD contents sheet is contained in Appendix 1.3. GOC© BP Exploration 1989 - 2001 All Rights Reserved SUBJECT: 1.5.3 GUIDANCE ON CERTIFICATION SECTION 1.0 GOC© AMERICAS EDITION REVISION: 1 SYSTEM PRINCIPLES PAGE: 44 Construction/Maintenance Authority The Construction/Maintenance Authority, in conjunction with the Commissioning Authority, shall produce system handover limits, raise Discipline Input Sheets (DIS's) by discipline, input the data into © MANCON (where appropriate) and produce the HCP's. Once the construction, maintenance and pre-commissioning works have been completed, punch list(s) produced and MANCON© updated (where appropriate), the Construction/Maintenance Authority shall handover the system(s), with the requisite completed MC1's, to the Commissioning Authority. 1.5.4 Commissioning Authority The Commissioning Authority, on satisfactory acceptance of the MC1 from the Construction/Maintenance Authority, will complete all © commissioning activities, update the punch list, update MANCON (where appropriate) and then handover the system, with the requisite completed SH1, to the Operating Authority. 1.5.5 Certification Administrator The Certification Administrator undertakes the compilation, verification and auditing of the certification process. 1.5.6 Handover Management Handover Management, (SH1 allocation authority) controls the issuing, deletion and general control of the unique system handover numbers (SH1's). GOC© BP Exploration 1989 - 2001 All Rights Reserved SUBJECT: 1.5.7 GUIDANCE ON CERTIFICATION SECTION 1.0 GOC© AMERICAS EDITION REVISION: 1 PAGE: 45 SYSTEM PRINCIPLES Operating Authority The operating authority must be satisfied that all steps have been taken by all the other performing bodies, to ensure that the system offered for acceptance is safe, effective and operable and that the HCP will meet all Integrity Authority and legislative requirements of the country or state whose jurisdiction the installation is subject. The operating authority signs the SH1 as acceptance of the operational system, subject to the constraints/limitations detailed above. asset nominated authorities. 1.6 CHANGE CONTROL 1.6.1 Requirement for Change Refer to Appendix 1.4 for the The DIS's / I&T plan is reviewed and then fixed during the design/maintenance planning stage, but it is usually inevitable that the system limits and/or I&T requirements for some systems may require to be changed after the approval stage but at some stage before handover to the operator. The DIS's / I&T plan specify the minimum requirements for inspection and testing, and generally this will be sufficient for operational purposes. If, however, further activities are identified, then the plan must be changed. Similarly, operational reasons may dictate that the limits of the system must be changed. The mechanism for these changes is contained in the following subsections. It is important that the correct form is selected so that the information can be processed in an expedient manner. 1.6.2 Handover Change Request (HCR) The Handover Change Request (HCR) form is used for controlling post approval changes to system handover limits and/or Data. The form, which may be raised on-site or offsite, should be transmitted to the appointed authority, for approval. If the HCR is accepted, the limits and/or data should be amended and the relevant information transmitted GOC© BP Exploration 1989 - 2001 All Rights Reserved SUBJECT: GUIDANCE ON CERTIFICATION SECTION 1.0 GOC© AMERICAS EDITION REVISION: 1 SYSTEM PRINCIPLES PAGE: 46 along the normal lines of communication (refer to section 1.6 of this document). If, however, the HCR is rejected then it should be returned to the originator, together with an explanation of the rejection. 1.6.3 MANCON© Change When MANCON is being used as the certification management system for recording and tracking purposes, then when the HCR is approved, it also provides the necessary authorization for the change(s) to be © © incorporated into MANCON , using the appropriate MANCON procedures. GOC© BP Exploration 1989 - 2001 All Rights Reserved SUBJECT: GUIDANCE ON CERTIFICATION SECTION 1.0 GOC© AMERICAS EDITION REVISION: 1 PAGE: 47 SYSTEM PRINCIPLES 1.7 SYSTEM FLOW 1.7.1 Sequence of Events In the following steps the word "MANCON©" is used in the context of being an example of one of the certification management systems available and in use within BP. Other assets, using alternative systems, should replace the word "MANCON©" with their own system identifier. Sequence of events: a) BOD/SOW produced by the design/maintenance planning authority should be transmitted to the Construction/Maintenance Authority. b) The Construction/Maintenance Authority, in conjunction with the Commissioning Authority, should define the limits of system handover, by marking up the system drawings, and adding a unique system handover identifier number, obtained from the SH1 allocation authority. c) The Construction/Maintenance Authority discipline engineers should allocate the construction/maintenance inspection and test requirements. d) The Commissioning Authority discipline engineers should allocate the commissioning inspection and test requirements. e) Once the I&T plan has been authorized by all appropriate authorities, the Certification Administrator should produce the inspection and test certificates, the approved I&T requirements matrices and combine these with the appropriate marked up drawings to compile the HCP. f) The Certification Administrator should then transmit the HCP to site. GOC© BP Exploration 1989 - 2001 All Rights Reserved SUBJECT: g) GUIDANCE ON CERTIFICATION SECTION 1.0 GOC© AMERICAS EDITION REVISION: 1 PAGE: 48 SYSTEM PRINCIPLES The Construction/Maintenance performing body should complete his activities and as work progresses, the Certification Administrator should update MANCON© (if appropriate) and insert the completed I&T certificates in the HCP until handover, to the Commissioning Authority, is possible. h) When all construction/maintenance activities have been completed, the Construction/Maintenance performing body, the commissioning performing body and, if possible, the operations representative should then carry out a joint punch to the system handover limits. i) The Construction/Maintenance Authority should then complete and sign the MC1 and, together with the agreed priority ‘B’ item Punch List Items, hand over the HCP to the Commissioning Authority. j) The Commissioning Authority should review the HCP for acceptability and if satisfied, sign the MC1 as acceptance of the system. k) The commissioning performing body should complete its activities and as work progresses, the Certification Administrator should update MANCON© (if appropriate) and insert the completed I&T certificates in the HCP until handover, to the operating authority, if possible. l) When all commissioning activities have been completed, the commissioning performing body, the operations representative and, if possible, the Construction/Maintenance performing body should then carry out a joint punch to the system handover limits. m) The Commissioning Authority completes and signs the SH1 and together with the agreed priority B item Punch List Items hands over the HCP to the operating authority. n) The operating authority should review the HCP for acceptability and once satisfied, sign the SH1 as acceptance of the system. GOC© BP Exploration 1989 - 2001 All Rights Reserved SUBJECT: GUIDANCE ON CERTIFICATION SECTION 1.0 GOC© AMERICAS EDITION REVISION: 1 PAGE: 49 SYSTEM PRINCIPLES o) Outstanding punch list form (PL1) items and Engineering Query (EQ) actions should remain live and tracked by MANCON© (if appropriate) until completion. Any further certificates, “as-built” drawings etc., resulting from completed PL1 and EQ actions should be added to the accepted HCP and, where appropriate, copies of appropriate documentation transmitted to the operating authority for information. To ensure timely "as-building" of documentation, it is recommended that the HCP be returned to the engineering authority at the earliest opportunity. To achieve this feature, if issues such as EQ resolution etc., are outstanding at point of SH1 approval by the Operating Authority and are expected to take some time, due to material deliveries etc., then consideration should be given to transferring these works to a separate SH1, undertaking amendment/close-out/referencing appropriate). GOC© of documentation BP Exploration 1989 - 2001 All Rights Reserved (as SUBJECT: 1.7.2 GUIDANCE ON CERTIFICATION SECTION 1.0 GOC© AMERICAS EDITION REVISION: 1 SYSTEM PRINCIPLES PAGE: 50 Flowcharts The remaining pages of this section contain the following flowcharts: a) Flowchart 1.7.3 Handover Sequence of Events (Off-site) b) Flowchart 1.7.4 Handover Sequence of Events (On-site) c) Flowchart 1.7.5 Handover Change Request. GOC© BP Exploration 1989 - 2001 All Rights Reserved SUBJECT: GUIDANCE ON CERTIFICATION SECTION 1.0 GOC© AMERICAS EDITION REVISION: 1 PAGE: 51 SYSTEM PRINCIPLES Handover Certification Pack (HCP) Off-site Preparation Flowchart 1.7.3 BOD/Scope of Work Raised by the Design / Maintenance Authority Construction / Maintenance Authority Set System Limits and Mark-Up Drawings Allocate SH1 Handover No. (Mnemonics) PP1 & PP1 duration (Where appropriate) Construction / Maintenance Engineers Generate I&T Requirements Commissioning Discipline Engineers Generate I&T Requirements Certification Administrator Complies approved HCP Certification Administrator Transmits the HCP To Site GOC© BP Exploration 1989 - 2001 All Rights Reserved SUBJECT: GUIDANCE ON CERTIFICATION SECTION 1.0 GOC© AMERICAS EDITION REVISION: 1 PAGE: 52 SYSTEM PRINCIPLES Handover Certification Pack (HCP) On-site Review and Acceptance Flowchart 1.7.4 ` Is the work scope for an existing Operating Facility? YES Operations to issue an SS1 Certificate prior to any work commencing within the SH1 Handover Limit NO Works Progressed to MC1 Status HCP Updated Certification Management System Reviewed and Update (As Appropriate) Construction/Maintenance Authority sign off MC1 HCP offered to Commissioning Authority Commissioning Authority to Review HCP and signs MC1 when acceptable Certification Management System Reviewed and Update (As Appropriate) Commissioning Authority Progresses Works/Handover to SH1 Status Commissioning Authority Progresses HCP and signs SH1 – HCP offered to the Operator Certification Management System Reviewed and Update (As Appropriate) Operating Authority Reviews HCP and signs SH1 as appropriate Certification Management System Reviewed and Update (As Appropriate) GOC© BP Exploration 1989 - 2001 All Rights Reserved GUIDANCE ON CERTIFICATION SECTION 1.0 GOC© AMERICAS EDITION REVISION: 1 SUBJECT: PAGE: 53 SYSTEM PRINCIPLES Handover Change Request (HCR) Flowchart 1.7.5 HCR Raised by originator Refer to section 5 HCR Transmitted to The Appropriate Authority Approved HCR Reviewed by Approving Authority Not Approved HCR Return to originator with explanation of rejection Limits and/or Data Amended on Drawings and DIS / ITS Plan updated to cover limit HCR Updated Changes to DIS / I&T Plan implimented GOC© BP Exploration 1989 - 2001 All Rights Reserved GUIDANCE ON CERTIFICATION SECTION 1.0 GOC© AMERICAS EDITION REVISION: 1 SUBJECT: SYSTEM PRINCIPLES EXHIBIT 1 STANDARD FORMS Form No. Title HCR Handover Change Request SS1 System Safe Certificate MC1 Mechanical Completion Certificate PL1 Punch List SH1 System Handover Certificate PP1 Plant Performance Certificate NP1 Non-Performance Certificate GOC© BP Exploration 1989 - 2001 All Rights Reserved PAGE: 54 SH1 No: FORM HCR Work Pack No: HCR Number: Discipline: HANDOVER CHANGE REQUEST (HCR) From : SITE: PLEASE NAME OFFICE CONTACT BELOW : Date : To : DESCRIPTION & REASON FOR CHANGE: Marked-up copies of P&ID's / Block Diagrams / DIS/ITS Print-out(s) detailing proposed Limit and/or Data Change - include all SH1/MC1 No(s) affected. IS THIS CHANGE THE RESULT OF AN EQ? * YES/NO IF 'YES' STATE EQ REF : * APPROVED / NOT APPROVED (* DELETE AS APPROPRIATE ) MAINTENANCE/CONSTRUCTION: COMMISSIONING: AUTHORITY AUTHORITY DATE : DATE : COMMENTS : CHANGE IMPLEMENTED BY : ____________________________ GOC© DATE : ____________________ BP Exploration 1989 – 2001 All Rights Reserved Americas REV. 1 Project Title FORM SS1 (SIDE 1) SH1 Number: Maintenance No: Work Pack No: SYSTEM SAFE CERTIFICATE SITE: HANDOVER TITLE: MC1 APPLICABLE *YES/NO MC1 CERTIFICATE No(s): FOR SAFE SYSTEM OF WORK CONTROL MEASURES SEE THE REVERSE SIDE OF THIS FORM HANDOVER INCLUDES: * ATTACH MARKED-UP DRAWINGS OF LIMITS OF SYSTEM / EQUIPMENT HANDOVER EXCLUDES: OPERATING AUTHORITY HEREBY CONFIRMS THAT THE ABOVE SYSTEM AS DEFINED HAS BEEN ISOLATED AND ALL NECESSARY TESTS AND PRECAUTIONS CARRIED OUT IN READINESS FOR SAFE WORK WITHIN THE BOUNDARY LIMITS OF THE ISOLATION. SIGNED ____________________________________________ DATE _______________________________ CONSTRUCTION / MAINTENANCE / COMMISSIONING ACCEPTANCE AUTHORITY HEREBY ACCEPTS THE SYSTEM AS DEFINED SUBJECT TO THE RESPONSIBILITIES/LIMITATIONS AS SHOWN ON THE CONTROL MEASURES REFERENCED OVERLEAF. SIGNED ____________________________________________ DATE _______________________________ * Delete as Appropriate GOC© BP Exploration 1989 - 2001 All Rights Reserved DOUBLE SIDED FORM Americas Rev. 1 SSOW CONTROL MEASURES SH1 NUMBER: OPERATING AUTHORITY AREA AUTHORITY OR DELEGATE STAGE 2 RISK ASSESSMENT (APPLICABLE *YES/NO) STAGE 2 RA No:___________________________ SIGNED: DATE: ISOLATION CONFIRMATION (APPLICABLE *YES/NO) ICC No: ___________________________ SIGNED: DATE: SYSTEM FLUSH / PURGE / CLEAN SYSTEM FLUSHED / PURGED / CLEANED (APPLICABLE *YES/NO) SIGNED: DATE: ISOLATION MONITORING DOUBLE BLOCK & BLEED MONITORING IN PLACE (APPLICABLE *YES/NO) SIGNED: DATE: OTHER CONDITIONS / PROCEDURES HANDOVER INCLUDES WORKSITE WORKSITE IN A CLEAN AND SAFE CONDITION SIGNED: DATE: SERVICES INSULATION / SCAFFOLDING COMPLETION SIGNED: * Delete as Appropriate DATE: GOC© BP Exploration 1989 - 2001 All Rights Reserved DOUBLE SIDED FORM Americas Rev. 1 Project Title: FORM MC1 (SIDE 1) MC1 Number: Maintenance No: Work Pack No: MECHANICAL COMPLETION CERTIFICATE SITE: HANDOVER TITLE : NOTE: FOR PUNCH LIST REFERENCE NUMBER(S) SEE THE REVERSE SIDE OF THIS FORM HANDOVER INCLUDES : HANDOVER EXCLUDES : CONSTRUCTION/MAINTENANCE AUTHORITY I HEREBY CONFIRM THAT THE ABOVE SYSTEM AS DEFINED, HAS BEEN CONSTRUCTED, INSTALLED, MAINTAINED AND TESTED IN FULL ACCORDANCE WITH DESIGN DRAWINGS, AND/OR MAINTENANCE SCHEDULES. SIGNED ____________________________________________ DATE _______________________________ COMMISSIONING AUTHORITY I HEREBY ACCEPT THE SYSTEM AS DEFINED SUBJECT TO THE RESPONSIBILITIES / LIMITATIONS AS SHOWN ON THE PUNCH LISTS REFERENCED OVERLEAF. SIGNED ____________________________________________ DATE _______________________________ GOC© BP Exploration 1989 - 2001 All Rights Reserved DOUBLE SIDED FORM Americas Rev. 1 SCOPE COMPLETION CONSTRUCTION/MAINTENANCE PERFORMING AUTHORITY MC1 NUMBER: MECHANICAL STRUCTURAL COMPLETION (APPLICABLE *YES/NO) PUNCH LIST No:___________________________ SIGNED: DATE: MECHANICAL COMPLETION (APPLICABLE *YES/NO) PUNCH LIST No:___________________________ SIGNED: DATE: PIPING COMPLETION (APPLICABLE *YES/NO) PUNCH LIST No:___________________________ SIGNED: DATE: CONTROL INSTRUMENT COMPLETION (APPLICABLE *YES/NO) PUNCH LIST No:___________________________ SIGNED: DATE: FIRE & GAS COMPLETION (APPLICABLE *YES/NO PUNCH LIST No:___________________________ SIGNED: TELECOMS COMPLETION DATE: (APPLICABLE *YES/NO) PUNCH LIST No:___________________________ SIGNED: DATE: ELECTRICAL ELECTRICAL COMPLETION (APPLICABLE *YES/NO) PUNCH LIST No:___________________________ SIGNED: DATE: CIVIL (Including Architectural) CIVIL COMPLETION (APPLICABLE *YES/NO) PUNCH LIST No:___________________________ SIGNED: DATE: PROTECTIVE COATINGS (Including Insulation) PAINTING/COATING & (APPLICABLE *YES/NO) INSULATION COMPLETION PUNCH LIST No:___________________________ SIGNED: DATE: *Delete as Appropriate GOC© BP Exploration 1989 - 2001 All Rights Reserved DOUBLE SIDED FORM Americas Rev. 1 Project Title: Maintenance No: Work Pack No: SH1 No: MC1 No: PUNCH LIST RAISED BY: PERFORMING BODY DISCIPLINE SHT OF LOCATION: CLEARANCE BODY * VENDOR/CONTRACTOR VEN * CONSTRUCTION CON * COMMISSIONING COM * MAINTENANCE MTN ITEM No SITE: PUNCH LIST NUMBER PUNCH LIST FORM * OPERATING FORM PL1 DATE PRINT NAME SIGNATURE OPS DESCRIPTION EST. HRS. MAT. REQ No CAT CLEARANCE BODY DATE CLEARED SIGNED NOTES: 1. OUTSTANDING PAINTING/HEAT TRACING AND INSULATION TO BE RECORDED ON A UNIQUE PUNCH LIST FOR PAINTING/HEAT TRACING WITHIN THE LIMITS OF THIS HANDOVER. CATEGORIES: 'A' ITEMS TO BE REPAIRED, COMPLETED OR CORRECTED BEFORE THE EQUIPMENT CAN BE SAFELY OPERATED 'B' ITEMS THAT CAN BE REPAIRED, COMPLETED OR CORRECTED AT A LATER DATE AND WHICH ALLOWS THE EQUIPMENT TO BE COMMISSIONED/OPERATED WITHOUT JEOPARDIZING PLANT OR PERSONNEL *Delete as Appropriate GOC© BP Exploration 1989 - 2001 All Rights Reserved Americas Rev. 1 Project Title: FORM SH1 (SIDE 1) SH1 Number: Maintenance No: Work Pack No: SYSTEM HANDOVER CERTIFICATE SITE: HANDOVER TITLE : MC1 APPLICABLE *YES/NO MC1 CERTIFICATE No(s): NOTE: FOR PUNCH LIST REFERENCE NUMBER(S) SEE THE REVERSE SIDE OF THIS FORM HANDOVER INCLUDES : HANDOVER EXCLUDES : COMMISSIONING AUTHORITY I HEREBY CONFIRM THAT THE ABOVE SYSTEM AS DEFINED HAS BEEN COMMISSIONED AND ALL NECESSARY TESTS CARRIED OUT IN READINESS FOR SAFE CONTINUOUS OPERATION. SIGNED ____________________________________________ DATE _______________________________ OPERATING ACCEPTANCE AUTHORITY I HEREBY ACCEPT THE SYSTEM AS DEFINED AND SUBJECT TO THE RESPONSIBILITIES / LIMITATIONS BEING COMPLETE AS DEFINED ON THE PUNCH LIST(S) REFERENCED OVERLEAF. SIGNED ____________________________________________ * Delete as Appropriate GOC© DATE _______________________________ BP Exploration 1989 - 2001 All Rights Reserved DOUBLE SIDED FORM Americas Rev. 1 SCOPE COMPLETION COMMISSIONING / OPERATIONS AUTHORITY SH1 NUMBER: MECHANICAL STRUCTURAL COMPLETION (APPLICABLE *YES/NO) PUNCH LIST No:___________________________ SIGNED: DATE: MECHANICAL COMPLETION (APPLICABLE *YES/NO) PUNCH LIST No:___________________________ SIGNED: DATE: PIPING COMPLETION (APPLICABLE *YES/NO) PUNCH LIST No:___________________________ SIGNED: DATE: CONTROL INSTRUMENT COMPLETION (APPLICABLE *YES/NO) PUNCH LIST No:___________________________ SIGNED: DATE: FIRE & GAS COMPLETION (APPLICABLE *YES/NO) PUNCH LIST No:___________________________ SIGNED: TELECOMS COMPLETION DATE: (APPLICABLE *YES/NO) PUNCH LIST No:___________________________ SIGNED: DATE: ELECTRICAL ELECTRICAL COMPLETION (APPLICABLE *YES/NO) PUNCH LIST No:___________________________ SIGNED: DATE: CIVIL (Including Architectural) CIVIL COMPLETION (APPLICABLE *YES/NO) PUNCH LIST No:___________________________ SIGNED: DATE: PROTECTIVE COATINGS (Including Insulation) PAINTING/COATING & (APPLICABLE *YES/NO) INSULATION COMPLETION PUNCH LIST No:___________________________ SIGNED: DATE: * Delete as Appropriate GOC© BP Exploration 1989 - 2001 All Rights Reserved DOUBLE SIDED FORM Americas Rev. 1 Project Title: FORM PP1 (SIDE 1) SH1 Number (s) : Maintenance No: Work Pack No: PLANT PERFORMANCE CERTIFICATE SITE: TITLE : PLANT PERFOMANCE DURATION: PLANT PERFORMANCE COVERS THE FOLLOWING SYSTEM(s) : NON-PERFOMANCE REPORT (NP1) ATTACHED * YES / *NO NP1 No : ENGINEERING AUTHORITY HEREBY CONFIRMS THAT THE FACILITY PLANT PERFORMANCE TEST(s) AS DEFINED, ARE IN ACCORDANCE WITH DESIGN AND VENDOR REQUIREMENTS, SPECIFICATIONS AND DRAWINGS AND MEET THE EXPECTATIONS OF DESIGN CRITERIA AND INTENDED PURPOSE. SIGNED ___________________________________________ DATE _____________________________ COMMISSIONING AUTHORITY HEREBY CONFIRMS THAT THE FACILITY PLANT PERFORMANCE TEST(s) ARE COMPLETE, AND ARE IN ACCORDANCE WITH THE PERFORMANCE STANDARDS AND SPECIFICATIONS AND MEET THE EXPECTATIONS OF DESIGN CRITERIA AND INTENDED PURPOSE. SIGNED ___________________________________________ DATE _____________________________ OPERATIONS AUTHORITY HEREBY ACCEPTS THE FACILITY PLANT PERFORMANCE TEST(s) AS DEFINED, MEET THE EXPECTATIONS OF THE DESIGN CRITERIA AND INTENDED PURPOSE, AND ASSUMES RESPONSIBILITY FOR MAINTAINING THE TECHNICAL INTEGRITY AND DESIGN CRITERIA OF THE PLANT. SIGNED ___________________________________________ DATE _______________________________ * Delete as Appropriate GOC © BP Exploration 1989 - 2001 All Rights Reserved Americas Rev. 1 Project Title: FORM NP1 SH1 Number (s) : Maintenance No: Work Pack No: NON-PERFORMANCE CERTIFICATE EQUIPMENT No : SITE: EQUIPMENT DESCRIPTION : SYSTEM : LOCATION : COMMISSIONING PROCEDURE No(s) : PLANT PERFOMANCE DURATION: Report: USE CONTINUATION SHEET IF REQUIRED COMPLETED BY APPROVED BY COMPANY SIGNATURE PRINT NAME DATE * Delete as appropriate GOC© BP Exploration 1989 - 2001 All Rights Reserved Americas Rev. 1 GUIDANCE ON CERTIFICATION GOC © AMERICAS EDITION SUBJECT: SYSTEM PRINCIPLES - APPENDICES APPENDIX 1.0 Operations System Mnemonics Matrix Example GOC© BP Exploration 1989 – 2001 All Rights Reserved SECTION 1 REVISION: 1 PAGE: i SYSTEM MNEMONICS – MILNE POINT SH1 NUMBER Example C 22 2 0 C 9 9 9 SEQUENTIAL NUMBER PRIMARY SYSTEMS LOCATION A A-PAD HANDOVER TYPE IDENTIFIER SECONDARY SYSTEM DESCRIPTION 0 WELLPADS & WELLS 1 CONSTRUCTED/COMMISSIONED C DESTRUCT D B B-PAD C C-PAD E E-PAD LIQUID SEP./PUMPING 2 F F-PAD GAS SYSTEMS 3 G G-PAD WATER SYSTEMS 4 H PAD I I-PAD FLARE/RELIEF 5 6 J J-PAD SAFETY / ESD SYSTEMS K K-PAD DRILLING SYSTEMS 7 L L-PAD UTILITIES 8 X CFP STRUCTURAL 9 PRIMARY SYSTEM 1 (LISTED UNDER RESPECTIVE PRIMARY SYSTEM) PRIMARY SYSTEM 2 (WELL PADS & WELLS) PRIMARY SYSTEM 3 TEMPORARY T RE-INSTATEMENT/REFURBISHMENT R SHUTDOWN DEPENDENT S EQUIPMENT OUTAGE E PRIMARY SYSTEM 4 PRIMARY SYSTEM 5 (GAS SYSTEMS) (WATER SYSTEMS) (FLARE / RELIEF) ASSOCIATED SECONDARY SYSTEMS ASSOCIATED SECONDARY SYSTEMS ASSOCIATED SECONDARY SYSTEMS (LIQUID SEPARATION) ASSOCIATED SECONDARY SYSTEMS ASSOCIATED SECONDARY SYSTEMS 1ST STG / G-LIFT DRIVE TRAIN 1 1ST STG / G-LIFT DRIVE TRAIN 2 2ND / 3RD STG DRIVE TRAIN 1 2ND / 3RD STG DRIVE TRAIN 2 1ST STG COMP TRAIN 1 1ST STG COMP TRAIN 2 1ST STG COMMON EQUIP. 2ND STG COMP TRAIN 1 01 02 03 04 11 12 13 21 WATER GENERAL SOURCE WATER GENERAL SOURCE WATER DEGASSING A-PAD/CFP SOURCE WATER B-PAD/CFP SOURCE WATER PROD WATER GENERAL PROD WATER COLLECTION 08 2ND STG COMP TRAIN 2 22 PROD WATER DEOILING 00 10 11 12 13 20 21 22 23 09 10 2ND STG COMMON EQUIP. 3RD STG COMP TRAIN 1 23 PROD WATER FILTRATION 24 PROD WATER BACKWASH 25 3RD STG COMP TRAIN 2 3RD STG COMMON EQUIP. DESANDING SYSTEM L-PAD TO C TO CFP 6” P/LINE 11 12 31 32 33 WATER INJ GENERAL 26 30 41 L-PAD TO C-PAD 14” P/LINE 13 41 WATER INJ SURGE DRUM 31 SLUG CATCHER 1ST STAGE 20 42 WATER INJ BOOSTER PUMP 32 ESP MODULE 50 51 GAS LIFT COMP TRAIN 1 GAS LIFT COMP TRAIN 2 HEATER COMMON 30 GAS LIFT COMMON EQUIP. 43 33 TEST SEP MODULE 52 HEATER TRAIN 1 31 HYDRAULIC MODULE PAD HV POWER 53 HEATER TRAIN 2 50 51 2ND STAGE SEP TRAIN 1 GAS INJ COMP TRAIN ‘A’ 2ND STAGE SEP TRAIN 2 42 GAS INJ COMP TRAIN ‘B’ 60 61 CFP TO E-PAD 4” WATER INJ PAD LV POWER 60 61 32 41 GAS DEHYDRATION GLYCOLREGENERATION WATER INJ PUMPING CFP TO B-PAD 8’ WATER INJ CFP/C P/L TO T-14 WATER INJ 37 PAD 24 V UPS / BATTERIES 62 3RD STAGE SEP TRAIN 1 GAS INJ COMP ‘C’ PAD 62 T-14 / I-PAD 6’ WATER INJ LAUNCHER / RECEIVERS PAD UTILITIES 70 80 81 3RD STAGE SEP TRAIN 2 51 52 CFP TO ‘B’ PAD 6’ G-LIFT 63 C-PAD TO L-PAD 6” WATER INJ 38 39 60 B-PAD TO D-PAD 4” G-LIFT 64 CONTROL ROOMS & PANELS 96 CFP TO C-PAD 6” GAS LIFT 65 MULTICOR CABLES 97 82 EXPORT PIPELINE 70 80 CFP TO E-PAD 3” GAS INJ 66 83 84 OIL RESERVE TANKS 81 C-L-F 8” GAS INJ CONTROL ROOMS & PANELS MULTICORE CABLES COMMON PIG LAUNCHER CONTROL ROOMS & PANELS CHEMICAL INJECTION 85 86 96 97 67 70 PROD FLUID HEATING 87 IWAG START-UP AIR 88 B-PAD TO CFP 14” P/LINE 00 C-PAD TO CFP 14” P/LINE D-PAD TO B-PAD 14” P/LINE E-PAD TO CFP 14” P/LINE E-PAD TO CFP 4” P/LINE F-PAD TO L-PAD 14” P/LINE G-PAD TO CFP 10”/14” P/LINE G-PAD TO H-PAD 3” TEST I-PAD TO J/G 8” P/LINE 01 02 03 04 05 06 07 10 20 J-PAD TO G-PAD 8” P/LINE 30 K-PAD TO E-PAD 14” P/LINE 40 PAD WATER INJ PUMPING PAD HEATERS PADS / WELLS / FLOWLINES ESP WELLS GAS INJECTION WELLS GAS LIFT WELLS PRODUCTION WELLS WATER INJECTION WELLS SOURCE WATER WELLS WAG WELLS SAND INJECTION WELLS 00 01 02 03 04 05 06 PRODUCTION HEADER TEST HEADER / SEP GAS INJ HEADER WATER INJ HEADER INSTRUMENT AIR FUEL GAS CLOSED DRAIN OPEN DRAIN ATMOSPHERIC VENT LETTER POWER 07 08 DIESEL FUEL 89 CENTRAL HYDRAULICS CONTROL ROOM / PANELS MULTICORE CABLES 90 J-PAD TO I TO H 3” P/LINE EXPORT COOLERS / PUMPS OIL METERING MULTICORE CABLES PROD WATER DEGASSING CFP TO C-PAD 8’ WATER INJ FLARE SYSTEM GENERAL RELIEF HEADER ATMOSPHEREIC VENT FLARE IGNITION FLARE ASSIST GAS CONTROL ROOM/PANELS MULTICORE CABLES 00 10 20 30 40 96 97 34 35 36 96 97 96 97 PRIMARY SYSTEM 0 PRIMARY SYSTEM 6 PRIMARY SYSTEM 7 PRIMARY SYSTEM 8 PRIMARY SYSTEM 9 (SAFETY / ESD) (DRILLING SYSTEM) (UTILITIES) (STRUCTURAL) (POWER) ASSOCIATED SECONDARY SYSTEMS ASSOCIATED SECONDARY SYSTEMS ASSOCIATED SECONDARY SYSTEMS ASSOCIATED SECONDARY SYSTEMS ASSOCIATED SECONDARY SYSTEMS 10 CONTROL ROOM / PANELS 96 SERVICE WATER 10 LIFE SUPPORT FACILITY 01 POWER GENERATION 10 FIRE & GAS 20 MULTICORE CABLES 97 OF QUARTERS FACILITY 11 GF GARAGE FACILITY MV MAINS DISTRIBUTION 12 DELUGE 40 INERT GAS 12 13 02 03 HV MAINS DISTRIBUTION 30 UTILITY AIR INSTRUMENT AIR 11 FIREWATER WAREHOUSE FACILITY 23 LV MAINS DISTRIBUTION HVAC (MODULE) 50 JET WATER 14 AUXILARY INJ MODULE 47 STANDBY GENERATOR 14 INTEGRATED CONTROL SYSTEM 90 POTABLE WATER 15 53 STANDBY GEN DISTRIBUTION 15 NETWORKS ESD 13 91 DIESEL 16 PRODUCTION SEP MODULE FLUID INJ MODULE 54 UPS SYSTEM COMMUNICATIONS 92 GASOLINE 17 GAS COMPRESSION MODULE 55 MOD 68 GENERATION 16 17 CONTROL ROOM / PANELS 96 COMPRESSOR LUBE OIL 18 POWER GEN. MODULE 56 CONTROL ROOMS & PANELS 96 MULTICORE CABLES 97 FUEL GAS 20 UTILITIES MODULE 57 MULTICORE CABLES 97 METHANOL STORAGE 30 PIPELINE MODULE 58 METHANOL INJ 31 STORAGE & PUMP MODULE 61 35 FLARE MODULE 62 POUR POINT DEPRESSANT 39 GENERAL ROADS & PADS 70 DEFORMER INJ 40 BRIDGES & CULVERTS 71 POLY-ELECTROLYTE INJ 41 CORROSION INHIBITOR 42 BIOCIDE INJECTION 43 SCALE INHIBITOR 44 CHEMICAL INJ GENERAL DE-EMULSIFIER INJECTION 46 OXY SCAVENGER INHIBITOR 47 SEQUESTERING AGENT INHIBITOR 48 DETERGENT INHIBITOR 49 COOLING HEATING MEDIUM 50 DRAINS GENERAL June 2001 / 02 45 COAGULANT INJECTION 60 CLOSED DRAIN 61 OPEN DRAIN 62 SLOP OIL 63 WASTE DISPOSAL 64 GLYCOL STORAGE 70 HVAC (ACCOMODATION) 80 MODULE SPACE HEATING 81 CONTROL ROOM & PANELS 96 MULTICORE CABLES 97 SYSTEM MNEMONICS - SALTEND HANDOVER NUMBER Example P I P S S T 1 0 0 0 SEQUENTIAL NUMBER (XXXX) PRIMARY SYSTEMS (P) PLANT IDENTIFIER (PI) ID LETTERS VAM/ETAC (COMMON OFFSITES) VAM ETAC IOS TSEP HULL SITE CO VA EA IO TS HS SECONDARY SYSTEM (SS) UTILITES 1 STRUCTURES 2 RAW MATERIALS & PRODUCTS 3 SPARE 4 SPARE 5 CONTROL & INSTRUMENT (SAFETY SYSTEMS) 6 ETAC PROCESS 7 VAM PROCESS 8 ELECTRICAL 9 HANDOVER TYPE IDENTIFIER (T) (LISTED UNDER RESPECTIVE PRIMARY SYSTEM) DESCRIPTION LETTER CONSTRUCTED/COMMISSIONED C DESTRUCT D TEMPORARY T RE-INSTATEMENT/REFURBISHMENT R SHUTDOWN DEPENDANT S EQUIPMENT OUTAGE E PRIMARY SYSTEM 1 (UTILITIES) ASSOCIATED SECONDARY SYSTEMS WATER - TOWNS - PROCESS - COOLING 110 111 112 STEAM - HP IP LP LLP STREAM TRACING 120 121 122 123 124 CONDENSATE - HP IP LP LLP 130 131 132 133 PRIMARY SYSTEM 2 200 RAW MATERIALS & PRODUCTS PRIMARY SYSTEM 6 - TANKER EXPORT - FLARE FIREWATER ROAD LOADING EFFLUENT PIT 150 151 152 153 ASSOCIATED SECONDARY SYSTEMS ESD LOGIC 600 DCS LOGIC 601 CONTROL SCHEMES 602 PACKAGE CONTROLS 603 CONTROL & MARSHALLING PANELS 604 MULTI CORE CABLES 605 ETAC PROCESS ASSOCIATED SECONDARY SYSTEMS ASSOCIATED SECONDARY SYSTEMS 300 301 302 303 304 305 306 307 308 309 310 311 PRIMARY SYSTEM 9 PRIMARY SYSTEM 8 (PLATFORM FABRIC) (VAM PROCESS) ASSOCIATED SECONDARY SYSTEMS ASSOCIATED SECONDARY SYSTEMS - PARENT 700 - PARENT 800 - REACTION 710 - REACTION 810 - DISTILLATION 720 - DISTILLATION 820 - CHEMICAL HANDLING 740 - BENEFIELD UNIT 830 - HEAVY ENDS 840 - CHEMICAL HANDLING 850 ANCILLARIES VAM PROCESS n HYDRAULIC SYSTEMS 80 n CONTROL ROOMS/PANELS n MULTICORE CABLES 96 97 n HEAT TRACING/INSULATION/CLAD 98 99 n COMMON ANCILLARIES ARE COMMON TO PRIMARY SYSTEMS 1 - 8 January 2001 / 01 (SPARE) (SPARE) PRIMARY SYSTEM 7 ASSOCIATED SECONDARY SYSTEMS PRIMARY SYSTEM 5 PRIMARY SYSTEM 4 PARENT ETHYLENE OXYGEN ACETIC ACID VAM ACETALDEHYDE STREAM HEAVY ORGANICE SECONDARY PRODUCT LIGHT ORGANICE SECONDARY PRODUCT ETAC PRODUCT VAM PRODUCT GAS EXPORT STREAMS POTASSIUM HYDROXIDE CLOSED DRAIN / OFF SPEC TANK (ETAC PROCESS) - 140 141 142 143 144 145 ASSOCIATED SECONDARY SYSTEMS (CONTROL & INSTRUMENTS SAFETY SYSTEMS) CONTROL & INSTRUMENTS PLANT AIR INSTRUMENT AIR SPARE HP NITROGEN LP NITROGEN NATURAL GAS PRIMARY SYSTEM 3 ASSOCIATED SECONDARY SYSTEMS - PARENT - (RAW MATERIALS & PRODUCTS) (STRUCTURES) STRUCTURES GASEOUS UTILITIES ELECTRICAL - 33 kV POWER 3.3 kV POWER 415 V POWER FIRE DETECTION & ALARMS GAS DETECTION & ALARMS LIGHTING SMALL POWER HEAT TRACING 900 901 902 903 904 905 906 907 SYSTEM MNEMONICS - BRUCE HANDOVER NUMBER Example B R U 2 1 2 C 9 9 9 9 SEQUENTIAL NUMBER FACILITY IDENTIFIER BRUCE BRU PRIMARY SYSTEMS SECONDARY SYSTEM HANDOVER TYPE IDENTIFIER LETTER WELLS 1 LIQUID STABILISATION, PUMPING & EXPORT 2 CONSTRUCTED/COMMISSIONED C GAS COMPRESSION, CONDITIONING, LIFT. RE-INJECTION & EXPORT 3 DESTRUCT D DESCRIPTION (LISTED UNDER RESPECTIVE PRIMARY SYSTEM) 4 WATER SYSTEMS 5 FLARE AND VENT SYSTEMS TEMPORARY T RE-INSTATEMENT/REFURBISHMENT R SHUTDOWN DEPENDENT S EQUIPMENT OUTAGE E 6 SAFETY SYSTEMS DRILLING SYSTEMS 7 UTILITIES 8 PLATFORM FABRIC 9 PRIMARY SYSTEM 1 (WELLS) ASSOCIATED SECONDARY SYSTEMS PLATFORM PLATFORM WELL WELL SLOT WELL --A22 --A09 A01 A06 --- A1 B1 B2 B3 A20 --- A14 A8 A17Y A12Z A10Y --A24 A08 ----- A2 A3 A4 A5 A6 A7 SLOT WELL C1 C2 C3 C4 C5 C6 --A23 C7 C8 A03 A16Z A18 A05 ----- B4 B5 B6 B7 B8 WAD PLATFORM PLATFORM SLOT KEITH WELL SLOT D1 D2 B01 B04Y M2 A04 A07 A02 A11 D3 D4 D5 D6 B02Z B03Z B06 B05 M3 M4 M5 M6 ----- D7 D8 SLOT WELL M1 SLOT K1 K2 M7 M8 -- PRIMARY SYSTEM 2 PRIMARY SYSTEM 3 PRIMARY SYSTEM 4 PRIMARY SYSTEM 5 (LIQUID STABILISATION, PUMPING & EXPORT) (GAS SYSTEMS) (WATER SYSTEMS) (FLARE AND VENT SYSTEMS) ASSOCIATED SECONDARY SYSTEMS ASSOCIATED SECONDARY SYSTEMS ASSOCIATED SECONDARY SYSTEMS ASSOCIATED SECONDARY SYSTEMS n H.P. HYDROCYCLONES n L.P. HYDROCYCLONES 01 HP FLARE 02 LP FLARE ATMOSPHERIC VENT 10 20 30 20 MAINTENANCE VENT 40 30 FLARE IGNITION 50 H.P. GAS CONDENSATE TEST MANIFOLD 00 L.P. COMPRESSOR 10 DE-OILING M.P. GAS CONDENSATE TEST MANIFOLD STATFJORD TEST MANIFOLD 01 02 M.P. COMPRESSOR A M.P. COMPRESSOR B 20 21 DE-GASSING 10 M.P. GAS CONDENSATE PRODUCTION MANIFOLD A 03 M.P. COMPRESSOR C 22 WATER INJECTION M.P. GAS CONDENSATE PRODUCTION MANIFOLD B STATFJORD OIL PRODUCTION MANIFOLD 04 05 DEHYDRATION TRAIN A DEHYDRATION TRAIN B 30 31 PRODUCED WATER REINJECTION KEITH PRODUCTION MANIFOLD 06 GLYCOL REGENERATION A H.P. SEPARATOR TRAIN A 10 GLYCOL REGENERATION B 32 33 H.P. SEPARATOR TRAIN B EXPORT COMPRESSOR A 40 PUQ TEST SEPARATOR 11 12 EXPORT COMPRESSOR B 41 L.P. SEPARATOR TRAIN A L.P. SEPARATOR TRAIN B 13 14 CR SLUG CATCHER 15 EXPORT COMPRESSOR C WARM UP HOT GAS GAS RE-INJECTION GAS FISCAL METERING 42 43 50 60 70 CR TEST SEPARATOR 16 MOL BOOSTER PUMP A 20 GAS EXPORT PIPELINE MOL BOOSTER PUMP B MOL BOOSTER PUMP C 21 22 GAS REINJECTION PIPE LINE 81 KEITH GAS LIFT MANIFOLD 90 MOL PUMP A 30 MOL PUMP B MOL PUMP C 31 32 LIQUID FISCAL METERING LIQUID EXPORT PIPE LINE 40 50 WAD TEST PIPE LINE WAD PRODUCTION PIPE LINE 60 70 PRIMARY SYSTEM 6 PRIMARY SYSTEM 7 (SAFETY SYSTEMS) ASSOCIATED SECONDARY SYSTEMS EVACUATION SYSTEMS PLATFORM CONTROLS EMERGENCY POWER FIRE PROTECTION (ACTIVE) n HELIDECK n LIFEBOATS n OTHER ESCAPE ACCOMODATION PLANT VENTILATION 01 02 MUD MIXING - ACTIVE AND RESERVE 03 FLUIDS n INDUSTRIAL WATER n POTABLE WATER n PLANT AIR n INSTRUMENT AIR MUD MIXING - DEGASSING/DESANDING 04 MUD PUMPS 05 n FIRE & GAS 12 RIG UTILITIES n TELECOMS n GENERAL ADDRESS 13 14 CEMENTER UNIT 06 07 CUTTINGS RE-INJECTION 08 n PLATFORM ADDRESS 15 WELL SERVICES EQUIPMENT n NAVAIDS 09 16 n WASH WATER n INTEGRATED CONTROLS 17 CHEMICALS n DEMULSIFIER n CONTROL NETWORKS 18 n COMMUNICATIONS 19 n CR MCS 20 n POWER GENERATION n POWER DISTRIBUTION 21 n UPS / BATTERIES n FIRE PUMPS n FIRE LOOP 23 31 n n n n n 09 n CORROSION INHIBITOR n SCALE INHIBITOR n n n n n 22 32 33 INERT GAS SEAWATER DIESEL FUEL GAS SPARE NUMBER OXYGEN SCAVENGER CHLORINATION BIOCIDE HYDRATE REMOVER/INHIB ANTIFOAM 11 COMMS 12 13 SANITARY 19 n WAX INHIBITOR 20 21 n SPARE NUMBER 22 35 n HAZARDOUS OPEN DRAINS n DELUGE n COATINGS 38 n FIREWALLS 42 n TEMPORARY REFUGE 51 n HVAC 52 n MEDICAL SUITE 53 n HOTEL FACILITIES 54 n DIRAVENT SYSTEMS 61 n BLOW-OUT PANELS PERSONNEL PROTECTION n B.A. SETS n SURVIVAL SUITS 42 51 n NETWORKS n SEWAGE 52 61 18 n POLYELECTROLYTE n HALON n SPRINKLER n EXTINGUISHERS 36 37 n COOLING MEDIUMS n TELEPHONES 71 14 HELICOPTER n HELICOPTER REFUELING 81 n MATERIAL HANDLING 15 SUPPORT FACILITY AND LIFTING 16 EQUIPMENT n WORKSHOP/LABORATORIES 82 17 n CLOSED DRAINS DRAINS ASSOCIATED SECONDARY SYSTEMS 00 POWER GEN n MAIN GENERATION 31 01 n HV MAIN GENERATION DIST. 32 n MV MAIN GENERATION DIST. 33 02 03 n LV MAIN GENERATION DIST. 34 n STANDBY GENERATION 04 35 05 n STANDBY GENERATION DIST. 36 n LIGHTING & SMALL POWER 37 06 n WELDING SOCKETS 38 07 n HEATING MEDIUMS 41 08 MEDIUMS 34 EXPLOSION PROTECTION n BLAST WALLS January 2001 / 01 BULK CEMENT HANDLING BULK MUD HANDLING (PLATFORM FABRIC) ASSOCIATED SECONDARY SYSTEMS n MUSTER AREAS 04 n EMERGENCY SHUTDOWN 11 n HYDRANT / MONITORS n FOAM FIRE PROTECTION (PASSIVE) (UTILITIES) ASSOCIATED SECONDARY SYSTEMS 01 02 03 PRIMARY SYSTEM 9 PRIMARY SYSTEM 8 (DRILLING SYSTEM) 23 n NON HAZARDOUS OPEN DRAINS 24 25 n STORM DRAINS 41 71 72 81 82 ANCILLARIES n HYDRAULIC SYSTEMS 80 n CONTROL ROOMS/PANELS n MULTICORE CABLES 96 97 n HEAT TRACING/INSULATION/CLAD 98 99 n COMMON D PLATFORM n MAIN MODULE (D10) n DRILLING MODULE AND DERRICK (D20) PUQ PLATFORM n LEVEL 1 & 2 (P10) n LEVEL 3, 4, 5 (P20) n FLARE STACK (P30) n ACCOMODATION (P40) D1 D2 P1 P2 P3 P4 n D TO PUQ BRIDGE (P60) P6 CR PLATFORM n MAIN MODULE n D TO CR BRIDGE C10 C40 SYSTEM MNEMONICS - FORTIES SH1 NUMBER Example A 2 1 2 C 9 9 9 9 SEQUENTIAL NUMBER PLATFORM IDENTIFIER PLATFORM PRIMARY SYSTEMS LETTER FORTIES ALPHA A FORTIES BRAVO B FORTIES CHARLIE C FORTIES DELTA D FORTIES ECHO E FORTIES UNITY U DYCE X HANDOVER TYPE IDENTIFIER SECONDARY SYSTEM DESCRIPTION LETTER PLATFORM FABRIC 0 WELLS 1 CONSTRUCTED/COMMISSIONED C M.O.L. SYSTEM 2 DESTRUCT D NGL/DGL SYSTEMS 3 UTILITIES (LISTED UNDER RESPECTIVE PRIMARY SYSTEM) TEMPORARY T RE-INSTATEMENT/REFURBISHMENT R SHUTDOWN DEPENDENT S 4 FLARE AND VENT SYSTEMS 5 PLATFORM EMERGENCY AND SAFETY SYSTEMS EQUIPMENT OUTAGE E 6 GAS LIFT SHUTDOWN G DRILLING SYSTEMS 7 NGL SHUTDOWN N IMPORT/EXPORT SYSTEMS 8 PWD SHUTDOWN P PLATFORM GENERATION 9 PRIMARY SYSTEM 1 PRIMARY SYSTEM 1 PRIMARY SYSTEM 1 PRIMARY SYSTEM 1 PRIMARY SYSTEM 1 (WELLS) (WELLS) (WELLS) (WELLS) (WELLS) ASSOCIATED SECONDARY SYSTEMS ASSOCIATED SECONDARY SYSTEMS ASSOCIATED SECONDARY SYSTEMS ASSOCIATED SECONDARY SYSTEMS ASSOCIATED SECONDARY SYSTEMS FORTIES DELTA FORTIES ECHO FORTIES ALPHA WELL WELL FORTIES BRAVO 03 4/1 SLOT 21 1/2 02 4/2 20 1/3 01 4/3 19 1/4 04 4/4 22 1/5 05 4/5 23 1/6 06 4/6 24 1/1 SLOT WELL SLOT WELL 1/1 06 4/1 1/2 1/3 2/1 09 08 07 2/1 09 5/1 27 2/3 2/2 08 5/2 26 2/4 10 2/3 07 5/3 25 2/5 11 2/4 10 5/4 28 2/6 12 2/5 11 5/5 29 3/1 15 2/6 12 5/6 30 3/1 15 6/1 33 3/2 14 6/2 32 3/3 13 6/3 31 3/4 03 SLOT 21 20 10 1/2 05 4/2 20 E2 15 1/3 04 4/3 19 E3 09 2/1 09 4/4 22 E4 04 2/2 08 4/5 23 4/6 02 27 07 24 E5 2/3 5/1 E6 08 10 27 2/4 5/2 26 E7 14 2/5 11 5/3 25 E8 07 2/6 12 5/4 28 E9 13 3/1 15 5/5 29 E10 03 3/2 14 5/6 30 E11 16 3/3 13 6/1 33 E12 12 3/4 16 6/2 32 E13 05 6/3 31 E14 01 19 4/4 22 1/4 04 4/4 22 4/5 23 1/5 05 4/5 23 4/6 24 1/6 06 4/6 24 5/1 27 5/4 5/5 25 28 29 5/6 30 08 5/2 26 2/3 07 5/3 25 2/4 10 5/4 28 2/5 11 5/5 29 2/6 12 5/6 30 3/1 15 6/1 33 6/2 32 2/2 3/3 13 6/1 33 3/2 14 3/4 16 6/2 32 3/3 13 16 3/5 17 6/3 31 3/4 16 3/5 17 3/5 17 3/6 18 3/5 17 3/6 18 3/6 18 3/6 18 HYDRAULIC SYSTEMS CONTROL ROOMS/PANELS MULTICORE CABLES HYDRAULIC SYSTEMS 80 96 HEAT TRACING/INSULATION/CLAD 97 98 COMMON 99 CONTROL ROOMS/PANELS MULTICORE CABLES HEAT TRACING/INSULATION/CLAD COMMON 99 31 HYDRAULIC SYSTEMS 80 96 97 98 6/3 HYDRAULIC SYSTEMS 80 96 CONTROL ROOMS/PANELS MULTICORE CABLES HEAT TRACING/INSULATION/CLAD 97 98 COMMON 99 CONTROL ROOMS/PANELS MULTICORE CABLES HEAT TRACING/INSULATION/CLAD COMMON PRIMARY SYSTEM 2 PRIMARY SYSTEM 3 PRIMARY SYSTEM 4 (M.O.L.SYSTEM) (NGL/DGL SYSTEMS) (UTILITIES) ASSOCIATED SECONDARY SYSTEMS ASSOCIATED SECONDARY SYSTEMS 80 96 HYDRAULIC SYSTEMS CONTROL ROOMS/PANELS MULTICORE CABLES 97 98 99 HEAT TRACING/INSULATION/CLAD COMMON BULK SEPARATOR FEED SYSTEMS 01 NGL GAS COMPRESSOR 01 TEST SEPARATOR FEED SYSTEMS 02 V16 SYSTEM 02 BULK SEPARATOR V01 BULK SEPARATOR V02 03 04 V06/V19/GLYCOL SYSTEM 03 PLANT AIR SYSTEM INSTRUMENT AIR SYSTEM 02 03 V17 SYSTEM 04 TEST SEPARATOR PRODUCTION GAS SCRUBBING 05 06 V18 SYSTEM 05 V20 GAS SCRUBBING 06 GAS LIFT MANIFOLD LP BOOSTER/TRANSFER PUMPS 07 NGL PLANT RECYCLE 07 NITROGEN SYSTEM SEAWATER DISTRIBUTION SYSTEM DIESEL DISTRIBUTION FUEL GAS DISTRIBUTION 04 05 06 07 08 RISER LIFT GAS SUPPLY (ON F A) 08 MULTIPHASE PUMP 09 GAS LIFT COMPRESSOR 10 P W COLLECTION HEADER V160 DEGASSING VESSEL 10 11 TURBINE IGNITION GAS SUPPLY DEMULSIFIER SYSTEM CORROSION INHIBITOR SYSTEM KO/UNLOADING COMPRESSOR 11 CLOSED CIRCUIT COOLING SYSTEM 12 V601 DEGASSING VESSEL 12 08 10 11 12 13 CONTROL ROOMS/PANELS PWRI 13 96 MULTICORE CABLES P W T TRAIN A (T602/W38) 14 97 P W T TRAIN B (T601/W600) 15 HEAT TRACING/INSULATION/CLAD COMMON 98 99 STAND BY HYDROCYCLONE (FA ONLY) 16 RECLAIMED OIL VESSEL V1760 (FA & FD) 17 SEAWATER INJECTION SYSTEM 20 PRODUCED WATER SANDWASH SUPPLY 30 SEAWATER SANDWASH SUPPLY 31 HYDRAULIC SYSTEMS 80 SCALE INHIBITOR SYSTEM OXYGEN SCAVENGER/BIOCIDE SYSTEM SODIUM HYPOCHLORITE SYSTEM FLOTATION AGENT SYSTEM CLOSED DRAIN SYSTEM TRI-ETHYLENE GLYCOL 01 ASSOCIATED SECONDARY SYSTEMS STANDBY GENERATION HV SWITCHBOARDS/DISTRIBUTION LV SWITCHBOARDS/DISTRIBUTION 30 HP FLARE SYSTEM 01 31 32 MP FLARE SYSTEM LP FLARE SYSTEM 02 03 LIGHTING AND SMALL POWER WELDING SOCKETS 33 34 UPS/BATTERIES NAVAIDS TELECOMMUNICATIONS ACCOMMODATION 35 36 37 40 41 LLP FLARE SYSTEM ATMOSPHERIC VENT SYSTEM MAINTENANCE VENT SYSTEM FLARE IGNITION CONTROL ROOMS/PANELS 04 05 06 07 96 MULTICORE CABLES HEAT TRACING/INSULATION/CLAD 97 98 COMMON 99 SANITARY SERVICES HVAC HELICOPTER REFUELLING DRAG REDUCING AGENT (DRG) 18 T71 AND LP DRAIN SYSTEM OPEN DRAIN SYSTEM 20 COMMON METHANOL INJECTION SYSTEM 22 16 17 50 60 70 80 96 97 98 99 21 96 MULTICORE CABLES 97 HEAT TRACING/INSULATION/CLAD COMMON 98 99 PRIMARY SYSTEM 6 PRIMARY SYSTEM 7 (IMPORT/EXPORT SYSTEMS) ASSOCIATED SECONDARY SYSTEMS ASSOCIATED SECONDARY SYSTEMS PRIMARY SYSTEM 9 PRIMARY SYSTEM 0 (PLATFORM GENERATION) (PLATFORM FABRIC) PRIMARY SYSTEM 8 (DRILLING SYSTEM) (PLATFORM EMERGENCY AND SAFETY SYSTEMS) ASSOCIATED SECONDARY SYSTEMS ASSOCIATED SECONDARY SYSTEMS ASSOCIATED SECONDARY SYSTEMS PACKAGE 1 SWITCHGEAR 01 PACKAGE 2 MOL 02 PACKAGE 3 WELLHEADS 03 04 PACKAGE 4 DRILLING UTILITIES 04 HYDROSTART 05 PACKAGE 5 PRODUCTION 05 CONTROL ROOMS/PANELS 96 97 PACKAGE 6 DRILLING/BOP 06 MULTICORE CABLES PACKAGE 7 GENERATION 07 HEAT TRACING/INSULATION/CLAD 98 PACKAGE 8 NGL PLANT 08 COMMON 99 PACKAGE 9 NORTH ACCOMMODATION SOUTH TRUSS ACCOMMODATION 09 10 PACKAGE 11 HELIDECK 11 PACKAGE 12 FLARE TOWER 12 13 FIRE PROTECTION SYSTEM 01 BULK MUD HANDLING 01 EXPORT SYSTEM 01 02 FE 12" BULK TRANSFER SYSTEM 01 02 BULK CEMENT HANDLING JO1 HP FIREWATER LOOP 02 LP FIREWATER LOOP 03 MUD MIXING - ACTIVE AND RESERVE 03 FE 6" TEST TRANSFER SYSTEM 03 JO2 JO3 02 03 HYDRANT/MONITORS 04 MUD MIXING - DEGASSING/DESANDING 04 FISCAL METERING SYSTEM 04 JO4 HI-EX FOAM 05 AIR COOLING - MUD PUMPS 05 FE BULK IMPORT SYSTEM ON FA 05 HALON SYSTEMS 06 RIG UTILITIES 06 FE TEST IMPORT SYSTEM ON FA 06 SPRINKLER SYSTEM 07 CONTROL ROOMS/PANELS 96 INFIELD IMPORT SYSTEM ON FC 07 DELUGE SYSTEM 08 MULTICORE CABLES 97 BRAE IMPORT SYSTEM 08 EXTINGUISHERS 09 HEAT TRACING/INSULATION/CLAD 98 MONTROSE IMPORT SYSTEM 09 FIRE & GAS DETECTION/CONTROL 10 COMMON 99 BUCHAN IMPORT SYSTEM 10 PERSONNEL PROTECTION 20 FORTIES FIELD 36" EXPORT SYSTEM 11 FIREWALLS 30 FORTIES FIELD 32" EXPORT SYSTEM 12 EMERGENCY SHUTDOWN SYSTEM 40 UNITY MANIFOLD 20 21 PACKAGE 13 DRILLING DERRICK 22 PACKAGE 14 OFFICE BLOCK 14 98 BRUCE IMPORT SYSTEM NELSON IMPORT SYSTEM 23 PACKAGE 15 GRID LINE 1 15 99 ETAP IMPORT SYSTEM 24 PACKAGE 16 RADIO TOWER 16 BRITANNIA 25 GAS INJECTION MANIFOLD 17 CONTROL ROOMS/PANELS 96 GL PROCESS MODULE 18 MULTICORE CABLES 97 GL COMPRESSOR MODULE 19 HEAT TRACING/INSULATION/CLAD 98 MATERIAL HANDLING 96 COMMON 99 ARCHITECTURAL 97 PAINTING/PROTECTIVE COATING 98 COMMON 99 CONTROL ROOMS/PANELS MULTICORE CABLES 96 97 HEAT TRACING/INSULATION/CLAD COMMON January 2001 / 01 98 99 PRIMARY SYSTEM 5 MECH HANDLING/LIFTING EQUIP HYDRAULIC SYSTEM CONTROL ROOMS/PANELS MULTICORE CABLES HEAT TRACING/INSULATION/CLAD 14 15 80 96 97 (FLARE AND VENT SYSTEMS) ASSOCIATED SECONDARY SYSTEMS POTABLE WATER CONTROL ROOMS/PANELS SLOT E1 19 26 WELL SLOT 21 4/3 5/1 WELL 4/1 01 09 SLOT 06 02 2/1 WELL 1/1 1/3 5/3 14 1/1 WELL 4/1 1/2 5/2 3/2 21 SLOT 20 4/3 04 WELL 4/2 4/2 05 2/2 FORTIES CHARLIE SLOT SCOTT IMPORT SYSTEM SYSTEM MNEMONICS - ANDREW & CYRUS SH1 NUMBER Example 7 2 1 2 C 9 9 9 9 SEQUENTIAL NUMBER PLATFORM IDENTIFIER PLATFORM CODE ANDREW 7 CYRUS 8 PRIMARY SYSTEMS HANDOVER TYPE IDENTIFIER SECONDARY SYSTEM DESCRIPTION 1 OIL SYSTEMS 2 CONSTRUCTED/COMMISSIONED C GAS SYSTEMS 3 DESTRUCT D WATER SYSTEMS 4 FLARE & VENT SYSTEMS (LISTED UNDER RESPECTIVE PRIMARY SYSTEM) TEMPORARY T RE-INSTATEMENT/REFURBISHMENT R SHUTDOWN DEPENDENT S EQUIPMENT OUTAGE E 5 PLATFORM EMERGENCY AND SAFETY SYSTEMS 6 DRILLING SYSTEMS 7 UTILITES 8 PLATFORM FABRIC 9 PRIMARY SYSTEM 1 PRIMARY SYSTEM 1 (WELLS) (WELLS) ASSOCIATED SECONDARY SYSTEMS ASSOCIATED SECONDARY SYSTEMS CYRUS ANDREW WELL WELL SLOT 13 01 02 14 02 03 15 03 04 16 04 05 17 05 06 18 06 07 19 07 08 20 08 09 21 09 10 22 10 11 23 11 12 24 12 80 96 97 HYDRAULIC SYSTEMS CONTROL ROOMS/PANELS MULTICORE CABLES HEAT TRACING/INSULATION/CLAD COMMON 98 99 HEAT TRACING/INSULATION/CLAD COMMON ANDREW PRODUCTION CYRUS PRODUCTION 98 99 (FLARE AND VENT SYSTEMS) (WATER SYSTEMS) ASSOCIATED SECONDARY SYSTEMS 97 PRIMARY SYSTEM 5 PRIMARY SYSTEM 4 (GAS SYSTEMS) ASSOCIATED SECONDARY SYSTEMS 80 96 CONTROL ROOMS/PANELS MULTICORE CABLES PRIMARY SYSTEM 3 (OIL SYSTEM) ASSOCIATED SECONDARY SYSTEMS ASSOCIATED SECONDARY SYSTEMS n TEST SEPARATOR HYDROCYCLONES 00 HP FLARE 10 10 n H.P. SEPARATOR HYDROCYCLONES 01 H.P. COMPRESSION 20 n L.P. SEPARATOR HYDROCYCLONES 02 DEHYDRATION 30 13 EXPORT COMPRESSION 40 14 15 GAS LIFT 50 GAS FISCAL METERING 60 MP FLARE LP FLARE LLP FLARE ATMOSPHERIC VENT MAINTENANCE VENT FLARE IGNITION 20 30 40 50 60 70 GAS EXPORT PIPELINE 70 RE- INJECTION 80 00 COMPRESSOR TURBINE 00 10 11 L.P. COMPRESSION 12 n FISCAL METERING n M.O.L. PUMPING n EXPORT PIPELINE n SEPARATION n BOOSTER PUMPING 20 TEST SEPARATOR H.P. SEPARATOR L.P. SEPARATOR BOOSTER PUMPING SLOT 01 PRIMARY SYSTEM 2 n n n n WELL SLOT HYDRAULIC SYSTEMS ANDREW TESTING LETTER WELLS 21 DE-OILING n CYRUS SEPARATOR HYDROCYCLONES 03 DE-GASSING 10 SEPARATOR DE- SANDING 20 n LIQUID FISCAL METERING 22 CYRUS PIPELINES/RISERS n PRODUCTION n GAS LIFT 30 31 n RISER LIFT 32 PRIMARY SYSTEM 6 (PLATFORM EMERGENCY AND SAFETY SYSTEMS) ASSOCIATED SECONDARY SYSTEMS EVACUATION SYSTEMS PLATFORM CONTROLS EMERGENCY POWER FIRE PROTECTION (ACTIVE) ACCOMODATION ASSOCIATED SECONDARY SYSTEMS BULK MUD HANDLING 01 BULK CEMENT HANDLING 02 03 MUD MIXING - ACTIVE AND RESERVE 03 n MUSTER AREAS n EMERGENCY SHUTDOWN n FIRE & GAS 04 MUD MIXING - DEGASSING/DESANDING 04 11 AIR COOLING - MUD PUMPS 05 12 RIG UTILITIES n TELECOMS n GENERAL ADDRESS 13 14 CONTROL ROOMS/PANELS 06 96 MULTICORE CABLES n PLATFORM ADDRESS 97 15 n NAVAIDS 16 n POWER GENERATION n POWER DISTRIBUTION 21 22 23 n UPS/BATTERIES n FIRE PUMPS n FIRE LOOP n HALON n SPRINKLER n EXTINGUISHERS 35 36 37 n DELUGE n COATINGS 38 n FIREWALLS 42 n TEMPORARY REFUGE 51 n HVAC 52 41 53 n HOTEL FACILITIES 54 n DIRAVENT SYSTEMS 61 n SURVIAL SUITS 71 72 81 82 n POTABLE WATER n n n n n n n PLANT AIR INSTRUMENT AIR INERT GAS SEAWATER DIESEL FUEL GAS TURBINE IGNITION GAS n WASH WATER CHEMICALS n DEMULSIFIER n CORROSION INHIBITOR n SCALE INHIBITOR n n n n 32 n FOAM n BLOW-OUT PANELS 98 FLUIDS 31 33 34 EXPLOSION PROTECTIONn BLAST WALLS HEAT TRACING/INSULATION/CLAD PRIMARY SYSTEM 0 (PLATFORM FABRIC) ASSOCIATED SECONDARY SYSTEMS 02 PERSONNEL PROTECTIONn B.A. SETS January 2001 / 01 (UTILITIES) 01 n MEDICAL SUITE PLANT VENTILATION PRIMARY SYSTEM 8 (DRILLING SYSTEM) n HELIDECK n LIFEBOATS n OTHER ESCAPE n HYDRANT/MONITORS FIRE PROTECTION (PASSIVE) PRIMARY SYSTEM 7 DRAINS OXYGEN SCAVENGER CHLORINATION BIOCIDE HYDRATE REMOVER/INHIB 01 02 03 04 05 06 07 08 POWER GENERATION 09 MEDIUMS 11 12 13 COMMS 14 15 16 17 n HAZARDOUS CLOSED DRAINS 21 n SAFE CLOSED DRAINS n HAZARDOUS OPEN DRAINS n SAFE OPEN DRAINS n STORM DRAINS 22 23 24 25 ASSOCIATED SECONDARY SYSTEMS 31 n MAIN GENERATION n HV MAIN GENERATION DIST. 32 n MV MAIN GENERATION DIST. 33 n LV MAIN GENERATION DIST. 34 n STANDBY GENERATION 35 n STANDBY GENERATION DIST. 36 n LIGHTING & SMALL POWER 37 n WELDING SOCKETS n HEATING MEDIUMS n COOLING MEDIUMS 38 41 42 51 SANITARY n TELEPHONES n NETWORKS n SEWAGE HELICOPTER n TBA 52 61 71 SUPPORT FACILITY n MATERIAL HANDLING 81 n WORKSHOP/LABORATORIES 82 SWITCHGEAR 01 ACCOMMODATION 02 HELIDECK 03 FLARE TOWER 04 DRILLING DERRICK 05 GAS COMPRESSION 06 ARCHITECTURAL 07 PAINTING/PROTECTIVE COATING 08 SYSTEM MNEMONICS - ETAP HANDOVER NUMBER Example 2 1 0 2 1 8 C 9 9 9 9 SEQUENTIAL NUMBER FACILITY IDENTIFIER ETAP (General) PdR QU MACHAR MUNGO MONAN HERON EGRET SKUA MARNOCK MIRREN SCOTER PIPELINE - OIL PIPELINE - GAS PRIMARY SYSTEMS 210 211 212 221 231 232 241 242 243 251 252 253 271 281 WELLS SECONDARY SYSTEM HANDOVER TYPE IDENTIFIER 1 OIL SYSTEM 2 GAS SYSTEM 3 WATER SYSTEM 4 FLARE & VENT SYSTEMS 5 SAFETY SYSTEMS 6 DRILLING SYSTEMS 7 UTILITIES 8 PLATFORM FABRIC 9 DESCRIPTION (LISTED UNDER RESPECTIVE PRIMARY SYSTEM) LETTER CONSTRUCTED/COMMISSIONED C DESTRUCT D TEMPORARY T RE-INSTATEMENT/REFURBISHMENT R SHUTDOWN DEPENDANT S EQUIPMENT OUTAGE E PRIMARY SYSTEM 1 (WELLS) ASSOCIATED SECONDARY SYSTEMS SLOT MORAN MACHAR PRODUCTION MARNOCK WELL WELL SLOT WELL SLOT WELL HERON/EGRET/SKUA SLOT MIRREN/SCOOTER WELL SLOT MACHAR WATERFORD MUNGO WELL SLOT WELL SLOT WELL SLOT WELL WELL SLOT WELL SLOT 01 11 20 30 40 50 60 70 80 86 96 02 03 12 13 21 22 31 32 41 42 51 52 61 62 71 72 81 82 87 88 97 98 04 14 23 33 43 53 63 73 83 15 24 34 44 54 64 74 84 90 16 25 35 45 55 65 75 85 91 07 17 26 36 46 56 66 76 92 08 09 18 19 27 28 37 38 47 48 57 58 67 68 77 78 93 94 29 39 49 59 69 79 95 - PRIMARY SYSTEM 3 PRIMARY SYSTEM 4 PRIMARY SYSTEM 5 (GAS SYSTEMS) (WATER SYSTEMS) (FLARE AND VENT SYSTEMS) MACHAR 00 MUNGO LIQUIDS 01 MUNGO/MONAN GAS 02 HERON CLUSTER (PIPELINE A) 03 HERON CLUSTER (PIPELINE B) 04 FUTURE A 09 FUTURE B 10 MIRREN 11 SCOTER 12 60 70 71 72 73 79 80 82 - HERON CLUSTER 20 OIL METERING - (FISCAL) 83 - SCOTER 30 OIL EXPORT COOLING 84 SLUGCATCHERS - MACHAR MUNGO/MONAN HERON CLUSTER MIRREN SCOTER 40 41 42 44 45 OIL EXPORT PUMPING 85 EXPORT PIPELINE (INCLUDING OIL PIGGING) 86 - HERON CLUSTER 51 L.P. GAS MANIFOLD L.P. COMPRESSION - TRAIN 1 - TRAIN 2 - DISCHARGE COOLING 00 11 12 13 H.P. GAS - MANIFOLD - GAS COOLING - KNOCK OUT 30 31 32 GAS DEHYDRATION GAS CHILLING 40 45 GAS EXPORT - COMPRESSION TRAIN 1 - COMPRESSION TRAIN 2 51 52 GAS METERING (FISCAL) 60 GAS EXPORT PIPELINE (INCLUDING GAS SPHERING/PIGGING) 61 GAS INJECTION COMPRESSION MUNGO GAS INJECTION PIPELINE GAS INJECTION MANIFOLD RISER GAS LIFT MARNOCK CONDENSATE BANKING COMPRESSION 70 71 72 90 93 HYDROCYLONES - H.P. PRODUCTION - H.P. TEST - L.P. 10 11 12 PRODUCED WATER - DEGASSER VESSEL - DISPOSAL - RE-INJECTION RECYCLE COOLER - RE-INJECTION PUMPS - RE-INJECTION MANIFOLD 14 15 21 22 23 WATER INJECTION - DEAERATION - BOOSTER PUMPS - PUMPS - VACUUM PACKAGE - PIPELINE - CPF TO MUNGO - PIPELINE CPF TO MACHAR - MANIFOLD - WASHDOWN SUPPLY/DISTRIBUTION 50 51 52 53 54 55 56 57 WASH WATER - BOOSTER PUMPS - SULPHATE REDUCTION - CRUDE WASHING PUMPS - PIPELINE TO HERON CLUSTER 60 61 62 63 PRIMARY SYSTEM 6 PRIMARY SYSTEM 7 PRIMARY SYSTEM 8 (SAFETY SYSTEMS) (DRILLING SYSTEM) (UTILITIES) ASSOCIATED SECONDARY SYSTEMS ASSOCIATED SECONDARY SYSTEMS EVACUATION SYSTEMS - HELIDECK LIFEBOATS OTHER ESCAPE MUSTER AREAS 01 02 03 04 PLATFORM CONTROLS - EMERGENCY SHUTDOWN FIRE & GAS TELECOMS GENERAL ADDRESS 11 12 13 14 - PLATFORM ADDRESS - NAVAIDS 15 16 - INTEGRATED CONTROLS - CONTROL NETWORKS - COMMUNICATIONS 17 18 19 DRILLING BULK MUD HANDLING BULK CEMENT HANDLING MUD MIXING - ACTIVE AND RESERVE MUD MIXING - DEGASSING/DESANDING MUD PUMPS RIG UTILITIES CEMENT UNIT CUTTINGS RE-INJECTION 01 02 03 04 05 06 07 08 09 FLUIDS - POWER GENERATION - POWER DISTRIBUTION - UPS / BATTERIES 21 22 23 FIRE PROTECTION (ACTIVE) - 31 32 33 34 35 36 37 41 42 43 44 45 46 47 48 49 FIRE PUMPS HYDRANT / MONITORS FIRE LOOP FOAM HALON SPRINKLERS EXTINGUISHERS DELUGE SYSTEM 1 DELUGE SYSTEM 2 DELUGE SYSTEM 3 DELUGE SYSTEM 4 DELUGE SYSTEM 5 DELUGE SYSTEM 6 DELUGE SYSTEM 7 DELUGE SYSTEM 8 DELUGE SYSTEM 9 - COATINGS - FIREWALLS 50 51 EXPLOSION PROTECTION - BLAST WALLS - BLOW-OUT PANELS 52 53 ACCOMMODATION 54 55 56 57 58 PLANT VENTILATION - LIVING QUARTERS TEMPORARY REFUGE HVAC MEDICAL SUITE HOTEL FACILITIES - DIRAVENT SYSTEMS 59 POWER GENERATION - INDUSTRIAL WATER POTABLE WATER PLANT AIR INSTRUMENT AIR INERT GAS SEAWATER DIESEL FUEL GAS TURBINE IGNITION GAS HELIFUEL - INJECTION (COMMON) 10 DEMULSIFER 11 CORROSION INHIBITOR 12 SCALE INHIBITOR 13 OXYGEN SCAVENGER 14 HYPOCHLOITE 15 BIOCIDE 16 POLYELECTROLYTE 17 WAX INHIBITOR 18 REVERSE EMULSION BREAKER 19 H2S SCAVENGER 20 CHILORINATION 21 METHONNOL STORAGE/HAND. 22 METHONNOL INJECTION 23 ANTIFOAM 24 THI 25 BIOCIDE 26 HGI 27 - MAIN POWER GEN 1 MAIN POWER GEN 2 WELDING SOCKETS LIGHTING & SMALL POWER AUXILIARY GENERATOR AUXILIARY GEN DIST. HV MAIN GEN. DIST. MV MAIN GEN. DIST. LV MAIN GEN. DIST. ANCILLARIES 00 01 02 03 04 05 06 07 08 09 60 61 TOPSIDE HYDRAULICS (EXCLUDING WELLHEADS) SUB-SEA HYDRAULICS 91 92 10 30 50 70 (PLATFORM FABRIC) ASSOCIATED SECONDARY SYSTEMS MEDIUMS - HEATING MEDIUMS - COOLING MEDIUMS 41 42 JACKET APPURTENANCES (CASSONS ETC.) 00 COMMS - TELEPHONES - NETWORKS 51 52 SANITARY DRAINS - SEWAGE 61 - CLOSED 62 - HAZARDOUS OPEN 63 - NON-HAZARDOUS OPEN 64 - STORM 65 SWITCHGEAR ACCOMMODATION HELIDECK FLARE TOWER DRILLING DERRICK GAS COMPRESSION BRIDGE ARCHITECTURAL PAINTING/PROTECTIVE/COATINGS 01 02 03 04 05 06 07 08 09 SUPPORT FACILITY - MATERIAL HANDLING & LIFTING EQUIPMENT - WORKSHOPS/LAB 66 GLYCOL - STORAGE & HANDLING - REGENERATION - LEAN CONDITIONING 70 71 72 BRIDGE - INTERFACES 89 UMBILICALS - 90 91 92 93 94 95 96 97 98 99 MACHAR MUNGO MONAN EGRET - HERON SKUA - EGRET CPF - SKUA FUTURE ‘A’ FUTURE ‘B’ MIRREN SCOTER 67 31 32 33 34 35 36 37 38 39 n HYDRAULIC SYSTEMS 80 n CONTROL ROOMS/PANELS n MULTICORE CABLES 96 97 n HEAT TRACING/INSULATION/CLAD 98 99 n COMMON PERSONNEL PROTECTION - B.A. SETS - SURVIVAL SUITS H.P. PROCESS RELIEF L.P. PROCESS RELIEF ATMOSPHERIC VENTING FLARE IGNITION PRIMARY SYSTEM 9 ASSOCIATED SECONDARY SYSTEMS CHEMICALS EMERGENCY POWER ASSOCIATED SECONDARY SYSTEMS ASSOCIATED SECONDARY SYSTEMS ASSOCIATED SECONDARY SYSTEMS REFERENCE OIL ALLOCATION METERING PRODUCTION MANIFOLD TEST MANIFOLD PRODUCTION SEPARATION TEST SEPARATION NODE OIL HEATER L.P. SEPARATION OIL BOOSTER PUMPING SUB-SEA MULTIPHASE FIRE PROTECTION (PASSIVE) 99 PRIMARY SYSTEM 2 PIGGING OIL TEST SEPARATION SLOT (LIQUID STABILISATION, PUMPING & EXPORT) ASSOCIATED SECONDARY SYSTEMS BULK IMPORT PIPELINE WELL 89 05 06 10 GENERAL WELLHEAD SERVICES OVERFLOW/SPARE SLOT ANCILLARIES ARE COMMON TO PRIMARY SYSTEMS 1 - 8 January 2001 / 01 Source: Legend Sheet 6 Numbering B-210X-48-18-0001.6 Rev Z1 SYSTEM MNEMONICS - HARDING HANDOVER NUMBER Example H 2 2 1 C 9 9 9 9 SEQUENTIAL NUMBER FACILITY IDENTIFIER HARDING H PRIMARY SYSTEMS SECONDARY SYSTEM WELLS 1 OIL SYSTEM 2 GAS SYSTEM 3 WATER SYSTEM 4 FLARE & VENT SYSTEMS 5 SAFETY SYSTEMS 6 DRILLING SYSTEMS 7 UTILITIES 8 PLATFORM FABRIC 9 HANDOVER TYPE IDENTIFIER (LISTED UNDER RESPECTIVE PRIMARY SYSTEM) LETTER DESCRIPTION CONSTRUCTED/COMMISSIONED C DESTRUCT D TEMPORARY T RE-INSTATEMENT/REFURBISHMENT R SHUTDOWN DEPENDANT S EQUIPMENT OUTAGE E PRIMARY SYSTEM 1 (WELLS) ASSOCIATED SECONDARY SYSTEMS WELL SLOT DESCRIPTION WELL SLOT DESCRIPTION PN 1 1 2 SPARE OIL PRODUCTION 101 102 PIC3 13 FUTURE 113 AQ1 14 AQUIFER 114 PC1 3 OILPRODUCTION 103 PNE1 4 FUTURE 104 AQ2 PIC1 15 16 AQUIFER OIL PRODUCTION 115 116 WC1 5 WATER INJECTION 105 WS1 17 WATER INJECTION 117 PC5 6 OIL PRODUCTION 106 PS2 18 OIL PRODUCTION 118 PC2 IC2 7 8 OIL PRODUCTION OIL PRODUCTION 107 108 PSE3 19 OIL PRODUCTION 119 - 20 SPARE 120 WC2 9 WATER INJECTION 109 PC4 10 OIL PRODUCTION 110 SE2 PS1 21 22 FUTURE OIL PRODUCTION 121 122 PC3 11 OIL PRODUCTION 111 PSE1 23 OIL PRODUCTION 123 GI1 12 CAP GAS 112 - 24 SPARE 124 MNEMONIC PRIMARY SYSTEM 2 PRIMARY SYSTEM 3 PRIMARY SYSTEM 4 PRIMARY SYSTEM 5 (OIL PROCESSING) (GAS SYSTEM) (WATER SYSTEM) (FLARE AND VENT SYSTEMS) ASSOCIATED SECONDARY SYSTEMS TEST SEPARATION - PARENT -TEST MANIFOLD -TEST SEPARATOR 210 211 212 - PARENT - PROD MANIFOLD - HP SEPARATOR 220 221 222 - 230 231 232 233 234 TANKER EXPORT TANKER LOADING PIPELINE EXPORT LP SEPARATION/ WATER REMOVAL OIL PRODUCTION - SAMPLING PARENT LP SEPARATOR COALESCER CRUDE TRANSFER PUMP PROD WATER PUMP - PARENT - FAST LOOP - METERING - PIPELINE EXPORT - OIL TO STORAGE 240 241 - CRUDE EXPORT - CRUDE 250 251 252 COMPRESSOR COMMON EQUIP - COMPRESSOR DRIVE - COMPRESSOR LUBE OIL - COMPRESSOR SEAL GAS - COMPRESSOR BUFFER GAS 310 311 312 313 314 L.P. COMPRESSION 320 H.P. COMPRESSION 330 340 341 342 343 253 - PARENT - MOL PUMPS - EXPORT PIPELINE 260 261 262 METERING PROVER 270 SAND REMOVAL PUMPS 280 GAS TREATMENT - GAS CONDITIONING - DEHYDRATION - GLYCOL REGENERATION STL SUBSEA SYSTEMS 290 GAS LIFT 350 CAP GAS TREATMENT 360 LP COMPRESSOR (GREEN) 370 242 243 PRIMARY SYSTEM 6 PRIMARY SYSTEM 7 PRIMARY SYSTEM 8 (SAFETY SYSTEMS) (DRILLING SYSTEM) (UTILITIES) ASSOCIATED SECONDARY SYSTEMS ASSOCIATED SECONDARY SYSTEMS EVACUATION SYSTEMS PLATFORM CONTROLS - PARENT HELIDECK LIFEBOATS OTHER ESCAPE MUSTER AREAS 610 611 612 613 614 RIG 710 WELL CONTROL SYSTEM 720 MUD 730 - PARENT EMERGENCY S/D FIRE & GAS TELECOMS G.A./P.A. 620 621 622 623 624 CEMENT 740 - NAVAIDS - INTEGRATED CONTROL 625 626 - CONTROL NETWORKS - HYDRAULICS 627 628 EMERGENCY POWER - PARENT POWER GENERATION POWER DISTRIBUTION UPS / BATTERIES 630 631 632 633 FIRE PROTECTION (ACTIVE) PARENT FIRE PUMPS FIRE LOOP HYDRANT / MONITORS FOAM HALON SPRINKLERS EXTINGUISHERS DELUGE SYSTEM 640 641 642 643 644 645 646 647 648 - FIRE PROTECTION (PASSIVE) - PARENT - COATINGS - FIREWALLS 650 651 652 ACCOMMODATION - 660 661 662 663 664 PLANT VENTILATION - PARENT - DIRAVENT SYSTEM 670 671 EXPLOSION PROTECTION - PARENT - BLAST WALLS - BLOW-OUT PANELS 680 681 682 - PARENT - B.A. SETS - SURVIVAL SUITS 690 691 692 PERSONNEL PROTECTION PARENT TEMPORARY REFUGE HVAC MEDICAL SUITE HOTEL FACILITIES PROD WATER HYDROCYCLONES 410 H.P. FLARE 510 WATER INJECTION 420 L.P. FLARE 520 AQUIFER SYSTEM - AQUIFER MANIFOLD - AQUIFER DRUM 430 431 432 ATMOSPHERIC VENT 530 MAINTENENCE VENT 540 FLARE IGNITION 550 PRIMARY SYSTEM 9 (PLATFORM FABRIC) ASSOCIATED SECONDARY SYSTEMS PROCESS UTILITIES - PARENT POT / FRESH WATER PLANT AIR INSTRUMENT AIR - SEA WATER DIESEL FUEL GAS ATK 810 811 812 813 814 815 816 817 818 - PARENT DEMULSIFIER CORROSSION INHIB SCALE INHIBITOR OXY SCAVENGER CHLORINATION BIOCIDE METHANOL ANTIFOAM 820 821 822 823 824 825 826 827 828 DRAINS - PARENT HAZ CLOSED DRAINS HAZ OPEN DRAINS NON HAZ OPEN DRAINS 830 831 832 833 POWER GEN. - PARENT MAIN GENERATION MAIN GEN DIST (HV) MAIN GEN DIST (MV) MAIN GEN DIST (LV) STANDBY GENERATION STANDBY GEN DIST LIGHTING/ SMALL SOCKETS 840 841 842 843 844 845 846 847 CHEMICALS HEATING MEDIUM COOLING MEDIUM HVAC ASSOCIATED SECONDARY SYSTEMS - PARENT 8 70 SANITORY SERVICES - PARENT - SEWAGE 880 881 SUPPORT FACILITIES - 890 891 892 893 PARENT MATERIAL HANDLING WORKSHOP / LAB BILGE / BALLAST 850 851 ANCILLARIES n HYDRAULIC SYSTEMS 80 n CONTROL ROOMS/PANELS n MULTICORE CABLES 96 97 n HEAT TRACING/INSULATION/CLAD 98 99 n COMMON ANCILLARIES ARE COMMON TO PRIMARY SYSTEMS 1 - 8 January 2001 / 01 ASSOCIATED SECONDARY SYSTEMS ASSOCIATED SECONDARY SYSTEMS ASSOCIATED SECONDARY SYSTEMS - PARENT - BASE STORAGE TANKER METERING HP SEPARATION MNEMONIC UTILITIES AREA COMP - LEGS - UTILITY AREAS - HELIDECK 910 911 912 913 LIVING QUARTERS 920 DRILLING STRUCTURE - DERRICK - SUB STRUCTURE 930 931 932 PROCESS & DRILLING AREA - PROCESS AREA - FLARE BOOM 940 941 942 GRAVITY BASE TANK 950 MARINE - JACKING AND LOCKING SYS - ROV 960 960 960 SYSTEM MNEMONICS - NORTH EVEREST HANDOVER NUMBER Example E R 2 2 1 C 9 9 9 9 SEQUENTIAL NUMBER FACILITY PRIMARY SYSTEMS IDENTIFIER NORTH EVEREST LOMOND ERSKINE ARMADA EV LO ER AR SECONDARY SYSTEM WELLS 1 OIL SYSTEM 2 GAS SYSTEM 3 WATER SYSTEM 4 FLARE & VENT SYSTEMS SAFETY SYSTEMS 6 DRILLING SYSTEMS 7 UTILITIES 8 PLATFORM FABRIC 9 (WELLS) ERSKINE LOMOND ASSOCIATED SECONDARY SYSTEMS D TEMPORARY T RE-INSTATEMENT/REFURBISHMENT R SHUTDOWN DEPENDANT S EQUIPMENT OUTAGE E (WELLS) ASSOCIATED SECONDARY SYSTEMS ASSOCIATED SECONDARY SYSTEMS MNEMONIC 01 101 01 101 SLOT 11 11 111 02 102 02 102 12 112 02 102 12 112 03 103 103 104 113 03 103 104 03 04 13 04 14 114 04 104 13 14 113 114 05 06 105 106 05 105 15 115 05 105 15 115 06 106 07 107 116 117 06 07 106 107 116 107 16 17 16 07 17 117 08 108 08 108 18 118 08 108 18 118 09 10 109 110 19 119 09 109 20 120 10 110 19 20 119 120 21 121 21 121 OIL PROCESSING - SEPARATION WELL SLOT MNEMONIC WELL MNEMONIC 111 WELL PRIMARY SYSTEM 3 (OIL PROCESSING) (GAS SYSTEM) PARENT TEST SEPARATION TEST MANIFOLD & TEST SEPARATOR CONDENSATE EXPORT - PARENT - PIPELINE PUMPS - CONDENSATE EXPORT 250 251 252 - PARENT - PRODUCTION MANIFOLD & HP SEPARATOR - IP SEPARATOR - LP SEPARATOR - CONDENSATE HEATER 220 221 COMMON CONDENSATE EXPORT - PARENT 260 222 223 224 ERSKINE SEPARATION - PARENT - SURGE VESSEL - SURGE VESSEL BOOSTER PUMPS 230 231 232 - 270 271 272 273 274 275 276 PARENT SAMPLING METERING METER PROVER PARENT PIG RECEIVER HP SEPARATOR SEPARATOR COOLER & EXPORT PUMPS METERING EXPORT - PARENT - WELL (WATER SYSTEM) 350 351 352 353 354 355 TRAIN 1 COMPRESSOR COMMON EQUIPT - GAS TURBINE - LUBE OIL - SEAL GAS 320 321 322 323 ERSKINE COMPRESSOR COMMON EQUIPMENT - GAS TURBINE - COMPRESSOR LUBE IOL - COMPRESSOR SEAL GAS 360 GAS PROCESSING 330 331 332 333 GAS EXPORT - SAMPLING - GAS METERING - GAS EXPORT - ARMADA GAS EXPORT - COMMON GAS EXPORT 370 371 372 373 374 375 VR COMPRESSION - LP VR COMPRESSOR - IP VR COMPRESSOR 380 381 382 GLYCOL REGENERATION - GLYCOL REGENERATION SYSTEM 390 391 PRIMARY SYSTEM 6 PRIMARY SYSTEM 7 (SAFETY SYSTEMS) (DRILLING SYSTEM) ASSOCIATED SECONDARY SYSTEMS 340 341 342 343 361 362 363 (UTILITIES) SAFETY SYSTEMS - PARENT 600 RIG 710 UTILITES - PARENT 800 510 EVACUATION SYSTEMS 720 PROCESS UTILITIES 520 MUD 730 ATMOSPHERIC VENT 530 610 611 612 613 614 WELL CONTROL SYSTEM LP FLARE - CEMENT 740 - PARENT POT / FRESH WATER PLANT AIR INSTRUMENT AIR SEA WATER DIESEL FUEL GAS ATK NITROGEN 810 811 812 813 814 815 816 817 818 CHEMICALS - PARENT DRA CORROSSION INHIBITOR SCALE INHIBITOR OXY SCAVENGER CHLORINATION BIOCIDE METHANOL DEMULSIFER SOLVENT/DISPERANT 820 821 822 823 824 825 826 827 828 829 DRAINS - PARENT - HAZ CLOSED DRAINS - HAZ OPEN DRAINS - NON HAZ OPEN DRAINS 830 831 832 833 540 PIPELINE FLARE 550 PLATFORM CONTROLS - PARENT EMERGENCY S/D FIRE & GAS TELECOMS G.A./P.A. NAVAIDS INTEGRATED CONTROLS CONTROL NETWORKS HYDRAULICS 620 621 622 623 624 625 626 627 628 EMERGENCY POWER - PARENT POWER GENERATION POWER DISTRIBUTION UPS / BATTERIES 630 631 632 633 FIRE PROTECTION (ACTIVE) PARENT FIRE PUMPS FIRE LOOP HYDRANT / MONITORS FOAM HALON SPRINKLERS EXTINGUISHERS DELUGE SYSTEM 640 641 642 643 644 645 646 647 648 - FIRE PROTECTION (PASSIVE) - PARENT - COATINGS - FIREWALLS 650 651 652 ACCOMMODATION - 660 661 662 663 664 PARENT TEMPORARY REFUGE HVAC MEDICAL SUITE HOTEL FACILITIES PLANT VENTILATION - PARENT - DIRAVENT SYSTEM 670 671 EXPLOSION PROTECTION - 680 681 682 690 691 PERSONNEL PROTECTION PARENT BLAST WALLS BLOW-OUT PANELS PARENT B.A. SETS ANCILLARIES n HYDRAULIC SYSTEMS POWER GENERATION - PARENT - MAIN GENERATION - A - MAIN GENERATION - B - MAIN GENERATION - C - STANDBY GENERATION - STANDBY GENERATION DIST. - LIGHTING/ SMALL SOCKETS - WELDING SOCKETS 840 841 842 843 844 845 846 847 HEATING MEDIUM COOLING MEDIUM 850 851 COMMUNICATIONS - PARENT - TELECOMS - NETWORKS 860 861 862 HVAC - PARENT 870 SANITORY SERVICES - PARENT - SEWAGE - SEWAGE CAISON 880 881 882 SUPPORT FACILITIES - 890 891 892 893 80 n CONTROL ROOMS/PANELS n MULTICORE CABLES 96 97 n HEAT TRACING/INSULATION/CLAD 98 99 n COMMON January 2001 / 01 ANCILLARIES ARE COMMON TO PRIMARY SYSTEMS 1 - 8 PARENT MATERIAL HANDLING WORKSHOP / LABORATORIES BILGE & BALLAST ERSKINE PRODUCED WATER - HP HYDROCYCLONES - LP HYDROCYCLONES - PRODUCE WATER DEGAS 420 421 422 423 ASSOCIATED SECONDARY SYSTEMS 500 FLARE IGNITION 400 410 411 412 413 (PLATFORM FABRIC) ASSOCIATED SECONDARY SYSTEMS HP FLARE PARENT HELIDECK LIFEBOATS OTHER ESCAPE MUSTER AREAS WATER PROCESSING - PRODUCED WATER(EV & LO) -TILTED PLATE SEPARATOR - REJECT OIL PUMPS - PRODUCE WATER DUMP PRIMARY SYSTEM 9 PRIMARY SYSTEM 8 ASSOCIATED SECONDARY SYSTEMS MNEMONIC ASSOCIATED SECONDARY SYSTEMS ERSKINE GAS PROCESSING - GAS TREATMENT - EXPORT COMPRESSOR - FLASH GAS COMPRESSOR - EXPORT GAS METERING - GAS EXPORT TRAIN 2 GAS TREATMENT DENSE PHASE COMP REINJECTION COMP SLOT PRIMARY SYSTEM 4 300 301 310 311 312 313 - PARENT GAS COOLERS TRAIN 1 GAS TREATMENT DENSE PHASE COMP REINJECTION COMP TRAIN 2 COMPRESSOR COMMON EQUIPT - GAS TURBINE - LUBE OIL - SEAL GAS PRIMARY SYSTEM 5 ASSOCIATED SECONDARY SYSTEMS GAS PROCESSING TRAINS 1 & 2 FEED GAS PROCESSING 280 240 241 242 243 (FLARE & VENT SYSTEMS) MNEMONIC 101 ASSOCIATED SECONDARY SYSTEMS 200 210 211 CONDENSATE METERING & SAMPLING - SLOT 01 PRIMARY SYSTEM 2 ARMADA IMPORT FLARES & VENTS C DESTRUCT EVEREST ASSOCIATED SECONDARY SYSTEMS CONDENSATE SURGE LETTER CONSTRUCTED/COMMISSIONED PRIMARY SYSTEM 1 PRIMARY SYSTEM 1 (WELLS) SLOT DESCRIPTION 5 PRIMARY SYSTEM 1 WELL HANDOVER TYPE IDENTIFIER (LISTED UNDER RESPECTIVE PRIMARY SYSTEM) UTILITIES AREA COMP - LEGS - UTILITY AREAS - HELIDECK 910 911 912 913 LIVING QUARTERS 920 DRILLING STRUCTURE - DERRICK - SUB STRUCTURE 930 931 932 PROCESS & DRILLING AREA - PROCESS AREA - FLARE BOOM 940 941 942 GUIDANCE ON CERTIFICATION GOC © AMERICAS EDITION SUBJECT: SYSTEM PRINCIPLES - APPENDICES APPENDIX 1.1 System Handover Limit Examples GOC© BP Exploration 1989 – 2001 All Rights Reserved SECTION 1 REVISION: 1 PAGE: ii GUIDANCE ON CERTIFICATION SECTION 1.0 GOC© AMERICAS EDITION REVISION: 1 SUBJECT: APPENDIX 1.1 – LOSH LEGEND PAGE: 1 LOSH Legend Each handover by default would contain a green LOSH drawing, the Handover Authority may then decide to include additional drawings highlight accordingly to give the different phases the appropriate profile and visibility. If a Handover was phased as below each phase would be represented by an MC1, for example if the handover was for the Bruce Platform, the SH1 number could be: - BRU 212C0158 would be made up from the following MC1’s; SH1: - BRU 212C0158 (Limit of System Handover - Green Highlighted Drawing) MC1: - BRU 212C0158+01 (Pre-Shutdown Scope – Blue Highlighted Drawing) MC1: - BRU 212C0158+02 (Shutdown Scope – Yellow Highlighted Drawing) MC1: - BRU 212C0158+03 (Post-Shutdown Scope – Red Highlighted Drawing) Limits of System Handover Pre-Shutdown Scope Shutdown Scope Post-Shutdown Scope GOC© BP Exploration 1989 - 2001 All Rights Reserved Americas Revision 1 Limits Of System Handover (Forties) SYSTEM "BATTERY LIMITS" 210 UPSTREAM TECHNOLOGY 212 V01 203 203 HV LCV 245 245 210 ESDV 1858 A 210 212 ESDV 1858 ESDV 1858 A B LCV 1827 212 V601 212 215 215 214 T601 215 W38 214 V02 204 212 20 4 210 W600 215 214 211 210 T602 214 HV LCV ESDV ESDV PCV 275 275 1822 A 1822 B 1815 V160 211 212 215 OVERBOARD 211 205 212 TO SEADUMP 213 V03 205 212 ESDV ESDV LCV 1912 A 1912 B 215B ESDV ESDV LCV 1913 A 1913 B 215A 214 213 PROD WATER 205 211 PRODUCED WATER DISPOSAL SYSTEM INJECTION PUMPS PRODUCED WATER TO WELLHEADS PACKAGE 1 ECP3003 U.P.S. SUITE A.C. DIST SECTION EMERGENCY STOP PB 1 EMERGENCY STOP PB 2 11 KV SUPPLY CB 4 PACKAGE IX RED SHUTDOWN SYSTEM V.S.D. TRANSFORMER T 3008 V.S.D. CUBICLES K 3000 VSD - CP REMOTE EMERGENCY STOP HEAT EXCHANGE FAN K 3000 & K 3001 INTERPOSING RELAY PANEL COMPRESSOR CONTROL PANEL AUX. MCC 12 NGL CONTROL ROOM SOUTH WEST CANTILEVER MB-AL-E-006 TRACE HEATING PANEL ‘D’ TO GAS LIFT MANIFOLD COMPRESSOR SKID MOTOR PACKAGE LIMITS SYSTEM LIMITS Figure 9 PROCESS SKID FROM SOURCE GAS SUPPLY GUIDANCE ON CERTIFICATION GOC © AMERICAS EDITION SUBJECT: SYSTEM PRINCIPLES - APPENDICES APPENDIX 1.2 GOC "Carrier" Certificate Example Technical Integrity Assurance Flowcharts Functional Certification Flowchart GOC© BP Exploration 1989 – 2001 All Rights Reserved SECTION 1 REVISION: 1 PAGE: iii SAMPLE Project Title: AFA 2424 (ESCAPE TO SEA) Maintenance No: Work Pack No: No 1 SH1 No: C620C0586 MC1 No: C620C0586+01 MECHANICAL HANDLING INSTALLATION CERTIFICATE FORM MH1 SITE: FORTIES CHARLIE SHT 1 EQUIPMENT No. LIFERAFT No 4 LOCATION NE CORNER WIN No. 5129-1890 & 5129-1891 DRAWING No 2424-03-01-53-109-015 OF 1 SERIAL No. N/A DESCRIPTION LIFERAFT PAINTER PADEYE/DONUT G.A. No STATION No 4 ITEM/DESCRIPTION OF CHECK SIGNATURE 1. TRANSIT DAMAGE CORRECT N/A 2. FIXED EQUIPMENT INSTALLED IN ACCORDANCE WITH APPROVED DRG's AND SPEC. 20/04/01 3. TRAVEL & OPERATION OF EQUIP. UNRESTRICTED & IN ACCORDANCE WITH DESIGN SPEC. 4. ASSOCIATED ALIGNMENT CHECKS COMPLETE ON: 20/04/01 ------------------------ (a) RUNWAY BEAMS N/A (b) GANTRIES N/A (c) BEAM TRANSFER AND LATCH MECHANISMS N/A (d) ASSOC. MECH. EQUIP. i.e. WINCHES, HOISTING MECHANISMS N/A (e) OTHER: N/A 5. ASSOCIATED LIFTING APPLICANCES CORRECTLY INSTALLED, TAGGED AND CERTIFIED: (a) DATE BEAM TROLLIES ------------------------ -------------- -------------- N/A (b) COMBINED TROLLEY HOISTS N/A (c) CHAIN HOISTS N/A (d) OTHERS: N/A 6. ASSOCIATED DESIGNATED LIFTING TACKLE CORRECTLY INSTALLED, TAGGED & CERTIFIED: ------------------------ (a) WIRE ROPES N/A (b) SHEAVE BLOCKS N/A (c) SHACKLES N/A (d) BEAM CLAMPS N/A (e) SLINGS N/A (f) EYEBOLTS N/A (g) OTHERS: N/A -------------- 7. CHECK S.W.L.S. IF ALL EQUIP, WITHIN AN INSTALLED LIFTING SYSTEM ARE COMPATIBLE 20/04/01 8. PERSONNEL PROTECTION AND SAFETY DEVICES CORRECTLY INSTALLED 20/04/01 9. EQUIPMENT IDENTIFICATION AND S.W.L. CLEARLY MARKED 10. CHECK THAT ALL MATERIAL AND FABRICATION REQUIREMENTS AS PER SPECIFICATION AND APPROVED DRAWING HAVE BEEN MET AND ALL CERTIFICATION IS RECORDED. (APPLICABLE TO INSTALLATION OF FIXED EQUIPMENT) 11. ALL EQUIPMENT CORRECTLY INSTALLED AND AVAILABLE FOR PROOF LOAD TEST SEE PUNCH LIST 20/04/01 20/04/01 20/04/01 COMMENTS COMPLETED BY APPROVED BY AMEC BP PRINT NAME A.SERVICE A.CLIENT DATE 20/04/01 20/04/01 COMPANY SIGNATURE GOC © BP Exploration 1989 – 2001 All Rights Reserved Americas REV. 1 Project Title: AFA 2424 (ESCAPE TO SEA) Maintenance No: Work Pack No: No 1 SH1 No: C620C0586 MC1 No: C620C0586+01 SAMPLE MECHANICAL HANDLING ACCEPTANCE CERTIFICATE FORM MH2 (SIDE 1) SITE: FORTIES CHARLIE SHT 1 OF 1 ITEM LIFERAFT PAINTER PADEYE/DONUT LOCATION NE CORNER DONUT STATION No 4 EQUIPMENT No LIFERAFT No 4 S.W.L. 300 KG & 333 KG WIN No 5129-1890 & 5129-1891 PROOF LOAD 600 KGS & 666 KGS SERIAL No N/A PROOF LOAD CERTIFICATE No 940414 CERTIFYING AUTHORITY BIS DRAWING No 2424-03-01-53-109-015 MAKER & DATE OF MAKE DATE FIRST PUT INTO USE DATE OF LAST RECORD EXAMINATION (IF SEEN). NAME OF PERSON WHO CONDUCTED LAST EXAMINATION AND OF HIS EMPLOYER. FIRST EXAMINATION PARTS NOT ACCESSIBLE FOR THOROUGH EXAMINATION NONE PARTS THAT REQUIRE OPENING UP AT THE NEXT EXAMINATION NONE PARTICULARS OF DEFECTS AND REMEDY PARTICULARS OF ANY DEFECT FOUND IN THE LIFTING APPLICANCE AND THE REPAIRS (IF ANY) REQUIRED, EITHER ; i IMMEDIATELY OR, ii WITHIN A SPECIFIED TIME (WHICH MUST BE STATED) TO ENABLE THE LIFTING APPLICANCE OR LIFTING GEAR TO CONTINUE TO BE USED WITH SAFETY. (IF NO SUCH REPAIRS ARE REQUIRED, THE WORK 'NONE' IS TO BE ENTERED) NONE SAFE WORKING LOAD SUBJECT TO THE REPAIRS, RENEWALS AND ALTERATIONS (IF ANY) SPECIFIED ABOVE IN THE CASE OF A CRANE WITH A VARIABLE OPERATING RADIUS, INCLUDING A CRANE WITH DERRICKING JIB, THE SAFE WORKING LOAD AT VARIOUS RADII OF THE JIB, TROLLEY OR CRAB TO BE STATED NONE SECTION 1 (TO BE COMPLETED WHERE APPROPRIATE TO PERMANENT LIFTING TACKLE INCLUDED IN PROOF LOAD TEST) ITEM DESCRIPTION TAG/IDENTIF. No S.W.L. CERTIFICATE No 5129-1890 5129-1891 333 KG 300 KG 940414 940414 1. DONUT POST PADEYE 2. PAINTER PADEYE 3. 4. 5. 6. SECTION 2: IF APPLICABLE, STATE ANY SPECIFIC LIFTING RESTRICTIONS WHICH MAY APPLY TO THE LIFTING EQUIPMENT OR SYSTEM AND WHICH IS REQUIRED TO BE CLEARLY MARKED ON THAT EQUIPMENT SECTION 3: IF APPLICABLE, REFERENCE ANY FABRICATION, NDT, MATERIAL CONTROL CERTIFICATION AND INSPECTION REPORTS RELATING TO THE CONSTRUCTION INSTALLATION ACTIVITIES COPIES OF ALL PROOF LOAD CERTIFICATION LISTED ABOVE TO ACCOMPANY THIS CERTIFICATE COMPANY SIGNATURE PRINT NAME DATE COMPLETED BY BIS BP A.SERVICE 25/04/01 A.CLIENT 25/04/01 GOC APPROVED BY © BP Exploration 1989 – 2001 All Rights Reserved DOUBLE SIDED FORM Americas REV. 1 MECHANICAL HANDLING EXAMINATION REPORT EQUIPMENT No. LIFERAFT No 4 SH1 No WIN No. MC1 No. C620C0586+01 1529-1890 & 1529-1891 FORM MH2 (SIDE 2) C620C0586 SERIAL No. N/A S.W.L. 300 KGs & 333 KGs DRAWING No 2424-03-01-53-109-015 PROOF LOAD TEST CERTIFCATE No 940414 EXAMINATION REPORT 5129-1890 - ACCEPTABLE 5129-1891 - POST TO BE STENCILLED WITH WIN NUMBER AND SWL. THIS HAS BEEN RECORDED ON THE HANDOVER PUNCH LIST. COMMENTS REFER TO ATTACHED BUCHAN INSPECTION SERVICES (BIS) TEST CERTIFICATE No 940414 PUNCH LIST NO. COMPLETED BY APPROVED BY BIS BP PRINT NAME A.SERVICE A.CLIENT DATE 24/04/01 25/04/01 COMPANY SIGNATURE GOC © BP Exploration 1989 – 2001 All Rights Reserved DOUBLE SIDED FORM Americas REV. 1 Technical Integrity Assurance Rev 03 Documentation requirements for Systems to be Handed Over or returned to the Operator for Operational use Mechanical Discipline - Vessels & Piping No Yes Project or Modification? Yes No Hydro-Carbon, Hydraulic or Methanol Systems? No Water or Air / Nitrogen System? No (including Potable or Foul) Yes No Has the Item been Strength Tested? Yes Operating Pressure No over 100 psig (Water) or 15 psig (Air)? Yes GOC© BP Exploration 1989 – 2001 All Rights Reserved Will Integrity (Containment) be broken? Yes Has the Item Yes been Strength Tested? No Is a Major No Components Involved? Yes Strength-test(MP1) &/or Leak Test (SL1) &/or Joint Service Test (JI1) - Implement GOC process to demonstrate TI. High Risk Leak Test(SL1) & Joint Service Test (JI1) - raise SH1and Record in Maintenance Management System. Medium/High Risk Strength-test (MP1) & / or Joint Service Test (JI1). Record in Maintenance Management System. Medium/Low Risk No Formal Testing, Certification or Documentation Required. Low Risk Rev 03 Technical Integrity Assurance Documentation requirements for Systems to be Handed Over or returned to the Operator for Operational use Electrical and Control Disciplines Will Integrity (Circuitry) be broken? (This Includes Software Modifications) No GOC© Yes Yes Does the Activity involve No Temporary Portable Equipment? Yes Implement GOC to Demonstrate Technical Integrity of Project or Modification High Risk BP Exploration 1989 – 2001 All Rights Reserved Is the Activity a new Project or Modification to a No Facility? Does the Repair / Does the Repair / Maintenance involve Maintenance involve Major Components of No Major Components of No the Plant or Electrical the ESD or Fire & Gas Systems? Systems? Yes Raise appropriate GOC Certificates to ensure TI is maintained, record in the Maintenance Management System Medium/High Risk Yes No Formal Testing Certification or Documentation Required. Update Maintenance Management System Medium/Low Risk No Formal Testing, Certification or Documentation Required. Low Risk Functional Certification Flowchart WESTERN HEMISPHERE FABRICATION ACTIVITIES MECHANICAL - GOC 2 - 7 FUNCTIONALITY CHECKING ACTIVITIES JI1 PART A COMPLETE – DATA CARRIED FORWARD MW1 MP1 JI1 PART B COMPLETE DATA CARRIED FORWARD JI1 PIPING SF1 VESSELS MV1 JI1 MACHINERY MM1 JI1 HANDLING EQUIPMENT MH1 MH2 HVAC MM1 SP2 MM2 SL1 JI1 SL1 JI1 SL1 JI1 JI1 Part B JI1 Part A 1 SS1 AS1 JI1 Part C AS2 Non -Fabrication Activities SYSTEM SAFE CERTIFICATE CONTROL - GOC 8 INSTRUMENTS FIRE & GAS TELECOMS ELECTRICAL - GOC 9 1 JOINT INTEGRITY CERTIFICATE MS1 ARCHITECTURAL SERVICES IRN JI1 MW1 STRUCTURAL INSPECTION RELEASE NOTE 3 Note on SS1Certificate THE SYSTEM SAFE CERTIFICATE (SS1) FACILITATES THE HANDOVER OF THE SYSTEM FROM THE OPERATING AUTHORITY TO THE CONSTRUCTION AUTHORITY TO CONFIRM THE SYSTEM IS ISOLATED AND IS IN A SAFE CONDITION READY FOR CONSTRUCTION TO COMMENCE. MECHANICAL COMPLETION CERTIFICATE MC1 CC1 PP1 SYSTEM HANDOVER CERTIFICATE PLANT PERFORMANCE CERTIFICATE PL1 NP1 PUNCH LIST NONPERFOMANCE SC1 EE1 2 PL1 EE2 PUNCH LIST 2 EE3 EE4 EE14 3 Note on JI1Certificate ALL FLANGES, JOINTS, COMPRESSION FITTINGS OR PLUGS IN PORTED BLANKS, IN PIPEWORK CONTAINING PROCESS HYDROCARBONS, DIESEL, PROCESS CHEMICALS, HYDRAULIC FLUIDS, LUBRICATION OIL SYSTEMS, WATER INJECTION, WATER RE - INJECTION. MUST BE TAGGED AND RECORDED ON A JI1 CERTIFICATE. APPLY SL1 & JI1 CERTIFICATES. EE16 EE7 EE17 EE8 REFER TO GOC PIPING SECTION FOR FULL DETAILS EE18 EE9 EE11 EE13 EE15 EE6 EE10 SC1 Note on PL1Certificate AS PART OF THE CONTINUAL REVIEW & CLEARANCE PROCESS OF AGREED PUNCH LIST ITEMS. CARRY EXISTING ‘B’ ITEMS FORWARD TO PC1 & SH1 STAGE EE5 VENDORS/ SUPPLIERS WORKS SP1 SH1 CONSTRUCTION POWER DOWN OPERATIONAL PHASE COMMISSIONING POWER UP EE12 IRN SS1 MC1 PL1 SH1 PP1 NP1 MW1 MP1 MV1 MM1 MH1 MS1 AS1 AS2 HANDOVER MANAGEMENT : INSPECTION RELEASE NOTE : SYSTEM SAFE CERTIFICATE : MECHANICAL COMPLETION CERTIFICATE : PUNCH LIST : SYSTEM HANDOVER CERTIFICATE : PLANT PERFOMANCE CERTIFICATE : NON-PERFORMANCE CERTIFICATE MECHANICAL INSTALLATION : WELDING COMPLETION SUMMARY : PIPING COMPLETION : PRE-OPERATIONS INSPECTION : MACHINERY INSTALLATION : MECHANICAL HANDLING INSTALLATION : STRUCTURAL COMPLETION : FINAL PAINT COMPLETION : FINAL COATING/INSULATION COMPLETION CONTROL INSTALLATION CC1 : CONTROL COMPLETION CERTIFICATE ELECTRICAL INSTALLATION EE1 : LV & MV CABLE TEST CERTIFICATE EE2 : SWITCHGEAR, MCC, BUS DUCT TEST CERTIFICATE EE3 : LV & MV CIRCUIT BREAKERS TEST CERTIFICATE EE4 : CONTACTOR STARTER & VSD TEST EE5 : MV FUSED AIR SWITCH INSPECTION CERTIFICATE EE6 : POWER TRANSFORMER TEST EE7 : NEUTRAL GROUNDING RESISTOR TEST EE8 : HEAT TRACE TEST EE9 : ELECTRICAL GROUNDING EE10 : HAZARDOUS LOCATIONS EE11 : INSTRUMENT TRANSFORMER TEST EE12 : PRIMARY & SECONDARY INJECTION RELAY TEST GOC© BP Exploration 1989 - 2001 All Rights Reserved MECHANICAL TESTING : SYSTEM FLUSH : SYSTEM LEAK OR SERVICE TEST : JOINT INTEGRITY CERTIFICATE : PRE-OPERATIONS ALIGNMENT : MECHANICAL HANDLING LOAD TEST : SYSTEM PERFORMANCE TESTS CONTROL TESTING SC1 : SYSTEM CONTROL (FUNCTION) TEST(s) SP1 : SYSTEM PERFORMANCE TEST (HIPS) SF1 SL1 JI 1 MM2 MH2 SP2 EE13 EE14 EE15 EE16 EE17 EE18 : : : : : : ELECTRICAL TESTING ELEC. MOTOR/ROT. MACHINERY TEST BATTERIES/BATTERY CHARGER TEST U.P.S. TEST GENERAL TEST CERTIFICATE ** ** CAN BE USED IN BOTH NAV - AIDS TEST CONSTRUCTION & AC GENERATOR TEST COMMISSIONING PHASES Western Hemisphere Revision 1 GUIDANCE ON CERTIFICATION GOC © AMERICAS EDITION SUBJECT: SYSTEM PRINCIPLES - APPENDICES APPENDIX 1.3 Typical Basis of Design Contents GOC© BP Exploration 1989 – 2001 All Rights Reserved SECTION 1 REVISION: 1 PAGE: iv BP Exploration Typical 'BASIS OF DESIGN' Contents Sheet Section 1 2 3 4 5 6 7 8 9 10 11 12 - GOC© Content Introduction Current Status Proposed Solution Scope of Work Design Data Weight Impact Safety Aspects Handover Strategies Constructability/Commissionability Drawings Data Capture Manuals and Training Requirements BP Exploration 1989 – 2001 All Rights Reserved Americas REV. 1 GUIDANCE ON CERTIFICATION GOC © AMERICAS EDITION SUBJECT: SYSTEM PRINCIPLES - APPENDICES APPENDIX 1.4 Asset Nomination of Authorities GOC© BP Exploration 1989 – 2001 All Rights Reserved SECTION 1 REVISION: 1 PAGE: v Asset Nomination of Authorities Activity Area Signatory Body Engineering • Discipline - Mechanical - Piping - Structural - HVAC - Architectural Services - Electrical - Instruments - Fire & Gas - Telecoms - Civil • Handover Management • EQ Management • CA Co-ordination • As-Build Co-ordination • Master Records Update / Close-out • Approval Authority Construction • Discipline - Mechanical - Piping - Structural - HVAC - Architectural Services - Electrical - Instruments - Fire & Gas - Telecoms - Civil • Approval Authority Maintenance • Discipline - Mechanical - Piping - Structural - HVAC - Architectural Services - Electrical - Instruments - Fire & Gas - Telecoms - Civil • Approval Authority GOC© BP Exploration 1989 – 2001 All Rights Reserved Americas REV. 1 Asset Nomination of Authorities Activity Area Signatory Body Commissioning • Discipline - Mechanical - Piping - Structural - HVAC - Architectural Services - Electrical - Instruments - Fire & Gas - Telecoms - Civil • Approval Authority Operations • Discipline - Mechanical - Piping - Structural - HVAC - Architectural Services - Electrical - Instruments - Fire & Gas - Telecoms - Civil • Approval Authority Site Handover Management • Handover Control • Drawing / Documentation Control • EQ Control • Punch List Control • Approval Authority GOC© BP Exploration 1989 – 2001 All Rights Reserved Americas REV. 1 GUIDANCE ON CERTIFICATION GOC © AMERICAS EDITION SUBJECT: SYSTEM PRINCIPLES - APPENDICES APPENDIX 1.5 Glossary of Terms GOC© BP Exploration 1989 – 2001 All Rights Reserved SECTION 1 REVISION: 1 PAGE: vi SUBJECT: GUIDANCE ON CERTIFICATION APPENDIX 1.5 GOC© AMERICAS EDITION REVISION: 1 GLOSSARY OF TERMS PAGE: 1 GLOSSARY OF TERMS It is appreciated that staff who have worked and are familiar with the Guidance On Certification© (GOC©) will understand the abbreviations used, and so will not need to use this glossary. However, in the case of new staff, they may not understand the terminology and so this maybe a useful reference. Incidentally, it will also serve to restrict the number of abbreviations which are used for any one piece of information i.e. Drawing Number should be DRG NO or DRW NO and NOT both. ABS American Bureau of Standards AFA Approved For Alteration ACC Accepted AFC Approved For Construction (Drawing) AS1 Final Paint Completion Certificate AS2 Final Coatings/Insulation Completion Certificate BOD Basis of Design CA Certifying Authority CBT Computer Based Training CC Commissioning Controller CE Certification Engineer CC1 Control Completion Certificate CCO Commissioning Co-ordinator CMP Commissioning Management Process COF Certificate of Ftness certifies that the installation is fit to be the established/stationed and maintained in the relevant waters. CS Commissioning Superintendent GOC© BP Exploration 1989 – 2001 All Rights Reserved SUBJECT: GUIDANCE ON CERTIFICATION APPENDIX 1.5 GOC© AMERICAS EDITION REVISION: 1 GLOSSARY OF TERMS DC Document Control DCR Design Construction Regulations DIS Data Input Sheet DRW No Drawing Number DP Dye Penetrate DTI Department of Trade and Industry (UK) PAGE: 2 EE1 SHT 01 02 03 04 Shielded Instrument Cable, Insulation Resistance Cable and Wire Insulation, Insulation Resistance Cable D.C. High Potential Step Voltage Insulation Resistance and DC Hi-Pot Graph EE2 SHT 01 02 Switchgear Bus Insulation and Phasing MCC Bus Insulation and Phasing EE3 SHT 01 02 03 04 L.V. Power Circuit Breaker Molded Case Breakers Med. Voltage Circuit Breaker High Voltage Limited Oil Interrupter EE4 SHT 01 02 03 Contact Type Starter Motor Thermal Overload Relay Variable Speed Drives EE5 SHT 01 Medium Voltage Air Switch Inspection EE6 SHT 01 02 03 Two Winding Power Transformer Transformer Turns Ratio (Requires Sketch on Back) Three Winding Power Transformer EE7 SHT 01 Neutral Grounding Resistor EE8 SHT 01 02 Heat Trace Tape Inspection (Electrical) Heat Trace Performance (Electrical) EE9 SHT 01 02 Electrical Ground System Test Grounding Resistance Test (Individual Electrodes) EE10 SHT 01 Hazardous Location Certificate EE11 SHT 01 Instrument Transformer Ratio Tests GOC© BP Exploration 1989 – 2001 All Rights Reserved SUBJECT: EE12 SHT 01 02 03 GUIDANCE ON CERTIFICATION APPENDIX 1.5 GOC© AMERICAS EDITION REVISION: 1 GLOSSARY OF TERMS PAGE: 3 Primary Injection Test Secondary Injection Test Relay Inspection (Individual units) 04 05 06 Over Current Relay Test Instantaneous Over Current Relay Test Over/Under Voltage Relay Test 07 08 09 Power Factor Relay Test Frequency Relay Test Transformer Differential Relay Test 10 Reverse Power Relay Test EE13 SHT 01 02 Motors and Motor Circuits, Phase Rotation & Tests Rotating Machinery EE14 SHT 01 02 Battery Load Test (Bank) Individual Battery Test Log EE15 SHT 01 UPS Power Supply EE16 SHT 01 General Test Certificate EE17 SHT 01 Navigational Aids EE18 SHT 01 02 AC Generator and Generator Circuits Test Rotating Machinery (AC Generator) Test (Individual Unit P.F. and PDA tests) E&ID Electrical * Instrumentation Diagram EQUIP No Equipment Identification Number EQ Engineering Query aka Request For Information (RFI) ESD Emergency Shutdown F&G Fire & Gas FLOW DIAG Flow Diagram FCO Functional Check Out (commissioning activities) GOC© BP Exploration 1989 – 2001 All Rights Reserved SUBJECT: GUIDANCE ON CERTIFICATION APPENDIX 1.5 GOC© AMERICAS EDITION REVISION: 1 GLOSSARY OF TERMS PAGE: 4 GA No General Arrangement Drawing Number G/L DRW Green Lined Drawing (Commissioning As Built) GOC © Guidance On Certification© HCP Handover Certification Pack aka Turnover Pack HCR Handover Change Request HIPS High Integrity Performance System HSE Health & Safety Executive HVAC Heating, Ventillation, Air Conditioning IA Integrity Authority ICS Instrument Contol System IFC Issued For Construction (Drawing) IRN Inspection Release Note is issued by an approved vendor to demonstrate item(s) are to the required specification I&T Inspection and Test ITS Inspection and Test Summary defines the minimum Inspection and Test requirements for a system, part system or workpack. IVA Independent Verification Authority JI1 Joint Integrity Installation Certiticate JB Junction Box JP No Job Pack Number LAD List of As-Built Drawings LOSH Limits of System Handover describes the boundries of a particular Handover (single or multi-disciplinary) from within which all the appropriate I&T activites can be established. LTO Licence to Operate gives the operator the authority to operate the plant within defined parameters. GOC© BP Exploration 1989 – 2001 All Rights Reserved GUIDANCE ON CERTIFICATION APPENDIX 1.5 GOC© AMERICAS EDITION REVISION: 1 SUBJECT: © GLOSSARY OF TERMS PAGE: 5 © MANCON MANagement CONtrol MAOP Maximum Allowable Operating Pressure MAWP Maximum Allowable Working Pressure MC1 Mechanical Completion Certificate is the formal handover from the construction/maintenance authority to the commissioning authority. MDR Material Data Reports ME Maintenance Engineer MH1 Mechanical Handling Installation & Acceptance Certificate MH2 Mechanical Handling Load Test Certificate MICC Mineral Insulated Control Cable MM1 Machinery Installation Certificate MM2 Machinery Alignment Certificate MMS Mineral Management System MP1 Piping Completion Certificate MPI Magnetic Particle Inspection MS1 Structural Completion Certificate MV1 Mechanical Vessel/Tank/Cassion Installation & PSV/RD - Pre Operations Inspection Certificate MW1 Weld/Bolt-Up Summary MPI Magnetic Particle Inspection MT Magnetic Particle Testing NCR Non-Conformance Report NDE Non-Destructive Examination NP1 Non-Performance Certificate NRV Non-Return Valve OIE Offshore Inspection Engineer OM Operations Manager OIM Offshore Installation Manager GOC© BP Exploration 1989 – 2001 All Rights Reserved GUIDANCE ON CERTIFICATION APPENDIX 1.5 GOC© AMERICAS EDITION REVISION: 1 SUBJECT: GLOSSARY OF TERMS PAGE: 6 PE Production Engineer PFD Process Flow Diagram PI Polarization Index P&ID Piping and Instrument Diagram P&ID No See P&ID PL1 Punch List Form PP1 Plant Performance Certificate PSV Pressure Safety Valve PT Liquid Penetrant Testing QA Eng Quality Assurance Engineer QC Quality Control QP Quality Plan RD Rupture Disk RE Resident Engineer R/L DRW Red Lined Drawing (Construction As Built) RO Repair Order RFI Request (Raise) For Information aka Engineering Query (EQ) SCE Senior Commissioning Engineer SC1 System Control Certificate SF1 System Flush Certificate SH1 System Handover Certificate is the formal handover from the commissioning authority to the operating authority. SL1 System Leak /ServiceTest SLD Single Line Diagram SOW Scope of Work SP1 System Performance Test (HIPS) SP2 System Performance Test(s) (HVAC) GOC© BP Exploration 1989 – 2001 All Rights Reserved SUBJECT: GUIDANCE ON CERTIFICATION APPENDIX 1.5 GOC© AMERICAS EDITION REVISION: 1 GLOSSARY OF TERMS PAGE: 7 SQAE Senior Quality Assurance Engineer SS1 System Safe Certificate SSK No Site Sketch Number SWL Safe Working Load TAG No Identification Number TI Technical Integrity ; The condition of a PLANT that meets its design criteria and intended purpose. Where deviation from these exist they have been identified and assessed and any changes necessary to ensure continued safe, efficient operation have been implemented. TIAF Technical Integrity Assurance Flowchart helps the user to evaluate the level of documentation/certification required commensurate with the risk. TIPS Technical Integrity Performance Standards TP Turnover Pack aka Handover Certification Pack (HCP) TQ Technical Query USCG United States Coast Guard WIN No Works Inspection Number WP No Work Pack Number WPS Welding Procedure Specification GOC© BP Exploration 1989 – 2001 All Rights Reserved SUBJECT: GUIDANCE ON CERTIFICATION SECTION 2.0 GOC © AMERICAS EDITION REVISION: 1 MECHANICAL- WELDING AND NDE SECTION 2.0 WELDING AND NDE GOC© BP Exploration 1989 – 2001 All Rights Reserved PAGE: 1 SUBJECT: GUIDANCE ON CERTIFICATION SECTION 2.0 GOC © AMERICAS EDITION REVISION: 1 MECHANICAL- WELDING AND NDE 2.1 ACTIONS 2.1.1 General PAGE: 2 Construction Management responsibilities and associated Quality Planning for welding activities is normally categorized and managed as follows: a) On-Site Work. The Construction Authority is responsible for ensuring that the Inspection & Test requirements are carried out and for management of the construction Contractor who provides labor and equipment only. b) Off-Site Work. The Construction Authority monitors the performance of the Management Contractor who is directly responsible for fabrication and Inspection and Test activities. c) For on-site work, those Inspection and Test activities that require to be performed and recorded to fulfill the minimum quality requirements are clearly defined on the specific Inspection & Test Summary (ITS) for the Project. d) For off-site work, those inspection and test activities performed by the Managing Contractor that are deemed by BP or their Delegated Authority to be at critical stages in the fabrication process and require to be witnessed before the contractor can proceed, will be clearly defined within the Contractor's Quality Plan (QP) or the supplied ITS. e) The term “construction” within this section should imply both on-site and off-site fabrication. f) All welding activities shall be checked for compliance and other requirements as detailed in, but not limited to: • • The latest revision of Issued For Construction (IFC) or Approved For Construction (AFC) Drawings and Schedules Codes and standards reference in this section GOC© BP Exploration 1989 – 2001 All Rights Reserved SUBJECT: 2.1.2 GUIDANCE ON CERTIFICATION SECTION 2.0 GOC © AMERICAS EDITION REVISION: 1 MECHANICAL- WELDING AND NDE PAGE: 3 • • • • Plant and Project Specifications Equipment Specifications and Data sheets BP Engineering Installation and Design Specifications Local, state, country and international standards, codes, and regulations as appropriate • Offshore - Special Standards, i.e. USCG, ABS and MMS Welders Qualifications All welders or welding operators shall have passed a welder qualification test to a code or standard as specified in the appropriate Specification. Such qualification tests shall have been witnessed by an approved independent third party inspector, acceptable to BP or their delegated authority. All records shall be endorsed by the Third Party Inspector and the authorized Welding Inspector whose decision on acceptance shall be final. Note: Where appropriate, for off-site work, the Senior Welding Inspector authorized by BP or its Delegated Authority may transfer the responsibility for witnessing welder qualifications Management Contractors Welding Inspector. to the 2.1.3 Prior Qualifications Prior qualifications of welders may be considered where the integrity of the records can be demonstrated and any such qualifications are current. 2.1.4 NDE Qualifications Qualifications and Certifications for Non-destructive examination (NDE) personnel shall be per the requirements listed in: ASNT-TC-1A: Recommended Practice for Personal Qualification & Certification in Nondestructive Testing AWS-QC1: Standard for AWS Certification of Welding Inspectors GOC© BP Exploration 1989 – 2001 All Rights Reserved SUBJECT: GUIDANCE ON CERTIFICATION SECTION 2.0 GOC © AMERICAS EDITION REVISION: 1 MECHANICAL- WELDING AND NDE 2.2 Weld Inspection 2.2.1 General a) Guidelines For Weld Inspection PAGE: 4 An essential requirement for the implementation of a simple control system for weld identification by utilizing the structural fabrication or isometric drawings, prior to the commencement of work. These drawings should detail the full weld history by identifying each weld and welder identification symbol. Material traceability falls within the following categories: b) For onsite fabrication BP operates secured materials storage system with approved auditable suppliers re materials certification and the level of traceability is appropriate to ensure materials meet the required project codes and specifications. c) For off site fabrication BP or their delegated authority ensures the fabricator has the appropriate and approved audible materials control system and warehousing procedures in operation. d) The following activities shall be performed by the Welding Inspector authorized by BP or Delegated Authority for onsite work, the Management Contractors Welding Inspector for offsite work and the Third Party Inspectorate, where applicable. e) Prior to commencement of welding activities the Welding Inspector shall ensure that: A procedure for cold and hot cutting and weld preparation, inclusive of material identification transfer, has been approved by BP or Delegated Authority; GOC© BP Exploration 1989 – 2001 All Rights Reserved SUBJECT: GUIDANCE ON CERTIFICATION SECTION 2.0 GOC © AMERICAS EDITION REVISION: 1 MECHANICAL- WELDING AND NDE PAGE: 5 A BP or Delegated Authority approved WPS is available to the welder/welding operator in written form or displayed prominently at the welding location; Welders/welder operators understand all requirements of the approved procedures and are qualified to carry out the work; A system to control the issue and use of welding consumables, as required by project specifications has been agreed by BP or Delegated Authority Welding Engineer and is in operation; Appropriate measures for the protection against inclement weather conditions have been taken; All welding equipment, where applicable, is certified as fit for use. All pre-heat and post weld heat treatment equipment has current calibration report and is certified for use. All weld preparations shall be in accordance with the specification requirements and be clean and free of contaminants; All fit-ups are within the weld procedure tolerances. f) During Welding operations, the Welding Inspector shall monitor that: The relevant weld procedure as required by the applicable scope of work is in place and that the operator is suitably qualified; The issue of consumables and their control conforms to the applicable weld and control procedure; Pre-heat and interpass temperature levels are maintained in accordance with approved WPS; GOC© BP Exploration 1989 – 2001 All Rights Reserved SUBJECT: GUIDANCE ON CERTIFICATION SECTION 2.0 GOC © AMERICAS EDITION REVISION: 1 MECHANICAL- WELDING AND NDE PAGE: 6 Runout tabs on critical pipe fabrication comply with the applicable welding procedure. Specified inspection hold points have been preformed by the appropriate NDE examiner or Welding Inspector. g) On completion of welding operations, the Welding Inspector shall: Visually inspect all welds to ensure compliance with the specification and good workmanship, and confirm that the welder's identification is marked adjacent to the weldment; Ensure that, where applicable, post weld heat treatment is carried out as per the specification, endorsing the heat treatment record charts accordingly; Ensure that where specified, a delay prior to NDT for ferritic steels is enforced. Verify that specified NDE inspections have been preformed prior/during the welding process (i.e.: MT or root pass). h) Prior to NDE operations the Welding Inspector should check that: All NDE procedures are approved by BP or delegated authority, to ensure that they conform to the requirements of the fabrication specification; All NDE operators’ qualifications and certifications are acceptable and are to the appropriate certification levels; All NDE equipment and consumables are certified and fit for use and certified as applicable; UT equipment should have current annual calibration sticker; GOC© BP Exploration 1989 – 2001 All Rights Reserved SUBJECT: GUIDANCE ON CERTIFICATION SECTION 2.0 GOC © AMERICAS EDITION REVISION: 1 MECHANICAL- WELDING AND NDE PAGE: 7 Inspection hold point areas that require crack detection to be witnessed by BP or Delegated Authority have been specified. i) Post NDE operations the Welding Inspector should check that: For ultrasonic, liquid penetrant or magnetic particle testing, the test has been carried out using the correct equipment, consumables and technique, and that results have been reported correctly and interpreted to the specification limits; For radiographic testing, the test has been carried out using the correct procedure, films have been developed in a correct manner and interpreted to the applicable code. j) All NDE operations should be monitored throughout fabrication and construction work as part of the overall quality control system. The above is the minimum requirement but is not exclusive and may be modified and categorized by the authorized Senior Welding Inspector or authorized Welding Engineer. k) The performance of each welder/welder operator should be assessed to ensure that his work meets minimum specification requirements with the minimum repair rate while meeting production milestones. Welder/welding operators who produce consistently bad workmanship shall be subject to retesting before being allowed to continue. The decision as to whether such a welder/welding operator can be allowed to restart welding operations is at the sole discretion of the Welding Inspector. l) Each weld examination record should be endorsed by the Welding Inspector to signify acceptance of the results. GOC© BP Exploration 1989 – 2001 All Rights Reserved SUBJECT: GUIDANCE ON CERTIFICATION SECTION 2.0 GOC © AMERICAS EDITION REVISION: 1 MECHANICAL- WELDING AND NDE 2.2.2 Use Of Forms a) General Requirements PAGE: 8 For on-site work, all reporting and recording of the results of Inspection © and NDE Tests shall be on the GOC standard form MW1 - Welding Completion Summary. For off-site, and on-site NDE, reporting and recording of results may be on the Contractor's standard NDE forms when approved by BP or Delegated Authority. Brief details of the various forms are given below. NDE reports can be used for recording the results of testing of more than one acceptable weld provided that: i. The welds are all on a single piping isometric or structural assembly drawing; ii. All parameters of the testing technique are identical for each weld; iii. Rejectable welds and any associated repairs are separately reported. NB: This extension of the use of NDE reports does not extend to pipe-line riser welds, which shall be individually reported. b) Ultrasonic Inspection Report To record the findings of the ultrasonic inspection and the techniques, equipment, and parameter(s) used. GOC© BP Exploration 1989 – 2001 All Rights Reserved SUBJECT: GUIDANCE ON CERTIFICATION SECTION 2.0 GOC © AMERICAS EDITION REVISION: 1 MECHANICAL- WELDING AND NDE PAGE: 9 Where necessary, a sketch showing reportable defect area dimensions and locations, or outlining limited examination circumstances, shall be attached to the parenting form. c) Magnetic Particle/Dye Penetrant Report To record the results of magnetic particle or liquid penetrant examinations and the parameters used. Where necessary, a sketch showing reportable defect area dimensions and locations, or outlining limited examination circumstances, shall be attached to the parenting form. d) Radiographic Report To record the results of radiographic examination of a weld, equipment, and the parameters used. Generally each report shall cover all of the parameters for the same spool, i.e. wall thickness, diameter, exposure time, density, radiation source type, film type, procedure number, etc., the report can cover more than one weld. e) MW1 - Welding/Bolt-up Completion Summary To record report numbers, including repairs for all visual examinations, NDE and post weld heat treatment carried out on each weld on a subassembly or pipe spool and bolted connections in order to provide a summary and allow easier retrieval of the back-up certificates. The MW1 can effectively be used as an acceptance document to front all weld inspection records within a Handover Certification Pack. GOC© BP Exploration 1989 – 2001 All Rights Reserved SUBJECT: f) GUIDANCE ON CERTIFICATION SECTION 2.0 GOC © AMERICAS EDITION REVISION: 1 MECHANICAL- WELDING AND NDE PAGE: 10 Heat Treatment Report To record the parameters used for the heat treatment of a component or weldment. The temperature-time record at the beginning of the heat treatment process should be "signed on" by the Welding Inspector and "signed off" when the process is complete. On completion of the heat treatment, the equipment calibration report and the printout from the temperature and time recorder shall be attached to the report for final acceptance. Where items have been post weld heat treated as a batch, all item numbers should be endorsed on the original temperature time record and the individual heat treatment reports (if more than one is required), should cross refer to the heat treatment report to which the original certifications is attached. g) Qualification Test Record All Welding Procedure Specifications and the results of monitoring weld deposits and the laboratory test results shall be on the Contractors preapproved standard forms. Welding Procedure Specification (WPS) Welding Procedure Qualification Test Report Macro Survey Test Results Charpy Impact Test Results Hardness Survey Test Results GOC© BP Exploration 1989 – 2001 All Rights Reserved SUBJECT: h) GUIDANCE ON CERTIFICATION SECTION 2.0 GOC © AMERICAS EDITION REVISION: 1 MECHANICAL- WELDING AND NDE PAGE: 11 Welder Approval Test Certificate All welders/welding operators shall be qualified to the approved WPS for the work to be carried out. All such welder/welding operators’ tests shall be recorded on the Contractors pre-approved standard form(s). i) Summary of Approved Welders A summary of all welders/welding operators, including Sub-contractors shall be maintained by the Welding Inspector and shall fully reference welder’s identification, procedures, positions, thickness and diameters, they are qualified to perform. j) Summary of Approved Weld Procedures A summary of all weld procedures including qualifying positions and reports, including Sub-contractor's, shall be maintained by the Welding Inspector. k) Summary of Approved NDE Technicians A summary of all NDE technicians, including Sub-contractor's, shall be fully referenced by type of NDE and shall be maintained by the Welding Inspector. l) Summary of Approved NDE Procedures All NDE procedures, including Sub-contractor's, shall be fully referenced on the NDE Procedure Register, which shall be maintained by the Welding Inspector. m) Weld Repair Register To be completed by particular structural assembly, construction isometric or spool piece drawing. GOC© BP Exploration 1989 – 2001 All Rights Reserved SUBJECT: GUIDANCE ON CERTIFICATION SECTION 2.0 GOC © AMERICAS EDITION REVISION: 1 MECHANICAL- WELDING AND NDE PAGE: 12 All repairs, including those performed prior to PWHT shall be recorded on the MW1 and the Weld Repair Register. Weld repairs shall be indicated as follows: R1 = First Repair R2 = Second Repair C1 = Re-weld These indicators shall be recorded as suffix to both the weld and inspection report numbers. Where welds are repaired or re-welded they shall retain their original weld number. Inspection reports for weld repairs or re-welds shall retain their original report number. GOC© BP Exploration 1989 – 2001 All Rights Reserved SUBJECT: GUIDANCE ON CERTIFICATION SECTION 2.0 GOC © AMERICAS EDITION REVISION: 1 PAGE: 13 MECHANICAL- WELDING AND NDE FLOWCHART 2 • Functional Certification Flowchart • Discipline: Mechanical (Welding) MW1 MC1 SH1 MW1: Welding Completion Summary MC1: Mechanical Completion Certificate SH1: System Handover Certificate GOC© BP Exploration 1989 – 2001 All Rights Reserved SUBJECT: GUIDANCE ON CERTIFICATION SECTION 2.0 GOC © AMERICAS EDITION REVISION: 1 MECHANICAL- WELDING AND NDE EXHIBIT 2 STANDARD FORMS Form No. Title MW1 Weld/Bolt-up Completion Summary GOC© BP Exploration 1989 – 2001 All Rights Reserved PAGE: 14 Project Title: Description: FORM MW1 Work Pack No: SITE: Maintenance No: Line No: WELD / BOLT-UP COMPLETION SUMMARY DRAWING NUMBER WELD CATEGORIES Insp. Initials WELD NUMBER S - SHOP WELD WELDERS IDENT W - FIELD WELD COMPILED BY WPS SH1 No: VISUAL INSPECT X - BRANCH NDE TYPE NDE ACCEPT DATE SW - SOCKET WELD SHT MC1 No: GASKET TYPE TORQUE Ft-Lbs R1 - FIRST REPAIR OF COMMENTS R2 - SECOND REPAIR C1 - RE-WELD APPROVED BY COMPANY SIGNATURE NAME DATE GOC© BP Exploration 1989 – 2001 All Rights Reserved Americas REV. 1 SUBJECT: GUIDANCE ON CERTIFICATION SECTION 3.0 GOC © AMERICAS EDITION REVISION: 1 MECHANICAL- PIPE TESTING PAGE: 1 SECTION 3.0 PIPE TESTING GOC© BP Exploration 1989 - 2001 All Rights Reserved SUBJECT: 3.1 GUIDANCE ON CERTIFICATION SECTION 3.0 GOC © AMERICAS EDITION REVISION: 1 MECHANICAL- PIPE TESTING PAGE: 2 ACTIONS 3.1.1 General a) The acceptance of off-site fabricated and on-site installed pipework is a composite function of Welding and Weld Inspection (Section 2.0), Pipe Testing (Section 3.0), and Architectural Services (Section 7.0). Input by the relevant discipline engineers is required during quality planning and subsequent development of an Inspection & Test Summary. All Pressure Testing shall be undertaken when suitable barriers and notices are in place around the test area. b) Pipework shall be checked for compliance and other requirements as detailed in, but not limited to: • • • • • • • c) The latest revision of Issued For Construction (IFC) or Approved For Construction (AFC) Drawings and Schedules Codes and standards reference in this section Plant and Project Specifications Equipment Specifications and Data sheets BP Engineering Installation and Design Specifications Local, state, country and international standards, codes, and regulations as appropriate Offshore - Special Standards, i.e. USCG, ABS and MMS Within the system limits or boundaries specified the piping shall be assembled into Test Packs to facilitate Pressure testing (strength-testing of welds), or the installation of pre-hydro tested and pre-certified flanged piping, that will only require to be leak-tested or service-tested postinstallation. The Piping Test Pack number will be pre-fixed with a two letter ID to indicate the type of test required. Below is listed the three most common Piping Test Pack prefixes. HT – Hydro test (strength-testing of welds, raise MP1) LT – Leak Test (leak test pre-certified/tested pipework, raise SL1) ST – Service-test (service-test pre-certified/tested pipework, raise JI1) GOC© BP Exploration 1989 - 2001 All Rights Reserved SUBJECT: GUIDANCE ON CERTIFICATION SECTION 3.0 GOC © AMERICAS EDITION REVISION: 1 MECHANICAL- PIPE TESTING PAGE: 3 The contents of Test Packs index, as a minimum, shall be as follows: i) Work Package Number, and/or Maintenance ID No., and Test Pack No; ii) Hydrotest Schematic where applicable; iii) Isometric drawings or site sketches, where applicable; iv) v) Flange make-up tagging procedure and /or Flange Check register; P&ID. d) The Engineering authority shall produce clear means of identifying the limits of test to reflect the simplicity or complexity, as appropriate, of the hydrotest scope. e) A safety valve shall be fitted to the test equipment or to the equipment/plant being tested, set to relieve at a pressure to prevent the test pressure being exceeded. The safety valve shall be capable of discharging the capacity of the charging system at the test pressure. f) The flowchart contained within this document gives guidelines on quality planning for both on-site and off-site pipe fabrication. 3.1.2 Use Of Forms a) General Requirements For on-site fabrication and installation, all reporting and recording of the results of inspections and tests shall be on the GOC© standard forms, listed in Exhibit 3 (at the end of this section), as specified by the Engineering Authority. For off-site fabrication, reporting and recording of the results of inspections and tests may be on the Contractor's standard forms when recommended by the authorized Mechanical Engineer and approved by the Engineering Technical Authority. GOC© BP Exploration 1989 - 2001 All Rights Reserved SUBJECT: b) GUIDANCE ON CERTIFICATION SECTION 3.0 GOC © AMERICAS EDITION REVISION: 1 MECHANICAL- PIPE TESTING PAGE: 4 MP1: Piping Completion Certificate To record that piping has been satisfactorily pressure tested and reinstated. It is also used to record the following: That flushing/blowing has been carried out to the required cleanliness following completion of Procedures 3.1 and 3.2; In the case of hydrotesting, that the requirements of Procedure 3.1 (3.1.43), should be used. The associated pressure, temperature and time records should be attached to form MP1; When carrying out pneumatic testing, Procedure 3.1, (3.1.5) shall be used; That piping has been satisfactorily reinstated in accordance with Procedure 3.1, (3.1.6). In the case of Fire and Gas piping, that the essential checks have been carried out, ensuring that the piping associated with the fire water mains, sprinkler, deluge and fire suppression systems have been satisfactorily reinstated, in accordance with Procedure 3.1, (3.1.7). c) SF1: System Flushing Certificate To be used by the Commissioning/Operations Authority to denote that a complete system has been flushed prior to leak testing (or completion of witnessed joint as appropriate) and prior to the affected line or system being brought into service. System flushing is to be carried out in accordance with Procedure 3.2, (3.2.1.). GOC© BP Exploration 1989 - 2001 All Rights Reserved SUBJECT: d) GUIDANCE ON CERTIFICATION SECTION 3.0 GOC © AMERICAS EDITION REVISION: 1 MECHANICAL- PIPE TESTING PAGE: 5 SL1: Leak Test Certificate To be used to acknowledge system reinstatement post flushing. To record and formalize the leak-testing of all flanges, joints, compression fittings or plugs in ported blanks, in piping containing, but not limited to: Process Hydrocarbon, Diesel, Process Chemicals, Hydraulic Fluids, Lubricant Oil Systems, Water Injection and Produced Water Re-Injection, or any piping that the facility deems to have a ‘high risk potential’. All Witness Joints will be checked and "signed in" on the SL1 certificate by the Commissioning/Operations representative. Restriction orifice plates and flow orifice plates shall be inspected and measured for size and confirmed Commissioning/Operations Authority and installed certificates by the approved accordingly. The leak test certificate will be supported by a marked up P&ID, clearly defining the test limits, readily identifying the system tested and recording the test pressure, duration and detailing any exclusions or exemptions. Where applicable Fire & Gas reinstatement will be recorded, reference Procedure 3.1 (3.1.7). Vendor leak tests, Vendor Companies, Services tests will also be recorded on this certificate. All such piping will be subject to leak-testing and service-testing, Pre and Post SH1 Handover. SL1 System Leak Test Certificate & JI1 (Joint Integrity Certificate) to be raised accordingly. Refer to Procedures 3.2 (3.2.2) and 3.2 (3.2.4). GOC© BP Exploration 1989 - 2001 All Rights Reserved SUBJECT: e) GUIDANCE ON CERTIFICATION SECTION 3.0 GOC © AMERICAS EDITION REVISION: 1 MECHANICAL- PIPE TESTING PAGE: 6 JI1: Joint Integrity Certificate i) High Risk To record and formalize the installation/making and/or remaking of all flanges, joints, compression fittings or plugs in ported blanks, in piping containing, but not limited to; Process Hydrocarbon, Diesel, Process Chemicals, Hydraulic Fluids, Lubricant Oil Systems, Water Injection and Produced Water Re-Injection, or any piping that the facility deems to have a ‘high risk potential’. All such pipework will be subject to Leak-testing and service-testing, Pre and Post SH1 Handover. To record information relating to the pulling-up and tightening of certain flanged joints on critical duties, when specified by the Commissioning/Operations Authority. Such joints will normally be, but will not be limited to, piping carrying hydrocarbons which cannot be subject to a strength and/or leak-test, but will generally be subject to Critical Joint Installation, Procedure 3.2 (3.2.3) and Service-Test, Procedure 3.2.4. All such joints will be checked and "signed-in" on the JI1 (Joint Integrity Certificate) by the Commissioning/Operations representative. • Part A of the Joint Integrity Certificate must be completed by the Installation Authority. • Part B of the Joint Integrity Certificate must be completed by the Commissioning Authority. • Part C must be completed by the Operating Authority, Post SH1 acceptance. Note: Parts A & B must be completed prior to SH1 acceptance. GOC© BP Exploration 1989 - 2001 All Rights Reserved SUBJECT: GUIDANCE ON CERTIFICATION SECTION 3.0 GOC © AMERICAS EDITION REVISION: 1 MECHANICAL- PIPE TESTING PAGE: 7 The JI1 (Joint Integrity Certificate) records that the Post SH1 ‘StartUp’ and ‘Warm Up’ service-tests have been carried out, and that each joint has been subject to one service-test at ‘Start-Up’ and ‘Warm-Up’ and one service-test every 12 hours thereafter, for a period of 7 days. Reference to Safe Isolation and Re-instatement of Plant (SIRP) UKCS-SSW-001, is recommended. ii) Low Risk For piping with low-risk potential, containing, but not limited to: Seawater, Firewater, Plant Air, Instrument Air, Domestic Waste, Potable Water/Towns Water and Industrial Water, may not be subject to the Flange/Joint Tagging Procedure, but will be subject to Inspection and/or service-testing, where appropriate, to ensure Technical Integrity has been achieved and/or maintained. The JI1 (Joint Integrity Certificate) will record that the Post SH1 ‘Start-Up’ and ‘Warm-Up’ service-tests, where appropriate, have been carried out. Where low-risk piping is recorded on the JI1 (Joint Integrity Certificate), columns that are not applicable, such as Tag Number, Joint Installed By, Date of Installation, Leak-tested By and SL1 Leak Test Number, are to be marked N/A. A marked-up P&ID will be attached to the JI1 (Joint Integrity Certificate) highlighting the service-test limit. The JI1 (Joint Integrity Certificate) requires signatures confirming the appropriate GOC© Procedures have been complete for high risk and low-risk pipework, as appropriate. GOC© BP Exploration 1989 - 2001 All Rights Reserved SUBJECT: GUIDANCE ON CERTIFICATION SECTION 3.0 GOC © AMERICAS EDITION REVISION: 1 MECHANICAL- PIPE TESTING PAGE: 8 3.1.3 Calibration a) It is imperative for both off-site and on-site testing that methods are established to ensure that the inspection and test equipment contained in Figure 1 are properly controlled and calibrated. b) The Contractor responsible for the testing activities contained within this Procedure shall have an established system for the control of this equipment. It shall be the responsibility of the BP or Delegated Authority's representative to ensure that the system is maintained. c) Such systems shall as a minimum address the following: i) Responsibility for control and maintenance of the system inclusive of care and use of each instrument type and performance of calibration activities; ii) Identification of instruments; iii) Calibration Procedures for each instrument type; iv) Frequency and accuracy of calibration; v) Traceability of calibration to a recognized national standard or against a secondary or in-house standard as appropriate; vi) Records of instrument calibrations and system review; vii) Out-of-calibration Procedure addressing both instruments overdue for calibration and those found to be inaccurate. GOC© BP Exploration 1989 - 2001 All Rights Reserved SUBJECT: GUIDANCE ON CERTIFICATION SECTION 3.0 GOC © AMERICAS EDITION REVISION: 1 MECHANICAL- PIPE TESTING PAGE: 9 TEST EQUIPMENT CALIBRATION CHART Equipment Calibration Tolerance Recommended Associated Method Standard Interval Pressure Chart Every 90 Days +/- 1% Recorders Dead-Weight National Tester Bureau of Notes Standards Thermo-couples Every 90 Days +/- 5% Temperature Every 90 Days +/- 1% Volumeters 1 Month +/- 1% Pressure Gauges Every 30 Days +/- 1% Dead-Weight If Not Used API Tester Every 12 Recorders RP1110 Months Figure 1 General Requirements: i) All Inspection equipment should be suitable for the purpose intended and regularly maintained and serviced. ii) Details above are for guidance and may be superceded by Project Specifications/Data Sheets. iii) In addition to the above the contractor shall calibrate any other inspection, measuring or test equipment identified by BP or their Delegated Authority. GOC© BP Exploration 1989 - 2001 All Rights Reserved SUBJECT: GUIDANCE ON CERTIFICATION SECTION 3.0 GOC © AMERICAS EDITION REVISION: 1 MECHANICAL- PIPE TESTING PAGE: 10 PIPE TESTING PROCEDURES Procedure No. 3.1 Installation - Pressure Test Procedure 3.1.1 – Joint Integrity Installation Procedure 3.1.2 - Piping Pre-test Inspection 3.1.3 - Hydrotest Cleaning & Flushing 3.1.4 - Hydrostatic Testing 3.1.5 - Pneumatic Testing 3.1.6 - Piping Completion 3.1.7 - Piping Completion (F&G) Procedure No. 3.2 Operability - Leak Test Procedure 3.2.1 - System Flushing Procedure 3.2.2 - Leak Test Procedure 3.2.3 - Witness Joint Procedure 3.2.4 - Service Test Procedure GOC© BP Exploration 1989 - 2001 All Rights Reserved GUIDANCE ON CERTIFICATION SECTION 3.0 GOC © AMERICAS EDITION REVISION: 1 MECHANICAL- PIPE TESTING PAGE: 11 SUBJECT: Procedure No. 3.1 3.1.1 Joint Integrity a) High Risk The purpose of the Joint Integrity installation procedure is to provide a process by which all risk-potential piping that has been installed and/or broken during construction/maintenance activities can be identified and recorded, so that joint integrity can be checked during leak-testing and maintained during Post SH1 ‘Start-Up’ and ‘Warm-Up’ service-tests. The JI1 (Joint Integrity Certificate) records that the Post SH1 ‘Start-Up’ and ‘Warm Up’ service-tests have been carried out, and that each joint has been subject to one service-test at ‘Start-Up’ and ‘Warm-Up’ and one service-test every 12 hours thereafter, for a period of 7 days. Reference to Safe Isolation and Re-instatement of Plant (SIRP) UKCSSSW-001, is recommended. The procedure detailed below shall be followed for maintenance activities when containment is broken or in the absence of an approved Flange/Joint Tagging procedure for construction activities during projects or modifications. GOC© BP Exploration 1989 - 2001 All Rights Reserved SUBJECT: GUIDANCE ON CERTIFICATION SECTION 3.0 GOC © AMERICAS EDITION REVISION: 1 MECHANICAL- PIPE TESTING PAGE: 12 If the Construction Authority has a procedure that meets the requirements and intent of this procedure then the Construction Authority’s procedure, will be reviewed and approved for use accordingly. i) Each tag will have a unique identification number. A supply of flange/joint tags shall be readily available at a number of location on the facility, i.e. the CCR, instrument and mechanical workshops. ii) All flanges, joints, compression fittings or plugs in ported blanks, in piping containing, but not limited to; process hydrocarbons, diesel, process chemicals, hydraulic fluids, lubrication oil systems, water injection and produced water re-injection must be tagged when installed or re-installed following maintenance. iii) Tag numbers must be marked-up on both a copy of the relevant P&ID and the corresponding JI1 (Joint Integrity Certificate) by the person who make or breaks the pipework joint integrity. iv) When the pipework is finally made up, the authorised and competent pipe fitter/technician carrying out the task must sign and date the appropriate box on the JI1 (Joint Integrity Certificate). v) The P&ID and JI1 (Joint Integrity Certificate) will form part of the Handover Certification Pack (HCP), to demonstrate joint integrity and technical integrity have been achieved and/or maintained. vi) On completion of a successful leak-test/service-test, the SL1/JI1 (Joint Integrity Certificate)s will be signed by the competent person carrying out the test. vii) In all new and/or disturbed piping where Post SH1 ‘Start-Up and ‘Warm-Up’ Service-testing is applicable, each joint will be monitored after the equipment has been brought into or returned to service and will be subject to one service-test at ‘Start-Up’ and GOC© BP Exploration 1989 - 2001 All Rights Reserved GUIDANCE ON CERTIFICATION SECTION 3.0 GOC © AMERICAS EDITION REVISION: 1 MECHANICAL- PIPE TESTING PAGE: 13 SUBJECT: ‘Warm-Up’ and one service-test every 12 hours thereafter, for a period of 7 days after the ‘Warm-Up’ service-test date, before the tags are removed. viii) During the monitoring period, all tagged piping must be inspected and this will be recorded on the JI1 (Joint Integrity Certificate). When the tags are removed this shall also be recorded on the JI1 (Joint Integrity Certificate), and the tags collected and returned to the Operating Authority. ix) When a number of new joints or breakages of containment are localized, one tag may be raised to control a number of items, e.g. within a lube oil skid, a number of instrument tapping’s around a pump. In these cases, the provision of leak-testing monitoring and recording are still required and break-points should be marked with a unique identification Number, e.g 1666A, 1666B etc on a P&ID or other such drawing. Low Risk b) For piping with low-risk potential, containing but not limited to: Seawater, Firewater, Plant Air, Instrument Air, Domestic Waste, Potable Water , Towns Water and Industrial Water, may not be subject to the Flange/Joint Tagging Procedure, or a system leak test. Quality of work is still important on low-risk systems and, as such, will be subject to inspection and/or service testing, where appropriate, to ensure Technical Integrity has been achieved and/or maintained. i) A service-test will be required for systems where the operating pressure is above 100 psig for water and 15 psig for air and a JI1 (Joint Integrity Certificate) will be raised accordingly. Refer to 3.1.2 Use of Forms e) Joint Integrity Certificate for full details. (Refer to Mechanical Technical Integrity Flowchart in Section 1, Appendix 1.2) GOC© BP Exploration 1989 - 2001 All Rights Reserved SUBJECT: ii) GUIDANCE ON CERTIFICATION SECTION 3.0 GOC © AMERICAS EDITION REVISION: 1 MECHANICAL- PIPE TESTING PAGE: 14 When the operating pressure is below 100 psig for water and 15 psig for air, then no formal testing or certification is required and the activity shall be recorded in the Maintenance Management System when applied to maintenance activities or on the MC1 and SH1 when applied to projects or modifications. (Refer to Mechanical Technical Integrity Flowchart in Section 1, Appendix 1.2) iii) For Maintenance work, when plugs for instrumentation or piping in hydrocarbon systems are broken, for example; or when sampling or blowing-down instruments, there is no requirements to implement the formal Joint Integrity/ Certification Process providing that: - The work is carried out by a competent and authorized person. - The original compression fittings are re-made. - Service-test is carried out by the technician carrying out the work. - All tasks, including the service-test, are completed within one shift. GOC© BP Exploration 1989 - 2001 All Rights Reserved SUBJECT: 3.1.2 GUIDANCE ON CERTIFICATION SECTION 3.0 GOC © AMERICAS EDITION REVISION: 1 MECHANICAL- PIPE TESTING PAGE: 15 Pre-Test Inspection The procedure detailed below shall be followed, for each line included in a test pack, prior to flushing and hydro-testing. The line(s) to be tested shall be "walked" by the Construction Authority's Representative to: a) Check all weld inspection and NDT is completed and form MW1 is completed. b) Check that installed piping complies with the P&ID(s), and piping specification(s). c) Check that the Joint Integrity Procedure and/or Flange Check List Register is complete. d) Check that the flange alignment is correct and that the correct bolts and gaskets are installed at all mechanical joints to the correct torque setting. For joints requiring bolt tensioning, that this has been carried out to the correct bolt tensioning procedures and results recorded. e) Check that all vents and drains are installed (add temporary vents and drains for testing as required). f) Check that the valve materials are correct - use code tagging. If tags are removed, check nameplate. g) Check that the rating of forged steel fittings is correct. h) Check that branch reinforcement is correct as per isometric / design. i) Visually check that pipe compound on screwed connections is to specifications. (Note that the use of PTFE tape on screwed GOC© BP Exploration 1989 - 2001 All Rights Reserved SUBJECT: GUIDANCE ON CERTIFICATION SECTION 3.0 GOC © AMERICAS EDITION REVISION: 1 MECHANICAL- PIPE TESTING PAGE: 16 connections on Hydrocarbon service is NOT permitted unless specifically stated in the installation procedure and agreed by BP). j) Check that all pipe joints are installed correctly and to specification. k) Check that the orientation of filters and strainers, traps, check valves, globe valves and control valves is correct for fluid flow. l) Check that all instrument connections are installed correctly to specification and that any delicate in-line instrumentation has been excluded from the test. m) Check that the orifice valve tap orientation is correct, also that taps and plugs have been seal welded. n) Check that orifice flanges have required upstream and downstream clearances, and orifice plates are removed after trial fitting. o) Check that all instrument thermowells have been installed. p) Ensure that all orifice plates, within the test limits, have been checked in accordance with control procedures. q) Check that all pipe supports are completely installed to the drawings and schedules. r) Check that all temporary pipe supports installed during fabrication have been removed, except those required to support gas lines etc., if those lines are to be hydro-tested. s) Check that stop limits on spring supports are in position, and that sleeved and bellow joints are adequately restrained. t) Check that there is no spring in the piping affecting pumps or vessel nozzles. GOC© BP Exploration 1989 - 2001 All Rights Reserved SUBJECT: GUIDANCE ON CERTIFICATION SECTION 3.0 GOC © AMERICAS EDITION REVISION: 1 MECHANICAL- PIPE TESTING PAGE: 17 u) Check that all NDT/stress relieving requirements are to specification and have been met and recorded. v) Check all chain wheels and hand wheel extensions to specified valves have been installed. w) Check all locking devices and interlocks to valves are installed. x) Check all pipe penetration seals have been installed. y) Check all relief valves and bursting discs have been removed. z) Check that where required, control valves have been removed from the test system. If control valves are being included in a test they may require air on the diaphragm to keep them open and other internal trim removed. No flushing allowed through control valves with “low noise” trim. In general, flashing through control valves shall be avoided, if practical and if so, will require company approval. aa) Check that the system and all line items or equipment, i.e. exchangers, drums etc. can safely withstand the system line specification test pressure and weight when full with test media. Note: Attention must be given to the differential pressure limitations across exchanger tube plates. i) Vessels and heat exchangers may only be included in a system test if the item has previously been pressure tested in accordance with the relevant code at a pressure not less than the piping system pressure test. Approval is required from Engineering Technical Authority. Check that manufacturer's and/or site test certificates endorsed by an independent inspectorate are available on site before approving inclusion within the test system of these items. GOC© BP Exploration 1989 - 2001 All Rights Reserved SUBJECT: ii) GUIDANCE ON CERTIFICATION SECTION 3.0 GOC © AMERICAS EDITION REVISION: 1 MECHANICAL- PIPE TESTING PAGE: 18 Before proceeding with system flushing, any defects noted as part of this Procedure must be corrected. iii) Satisfactory installation completion is to be specified by signing the relevant section of the Piping Completion Certificate MP1. GOC© BP Exploration 1989 - 2001 All Rights Reserved SUBJECT: GUIDANCE ON CERTIFICATION SECTION 3.0 GOC © AMERICAS EDITION REVISION: 1 MECHANICAL- PIPE TESTING PAGE: 19 3.1.3 Cleaning and Flushing a) The Construction Authority shall ensure that the following controls are applied for flushing: i) Flushing is not to be carried out through machinery or any other equipment which may be damaged by the procedure. Control valves and soft-seated valves should be removed during the flushing operation, but where this is not possible the internal fittings are to be removed. If flushing must be done through a pump, temporary strainers must be installed. Otherwise, ensure that piping spools or valves are dropped out and deflectors provided to prevent refuse from entering the pump. ii) Orifice plates, flow nozzles, pressure relieving devices, etc. are to be removed during flushing and testing. To avoid straining the piping while these items are removed, temporary spacers or spool pieces are to be installed. iii) These temporary fittings must conform to the specification of the system being tested. iv) Precautions are to be taken to ensure that water is safely drained away while flushing is being carried out. Deflectors should be provided, when necessary, to prevent refuse from entering open equipment or machinery. b) Prior to testing, each piping system or part system, as identified in the test pack, is to be cleared of debris by flushing with water or blowing with steam or air as appropriate to prove that it is clear from end to end. All flushing-out connections are to be provided with a basket for trapping debris. c) Flushing should be carried out using clean fresh water, potable water, treated sea water, air or steam as appropriate. For systems containing austenitic stainless steel piping and fittings the chloride ion content of GOC© BP Exploration 1989 - 2001 All Rights Reserved SUBJECT: GUIDANCE ON CERTIFICATION SECTION 3.0 GOC © AMERICAS EDITION REVISION: 1 MECHANICAL- PIPE TESTING PAGE: 20 the water shall be less than 50ppm. Carbon steel pipework flushed with sea water should be dried immediately after flushing to prevent corrosion. d) Systems open to atmosphere which do not require flushing should be blown down to ensure that lines are not restricted. e) On piping systems where the flushing medium is water, flow velocities of 1.5 to 2 times the normal operating velocity or 10 - 13 feet/sec. (3-4 meters/sec.), whichever is greater, should be achieved wherever possible. f) On piping systems where the flushing medium is air (oil free and dry) or steam, the flow velocity should not be less than 65 feet/sec. (20 meters/sec.). Records of flushing should be maintained by color marking of P&ID's to define the system flushing circuits, direction of flow, scope, equipment isolation and prime mover used. g) Flushing/blowing is to be carried out until the required cleanliness of the system is attained, after which Certificate MP1 will be signed in the appropriate box. h) Ensure any in-line service strainers are removed prior to flushing and that they are replaced after the flushing operation has been accepted as complete. Additional pre-test requirements from Asset specific and/or design house/engineering support and/or BP specifications and/or International Standards such ASME B31.3 (345) may have to be considered and referenced over and above the requirements detailed above. GOC© BP Exploration 1989 - 2001 All Rights Reserved SUBJECT: GUIDANCE ON CERTIFICATION SECTION 3.0 GOC © AMERICAS EDITION REVISION: 1 MECHANICAL- PIPE TESTING PAGE: 21 3.1.4 Hydrostatic Testing a) After flushing is satisfactorily completed, pressure testing may proceed. b) Testing must be carried out in accordance with the requirements specified on line test and piping line specification or otherwise must take into account the duty of the system, namely the process fluid and the operating pressures and temperatures. Note: i) All in-line valves shall be in the fully open position during the pressure test. Pressure tests shall not be made against closed block valves; Blinds shall be used with valves in the open position. Non Return Valves shall have either the disc removed or the jacket open for flushing and pressure testing. ii) Some in-line valves, notably, ball valves, must be tested with the valve in the half open position to ensure the seals are not exposed excessive differential pressure and to allow the valve stem and body to be pressured tested. iii) c) The Construction Authority's representative shall ensure that hydrostatic test requirements shown on isometric, P&ID, Line List and general arrangement drawings are compatible with the applicable codes and specifications. It should be noted that the design of piping systems for BP is generally based on the requirements of the ASME B31.3 chemical plant and petroleum refinery piping, which details the parameters for hydrostatic testing, as 1.5 x MAWP (Maximum Allowable Working Pressure), with variations to be considered as detailed in ASME B31.3 (345.4.2). d) The testing medium may be clean fresh water, potable water, 60/40% water/glycol treated inhibited sea water, oils, air or inert gases. Typically hydraulic oil and instrument air systems should only be tested using the GOC© BP Exploration 1989 - 2001 All Rights Reserved SUBJECT: GUIDANCE ON CERTIFICATION SECTION 3.0 GOC © AMERICAS EDITION REVISION: 1 MECHANICAL- PIPE TESTING PAGE: 22 specified operating medium. For austenitic stainless steel piping the chloride ion content of the water shall not be more than 50 ppm. e) Prior to filling a system with fluid, it may be prudent to carry out a low pressure air test under controlled conditions to ensure that there are no major leakages present. ASME B31.3 (345.2.1) limits the preliminary test pressure to 25 psig. f) Calibrated test gauges of suitable pressure indication range are to be installed at high/low/entry locations with individual isolation valves in the open position. The gauge at the highest point shall indicate the required test pressure. Pressure, temperature, recorders, and dead weights should be used on all hydrostatic tests for ASME B31.3, B31.4, B31.8 and API 1104 piping systems. g) All test gauges are to be given an individual reference number, calibrated on a regular basis and a calibration record maintained. h) All vents and other high point connections which can serve as vents shall be open during filling so that all air is vented prior to pressurization. i) Piping designed for vapor or gas shall be provided with additional temporary support, where necessary, to support the weight of the test liquid. j) When the test system is filled with the testing medium and the Construction Authority's representative is satisfied that air pockets have been removed, the pressure shall be gradually increased to the required test pressure as specified on the relevant line schedules. k) When pressurizing any test system continuous attendance and supervision must be maintained at the test pump. At all times during the test the pressure gauges should be monitored. Hydrostatic head on the gauge shall be taken into account, depending on the location of the gauge. GOC© BP Exploration 1989 - 2001 All Rights Reserved SUBJECT: l) GUIDANCE ON CERTIFICATION SECTION 3.0 GOC © AMERICAS EDITION REVISION: 1 MECHANICAL- PIPE TESTING PAGE: 23 On achieving the required test pressure, the test pump shall be disconnected physically from the test system. Piping and equipment subjected to the test shall be held at the test pressure for at least 30 minutes before a detailed inspection is started. m) The system under test shall then be visually inspected over its entire length by the Construction Authority's representative and each mechanical, welded joint, attachment etc. checked. The duration of the test shall be a minimum of 30 minutes, or the time taken to inspect the system under test, whichever is greater. n) Due attention must be paid to the effects of high/low ambient temperatures occurring during the test. The temperature of material under test must be safely above that at which brittle fracture may be initiated. o) If program requirements render it necessary to conduct testing during periods of ambient temperatures below or likely to be below 35°F (5°C), prior approval from BP or their Delegated Authority must be obtained for use of anti-freeze solution, or alternative testing media such as gas oil or Kerosene. Any flammable liquids used for testing should have a flash point above 149°F (65°C). Attention is drawn to the danger of brittle fracture occurring in carbon and low alloy steels below 60°F (15.5°C) unless the materials have adequate notch toughness. Prior to granting approval the BP or their Delegated Authorities' Specialist Vessel and Piping Engineer should be consulted regarding the pressurizing of systems and vessels at temperatures below 32°F (0°C). A separate test Procedure outlining storage and recovery facilities for the alternative test medium will require approval from BP or their Delegated Authority. p) If visual inspection over the entire length of the test system is not possible i.e. in partially buried or underground sections, then a 24 hour holding test shall be applied. Test gauges for this type of operation shall be of the dead weight chart recorder type producing both pressure and simultaneous temperature records over the 24-hour test period. GOC© BP Exploration 1989 - 2001 All Rights Reserved SUBJECT: GUIDANCE ON CERTIFICATION SECTION 3.0 GOC © AMERICAS EDITION REVISION: 1 MECHANICAL- PIPE TESTING PAGE: 24 This type of holding test is to be avoided whenever possible and preference should always be given to inspect the system visually as defined in l) above. q) If leaks are discovered, the necessary repairs or replacements shall be made until items being tested pass the test, and that the Construction Authority has been notified that the items being tested have passed the test. r) After satisfactory completion of the pressure test the Construction Authority's representative shall witness the gradual release of pressure and drain down. Test systems shall be de-pressurised by opening the depressurising valve in the test rig and drained by opening all vents and low point drain valves; adequate venting should be effected to avoid vacuum conditions occurring. s) All drained lines should be dried by purging with dry, oil free air. t) Pipeline pigging and gauging must be carried out in accordance with the applicable BP specification. Construction Authority’s representative shall verify pipeline dewatering and inspect and approve gauge plate condition. GOC© BP Exploration 1989 - 2001 All Rights Reserved SUBJECT: 3.1.5 a) GUIDANCE ON CERTIFICATION SECTION 3.0 GOC © AMERICAS EDITION REVISION: 1 MECHANICAL- PIPE TESTING PAGE: 25 Pneumatic Testing The following Procedure shall be followed for pneumatic testing, which may only be carried out if specified. Pneumatic testing may only be carried out when agreed in writing with: On-site - The Operator Off-site - BP or their delegated Authority Pneumatic Testing using pressures > 100psi should be avoided. b) The Construction Authority's representative shall be in charge of all activities associated with Pneumatic Testing. c) Testing should not be carried out at ambient temperatures below 60°F (15.5°C). If it is required to perform tests at ambient temperatures below 60°F (15.5°C), prior agreement shall be sought from BP or their Delegated Authority. d) The air for purging and testing shall be clean, dry and oil free. e) Access to pneumatic test areas shall be restricted solely to those persons required to conduct the test. Barriers shall be installed to prevent access to others. f) Test pressures will be 1.1 x MAWP (Maximum Allowable Working Pressure). g) Butt welds shall be 100% radiographed and all socket welds to be "NDE'd" before commencing pneumatic testing. h) A preliminary check shall be made at not more than 10 psig (0.70 bar gauge) pressure. GOC© BP Exploration 1989 - 2001 All Rights Reserved SUBJECT: i) GUIDANCE ON CERTIFICATION SECTION 3.0 GOC © AMERICAS EDITION REVISION: 1 MECHANICAL- PIPE TESTING PAGE: 26 The system shall be gradually pressurized to 60% of the indicated test pressure, and held at the pressure for a sufficient length of time to allow the piping to equalize strains, but not less than ten (10) minutes. j) The pressure shall then be reduced to 50% of the indicated test pressure and all joints re-tested for leaks. k) The pressure shall be raised in steps of not more than 10%, until the required test pressure has been reached. The pressure shall be held at each step during the pressurizing sequence (to allow the piping to equalise strains) for a period of not less than ten (10) minutes. The required test pressure shall be held for sufficient length of time to permit the testing of all joints, but under no circumstances shall this period be less than thirty (30) minutes. l) When the system has been brought up to test pressure, leak test solution shall be applied completely around all connections and welded joints in order to detect any leaks. m) Flanged joints shall be completely taped and small holes punched at the top or side to detect leaks. n) If leaks are discovered, the system shall be de-pressurised and the leaks repaired. o) The test solution (soapsuds) shall consist of a simple mixture of liquid detergent and water and shall be prepared not more than 24 hours in advance of the test. Throughout the test period, the bubble formation properties of the solution shall be checked. p) While the system is under test pressure, the test equipment shall be isolated from the system. GOC© BP Exploration 1989 - 2001 All Rights Reserved SUBJECT: 3.1.6 GUIDANCE ON CERTIFICATION SECTION 3.0 GOC © AMERICAS EDITION REVISION: 1 MECHANICAL- PIPE TESTING PAGE: 27 Piping Completion On each line the following checks are to be carried out by the Construction Authority's representative, to ensure satisfactory re-instatement of the piping under test: a) Check that the Construction Joint Integrity and/or Flange Check List Register is complete, where applicable, and that all piping has been installed/re-instated and flushing and hydrostatic testing has been satisfactorily completed and recorded. b) Check that the flange alignment is correct and that the correct bolts and gaskets are installed at all mechanical joints to the correct torque setting and that the bolts have been lubricated. For joints requiring bolt tensioning, that this has been carried out to the correct Bolt Tensioning Procedure and the results recorded accordingly. c) Check that the compound on screwed connections is to specification. (Note that the use of PTFE tape on screwed connections on Hydrocarbon service is NOT permitted unless specifically stated in the installation procedure and agreed by BP). d) Check that all vents and drains are correctly installed with plugs or blind flanges. e) Check that all temporary vents and drains have been seal welded where applicable. f) Check that all process blinds and spacers have been correctly installed as indicated on the P&ID. g) Check that all the spectacle blinds are in the correct (open or closed) position. h) Check that all pipe cleaning and pickling has been satisfactorily completed and recorded. GOC© BP Exploration 1989 - 2001 All Rights Reserved SUBJECT: GUIDANCE ON CERTIFICATION SECTION 3.0 GOC © AMERICAS EDITION REVISION: 1 MECHANICAL- PIPE TESTING PAGE: 28 i) Check that all control valves have been installed in the correct flow direction. j) Check that the specified block valves have their locking devices correctly installed. k) Check that all valves are functioning properly and that they are correctly lubricated and installed in the correct flow direction. l) Check that all temporary pipe spools have been removed and all control valves and internals have been re-instated in the correct flow position. m) Check that all Non Return Valve internals have been re-instated, and the valve has been installed in the correct flow direction, and any ‘jack open’ devices have been removed. Ensure the valve is functioning properly and that the spindles are lubricated. n) Check that all relief valves and rupture (bursting) discs have been correctly installed. o) Check that all gauges have been correctly installed. p) Check that all pump suction strainers have been correctly installed or temporary test strainers removed. q) Check that all chain wheels and hand wheel extensions to specified valves have been installed. r) Check that all locking devices and interlocks to valves are installed. s) Check that all pipes, including supports, have been installed as per design. t) Identify all piping that requires vibration tests when operational and record on the MP1 and on the Handover Punch List as outstanding Commissioning/Operations Item. GOC© BP Exploration 1989 - 2001 All Rights Reserved SUBJECT: u) GUIDANCE ON CERTIFICATION SECTION 3.0 GOC © AMERICAS EDITION REVISION: 1 MECHANICAL- PIPE TESTING PAGE: 29 Upon completion of the above and where appropriate, the Joint Integrity Procedure and/or or Flange Check List Register and conformation that all the appropriate joints have been tagged and the relevant tag I.D. is detailed on the appropriate drawings, the Construction Authority's representative and the Contractors authorized Representative, shall sign form MP1 Piping Completion Certificate v) Verify that all test blinds and filling liners are rated equal to or greater than that of the line class to be tested. w) Check that all flow meters have been installed in the correct flow direction. x) Check that orifice plates on flow meter runs are correctly installed. GOC© BP Exploration 1989 - 2001 All Rights Reserved SUBJECT: GUIDANCE ON CERTIFICATION SECTION 3.0 GOC © AMERICAS EDITION REVISION: 1 MECHANICAL- PIPE TESTING PAGE: 30 3.1.7 Fire and Gas Piping Completion a) For piping associated with the fire water mains, sprinkler and deluge systems, the following checks are to be carried out to ensure the return of piping under test to a state of mechanical completion. b) Check that all sprinkler heads, sprinkler rosettes and sprinkler nozzles have been correctly installed. c) Check that all hose couplings have been correctly installed. d) Check that all discharge heads on (non-Halon) fire suppression systems have been correctly installed. e) Confirm with Mechanical Group that: i) All fire hydrants/monitors have been correctly installed. ii) All foam monitors have been correctly installed. iii) All fire suppression (non-Halon) cylinder locations and fixings are correctly installed. Note: The use of Halon as a fire suppressant is being phased out by BP to comply with the Environmental Protection Regulations 1996 S.I. 506 Form MP1 shall be completed upon completion of this Procedure. Note: Painting, insulation and trace heating have not been included on the piping Procedures 3.1 & 3.2, as they will be covered by Certifications raised by other disciplines. GOC© BP Exploration 1989 - 2001 All Rights Reserved GUIDANCE ON CERTIFICATION SECTION 3.0 GOC © AMERICAS EDITION REVISION: 1 MECHANICAL- PIPE TESTING PAGE: 31 SUBJECT: 3.1.8 Certification a) The Construction Authority's representative who executed the system test shall sign the piping completion certificate Form MP1. Pressure, temperature, and time recorder charts shall be attached to Form MP1. b) The Construction Authority's representative shall ensure that the Construction Documentation Packages are progressively compiled and that pressure test certificates and associated documents fully define the results, the scope of test, isolated equipment, and date executed. c) On completion of test, the system shall be reinstated in accordance with requirements and the appropriate section of the piping completion certificate MP1. d) The Construction Authority’s representative shall ensure, where applicable, that the Joint Integrity Procedure and/or or Flange Check List Register is complete and that all the appropriate joints have been duly tagged and the relevant tag I.D. is detailed on the appropriate drawings. The flange/joint tags will remain in place until all Post Start-Up Integrity checks (service-tests) are carried out and the completion and acceptance of the JI1 (Joint Integrity Certificate) by Operations. GOC© BP Exploration 1989 - 2001 All Rights Reserved SUBJECT: GUIDANCE ON CERTIFICATION SECTION 3.0 GOC © AMERICAS EDITION REVISION: 1 MECHANICAL- PIPE TESTING PAGE: 32 Procedure No. 3.2 3.2.1 System Flushing a) The purpose of flushing is to ensure that systems to be handed over are clean and free from debris which may damage system equipment. b) Flushing Guidelines The system should be assessed and best flushing medium (air, water or a combination of both) selected taking into consideration safety, efficiency and convenience. c) System/lines to be flushed are to be checked against P & ID's to identify items that require removal prior to flushing. d) Flushing must not be via: Orifice Plates, Non-Return Valves, filters, machinery, vessels, control valves or speciality items (Thermowells, sampling/chemical injection quills, corrosion coupons, etc.). e) Where specialty items/fittings etc. are removed, they are to be wrapped in protective material and securely tied to their location with a commissioning label attached. f) If removal of equipment necessitates spool pieces to be inserted, the spool pieces must be of the same internal diameter as the piping. g) When flushing systems fitted with wafer type check valves, every effort should be made to remove these valves. If this is not possible the internal flap is to be removed (not tied back). On re-instatement the internals of the valves are to be checked for cleanliness/damage. h) Battery limits/off takes are to be isolated by blinding or locked closed valves with hazardous signs posted. GOC© BP Exploration 1989 - 2001 All Rights Reserved SUBJECT: i) GUIDANCE ON CERTIFICATION SECTION 3.0 GOC © AMERICAS EDITION REVISION: 1 MECHANICAL- PIPE TESTING PAGE: 33 All temporary blinds, spectacle blinds or orifice plates installed, turned or removed must be entered in the respective registers. j) Flushing of interconnecting piping should be in the direction of fall (high to low point) and from smaller piping into larger piping ensuring no debris is left trapped in dead legs. k) Flush rates must be high enough to remove heavy debris. l) The flush should be to an open end if possible. In the event of a flexible hose/pipe being required to route the medium away it should be of, at least, the same diameter or larger. m) The area of flush discharge should be cordoned off and hazardous signs posted. n) Where pipe sections/systems are sufficiently small and pipe diameters sufficiently large enough to allow visual inspection, then this can replace the requirement to flush. o) A combination of flushing and visual inspection can be accepted, and will be indicated on the SF1 certificate. p) On reinstatement, the system must be checked against P&ID's, the blinding/orifice register and the master P&ID's updated. q) The certificate SF1 shall be signed on completion of this Procedure. GOC© BP Exploration 1989 - 2001 All Rights Reserved GUIDANCE ON CERTIFICATION SECTION 3.0 GOC © AMERICAS EDITION REVISION: 1 MECHANICAL- PIPE TESTING PAGE: 34 SUBJECT: 3.2.2 Leak Testing a) The purpose of the leak test is to ensure the integrity of the system prior to handover. b) Safe System of Work i) A safe system of work will form part of the commissioning Procedure and be in place before the start of testing. This will ensure that after completion of pressure/leak testing, the pressure inside the system is reduced to atmospheric level, or as justified by a risk assessment, to an appropriate safe level before any work starts on that system. ii) The safe system of work to include the verification by the performing authority that on every occasion the system has safe working conditions, before work commences. iii) The valve on the pneumatic (e.g. nitrogen) supply line to the system should be locked in the closed position and blinded off when work is to be carried out on the system to which it is connected. Disconnection of the line to the system is preferred. This action should be a prerequisite of the permit to work. It should be signed as completed prior to the issue of the start of work on the system. iv) During any pneumatic test, if the test pressure is above the MAWP, or the pressuring source could exceed MAWP, a pressure relief valve shall be fitted to the test equipment, set to relieve marginally above the test pressure, and of adequate discharge capacity to relieve the volume supplied by the pressuring source to a safe area. GOC© BP Exploration 1989 - 2001 All Rights Reserved SUBJECT: GUIDANCE ON CERTIFICATION SECTION 3.0 GOC © AMERICAS EDITION REVISION: 1 MECHANICAL- PIPE TESTING PAGE: 35 Note! ASME B31.3, Process Piping, paragraph 345.5.2, titled “Pressure Relief Device” states: “A pressure relief device shall be provided, having a set pressure not higher than the test pressure plus the lesser of 50 psi (3.5 bar) or 10% of the test pressure.” v) The Performing Authority will ensure adequate training of all personnel involved in leak testing and provide test personnel with approved written Procedures. Note! Clamps or bolts on bolted flanges must not be loosened while the system is under pressure. When required the system should be isolated from pressure sources, depressurised and vented. The clamps should then be removed strictly in accordance with the manufacturer’s Procedures. Clamps should only be removed by competent persons who have been trained in manufacturers assembly/disassembly Procedures. It is important that items b) to p) are checked for completeness prior to leak testing. c) All outstanding items on punch list that would affect integrity of leak test have been cleared. d) Limits as defined in Commissioning Procedure are set on plant. e) All adjoining systems have been isolated by blindings or vented to prevent any pressure build up. f) All valves have been checked for freedom of movement. g) All valves internal to system are open. h) Instrumentation has been installed and is opened up to the leak test. i) Atmospheric vents/drains have been valve isolated or blanked. GOC© BP Exploration 1989 - 2001 All Rights Reserved SUBJECT: j) GUIDANCE ON CERTIFICATION SECTION 3.0 GOC © AMERICAS EDITION REVISION: 1 MECHANICAL- PIPE TESTING PAGE: 36 Insulation/cladding or blankets has been removed from flanges, valves, etc. k) All test equipment and system pressure limiting devices, such as pressure relief valves, should be set to the correct pressure. Sufficient pressure monitoring to avoid test pressure remaining undetected behind check valves and similar equipment should be incorporated. l) A fully operational newly calibrated PI of a suitable range should be fitted at or near each venting position, injection positions and whenever possible near to the places where work is to be carried out Pressure readings should be recorded as detailed in Procedure 8.3, Section 3.1.6. m) Pressuring point has been selected to ensure that the entire system is pressured. (Do not attempt to back flow through non-return valve; i.e., check valves). n) Ensure area-surrounding system under test is suitably cordoned off, and designated a “Keep Out Area” by erecting warning signs and barriers. Note! Only personnel essential for the operation of test equipment are to be allowed in the test area during pressurization and de-pressurization. o) Where appropriate, make a radio or P.A. announcement that a "Leak Test" is ongoing in the area. Testing should not start until all nonessential personnel are in a safe area. p) Under no circumstances shall the system under test be left unattended once the system is pressurized. r) As with any "Pressure" test, the system shall be pressured slowly, and in stages, the pressure of the system to be recorded at the various stages. The system is now ready for leak testing. GOC© BP Exploration 1989 - 2001 All Rights Reserved SUBJECT: s) GUIDANCE ON CERTIFICATION SECTION 3.0 GOC © AMERICAS EDITION REVISION: 1 MECHANICAL- PIPE TESTING PAGE: 37 Piping 'Under Test' i) Leak Testing is performed at 110% of Maximum Allowable Working Pressure (MAWP) or, if a relief valve which has a set pressure below 110% MAWP is included in the system under test, the test is conducted at 95% of the system relief valve set pressure. A leak test (hydraulic where practicable) is performed to prove the pressure tightness (i.e. fitness for service) of joints, seals and glands, etc. each time the integrity of containment systems is broken, either at hook-up/commissioning or post operations phase. The prevention of even minor leaks is particularly important where flammable or toxic fluids are concerned. ii) Pneumatic Leak Tests using an inert gas are used extensively on piping systems which are predominantly gas producing and some offsite sites both during commissioning and post operation phases, prior to the introduction of hydrocarbons. The accepted norm for these tests is to pressurize, using 99% nitrogen with a 1% helium tracer gas, up to a maximum of 110% MAWP. A specialist leak test contractor is normally employed for such tests. A typical target leakage rate of 20 scf/annum up to a maximum of 80 scf/annum, measured by means of equipment sensitive to the tracer gas, or by sonic or ultrasonic detector devices, should be used as the acceptable leakage range. Note! Pneumatic leak testing should not be carried out before the integrity of the equipment has been confirmed by a standard pressure test. iii) There should be sufficient venting positions to prevent fluid being trapped behind non-return check valves in dead legs or between isolation valves. Instruction will be required on how the system can be safely tested and vented in discrete sections. If this is the intended method of testing then all piping should be adequately marked so that each test can be identified. Where the section under test terminates at a valve, an assessment should be carried out to GOC© BP Exploration 1989 - 2001 All Rights Reserved GUIDANCE ON CERTIFICATION SECTION 3.0 GOC © AMERICAS EDITION REVISION: 1 MECHANICAL- PIPE TESTING PAGE: 38 SUBJECT: determine if a block & bleed or blind arrangement should be used to prevent a build up of pressure inside an adjacent section. iv) Gross (Preliminary) Air Leak Tests, using instrument air up to a maximum of 100 psig (8 barg), are often used at an early stage of hook-up/commissioning as a means of identifying large leaks, prior to performing the standard pressure tests. Note: ASME B31.3 paragraph 345.1.2 (c) recommends that no more than 25 psig air test shall be made prior to a hydrostatic test to locate major leaks. v) Service Leak Tests, using the service fluid rather than 110% MAWP tests, are acceptable methods of testing for leaks during the post operations phase on low pressure systems such as instrument air, potable water and diesel distribution systems. (Category D fluid service). vi) Raise, check and record pressure in increments (check flanges, valve glands, etc.), for leaks at each stage. vii) In water filled systems, it is important to ensure all air is vented and system is completely water filled. viii) Hold the final test pressure for at least 30 minutes with no visible leaks to atmosphere before a detailed inspection is started. (Use soapy water to bubble check for AIR/N2 TESTS). ix) Pressures should always be checked and recorded the following: • Completion of Test • Isolation from the pressure source • When de pressurization/venting has taken place The above should always be done immediately prior to the start of any further work on the system. GOC© BP Exploration 1989 - 2001 All Rights Reserved GUIDANCE ON CERTIFICATION SECTION 3.0 GOC © AMERICAS EDITION REVISION: 1 MECHANICAL- PIPE TESTING PAGE: 39 SUBJECT: t) Test Medium Select test medium from: • Air • Potable Water • WI Water • N2 • N2/Helium Test pressure as specified in the Commissioning Procedure. Note! Consideration should be given to ensure that during Nitrogen injection and bleeding the temperature does not fall to a level where a loss of structural integrity could occur in the test piece. u) Post Test Requirements On completion of Tests the following action is to be taken: • Slowly de-pressure the system. • • • • • • Make a radio or P.A. announcement that Leak Testing is complete. Remove the pressuring connection, remembering to include/indicate joints on connection, vents, etc., that will become witness joints and require inclusion in the certification (Service test), if applicable. Remove barriers and warning signs. Return the work permit. Mark up a relevant P&ID indicating the system limits and complete the SL1 certificate, refer to 3.2.2. Ensure JI1 certificate is available for post test integrity service tests. GOC© BP Exploration 1989 - 2001 All Rights Reserved SUBJECT: 3.2.3 a) GUIDANCE ON CERTIFICATION SECTION 3.0 GOC © AMERICAS EDITION REVISION: 1 MECHANICAL- PIPE TESTING PAGE: 40 Critical Joint Installation The following Procedure, in conjunction with the Joint Integrity Procedure 3.1 (3.1.1), shall be followed for the preparation, pulling up and tightening of certain flanged joints on critical duties, when specified by the Commissioning/Operations Authority. Such joints will normally be, but will not be limited to, pipe carrying hydrocarbons which will not be subject to a pressure and/or leak test. b) Advise Commissioning/Operations Authority prior to joint(s) installation to enable assessment for requirement to witness joint installation. c) Flange faces to be examined and visually inspected to ensure they are clean and damage free. d) Gasket to be examined and visually inspected to ensure it is new, damage free, and of correct specification and size. e) Nuts and stud bolts to be examined and visually inspected to be damage free and of correct specification (material) and size. f) Check flange faces are parallel and alignment is in accordance with specification. g) Check that joint is progressively tensioned evenly using a "criss-cross" bolt tightening sequence as required in the BP specification. h) All nuts to be pulled up to the required torque tightness, a minimum of one thread should be seen protruding through each nut, no excessive length of stud bolt should protrude through each nut. i) Check that there is no visible damage to the gasket when joint is compressed. j) Mark up a relevant P&ID indicating the appropriate joint(s) and complete the relevant section of the JI1 (Joint Integrity Certificate), refer to 3.1.2. Use of Forms e) Joint Integrity Certificate. GOC© BP Exploration 1989 - 2001 All Rights Reserved SUBJECT: GUIDANCE ON CERTIFICATION SECTION 3.0 GOC © AMERICAS EDITION REVISION: 1 MECHANICAL- PIPE TESTING PAGE: 41 3.2.4 Service Testing Procedure a) The "Service Test" is required in conjunction with the critical joint installation Procedure and Joint Integrity Procedure, on high risk piping or when it would be impracticable to leak test the system on completion of workscope. The service test will utilize the process fluid to test the piping for leaks. b) After all stages of the critical joint(s) installation and the Joint Integrity Procedure 3.1 (3.1.1) have been completed, and ensuring all outstanding items on Punch List that would affect system integrity have been cleared. c) Joints that have been split are closely scrutinised for leaks (i.e. fluid leakage, soapy bubble in gas systems and gas detection for hydrocarbons) during early stages of pressurization. d) Observe all joints that are under scrutiny for leaks until desired pressure (i.e. normal operating pressure) is achieved. e) The relevant parts of the JI1 (Joint Integrity Certificate) should be signed off on completion, refer to 3.1.2 Use of Forms e) Joint Integrity Certificate for full details. f) When a service-test in lieu of a Leak Test is carried out a waiver or concession has been granted, by the Approving Authority and/or the Operating Authority. As a result of the wavier/concession a SL1 System Leak Test Certificate will not be raised. The JI1 (Joint Integrity Certificate) will detail in the ‘Leak-tested by’ and ‘SL1 Leak Test Number’ boxes that a waiver/concession has been given, by entering the Engineering Query (EQ) or Operating Query (OQ) or Technical Query (TQ) identification number in these boxes. NOTE: A critical joint installation will ALWAYS be followed by a Service Test. GOC© BP Exploration 1989 - 2001 All Rights Reserved SUBJECT: g) GUIDANCE ON CERTIFICATION SECTION 3.0 GOC © AMERICAS EDITION REVISION: 1 MECHANICAL- PIPE TESTING PAGE: 42 Service-test on piping with low-risk potential, containing, but not limited to: Seawater, Firewater, Plant Air, Instrument Air, Domestic Waste, Potable Water/Towns Water and Industrial Water, will not be subject to the Flange/Joint Tagging Procedure, or a system Leak Test. Quality of work is still important on low-risk systems and as such will be subject to inspection and/or service testing, where appropriate, to ensure Technical Integrity has been achieved and/or maintained. A service test will be required for systems where the operating pressure is above 100 psig for water and 15 psig for air and a JI1 (Joint Integrity Certificate)s will be raised accordingly. Refer to Use of Forms e) Joint Integrity Certificate for full details of the intent of the JI1 (Joint Integrity Certificate). (Refer to Mechanical Technical Integrity Flowchart in Section 1, Appendix 1.2) Where the operating pressure is below 100 psi for water and 15 psi for air then no formal testing or certification is required and the activity will be recorded in the Maintenance Management System when applied to maintenance activities or on the MC1 and SH1 when applied to Projects or Modifications. (Refer to Mechanical Technical Integrity Flowchart in Section 1, Appendix 1.2) GOC© BP Exploration 1989 - 2001 All Rights Reserved GUIDANCE ON CERTIFICATION SECTION 3.0 GOC © AMERICAS EDITION REVISION: 1 MECHANICAL- PIPE TESTING PAGE: 43 SUBJECT: 3.2.5 Certification a) Complete the SL1 or JI1 certificates including the following information: (Wherever applicable) i) ii) MC1/SH1 numbers All line numbers iii) Vessel numbers iv) v) Tie-in numbers Valve numbers at test limits vi) Test medium vii) viii) Test pressure Test duration b) ix) Service test pressure x) xi) xii) Exclusions or exemptions Commissioning or completing assignee signature Operations or testing approval signature Attach a B size copy of the relevant P&ID's to the SL1 and/or JI1 with the system leak test/witness joints/service test limits highlighted and clearly identified. c) For N2/Helium testing the contractors certificate is to be attached to the SL1. d) The original SL1 and the marked up P&ID's are to be passed to the Certification Engineer or the Delegated Authority nominated by BP. e) Mark up the master System P&ID. GOC© BP Exploration 1989 - 2001 All Rights Reserved SUBJECT: GUIDANCE ON CERTIFICATION SECTION 3.0 GOC © AMERICAS EDITION REVISION: 1 MECHANICAL- PIPE TESTING PAGE: 44 FLOWCHART 3 • • Functional Certification Flowchart Discipline: Mechanical (Piping) MP1 MC1 MP1: MC1: SF1: SL1: SH1: JI1: SF1 SL1 SL1 SH1 JI1 Piping Completion Certificate Mechanical Completion Certificate System Flushing Certificate Leak Test Certificate System Handover Certificate Joint Integrity Certificate Note! Where Welding is carried out an MW1 - Welding Completion © Summary is required - Refer to GOC Section 2 GOC© BP Exploration 1989 - 2001 All Rights Reserved SUBJECT: GUIDANCE ON CERTIFICATION SECTION 3.0 GOC © AMERICAS EDITION REVISION: 1 MECHANICAL- PIPE TESTING PAGE: 45 EXHIBIT 3 STANDARD FORMS Form No. Form Title MP1 Piping Completion Certificate SF1 System Flushing Certificate SL1 JI1 Leak Test Certificate Joint Integrity Certificate DIS1 Data Input Sheet 1 – Section 3 Pipe Testing GOC© BP Exploration 1989 - 2001 All Rights Reserved PIPING COMPLETION CERTIFICATE Project Title: Maintenance No: Work Pack No: SH1 No: MC1 No: FORM MP1 Test Pack No: SHT SITE: LOCATION: OF P & ID No: SCOPE OF TEST: TEST PACK LIMIT FLUSHED PRIOR TO STRENGTH TEST? MW1 Complete Welding & NDE Pro 3.1.1 Complete Joint Integrity Pro 3.1.2 Complete Pre-Test Inspection Pro 3.1.3 Complete Cleaning & Flushing YES/NO* SIGNATURE: YES/NO* SIGNATURE: YES/NO* SIGNATURE: YES/NO* SIGNATURE: OPERATING PRESSURE PSIG STRESS RELIEVED* YES/NO* N.D.E. MEDIUM: * M.P.I* / D.P.* TEST PRESSURE PSIG YES/NO * FLUSHING MEDIUM: Pro 3.1.4 Complete Hydrostatic Testing Pro 3.1.5 Complete Pneumatic Testing Pro 3.1.6 Complete Piping Completion Pro 3.1.7 Complete Piping Completion (F&G) OPERATING TEMP INTERNAL LINING* 100%* / 10%* ISO No SIGNATURE: YES/NO* SIGNATURE: YES/NO* SIGNATURE: YES/NO* SIGNATURE: DEG F YES/NO* U.T* / RAD* TEST MEDIUM: YES/NO* FLOW MEDIUM: EXTERNAL FINISH* 100%* / 10%* NDE ACCEPT. TEST DURATION: LINE No VIBRATION TEST REQ PAINT* WRAP* YES/NO* INSULATE* LINE SPEC: TEST DATE: EQUIPMENT NUMBER (FROM) (TO) * YES/NO * YES/NO * YES/NO * YES/NO * YES/NO * YES/NO * YES/NO * YES/NO * YES/NO * YES/NO * YES/NO * YES/NO * YES/NO * YES/NO * YES/NO * YES/NO * YES/NO ALL LINES REQUIRING VIBRATION TESTS MUST BE DETAILED ON THE HANDOVER PUNCH LIST COMPLETED BY APPROVED BY COMPANY SIGNATURE PRINT NAME DATE * Delete as appropriate GOC© BP Exploration 1989 - 2001 All Rights Reserved Americas Rev. 1 Project Title: Maintenance No: Work Pack No: SH1 No: MC1 No: SYSTEM FLUSHING CERTIFICATE FORM SF1 SITE: SHT OF TITLE: Procedure 3.1.3 Complete Cleaning & Flushing FLUSH MEDIUM √ FLUSH * YES/NO/NA √ VISUAL Signature: P&ID DRAWING & LINE No(s) SIGN DATE REMARKS: √ CHECK AS APPROPRIATE SYSTEM WALKED AND CHECKED AGAINST P&ID(s) AND INTEGRITY CHECK COMPLETE COMPLETED BY APPROVED BY COMPANY SIGNATURE PRINT NAME DATE * Delete as appropriate GOC© BP Exploration 1989 - 2001 All Rights Reserved Americas Rev. 1 ***NOTE ! ONE (1) SF1 TO BE RAISED PER HANDOVER CERTIFICATION PACK (HCP) *** Project Title: Maintenance No: Work Pack No: SH1 No: MC1 No: FORM SL1 SITE: LEAK TEST CERTIFICATE SHT LOCATION: SL1 REF: SCOPE OF TEST: SYSTEM: FLUSH MEDIUM: Pro. 3.1.1 Complete Joint Integrity Pro. 3.1.6 Complete Piping Completion Pro. 3.2.1 Complete System Flushing OF JI1 REF: FLUSH DETAILS COLUMN: MARK ‘F’ FOR LINE FLUSHED OR ‘V’ IF VISUAL ONLY * YES/NO/NA SIGNATURE: * YES/NO/NA SIGNATURE: * YES/NO/NA SIGNATURE: Pro.3.2.2 Complete Leak Test Pro.3.2.3 Complete Witness Joint Complete Reinstatement OPERATING PRESSURE: PSIG OPERATING TEMP: TEST PRESSURE: PSIG TEST DURATION: P & ID No LINE No DEG F * YES/NO/NA SIGNATURE: * YES/NO/NA SIGNATURE: * YES/NO/NA SIGNATURE: FLOW MEDIUM: TEST MEDIUM: FLUSH DETAILS VIBRATION TEST REQ EQUIPMENT NUMBER (FROM) (TO) * YES/NO * YES/NO * YES/NO * YES/NO * YES/NO * YES/NO * YES/NO * YES/NO * YES/NO * YES/NO * YES/NO * YES/NO * YES/NO * YES/NO * YES/NO * YES/NO REMARKS ALL LINES REQUIRING VIBRATION TESTS MUST BE DETAILED ON THE HANDOVER PUNCH LIST PIPING INSTALLATION IN ACCORDANCE WITH RELEVANT CONTRACT SPECIFICATIONS, AND GOC SECTION 3 - PIPE TESTING. COMPLETED BY APPROVED BY COMPANY SIGNATURE PRINT NAME DATE * Delete as appropriate GOC© BP Exploration 1989 - 2001 All Rights Reserved Americas Rev. 1 Procedure 3.1.1 Complete Joint Integrity Project Title: Maintenance No: Work Pack No: SH1 No: MC1 No: JOINT INTEGRITY CERTIFICATE * YES/NO/NA SIGN: Procedure 3.1.3 Complete Cleaning & Flushing * YES/NO SIGN: Procedure 3.1.6 Complete Piping Completion * YES/NO SIGN: Procedure 3.2.3 Complete Witness Joint * YES/NO/NA SIGN: Procedure 3.2.4 Complete Service Test * YES/NO SIGN: LOCATION : Tag Number FORM JI1 SITE: SHT of SYSTEM : Part A Part B Part C Installation Phase Commissioning Phase Operational Phase Location (P&ID and Description) Joint Installed by Date of Installation Leak Tested by Parts A & B To be completed before the SH1 can be signed and the equipment safely operated COMPLETED BY APPROVED BY SL1 Leak Test Number Service Test after start up Service Test after warm up Service Test Period Service Test Period Service Test Period Service Test Period Tag Removal Date Complete Post SH1 acceptance - the equipment can be operated safely without jeopardizing plant, personnel or the environment REMARKS: COMPANY SIGNATURE PRINT NAME DATE * DELETE AS APPLICABLE GOC © BP Exploration 1989 - 2001 All Rights Reserved DOUBLE SIDED FORM Americas Rev. 1 JOINT INTEGRITY CERTIFICATE Form JI1 SHT of Part A Tag Number Location (P&ID and Description) * DELETE AS APPLICABLE Part B Joint Installed by Date of Installation GOC © Leak Tested by SL1 Leak Test Number Part C Service Test after start up Service Test after warm up BP Exploration 1989 - 2001 All Rights Reserved DOUBLE SIDED FORM Service Test Period Service Test Period Service Test Period Service Test Period Tag Removal Date Americas Rev. 1 JI1 Certificate How To……. Box 1 to 5: To be completed by Certification Administrator, this will contain Project Title workpack information and the SH1 No. Box 6: Will have the flange tag number inserted by the person who makes up or breaks the joint and tags the flange. This person will also mark up the P&ID that accompanies the certificate. Box 7: Detailed location of the flange. Box 8: Initialed by the person installing the joint (only personnel who are on the joint installation register can sign here). Box 9: Date of joint installation. Box 10: To be initialed by the person carrying out the leak test on completion. Box 11: Leak test number, this information will be taken from the SL1 Certificate on equipment that requires more than one leak test. Box 12: Service Test after start up to be carried out on all tagged joints. Box 13 to 17: Are checks to be carried out over the next 7 days as detailed on Procedure 3.1.1. Joint Integrity Installation Procedure. Box 18: The tag removal date. Box 19: To be completed by the person removing the tag and confirming the integrity of the joint. Box 20: To be signed by the operating authority. Notes Boxes 6 to 9 are Part A items and must be completed by the Installation Authority for piping with High risk potential. For Low risk potential joints refer to Procedure 3.1.1. Joint Integrity Installation Procedure. If a joint is broken on more than one occasion then a line is put through boxes 6, 7 and 8 and a new entry is put on the certificate using the original tag number. This will reduce confusion on the accompanying marked up P&ID. Boxes 10 and 11 are Part B items and the SH1 cannot be completed until they are all signed up. There will be circumstances where boxes 10 & 11 are not covered by a leak test, in these occasions NA will be entered. Boxes 12 to 18 are Part C items and will be completed after the SH1 has been signed and the equipment returned to service. GOC© BP Exploration 1989 - 2001 All Rights Reserved Americas Rev 1 DIS1 SHEET LOCATION : __________________ DATA INPUT SHEET 01 PROJECT : __________________ SECTION 3 - PIPE TESTING JP NO. HANDOVER ID RAISED BY: TEST PACK No P&ID No __________________________________ NOTE: JP No FOR HYDROTESTING LINE No DATE: ISO No ______________ GOC ASBUILT REQ'D (LAD) OF WORKSCOPE ID : ____________________ MAINTENANCE ID No : ____________________ TEST PRESSURE (PSIG) PIPING CERTIFICATES REQUIRED MW1 MP1 AS1 AS2 SF1 DATA ENTERED BY : ____________________ © BP Exploration 1989 - 2001 All Rights Reserved SL1 REMARKS DATE:___________ Americas Rev. 1 SUBJECT: GUIDANCE ON CERTIFICATION SECTION 4.0 GOC© AMERICAS EDITION REVISION: 1 MECHANICAL- MECHANICAL EQUIPMENT SECTION 4.0 MECHANICAL EQUIPMENT GOC© BP Exploration 1989 – 2001 All Rights Reserved PAGE: 1 SUBJECT: GUIDANCE ON CERTIFICATION SECTION 4.0 GOC© AMERICAS EDITION REVISION: 1 MECHANICAL- MECHANICAL EQUIPMENT 4.1 ACTIONS 4.1.1 General PAGE: 2 This document covers only the installation and pre-handover activities and does not specify requirements for suppliers of equipment. Mechanical Equipment shall be checked for compliance and other requirements as detailed in, but not limited to: • • • • • • • 4.1.2 The latest revision of Issued For Construction (IFC) or Approved For Construction (AFC) Drawings and Schedules Codes and standards reference in this section Plant and Project Specifications Equipment Specifications and Data sheets BP Engineering Installation and Design Specifications Local, state, country and international standards, codes, and regulations as appropriate Offshore - Special Standards, i.e. USCG, ABS and MMS Pumps & Compressors a) Machinery Procedure No. 4.1 lays down the checks that are required to ensure that the equipment is correctly installed. On completion of installation, the Construction Authority Mechanical Engineer will be required to complete the Mechanical Installation form MM1. b) 4.1.3 a) Machinery Procedure No. 4.2 lays down the method to adopt for alignment checks, which will be recorded on Certificate form MM2, and accepted by the Commissioning Authority Mechanical Engineer. Submersible pumps will not require an MM2 Alignment Certificate. Skid Mounted Units These will generally consist of vessels, pumps, compressors, drivers, piping, instrumentation, etc., mounted on a common frame. As equipment gets larger, there will usually be two frames, one for the driver and one for the driven equipment. Other disciplines will carry out their respective checks as required. The Construction Authority Mechanical Engineer will be required to carryout Machinery Procedure GOC© BP Exploration 1989 – 2001 All Rights Reserved SUBJECT: GUIDANCE ON CERTIFICATION SECTION 4.0 GOC© AMERICAS EDITION REVISION: 1 MECHANICAL- MECHANICAL EQUIPMENT PAGE: 3 4.2 for the units and record this fact on the Mechanical Installation Certificate form MM1. b) The Mechanical section of Handover Certification Packages for the units will typically contain: 1 - MM1 Certificate for the installation of the skid unit. 1 - MM1 Certificate for each pump or compressor. 1 - MM2 Certificate for each pump or compressor and associated driver unit. 4.1.4 Vessels And Tanks a) Vessels and tanks fabricated off and on-site will be installed in accordance with the following procedures: Procedure No 4.3 - General Requirements & Pressure Safety Relief Devices Procedure No 4.4 - Vessels & Tanks Fabricated (Off-Site) Procedure No 4.5 - Vessels & Tanks Modified (Off-Site) b) Each vessel installed shall be identified by the Construction Authority to ensure the installation conforms to drawings and specifications. Each installation shall be approved by acceptance of the certificate form MV1. Final closure shall be witnessed and accepted by the client/operations representative. c) 4.1.5 a) Base line thickness checks, prior to insulation, where applicable, shall be performed and recorded on the approved BP forms. Mechanical Handling Introduction This section gives the recommended minimum requirements to show that the Mechanical Handling Equipment is installed, and ready to be handed over to Commissioning for proof load testing. GOC© BP Exploration 1989 – 2001 All Rights Reserved SUBJECT: GUIDANCE ON CERTIFICATION SECTION 4.0 GOC© AMERICAS EDITION REVISION: 1 MECHANICAL- MECHANICAL EQUIPMENT PAGE: 4 Installation, test and inspection of lifting appliances shall comply with the statutory and mandatory requirements and, as appropriate, and specific requirements for individual items described in the BP Standards and Supplier documents for those items. With respect to site inspection and testing of the Totally Enclosed Motor Propelled Survival Craft (TEMPSC) Davits, reference shall be made to the appropriate regulations and laws of the country or state whose jurisdiction the off-shore installation is subject. b) General Certain classes of lifting equipment will require the attendance of a third party to review/witness the design and/or fabrication and/or testing. BP will lay down the full range of lifting equipment requiring third party involvement. Certain classes of lifting equipment may require the completion of the proof-load testing program to be carried out on-site and these are highlighted in the relevant procedures, e.g. Main Deck Cranes, Lifeboat Davits.. All Mechanical Handling Equipment will be required to undergo the inspections and tests as described here-in. The resulting certificates are required as part of the System Test Dossier and are mandatory. c) Mechanical Procedures Mechanical Handling Procedures lay down the checks that are required to ensure that the equipment is correctly installed and have been subjected to a proof-load testing program. Installation completion checks will culminate in the raising of a Mechanical Handling Installation Certificate - MH1. GOC© BP Exploration 1989 – 2001 All Rights Reserved SUBJECT: GUIDANCE ON CERTIFICATION SECTION 4.0 GOC© AMERICAS EDITION REVISION: 1 MECHANICAL- MECHANICAL EQUIPMENT PAGE: 5 The successful completion of the MH1 releases the subject mechanical handling equipment for start of the proof load testing program. Proof load testing shall be recorded on the mechanical Handling Acceptance Certificate - MH2. If load testing of a fabrication yard installed lifting appliance has been completed at fabricator’s/vendor’s site, then the testing will not normally be repeated on-site. This does not apply to "man-riding" equipment. Lifting Appliances shall be load tested prior to: i) Access being restricted, e.g. by the installation of the facility equipment (pumps, skids etc.) they are associated with; ii) Painting or coating of themselves or the structure they are attached to. d) Applicable to all Lifting Appliances During the examination of lifting appliances, the following must be recorded on the reverse side of the MH2. A Third Party Certificate Examination of Lifting Appliances, recording the load testing of appliances witnessed by the "Competent Person" is considered acceptable. i) Parts not accessible for thorough examination. ii) Parts that require opening up at the next examination. iii) Particulars of defects and remedy, particulars of any defect found in the lifting appliance of lifting gear which affects the safety of the appliance, and the repairs (if any) required, either immediately or within a specified time (which must be stated), to enable the lifting appliance to continue to be used with safety. GOC© BP Exploration 1989 – 2001 All Rights Reserved SUBJECT: GUIDANCE ON CERTIFICATION SECTION 4.0 GOC© AMERICAS EDITION REVISION: 1 MECHANICAL- MECHANICAL EQUIPMENT PAGE: 6 iv) Safe Working Load (SWL) subject to the repairs, renewals and alterations (if any) specified in (c) above. In the case of a crane with a variable operating radii, including a crane with a derricking jib, the safe working at various radii of the jib, trolley or crab is to be stated. The Mechanical Handling section contains the following procedures: Procedure No 4.6 - Cranes Procedure No 4.7 - Hoists, Trolleys & Gantries Procedure No 4.8 - Trolley Beams & Pad Eyes Procedure No 4.9 - Lifeboats & Davits e) Painting & Marking of Lifting Appliances i) Trolley Beams, lifting points (including associated supporting steelwork) and other pertinent appliances shall be painted safety yellow. ii) The Safe Working Load (SWL) and Equipment Tag numbers shall be painted onto the appliances in black letters, minimum 4 inches tall. The lettering shall be legible from the ground and operating position and routinely applied on both sides. For beams of greater lengths than 15 feet the SWL shall be applied at each end. iii) The SWL and Equipment Tag numbers shall be stamped into the appliance at the end adjacent to the operating position. iv) For lifting points, the requirements described in i) & ii) above shall apply to the associated supporting steelwork f) Lifeboats and Davits (if applicable) i) Where lifeboats (TEMPSC) are installed offshore, an MH1 certificate shall be raised to show correct installation of the lifeboat davits, and an MH2 for the load testing. Welding and NDE shall be recorded on the appropriate forms and reports, refer to Section 2. GOC© BP Exploration 1989 – 2001 All Rights Reserved SUBJECT: GUIDANCE ON CERTIFICATION SECTION 4.0 GOC© AMERICAS EDITION REVISION: 1 MECHANICAL- MECHANICAL EQUIPMENT PAGE: 7 ii) An MH1 certificate will be raised to show correct installation of the lifeboats and launch/retrieval system. iii) The complete system must be tested to the satisfaction of the approving authority, regulations and laws of the country or state whose jurisdiction the offshore installation is subject. 4.1.6 a) Use of Forms MM1: Mechanical Installation Certificate: Used to record that the installation of pumps, compressors and skid mounted units has been carried out in accordance with Machinery Procedure 4.1. The form shall be signed by the Construction and Commissioning Authorities. Any outstanding items shall be identified on the standard GOC© punchlist form PL1. b) MM2: Machinery Alignment Certificate: Used to record that pumps, compressors and other mechanical equipment have been aligned to interfacing equipment, such as motors, gears, turbines, etc., in accordance with Machinery Procedure 4.2. This shall be completed as part of MM1 above and signed by the Construction and Commissioning Authorities. c) MV1: Vessel/Tank/Caisson Installation & PSV/RD Inspection Certificate: MV1 Side 1 is used to record that all checks and tests have been carried out prior to closing the vessel, tank or caission as described in Section 4.1.5 and in accordance with Vessel Procedures No's 4.3, 4.4 and 4.5. GOC© BP Exploration 1989 – 2001 All Rights Reserved SUBJECT: GUIDANCE ON CERTIFICATION SECTION 4.0 GOC© AMERICAS EDITION REVISION: 1 MECHANICAL- MECHANICAL EQUIPMENT PAGE: 8 MV1 Side 2 is used to record that the pressure safety relief devices have been inspected and tested to the requirements of Section 3.2 of Vessel General Requirements Procedure 4.3. The form shall be signed by the Construction, Commissioning, Platform and Vendor Authorities, as applicable, to indicate satisfactory completion of modification, testing and inspection. The back up documentation shown in the flowchart contained in this document should be checked for availability and completion. Any outstanding work shall be punchlisted and recorded on the PL1 form. c) MH1: Mechanical Handling Installation Certificate: Used as a checklist to record that the lifting appliance has been installed correctly. This shall be signed by the Construction Authority prior to proof load testing being carried out. d) MH2: Mechanical Handling Acceptance Certificate: Used to record the proof load test and that the installation is mechanically complete. e) MH2: Mechanical Handling Acceptance Certificate (Cont. Sht): Record any defects, remedies, and recommendations from examination of lifting appliances on the reversed side of the MH2. GOC© BP Exploration 1989 – 2001 All Rights Reserved SUBJECT: GUIDANCE ON CERTIFICATION SECTION 4.0 GOC© AMERICAS EDITION REVISION: 1 MECHANICAL- MECHANICAL EQUIPMENT PAGE: 9 MECHANICAL PROCEDURES Machinery Procedure No. 4.1 - Pump/Compressor/Skid Mounted Unit Installation Procedure No. 4.2 - Machinery Alignment - General Requirements & Pressure Safety Relief Procedure No. 4.4 - Devices Vessel & Tanks Fabricated (Off-Site) Procedure No. 4.5 - Vessel & Tanks Modified (On-Site) Procedure No. 4.6 Procedure No. 4.7 Procedure No. 4.8 - Cranes Hoists, Trolleys and Gantries Trolley Beams and Pad Eyes Procedure No. 4.9 - Lifeboat Davits and Lifeboat Vessels Procedure No. 4.3 Mechanical Handling GOC© BP Exploration 1989 – 2001 All Rights Reserved SUBJECT: GUIDANCE ON CERTIFICATION SECTION 4.0 GOC© AMERICAS EDITION REVISION: 1 MECHANICAL- MECHANICAL EQUIPMENT PAGE: 10 Procedure No. 4.1 1.1 1.1.1 Pumps and Compressors General The following points are to be checked on all pumps, compressors and skid-mounted units: a) Check that the pump/compressor or skid unit is correct in all aspects to the drawings and data sheets, and has been installed to the manufacturer's recommendations and engineering design installation requirements. b) Check that the pump/compressor or skid unit is free from mechanical damage and is internally clean. c) Check that the holding down bolts of the skid unit, pump/compressor and driver to the base plate and the base plate to the floor are correctly installed and tightened. d) Check that the unit is level, correctly shimmed and fixed to the base. e) Check dissimilar metals isolation is achieved. f) Check that all ancillary equipment is installed and operational. g) Check that all drains and vents - including bedplate drains are connected and clear of obstruction. h) Check that all mechanical seals are clean and completed. i) Check that all piping is complete and correctly aligned, e.g. seal and lube oil systems are flushed correctly (pickled where necessary) and filled with the correct oil. j) Check that all interface points are correct to the vendor’s drawing(s). GOC© BP Exploration 1989 – 2001 All Rights Reserved SUBJECT: GUIDANCE ON CERTIFICATION SECTION 4.0 GOC© AMERICAS EDITION REVISION: 1 MECHANICAL- MECHANICAL EQUIPMENT PAGE: 11 k) Check that all ladders and walkways are complete. l) Check that all the painting, heat tracing and insulation is completed and the appropriate certificates are approved. m) Check that all bearings have correct lubrication. n) Check that all gearboxes and fluid couplings, where fitted, are filled with the correct lubrication. o) Check that all instrumentation, including PSV's, is correctly fitted, visible, accessible for maintenance purposes and tested. p) Check that all suction and discharge piping is completed, correctly aligned with the correct gaskets installed. Pipe strain induced on equipment shall not effect the alignment more than 0.002 inch from the 12:00 or 3:00 o’clock dial indicator position. q) Check that all temporary and permanent strainers are fitted and easily identified. r) Check that all rotating equipment is free to turn by hand. s) Prior to installation of coupling, check that the driver is in the correct direction of rotation. t) Check that the drive couplings, belts and guards are correctly fitted. u) Check that the machinery Alignment and Certificate MM2 is completed. v) Check that the mechanical Punchlist is raised, (form PL1). Refer to project specific requirements for rotating equipment (inspection, pre-commissioning, installation) and API RP 686 Recommended Practices for Machinery Installation and Installation Design. GOC© BP Exploration 1989 – 2001 All Rights Reserved SUBJECT: GUIDANCE ON CERTIFICATION SECTION 4.0 GOC© AMERICAS EDITION REVISION: 1 MECHANICAL- MECHANICAL EQUIPMENT PAGE: 12 1.1.1 Certification a) Mechanical Installation Certificate MM1 and/or the Machinery Alignment Certificate MM2 will be completed as appropriate by the Construction Authority Mechanical Engineer when the above checks have been carried out. Note: Paint, insulation and trace heating have not been included in this procedure as they will be covered by certification raised by other disciplines, i.e. (Architectural Services Section 7.0, and Electrical Section 9.0). GOC© BP Exploration 1989 – 2001 All Rights Reserved SUBJECT: GUIDANCE ON CERTIFICATION SECTION 4.0 GOC© AMERICAS EDITION REVISION: 1 MECHANICAL- MECHANICAL EQUIPMENT PAGE: 13 Procedure No. 4.2 2.1 Machinery 2.1.1 Machinery Alignment a) The following Procedures are to be performed in conjunction with the Machinery Alignment Certificate Form MM2. b) Abbreviations: DTI = Dial Test Indicator DBSE = Distance Between Shaft Ends TDC TIR c) = Top Dead Center = Total Indicated Runout All machinery will have the alignment checked by one of the following methods described below. Tolerances shall be within the manufacturers standard requirements or ± 0.002 inch TIR, whichever is less. d) Always rotate the shafts in the direction of rotation, and view the readings from the Driver to the Driven equipment. e) Enter the type of Alignment Procedure to be used on Form MM2 i.e. Reverse/Optical/Rim & Face. If Rim & Face is to be used, delete the titles Driver Hub & Driven Hub and insert the titles Face and Rim. f) Enter the target alignment that is to be achieved in the Required Alignment section. g) Always verify that equipment bearings are lubricated. Rotate the equipment by hand a couple of rotations, just prior to taking alignment readings. h) Prior to any of the following methods of alignment being undertaken, the concentricity checks must be carried out. GOC© BP Exploration 1989 – 2001 All Rights Reserved SUBJECT: GUIDANCE ON CERTIFICATION SECTION 4.0 GOC© AMERICAS EDITION REVISION: 1 MECHANICAL- MECHANICAL EQUIPMENT PAGE: 14 2.1.2 Concentricity Checks, Coupling Hub Run-Out a) Mount 2 Nos. DTI off the shaft of the driven machine, and place the pointers in their mid positions, one on the rim and one on the face of the Driver hub, and zero the clocks. Note: When taking the face readings ensure the end float in the shafts does not give inaccurate readings, i.e. push end float all one way. b) Rotate the Driver hub in the direction of rotation at least twice, at 90 degree intervals take the actual rim and face run-out, and enter readings on the Form MM2. c) Repeat above for the Driven hub. 2.1.3 Rim and Face Alignment a) Rim - Mount a DTI support bar on the Driver hub, place the pointer in its mid position on the Driven hub, and zero the clock at TDC (0 degrees). b) Turn the shaft in the direction of rotation, at least twice, and neter readings taken at 90 degree intervals on the Form MM2. c) Face - Mount a DTI between the faces of the Driver and Driven coupling hubs, ensuring that the shafts end float does not have any inaccuracies, i.e. push end float all one way. d) Set the DTI pointer in the mid range and zero the clock. e) Turn the shaft in the direction of rotation, at least twice, and enter readings taken at 90 degree intervals on the Form MM2. GOC© BP Exploration 1989 – 2001 All Rights Reserved SUBJECT: GUIDANCE ON CERTIFICATION SECTION 4.0 GOC© AMERICAS EDITION REVISION: 1 MECHANICAL- MECHANICAL EQUIPMENT PAGE: 15 2.1.4 Reverse Alignment a) Using offset DTI supports, mount the support for the DTI on the Driver hub and DTI on the Driven hub rim. Vice versa for Driven hub to Driver hub. b) Set the DTIs in mid range, and zero the clocks when both clocks are at TDC (0 degrees). c) Turn both shafts together in the direction of rotation, take reading simultaneously off both DTI's at 90 degree intervals, and enter them on the Form MM2. 2.1.5 Optical Alignment a) Complete the alignment using the Optical Manufacturers Alignment Procedure. b) Enter all readings on to the Optical Manufacturers Alignment sheet and attach it to the Form MM2. 2.1.6 Distance Between Shaft Ends (DBSE) a) Using an internal micrometer or vernier calliper, check the required DBSE between the driver and driven hubs, and enter on the Form MM2, taking into consideration any end float in the driver or driven equipment. Rotors for horizontal motors shall be set on their magnetic center prior to measuring and setting the DBSE. 2.1.7 Soft Footings a) Both driven unit and driver shall be checked for a "soft foot" condition. With the equipment final aligned and all the hold down bolts properly torqued, install two dial indicators from the driver shaft to the driven GOC© BP Exploration 1989 – 2001 All Rights Reserved SUBJECT: GUIDANCE ON CERTIFICATION SECTION 4.0 GOC© AMERICAS EDITION REVISION: 1 MECHANICAL- MECHANICAL EQUIPMENT equipment coupling hub. PAGE: 16 Position the indicators at 12:00 and 3:00 o’clock. b) Loosen one of the driver hold down bolts one at a time and verify that neither indicator moves more than 0.002 inch. c) Repeat step (b) until all driver and driven equipment hold down bolts have been checked. GOC© BP Exploration 1989 – 2001 All Rights Reserved SUBJECT: GUIDANCE ON CERTIFICATION SECTION 4.0 GOC© AMERICAS EDITION REVISION: 1 MECHANICAL- MECHANICAL EQUIPMENT PAGE: 17 Procedure No. 4.3 3.1 Vessels General Requirements 3.1.1. General The following points are to be checked on vessels and tanks, both fabricated offsite or modified on-site, and are in addition to any other specific procedure. a) All inspections will be in accordance with applicable codes, standards and Specifications. b) All vessel platforms, ladders and access arrangements will be inspected by the Construction Authority Mechanical Engineer to ensure compliance with design drawings, specifications, standards and safety aspects. c) The Construction and Commissioning Authorities will conduct an internal inspection of the vessel, to confirm cleanliness, damage free condition, and completion of internals installation to specification, including but not limited to the following: i) ii) iii) iv) v) vi) vii) viii) Demisting Pads Trays Coils Baffles Vortex Breaker Lining Packing Internal nuts suitably locked. d) Internal coating to be checked by a Paint Inspector. e) Check all insulation is correct and complete. f) Check all instrumentation is visible and accessible. GOC© BP Exploration 1989 – 2001 All Rights Reserved SUBJECT: GUIDANCE ON CERTIFICATION SECTION 4.0 GOC© AMERICAS EDITION REVISION: 1 MECHANICAL- MECHANICAL EQUIPMENT PAGE: 18 g) Check grounding and bonding is correct to specification. h) Check all piping connections, and manways are bolted up correctly and that the correct specification gaskets have been installed. i) Check that the holding down bolts are correctly tightened and/or torqued. j) Check that the details of vessel identification plate are correct. k) Check that the state registration has been completed and number assigned. l) Prior to final closure of the vessel/tank, the Construction and Commissioning Authorities shall inspect it internally. Discipline punch listing shall be carried out, as applicable, and the relevant PL1 forms raised. m) Vessel manufacturers data Material Data Reports (MDR’s) are available. 3.2 Pressure Safety Relief Devices 3.2.1 Pressure Safety Valves - General At site, pressure safety valves will be checked for freedom from damage and deterioration and the lifting pressure shall be tested on a suitable pressure rig. The testing authority will be subject to BP approval. All test methods must be agreed with BP before being put into operation. The following standard is applicable to this procedure: • API 510 - Requirements for Inspection & Repair of Pressure Relieving Devices GOC© BP Exploration 1989 – 2001 All Rights Reserved SUBJECT: GUIDANCE ON CERTIFICATION SECTION 4.0 GOC© AMERICAS EDITION REVISION: 1 MECHANICAL- MECHANICAL EQUIPMENT PAGE: 19 • API RP 576 - Inspection of Pressure Relieving Devices • • API RP 527 - Seat Tightness of Pressure Relief Valves ANSI B147.1 - Commercial Seat Tightness of Safety Relief Valves with Metal to Metal Seats (formerly API Standard 527). It is important that Pressure Safety Valves are stored in a secure warehouse with the valves standing vertically. When received, the valve blanking plates should be checked for damage, which could have allowed the passage of foreign material into the inlet nozzle and the body cavity. If Pressure Safety Valves are shipped without test-gags in place, then it will be necessary to strip down every valve to ensure that there has been no damage on seats or discs during transit and to remove any loose material. A Relief Valve shall be put into service within 60 days of being tested, calibrated and re-set. 3.2.2 a) Test Procedure Pressure safety valves shall be tested immediately prior to installation. If installation is deferred, the protective flange covers shall be refitted and the valve stored in a vertical position. When required for service, the valve must be re-tested. The pressure safety valve should be initially bench tested and then tested in-place prior to start-up. There may be some specific test requirements required by the regulatory agency that is in authority. All tests on pressure safety valves shall be the responsibility of the Construction Authority, and shall be recorded on certificate MV1 (Side 2). Tests shall be witnessed by the Commissioning or Integrity Authority, who shall countersign the MV1 to indicate witnessing. All pertinent data relating to PSV calibration shall be recorded on MV1 (Side 2). GOC© BP Exploration 1989 – 2001 All Rights Reserved SUBJECT: GUIDANCE ON CERTIFICATION SECTION 4.0 GOC© AMERICAS EDITION REVISION: 1 MECHANICAL- MECHANICAL EQUIPMENT PAGE: 20 The safety valves tests are in two stages: b) i) Popping and reseating. ii) Seat leakage test. Popping and Reseating Before popping the safety valve, the outlet flange shall be removed. The inlet nozzle should be wiped clean prior to testing. The safety valve 'cold set pressure' shall be ascertained and entered on the test record sheet. This pressure should be found on the valve data plate or on the valve data sheet. The test pressure shall be increased slowly until the safety valve is observed to pop and the pressure (as indicated by the 'maximum' pointer on the test gauge) shall be noted on the test record sheet. If the difference between the measured popping pressure and the cold set pressure is outside acceptable tolerances, the valve setting shall be adjusted in accordance with the manufacturer's instructions. The test pressure shall then be lowered and the reseating pressure noted and checked that it agrees with the safety valve specification. c) Seat Leakage Test Unless otherwise specified, the seat leakage rate shall be tested in accordance with ANSI B147.1. This test procedure is summarized as follows: Immediately after the popping the test pressure shall be lowered and held at 10% below the set pressure (5 psig or 0.35 bar g minimum) for the duration specified in ANSI B147.1. GOC© BP Exploration 1989 – 2001 All Rights Reserved SUBJECT: GUIDANCE ON CERTIFICATION SECTION 4.0 GOC© AMERICAS EDITION REVISION: 1 MECHANICAL- MECHANICAL EQUIPMENT PAGE: 21 The outlet flange shall be refitted complete with safety plug and the open end of the bleed pipe shall be immersed in water to a depth of 0.5 inches (13 mm) below the surface. The leakage rate in bubbles per minute will then be checked in accordance with ANSI B147.1. Should the leakage rate exceed the permitted tolerance, the popping and leakage tests shall be repeated to ensure that foreign particles are not preventing complete closure. Failure of the leakage test shall be corrected by dismantling the valve and lapping the disc and seat in accordance with the manufacturer's instructions. After testing, the valve shall be identified by a suitable color sticker. The bonnet cap shall be firmly secured and locked using a metal link and lead seal. Note: During testing to API 527 using the cap method, it is possible for air leakage to occur around the top bonnet flange; the outlet flange made off for the test; and the cap. These should be soap tested during the test to prove that there is no leakage. Alternatively, a flooded seat test should be nominated for valve discharge flanges greater than 2 inches and, after such test; the body cavity shall be thoroughly dried with instrument air. 3.2.3 Pilot Operated Safety Relief Valves A variety of Pressure Safety Valves operate with pilots and in every case pressure in the system activates a mechanism that is independent of the basic Relief Valve, which opens the valve to full capacity. Inspection, testing, maintenance and setting of the Pilot-Operated Relief Valves may be divided into two separate phases; the pilot mechanism phase and the basic relief valve phase. With test connections, the set pressure of some types of valve may be accurately tested while the GOC© BP Exploration 1989 – 2001 All Rights Reserved SUBJECT: GUIDANCE ON CERTIFICATION SECTION 4.0 GOC© AMERICAS EDITION REVISION: 1 MECHANICAL- MECHANICAL EQUIPMENT PAGE: 22 valve is in service. (If there is no isolation block valve under the relief valve, it may be inspected and repaired only while the vessel is out of service.) Because of the many varied types of Pilot-Operated Relief Valves available, the valve manufacturers recommendations for inspection and repair should be consulted and followed, along with API RP 576 Inspection of Pressure Relieving Devices. 3.2.4 Rupture Discs (RD) Rupture Discs (Bursting Discs) are pressure containing devices that are used in service where a large relieving capacity is required to give a rapid drop in pressure. A rupture disc is the pressure-containing and pressure-sensitive element of a rupture disc device. Rupture Discs maybe designed in several configurations, such as flat, domed (pre-bulged), or reverse acting. Most discs may require a rupture holder to enclose, seal, and clamp the rupture disc in position. This combination of the disc and holder is called a rupture disc device. Because rupture discs cannot be tested, they should be replaced on a regular schedule based on their application, manufacturer’s recommendations and past experience. Reference should be made to API RP 576 Inspection of Pressure Relieving Devices and API RP 520 Parts 1 and 2 on rupture discs. Care should be taken on installation, to ensure that the data and material specifications stamped on the data plate or tab handle agrees with the required specification and recorded on form MV1 (Side 2) by the Construction Authority. During installation, the Commissioning Authority will check to ensure the correct direction of flow. GOC© BP Exploration 1989 – 2001 All Rights Reserved SUBJECT: GUIDANCE ON CERTIFICATION SECTION 4.0 GOC© AMERICAS EDITION REVISION: 1 MECHANICAL- MECHANICAL EQUIPMENT PAGE: 23 3.3 Certification a) Form MV1 (Side 1) shall be completed by the Construction, Commissioning Authorities to record that the vessel checks have been carried out satisfactorily, to the requirements of the following Vessel Procedures: Procedure No. 4.3 - General Requirements Procedure No. 4.4 - Vessels and Tanks Fabricated (Off-Site) Procedure No. 4.5 - Vessels and Tanks Modified (On-Site) b) Form MV1 (Side 2) shall be completed by the Construction, Commissioning Authorities to record that the pressure safety relief devices have been inspected and tested to the requirements of Section 3.2 of Vessel General Requirements Procedure 4.3. GOC© BP Exploration 1989 – 2001 All Rights Reserved SUBJECT: GUIDANCE ON CERTIFICATION SECTION 4.0 GOC© AMERICAS EDITION REVISION: 1 MECHANICAL- MECHANICAL EQUIPMENT PAGE: 24 Procedure No. 4.4 4.1 Vessels and Tanks Fabricated (Off-Site) 4.1.1. General This section covers the inspection procedures to be carried out on pressure vessels and atmospheric tanks fabricated and tested in vendors facilities and should be carried out in conjunction with Vessel Procedure No. 4.3 - General Requirements. The following points are to be checked: a) Ensure the vessel is correct in all respects to the vendor drawings and data sheet. b) Prior to vessel placement, the foundation/structural support construction is to be checked for compliance with design drawings, specifications and for completion. c) The vessel is to be initially inspected for transit damage, and after placement for installation damage. d) Check PSV's have been installed correctly and are still in certification. e) Check "expansion end bolting to be loose". f) If it is intended to include the vessel within a piping pressure test pack, the Construction Authority Mechanical Engineer shall verify the existence on site of the dedicated vessel test certificate, and sight the Inspection Release Note. g) The piping system test pressure shall be compared with the vessel pressure, and the Construction Authority Mechanical Engineer will ensure that the pressure ranges are compatible, before authorizing the inclusion of the vessel in the piping system test. GOC© BP Exploration 1989 – 2001 All Rights Reserved SUBJECT: GUIDANCE ON CERTIFICATION SECTION 4.0 GOC© AMERICAS EDITION REVISION: 1 MECHANICAL- MECHANICAL EQUIPMENT PAGE: 25 4.1.2 Certification a) Form MV1 shall be completed by the Construction and Commissioning Authorities, to record that the vessel checks and documentation are complete, and that the requirements of Vessel Procedure No. 4.3 General Requirements, and Vessel Procedure No. 4.4 - Vessels and Tanks Fabricated (Off-site), have been carried out satisfactorily. GOC© BP Exploration 1989 – 2001 All Rights Reserved SUBJECT: GUIDANCE ON CERTIFICATION SECTION 4.0 GOC© AMERICAS EDITION REVISION: 1 MECHANICAL- MECHANICAL EQUIPMENT PAGE: 26 Procedure No. 4.5 5.1 Vessels and Tanks Modified (On-Site) 5.1.1 General This section covers the inspection procedures to be carried out during the on-site modification of vessels and tanks, in addition to the inspection activities outlined in the design specifications and drawings, and should be carried out in conjunction with Vessel Procedure No. 4.3 - General Requirements. a) All materials employed for the fabrication are to have passed inspection on receipt at stores operated by BP or their Delegated Authority. b) Before authorizing release of the vessel/tank for pressure testing, the Construction Authority Mechanical Engineer must be satisfied that the following inspection functions have been satisfactorily executed: i. All NDE requirements and welding must have been completed to the satisfaction of the Construction Authorities Welding Inspector and all welded attachments completed. ii. All temporary dog clips and plate alignment brackets shall have been removed, and weld deposits ground off, to the satisfaction of the Construction Authorities Welding Inspector, prior to stress relieving, if required. iii. Stress relieving, if a requirement, must be completed prior to pressure testing, and dedicated documentation certifying this activity completion made available. iv. Internal vessel inspection conducted to ensure completion of all works and applicable certification completed made available. GOC© BP Exploration 1989 – 2001 All Rights Reserved SUBJECT: v. GUIDANCE ON CERTIFICATION SECTION 4.0 GOC© AMERICAS EDITION REVISION: 1 MECHANICAL- MECHANICAL EQUIPMENT PAGE: 27 The vessel is correct in all respects to the fabrication drawings and data sheets, and that all necessary fabrication records are available and correct. c) When the Construction Authorities Mechanical Engineer is satisfied that all construction activities in the modification of the vessel have been completed, a vessel release authorization is to be issued for commencement of the pressure test to an agreed procedure. d) The vessel will then be released by the Construction Mechanical Engineer for any internal lining/painting and external insulation/painting work. Inspections will be executed by the Construction Authorities Mechanical Engineer/Inspectors during and after completion of these work activities. e) Vessel/Tank/equipment shall be re-certified and stamped by the Certifying Authority prior to being returned service, if so designated. 5.1.2 Certification a) Form MV1 shall be completed by the Construction, Commissioning and Platform Inspection Authorities, to record that the vessel checks, fabrication documentation and testing records are complete, and the requirements of Vessel Procedure No. 4.3 - General Requirements, and Vessel Procedure No. 4.5 - Vessels and Tanks Modified (On-Site), have been carried out satisfactorily. GOC© BP Exploration 1989 – 2001 All Rights Reserved SUBJECT: GUIDANCE ON CERTIFICATION SECTION 4.0 GOC© AMERICAS EDITION REVISION: 1 MECHANICAL- MECHANICAL EQUIPMENT PAGE: 28 Procedure No. 4.6 6.1 Cranes 6.1.1 General This procedure lays down the checks that are required to ensure that the subject crane is correctly installed and has been subjected to a full proof - load and function testing. Site inspection and testing of cranes will comply with the requirements of BP specifications and federal and state requirements or the appropriate regulations and laws of the country or state whose jurisdiction the installation is subject. Cranes will be erected and tested in accordance with the Vendors approved procedures and under the supervision of their representative. "On-site" welding or any modification to the crane is subject to authorization by the Vendors design office, the BP Site Engineers and CA approval. The following points are to be checked on all cranes and are in addition to the applicable text in the Mechanical Handling section 4.1.5. a) All mountings (turret/slewing ring, etc.) are to be checked against Vendor Drawings for correct installation, and all major fixing bolts checked for correct grade and torque setting. b) The settings and function of all safety devices are to be checked and tested or certified. c) All wire rope systems are to be checked to ensure that they are reeved in accordance with the Vendors instructions, that the wire rope remains captive within the sheave and drum and does not foul the crane during operation. d) All lubricants and coolants shall be checked for correct grade and quantity. GOC© BP Exploration 1989 – 2001 All Rights Reserved SUBJECT: e) GUIDANCE ON CERTIFICATION SECTION 4.0 GOC© AMERICAS EDITION REVISION: 1 MECHANICAL- MECHANICAL EQUIPMENT PAGE: 29 Check that the Vendor has provided certification that will cover but not be limited to the following: i. Crane as a whole Including Statutory requirements ii. Hooks iii. Snatch blocks iv. Wire ropes, hoist and boom hoist v. Special tackle, lifting, beams etc. for crane maintenance vi. Pressure vessels (air receiver for diesel air start) vii. All electrical/instrument items including hazardous area certificates viii. Structural steel and NDE reports ix. Slewing rings and fastenings x. All loose equipment for handling the crane (spreader beams, slings etc.) f) If load testing of a crane has only been partially achieved off-site, the testing will be completed when the crane is installed in its permanent location on-site. g) Cranes (pedestal and non-pedestal) are to be proof load tested to Statutory requirements with certified test weights and/or calibrated load cell, in the presence of a third party inspector as assigned by BP. h) All fabrication certification and load test certification of any supporting structure is available in addition to the crane load test. GOC© BP Exploration 1989 – 2001 All Rights Reserved SUBJECT: i) GUIDANCE ON CERTIFICATION SECTION 4.0 GOC© AMERICAS EDITION REVISION: 1 MECHANICAL- MECHANICAL EQUIPMENT PAGE: 30 On completion of the tests, a thorough examination of the crane will be undertaken by the inspector to ensure no damage or permanent strain has occurred. Some spot checking by NDT may be required at the discretion of the Inspector. Hooks shall be NDT after load test. 6.1.2 Certification a) Form MH1 - Mechanical Handling Installation Certificate, is to be used to record the satisfactory completion of the checks which are to be carried out, and requires endorsement to confirm that the required vendor certification is correct and available on-site, that the requirements of this procedure have been carried out, and that the crane has been installed in accordance with the specified design requirements. The successful completion of the MH1 releases the crane for start of the proof load-testing program. b) Form MH2 - Mechanical Handling Acceptance Certificate is to be used to record the proof load testing certificates and any other relevant certificates and/or restrictions. The MH2 requires endorsement to confirm the completion and witness of the proof load testing and will have attached the third party reports and test certificates. c) The Crane can be commissioned in advance using temporary supplies and be used as an installation aid during construction and commissioning of the facility. GOC© BP Exploration 1989 – 2001 All Rights Reserved SUBJECT: GUIDANCE ON CERTIFICATION SECTION 4.0 GOC© AMERICAS EDITION REVISION: 1 MECHANICAL- MECHANICAL EQUIPMENT PAGE: 31 Procedure No. 4.7 7.1 Hoists, Trolleys & Gantries 7.1.1. General This procedure lays down the checks that are required to ensure that the Hoists, Trolleys & Gantries are per specification, correctly installed and have been subjected to a full proof-load testing program. Site inspection and testing of this lifting equipment will comply with the requirements of BP specifications and federal and state requirements or the appropriate regulations and laws of the country or state the installation is subject. The following are to be checked on all hoists, trolleys & gantries and are in addition to the applicable text in the Mechanical Handling section 4.1.5. a) All lifting equipment has been installed in accordance with the Vendors approved procedures and drawings. b) Mounting beams, rails and guides must be inspected to ensure that the installation complies with the specified geometrical tolerances. c) The lifting devices themselves must be checked against vendor and/or design drawings for correct assembly and installation. d) All wire rope or chain systems are to be checked to ensure they are reeved in accordance with the vendors instructions and that the wire rope or chain remains captive within the sheave and drum and does not foul the lifting elements during operation. e) Safety catches on hooks must be checked for correct function. f) Check that the lifting equipment vendor, and Third Party Inspection Authority have provided the necessary load test certification for the equipment. GOC© BP Exploration 1989 – 2001 All Rights Reserved SUBJECT: GUIDANCE ON CERTIFICATION SECTION 4.0 GOC© AMERICAS EDITION REVISION: 1 MECHANICAL- MECHANICAL EQUIPMENT PAGE: 32 g) Trolleys and gantries must be travelled over all working conditions to ensure there are no interferences with other equipment. h) When the equipment has been partially dismantled to aid installation, those bolts removed must be replaced and torqued correctly. If the bolts were load bearing then the equipment must be tested as described in Mechanical Handling Procedure No. 4.8 7.1.2 Certification a) Form MH1 - Mechanical Handling Installation Certificate, is to be used to record the satisfactory completion of the checks which are to be carried out, and requires endorsement to confirm that the required certification is correct and available on site, that the requirements of the relevant procedure have been carried out, and that the lifting equipment has been installed in accordance with the specified design requirements. The successful completion of the Mechanical Handling Installation Certificate Form MH1 releases the installation for the start of the proofload testing program. b) Form MH2 - Mechanical Handling Acceptance Certificate, is to be used to record the proof-load testing certificates and any other relevant certificates and/or restrictions. The MH2 requires endorsement to confirm the completion and witness of the proof-load testing, and will have attached the Third Party Reports if the installation has been subjected to Third Party Inspection. GOC© BP Exploration 1989 – 2001 All Rights Reserved SUBJECT: GUIDANCE ON CERTIFICATION SECTION 4.0 GOC© AMERICAS EDITION REVISION: 1 MECHANICAL- MECHANICAL EQUIPMENT PAGE: 33 Procedure No. 4.8 8.1 Trolley Beams and Pad Eyes 8.1.1 General This procedure describes the checks that are required to ensure that the Trolley Beams and Pad Eyes are per specification, correctly installed and have been subjected to a full proof-load testing program. Site Inspection and testing of this lifting equipment will comply with the requirements of BP specifications and federal and state requirements or the appropriate regulations and laws of the country or state whose jurisdiction the installation is subject. The following are to be checked on all Trolley Beams and Pad Eyes and are in addition to the applicable text in the Mechanical Handling section 4.1.5. a) All lifting equipment has been installed in accordance with approved procedures and drawings. b) The Trolley Beams and Pad Eyes must be checked against design drawings for correct assembly and installation. c) All bolts are to be checked to ensure the correct grade and torque setting. d) All site fabricated Trolley Beams, main attachment points, Pad Eyes and other lifting appliances shall be considered primary structure with respect to material traceability, welding and NDE. e) Where a dedicated trolley is specified for a Trolley Beam, it is preferred to test using the trolley. Hoists should be trial erected on trolleys and Pad Eyes. GOC© BP Exploration 1989 – 2001 All Rights Reserved SUBJECT: f) GUIDANCE ON CERTIFICATION SECTION 4.0 GOC© AMERICAS EDITION REVISION: 1 MECHANICAL- MECHANICAL EQUIPMENT PAGE: 34 Lifting equipment is to be proof-load tested to Statutory requirements, with certified test weights or calibrated load cell, in the presence of Third Party Inspector as assigned by BP. g) Trolley Beams should have the Safe Working Load (SWL) traversed along the beam, deflections should be checked at the greatest span of the beam. The deflection should not exceed 1/500th of the span, for cantilever sections 1/250th at the SWL. An overload of 1.25 x SWL should be applied at the point of maximum deflection. Measure and record this deflection, remove all load and ensure the deflection returns to zero. The design contractor will specify pad eye design and test loads. h) All items must be stamped with TAG No. and SWL to show dedication to a particular Mechanical Handling Installation. i) Trolley Beams without dedicated trolleys will be proof-load tested using a "test” trolley. This must be clearly stated on the Mechanical Handling Acceptance Certificate Form MH2. j) The Safe Working Load, TAG No. and any limiting conditions shall be clearly painted on the Trolley Beam or adjacent to Pad Eye so as to be clearly visible to the operator. k) On completion of each proof-load test, a thorough examination of the tested lifting equipment shall be undertaken by the Inspection Authority, to ensure no damage or permanent strain has occurred. Checking by NDT will be required. GOC© BP Exploration 1989 – 2001 All Rights Reserved SUBJECT: GUIDANCE ON CERTIFICATION SECTION 4.0 GOC© AMERICAS EDITION REVISION: 1 MECHANICAL- MECHANICAL EQUIPMENT PAGE: 35 8.1.2 Certification a) Form MH1 - Mechanical Handling Installation Certificate, is to be used to record the satisfactory completion of the checks which are to be carried out, and requires endorsement to confirm that the required certification is correct and available on site, that the requirements of the relevant procedure have been carried out, and that the lifting equipment has been installed in accordance with the specified design requirements. The successful completion of the Mechanical Handling Installation Certificate Form MH1 releases the installation for the start of the proofload testing program. b) Form MH2 - Mechanical Handling Acceptance Certificate, is to be used to record the proof-load testing certificates and any other relevant certificates and/or restrictions. The MH2 requires endorsement to confirm the completion and witness of the proof-load testing, and will have attached the Third Party Reports if the installation has been subjected to Third Party Inspection. GOC© BP Exploration 1989 – 2001 All Rights Reserved SUBJECT: GUIDANCE ON CERTIFICATION SECTION 4.0 GOC© AMERICAS EDITION REVISION: 1 MECHANICAL- MECHANICAL EQUIPMENT PAGE: 36 Procedure No. 4.9 9.1 Lifeboat Davits and Lifeboat 9.1.1 General This procedure lays down the checks that are required to ensure that the Lifeboat Davits and Lifeboats for offshore use are per specification, correctly installed and have been subjected to a full proof-load testing program. Site inspection and testing of the Lifeboat and Davits will comply with the appropriate regulations and laws of the country or state whose jurisdiction the offshore installation is subject. The Lifeboat and Davits will be installed off-site and tested in accordance with the Vendors approved procedures, under the supervision of their representative and the Third Party Inspector. Additional on-site welding or any modification to the Davits is subject to authorization of the Vendor’s design office and the BP Site Engineer’s approval. The following points are to be checked on all Lifeboat installations and are in addition to the applicable text in the Mechanical Handling section 4.1.5. a) The Davits and Lifeboat are correct in all respects to the Vendors drawings. b) The Davits and Lifeboat are free from damage. c) The Davits and Lifeboat have been installed as required by Vendors design drawings and procedures. d) The settings and function of all safety devices are to be checked and proved. GOC© BP Exploration 1989 – 2001 All Rights Reserved SUBJECT: e) GUIDANCE ON CERTIFICATION SECTION 4.0 GOC© AMERICAS EDITION REVISION: 1 MECHANICAL- MECHANICAL EQUIPMENT PAGE: 37 Check that the Vendor has provided certification that will cover but not be limited to the following: i) Davits and Lifeboat as a whole including Statutory requirements. ii) Wire ropes, shackles, pulleys and hoist. iii) All electrical and instrumentation cables and equipment. iv) Structural steel and NDE reports. v) All life support equipment. f) The Lifeboat and Davits, as a single unit, will be proof-load tested after installation and shall be witnessed by a third party inspection as assigned by BP. g) Further testing and drops to sea level will be carried out on-site in line with (f) above. h) On completion of each part of the proof-load testing program, a thorough examination of the Davits, Lifeboats and support structure will be carried out to ensure no damage or permanent strain has occurred. Checking by NDT will be required. GOC© BP Exploration 1989 – 2001 All Rights Reserved SUBJECT: 9.1.2 GUIDANCE ON CERTIFICATION SECTION 4.0 GOC© AMERICAS EDITION REVISION: 1 MECHANICAL- MECHANICAL EQUIPMENT PAGE: 38 Certification Form MH1 - Mechanical Handling Installation Certificate is to be used to record the satisfactory completion of the checks which are to be carried out, and requires endorsement to confirm that the required Vendor Certification is correct and available on site, that the requirements of the procedure have been carried out, and the Davits and Lifeboat have been installed in accordance with the specified design requirements. The successful completion of the Mechanical Handling Installation Certificate Form MH1 releases the Davits/Lifeboat installation for the start of the proof-load testing program. If the Davits have been part proof-load tested prior to the installation of the Lifeboat, then a second MH1 will be raised for checking and approving this subsequent installation. Form MH2 - Mechanical Handling Acceptance Certificate is to be used to record the proof-load testing certificates and any other relevant certificates. The MH2 requires endorsement to confirm the completion and witness of the proof-load testing. If the Davits have been part proof-load tested prior to installation of the Lifeboat then the MH2 must be clearly marked to reflect this. Standard Proformas Form No MH1 MH2 Proforma Description Mechanical Handling Installation Certificate Mechanical Handling Acceptance Certificate GOC© BP Exploration 1989 – 2001 All Rights Reserved SUBJECT: GUIDANCE ON CERTIFICATION SECTION 4.0 GOC© AMERICAS EDITION REVISION: 1 MECHANICAL- MECHANICAL EQUIPMENT PAGE: 39 FLOWCHART 4.1 • Functional Certification Flowchart • Discipline: Mechanical MM1 MC1 MM2 SL1 SH1 MM1: Machinery Installation Certificate MC1: Mechanical Completion Certificate MM2: Pre-Operations Alignment Certificate SL1: System Leak or Service Test / Witness Joint Certificate SH1: System Handover Certificate Note! Where Welding is carried out, an MW1 - Welding Completion Summary is required - Refer to GOC© Section 2 GOC© BP Exploration 1989 – 2001 All Rights Reserved SUBJECT: GUIDANCE ON CERTIFICATION SECTION 4.0 GOC© AMERICAS EDITION REVISION: 1 PAGE: 40 MECHANICAL- MECHANICAL EQUIPMENT FLOWCHART 4.2 • • Functional Certification Flowchart Discipline: Mechanical (Vessels) MV1 MC1 SL1 SH1 MV1: Pre-Operations Inspection MC1: Mechanical Completion Certificate MM2: Pre-Operations Alignment Certificate SL1: SH1: System Leak or Service Test / Witness Joint Certificate System Handover Certificate Note! Where Welding is carried out, an MW1 - Welding Completion Summary is required - Refer to GOC© Section 2 GOC© BP Exploration 1989 – 2001 All Rights Reserved SUBJECT: GUIDANCE ON CERTIFICATION SECTION 4.0 GOC© AMERICAS EDITION REVISION: 1 PAGE: 41 MECHANICAL- MECHANICAL EQUIPMENT FLOWCHART 4.3 • • Functional Certification Flowchart Discipline: Mechanical (Handling Equipment) MH1 MH2 MC1 SH1 JI1 MH1: Mechanical Handling Installation Certificate MH2: Mechanical Handling Load Test Certificate MC1: Mechanical Completion Certificate SH1: JI1: System Handover Certificate Joint Integrity Certificate Note! Where Welding is carried out, an MW1 - Welding Completion Summary is required - Refer to GOC© Section 2 GOC© BP Exploration 1989 – 2001 All Rights Reserved SUBJECT: GUIDANCE ON CERTIFICATION SECTION 4.0 GOC© AMERICAS EDITION REVISION: 1 MECHANICAL- MECHANICAL EQUIPMENT PAGE: 42 EXHIBIT 4 STANDARD FORMS Form No. Form Title MM1 Mechanical Installation Certificate MM2 Machinery Alignment Certificate MV1 MH1 MH2 Vessel/Tank/Cassion Installation & PSV/RD Inspection Certificate Mechanical Handling Installation Certificate Mechanical Handling Acceptance Certificate DIS2 Data Input Sheet 2 - Section 4 Mechanical Note: Final acceptance of each report as complete and correct shall be authorization by the Construction and Commissioning Group, and other approved authorities. GOC© BP Exploration 1989 – 2001 All Rights Reserved Project Title: Maintenance No: Work Pack No: SH1 No: MC1 No: FORM MM1 SITE: MECHANICAL INSTALLATION CERTIFICATE PACKAGE NO: SYSTEM: EQUIPMENT NO: LOCATION: SHT * PROCEDURE 4.1 Complete : Unit Installation SIGNATURE DATE / / * PROCEDURE 4.2 Complete : Machinery Alignment SIGNATURE DATE / / OF P&ID NO: REMARKS PUNCH LIST NO. COMPLETED BY APPROVED BY COMPANY SIGNATURE PRINT NAME DATE * DELETE AS APPLICABLE GOC© BP Exploration 1989 – 2001 All Rights Reserved Americas REV. 1 Project Title: Maintenance No: Work Pack No: SH1 No: MC1 No: FORM MM2 SITE: MACHINERY ALIGNMENT CERTIFICATE SHT PACKAGE NO: LOCATION: P&ID No: GA No: PROCEDURE 4.1 Complete : Unit Installation EQUIP No SIGNATURE: DATE: / OF / DESCRIPTION INSPECTION No SERIAL No MANUFACTURER DESCRIPTION INSPECTION No SERIAL No MANUFACTURER ALIGNMENT TO EQUIP No REQUIRED ALIGNMENT 0° DRIVER HUB DRIVEN HUB D.B.S.E. COUPLING HUB RUN OUT 90° DRIVER RIM FACE ACTUAL ALGINMENT WITH PIPING FREE 0° DRIVER HUB DRIVEN HUB D.B.S.E. ACTUAL ALGINMENT WITH PIPING CONNECTED 0° DRIVER HUB DRIVEN HUB D.B.S.E. 0O 180 O 90O 270 O DRIVEN 270° RIM FACE 90° 180° 270° 90° 180° 270° READINGS VIEWED DRIVER TO DRIVEN 0O 90O 270 O 180° DRIVER DRIVEN D.B.S.E. 180 O COMMENTS Reverse Alignment attach Graph COMPLETED BY APPROVED BY COMPANY SIGNATURE PRINT NAME DATE * DELETE AS APPLICABLE GOC© BP Exploration 1989 – 2001 All Rights Reserved Americas REV. 1 Project Title: Maintenance No: Work Pack No: SH1 No: MC1 No: FORM MV1 (Side 1) SITE: VESSEL/TANK/CAISSON INSTALLATION & PSV/RD INSPECTION CERTIFICATE EQUIP TAG No: PSV / RD TAG No: DESCRIPTION: LOCATION OPERATING PRESSURE: PSIG SYSTEM: OPERATING TEMPERATURE: DEG F PACKAGE No: SERIAL No: P&ID No: MANUFACTURERS TEST CERT No: DRAWING No: SHT OF (see Side 2) INSPECTION No: TEST PRESSURE: PSIG TEST DURATION: MINS / HRS TEST MEDIUM: TEST DATE: THIS CERTIFICATE SHALL BE COMPLETED BY THE VENDOR, CONSTRUCTION AND COMMISSIONING AUTHORITIES TO RECORD THAT THE VESSEL CHECKS, FABRICATION DOCUMENTATION AND TESTING RECORDS ARE COMPLETE, AND THAT THE REQUIREMENTS OF THE FOLLOWING PROCEDURES HAVE BEEN CARRIED OUT SATISFACTORILY WHERE APPLICABLE. YES NO N/A 1. VESSEL PROCEDURE 4.3 - GENERAL REQUIREMENTS 2. VESSEL PROCEDURE 4.4 - VESSELS & TANKS FABRICATED (OFF-SITE) 3. VESSEL PROCEDURE 4.5 - VESSELS & TANKS MODIFIED (ON-SITE) COMMENTS NOTES WHERE THESE TANKS FORM PART OF MODULE STRUCTURES, THIS INSPECTION MAY DUPLICATE PARTS OF THE MAIN MODULE ACCEPTANCE PROCEDURES. INSPECTION TO BE CONDUCTED IN ACCORDANCE WITH APPLICABLE CONTRACT SPECIFICATIONS AND DESIGN CODES. COMPLETED BY APPROVED BY COMPANY SIGNATURE PRINT NAME DATE GOC© BP Exploration 1989 – 2001 All Rights Reserved DOUBLE SIDED FORM Americas REV. 1 FORM MV1 PSV/RD INSPECTION (SIDE 2) PSV / RD TAG No: INSPECTION No: P&ID No: REPORT NO: LOCATION: SYSTEM: EQUIPMENT / LINE NO. SERVICE DUTY TYPE INSPECTION: INSPECTED BY DATE LAST INSPECTION: DATE OF INSPECTION: NAMEPLATE DETAILS MANUFACTURER INLET SIZE / CLASS / TYPE / / MODEL NO./TYPE OUTLET SIZE / CLASS /TYPE / / SERIAL NO. ORIFICE PSV COLD SET PRESS. PSV COLD DIFF. SET PRESS. o o RD BURST PRESS @ 72 F/22 C BACK PRESS. PSIG SPRING RANGE PSIG RD HOLDER SIZE / CLASS PSIG RD FLANGE ASSY. NO. / PSI INSPECTION SPRING DETAILS BELLOWS FITTED LENGTH TRIM MATERIAL DIAMETER VALVE OVERHAULED NO. OF COILS BONNET CONDITION MATERIAL BODY CONDITION MAT. DIAMETER SPRING CONDITION COLOR CODE/NO. RD DISK MATL. / COATING YES / NO / TEST DETAILS (PSV ONLY) PRE POP PRESSURE PSIG TEST MEDIUM ACTUAL SET PRESSURE PSIG ADJUSTING BOLT MEASUREMENT BELLOW/BODY TEST BLOW DOWN RING SET ins or mm NOTCHES DOWN REMARKS/RECOMMENDATIONS INSPECTION PERIOD LIMITATIONS DATE OF NEXT INSPECTION MAJOR INSPECTION: SPECIAL INSPECTION: COMPLETED BY APPROVED BY COMPANY SIGNATURE PRINT NAME DATE GOC © BP Exploration 1989 – 2001 All Rights Reserved DOUBLE SIDED FORM Americas REV. 1 Project Title: Maintenance No: Work Pack No: SH1 No: MC1 No: FORM MH1 SITE: MECHANICAL HANDLING INSTALLATION CERTIFICATE EQUIPMENT No: SHT OF LOCATION: INSPECTION No: DRAWING No: SERIAL No: DESCRIPTION: GENERAL ARRANGEMENT No: PUNCH LIST No: ITEM/DESCRIPTION OF CHECK SIGNATURE DATE ----------------------- -------------- ----------------------- -------------- ----------------------- -------------- 1. TRANSIT DAMAGE CORRECT 2. FIXED EQUIPMENT INSTALLED IN ACCORDANCE WITH APPROVED DRAWINGS AND SPEC. 3. TRAVEL & OPERATION OF EQUIP. UNRESTRICTED & IN ACCORDANCE WITH DESIGN SPEC. 4. ASSOCIATED ALIGNMENT CHECKS COMPLETE ON: (a) RUNWAY (TROLLEY) BEAMS (b) GANTRIES (c) BEAM TRANSFER AND LATCH MECHANISMS (d) ASSOC. MECH. EQUIP. i.e. WINCHES, HOISTING MECHANISMS (e) OTHER: 5. ASSOCIATED LIFTING APPLICANCES CORRECTLY INSTALLED, TAGGED AND CERTIFIED: (a) BEAM TROLLIES (b) COMBINED TROLLEY HOISTS (c) CHAIN HOISTS (d) OTHERS: 6. ASSOCIATED DESIGNATED LIFTING TACKLE CORRECTLY INSTALLED, TAGGED & CERTIFIED: (a) WIRE ROPES (b) SHEAVE BLOCKS (c) SHACKLES (d) BEAM CLAMPS (e) SLINGS (f) EYEBOLTS (g) OTHERS: 7. CHECK S.W.L. IF ALL EQUIP, WITHIN AN INSTALLED LIFTING SYSTEM ARE COMPATIBLE 8. PERSONNEL PROTECTION AND SAFETY DEVICES CORRECTLY INSTALLED 9. EQUIPMENT IDENTIFICATION AND S.W.L. CLEARLY MARKED 10. CHECK THAT ALL MATERIAL AND FABRICATION REQUIREMENTS AS PER SPECIFICATION AND APPROVED DRAWING HAVE BEEN MET AND ALL CERTIFICATION IS RECORDED. (APPLICABLE TO INSTALLATION OF FIXED EQUIPMENT) 11. ALL EQUIPMENT CORRECTLY INSTALLED AND AVAILABLE FOR PROOF LOAD TEST COMMENTS COMPLETED BY APPROVED BY COMPANY SIGNATURE PRINT NAME DATE GOC© BP Exploration 1989 – 2001 All Rights Reserved Americas REV. 1 Project Title: Maintenance No: Work Pack No: SH1 No: MC1 No: FORM MH2 (SIDE 1) SITE: MECHANICAL HANDLING ACCEPTANCE CERTIFICATE SHT ITEM : LOCATION: EQUIPMENT No: SAFE WORKING LOAD (S.W.L.): INSPECTION No: PROOF LOAD: SERIAL No: PROOF LOAD CERTIFICATE No: VERIFING AUTHORITY: DRAWING No: MAKER & DATE OF MAKE: DATE FIRST PUT INTO USE: OF DATE OF LAST RECORD EXAMINATION (IF SEEN). NAME OF PERSON WHO CONDUCTED LAST EXAMINATION AND OF THE EMPLOYER. PARTS NOT ACCESSIBLE FOR THOROUGH EXAMINATION PARTS THAT REQUIRE OPENING UP AT THE NEXT EXAMINATION PARTICULARS OF DEFECTS AND REMEDY PARTICULARS OF ANY DEFECT FOUND IN THE LIFTING APPLICANCE AND THE REPAIRS (IF ANY) REQUIRED, EITHER ; i IMMEDIATELY OR, ii WITHIN A SPECIFIED TIME (WHICH MUST BE STATED) TO ENABLE THE LIFTING APPLICANCE OR LIFTING GEAR TO CONTINUE TO BE USED WITH SAFETY. (IF NO SUCH REPAIRS ARE REQUIRED, THE WORK 'NONE' IS TO BE ENTERED) SAFE WORKING LOAD SUBJECT TO THE REPAIRS, RENEWALS AND ALTERATIONS (IF ANY) SPECIFIED ABOVE IN THE CASE OF A CRANE WITH A VARIABLE OPERATING RADIUS, INCLUDING A CRANE WITH DERRICKING JIB, THE SAFE WORKING LOAD AT VARIOUS RADII OF THE JIB, TROLLEY OR CRAB TO BE STATED SECTION 1 (TO BE COMPLETED WHERE APPROPRIATE TO PERMANENT LIFTING TACKLE INCLUDED IN PROOF LOAD TEST) ITEM DESCRIPTION TAG/IDENTIF. No S.W.L. CERTIFICATE No 1. 2. 3. 4. 5. 6. SECTION 2: IF APPLICABLE, STATE ANY SPECIFIC LIFTING RESTRICTIONS WHICH MAY APPLY TO THE LIFTING EQUIPMENT OR SYSTEM AND WHICH IS REQUIRED TO BE CLEARLY MARKED ON THAT EQUIPMENT SECTION 3: IF APPLICABLE, REFERENCE ANY FABRICATION, NDT, MATERIAL CONTROL CERTIFICATION AND INSPECTION REPORTS RELATING TO THE CONSTRUCTION INSTALLATION ACTIVITIES COPIES OF ALL PROOF LOAD CERTIFICATION LISTED ABOVE TO ACCOMPANY THIS CERTIFICATE COMPLETED BY APPROVED BY COMPANY SIGNATURE PRINT NAME DATE GOC© BP Exploration 1989 – 2001 All Rights Reserved DOUBLE SIDED FORM Americas REV. 1 MECHANICAL HANDLING EXAMINATION REPORT FORM MH2 (SIDE 2) EQUIPMENT No. SH1 No INSPECTION No. MC1 No. SERIAL No. S.W.L. DRAWING No. PROOF LOAD TEST CERTIFCATE No. EXAMINATION REPORT COMMENTS PUNCH LIST NO. COMPLETED BY APPROVED BY COMPANY SIGNATURE PRINT NAME DATE GOC© BP Exploration 1989 – 2001 All Rights Reserved DOUBLE SIDED FORM Americas REV. 1 DIS2 LOCATION : __________________ DATA INPUT SHEET 2 PROJECT : __________________ NO. HANDOVER ID EQUIP No WIN No RAISED BY: __________________________________ NOTE: JP No FOR INSTALLATION / TESTING EQUIPMENT SWL LOAD TEST P&ID No DATE : ________________ GOC DRG No OF WORKSCOPE ID : ___________________ SECTION 4 - MECHANICAL J.P SHEET MAINTENANCE ID No : ______________ ASBUILT REQ'D (LAD) MECHANICAL CERTIFICATES REQUIRED MW1 MM1 MM2 DATA ENTERED BY : _________________________ © BP Exploration 1989 - 2001 All Rights Reserved MV1 MH1 MH2 SL1 DATE : ___________ Americas Rev. 1 AS2 SUBJECT: GUIDANCE ON CERTIFICATION SECTION 5.0 GOC© AMERICAS EDITION REVISION: 1 MECHANICAL- STRUCTURAL PAGE: 1 SECTION 5.0 STRUCTURAL GOC© BP Exploration 1989 – 2001 All Rights Reserved SUBJECT: 5.1 ACTIONS 5.1.1 General GUIDANCE ON CERTIFICATION SECTION 5.0 GOC© AMERICAS EDITION REVISION: 1 MECHANICAL- STRUCTURAL PAGE: 2 Construction Management responsibilities and associated quality planning for structural activities, is normally categorised and managed as follows: a) On-Site. The Construction Authority is responsible for the inspection and test activities and management of the construction Contractor who provides labor and equipment only; b) Off-Site. The Construction Authority monitors the performance of the Management Contractor who is directly responsible for the fabrication and Inspection and Test activities. c) For on-site, those inspection and test activities that require to be performed and recorded to fulfil the minimum quality control requirements, are clearly defined on the specified Inspection and Test Schedule (ITS) for the work. d) For off-site, those Inspection and Test activities performed by the Managing Contractor that are deemed by BP or their delegated authority to be at critical stages in the fabrication process and require to be witnessed before the Contractor can proceed, will be clearly defined within the Managing Contractor's quality plan (QP), and/or the supplied ITS. e) The acceptance of structural work is a composite function of Fabrication, N.D.E. and Inspection (Section 2) and Architectural Services (Section 7). Input by the relevant discipline engineers is required in quality planning and subsequent development of an ITS for both off-site and on-site Work. f) Flow charts give guidelines on handover of on-site work. GOC© BP Exploration 1989 – 2001 All Rights Reserved SUBJECT: g) GUIDANCE ON CERTIFICATION SECTION 5.0 GOC© AMERICAS EDITION REVISION: 1 MECHANICAL- STRUCTURAL PAGE: 3 All reporting and recording of inspection and acceptance of structural work shall be on the GOC© standard forms or alternatives where agreed by BP or the delegated authority. h) The Construction Authority shall exercise sufficient dimensional control over the Work and shall monitor or conduct surveys throughout prefabrication, fabrication, construction and installation stages of the Work to ensure that the specified design tolerances are achieved. The fabricator prior to installation shall establish reference marks and levels required to assist fit-up. i) The Construction Authority shall prepare, maintain and issue reports, which describe the extent, and contain the results, of all dimensional surveys carried out on-site and shall monitor reports produced by the fabricator off-site. 5.1.2 Installation The installation of Structural Items shall be checked for compliance and other requirements as detailed in but not limited to: • • • • • • • The latest revision of Issued For Construction (IFC) or Approved For Construction (AFC) Drawings and Schedules Codes and standards reference in this section Plant and Project Specifications Equipment Specifications and Data sheets BP Engineering Installation and Design Specifications Local, state, country and international standards, codes, and regulations as appropriate Offshore - Special Standards, i.e. USCG, ABS and MMS 5.1.3 Use of Forms a) Off-Site Structural Acceptance The MS1 will certify that all offsite fabrication activities for a discrete structure or its component parts, complies in all particulars with the required Design and that all specified Inspection and Testing is completed and accepted. GOC© BP Exploration 1989 – 2001 All Rights Reserved SUBJECT: GUIDANCE ON CERTIFICATION SECTION 5.0 GOC© AMERICAS EDITION REVISION: 1 MECHANICAL- STRUCTURAL PAGE: 4 The Structural Engineer authorised by BP or their Delegated Authority shall break down all discrete structures into the following classifications for certification purposes: • Discrete Structure (i.e. Module, Jacket, Module Support Frame, etc.) • Assembly (i.e. Module Truss or Jacket Truss, deck extension, etc.) Sub-Assembly (i.e. Truss Node or Tubular, etc.) • As a minimum, all sub-assemblies will require an MS1 certificate before they can be installed in to an assembly. All assemblies will require an MS1 certificate before they can be installed into the discrete structure. All discrete structures will require an MS1 certificate before they can be released for shipment onsite for installation. b) On-Site Structural Acceptance The MS1 will certify that all onsite activities relating to the on-site fabrication and installation of structural work have been completed and comply in all particulars with the approved design, fabrication and installation specifications and that all specified Inspection and Testing is completed. c) Concealed Area Acceptance When subsequent work creates concealed areas and prohibits further access for re-inspection of structural steel, the Construction Authority must note on the MS1 certificate that the concealed areas were inspected, prior to boxing in of stiffners or covering the deck area or cladding, etc. GOC© BP Exploration 1989 – 2001 All Rights Reserved SUBJECT: GUIDANCE ON CERTIFICATION SECTION 5.0 GOC© AMERICAS EDITION REVISION: 1 MECHANICAL- STRUCTURAL PAGE: 5 FLOWCHART 5 • Functional Certification Flowchart • Discipline: Mechanical (Structural) MS1 MC1 SH1 MS1: Structural Completion Certificate MC1: Mechanical Completion Certificate SH1: System Handover Certificate Note! Where Welding is carried out on MW1 - Welding Completion Summary is required - Refer to GOC© Section 2 GOC© BP Exploration 1989 – 2001 All Rights Reserved GUIDANCE ON CERTIFICATION SECTION 5.0 GOC© AMERICAS EDITION REVISION: 1 MECHANICAL- STRUCTURAL PAGE: 6 SUBJECT: EXHIBIT 5 STANDARD FORMS FORM NO. TITLE MS1 STRUCTURAL COMPLETION CERTIFICATE DIS3 Data Input Sheet 3 – Section 5 Structural Note: Final acceptance of the MS1 - Structural Completion Certificate will be by the Structural Engineer authorized by BP or their Delegated Authority. GOC© BP Exploration 1989 – 2001 All Rights Reserved Project Title: Maintenance No: Work Pack No: SH1 No: MC1 No: STRUCTURAL COMPLETION CERTIFICATE FORM MS1 (SIDE 1) SITE: SHT OF THIS CERTIFICATE VERIFIES THAT THE WORKS SHOWN ON THE LISTED DESIGN DRAWINGS HAVE BEEN FABCRICATED, INSTALLED AND TESTED IN CONFORMANCE WITH THE APPROVED DESIGNS, SPECIFICATIONS AND PROCEDURES. STRUCTURE/FABRICATION DESCRIPTION DRAWINGS REV ITEM DESCRIPTION OF ACTIVITY SIGNATURE *1 *2 *3 MATERIAL TRACEABILITY VERIFIED MATERIAL LOCATION PLAN APPROVED MATERIAL TRACEABILITY CONTROL SYSTEM VERIFIED Q.C. INSPECTOR *1 *2 *3 WELDING INSPECTOR *4 *5 NDE RESULTS SATISFACTORY PWHT RESULTS SATISFACTORY WELDING TRACEABILITY VERIFIED (WELDER IDENTS & PROCEDURES) WELD/NDE TRACEABILITY LOCATION DRAWING APPROVED WELD COMPLETION SUMMARY APPROVED 3 *1 *2 DIMENSIONAL CONTROL CHECKS SATISFACTORY DIMENSIONAL AS-BUILT SURVEYS APPROVED Q.C. INSPECTOR 4 *1 WEIGHT CONTROL AND C of G CHECKS COMPLETE Q.C. INSPECTOR 5 *1 FINAL VISUAL INSPECTION SATISFACTORY Q.C. INSPECTOR 6 *1 PAINTING/COATINGS & INSULATION SATISFACTORY Q.C. INSPECTOR 1 2 ENSURE THAT THE STRUCTURAL ACTIVITY CHECK LIST, ON THE REVERSE SIDE OF THIS FORM, IS COMPLETED AND APPROVED BY THE STRUCTURAL ENGINEER COMPLETED BY APPROVED BY COMPANY SIGNATURE PRINT NAME DATE *DELETE AS APPLICABLE GOC© BP Exploration 1989 – 2001 All Rights Reserved DOUBLE SIDED FORM Americas REV. 1 STRUCTURAL ACTIVITY CHECK LIST STRUCTURAL ENGINEER SH1 NUMBER ITEM DESCRIPTION OF ACTIVITY 1 ERECTION & FIT-UP OF STRUCTURAL MEMBERS OR FRAME COMPLETE 2 ALL BOLTS, NUTS & WASHERS INSTALLED & TIGHTENED 3 DECK PLATE INSTALLED 4 DECK GRATING INSTALLED & FULLY SECURED 5 HANDRAILS INSTALLED & FULLY SECURED 6 KICK PLATE INSTALLED & FULLY SECURED 7 VERTICAL LADDER ASSEMBLIES INSTALLED & FULLY SECURED TO STRUCTURE 8 ACCESS STAIR ASSEMBLIES INSTALLED & FULLY SECURED TO STRUCTURE 9 DOOR FRAMES INSTALLED AND FULLY SECURED TO THE STRUCTURE 10 DOORS HUNG, ALL FITMENTS FITTED & DOORS FULLY OPERATIONAL 11 ELECTRICAL / INSTRUMENT TRANSIT FRAMES INSTALLED 12 PIPE PENETRATIONS INSTALLED 13 EXTERNAL BULKHEAD CLADDING INSTALLED 14 ALL WELDING COMPLETE 15 ALL TEMPORARY INSTALLATION AIDS REMOVED AND REMAINING STRUCTURE DRESSED & MADE GOOD 16 P.W.H.T. COMPLETE 17 N.D.E. COMPLETE 18 PASSIVE FIRE PROTECTION COMPLETE 19 ENVIRONMENTAL INSULATION COMPLETE 20 PAINTING COMPLETE 21 VERIFICATION OF REVIEW & APPROVAL OF CONTRACTORS/SUBCONTRACTORS FABRICATION, INSPECTION & TEST DOSSIER COMPLETED BY YES NO N/A COMMENTS COMPANY SIGNATURE PRINT NAME DATE GOC© BP Exploration 1989 – 2001 All Rights Reserved DOUBLE SIDED FORM Americas REV. 1 DIS3 SHEET LOCATION : __________________ DATA INPUT SHEET 3 PROJECT : __________________ J.P NO. RAISED BY: HANDOVER ID DRAWING No DATE : __________________ ____________________________________ NOTE: JP No FOR INSTALLATION / WELDOUT WORKSCOPE ID : ___________________ SECTION 5 - STRUCTURAL DESCRIPTION GOC OF MAINTENANCE ID No : ______________ AS-BUILT REQ'D (LAD) MW1 STRUCTURAL AS1 AS2 MS1 DATA ENTERED BY : ____________________ © BP Exploration 1989 - 2001 All Rights Reserved COMMENTS DATE : ___________ Americas Rev. 1 SUBJECT: GUIDANCE ON CERTIFICATION SECTION 6.0 GOC© AMERICAS EDITION REVISION: 1 MECHANICAL - HVAC SECTION 6.0 HVAC GOC © BP Exploration 1989 – 2001 All Rights Reserved PAGE: 1 SUBJECT: GUIDANCE ON CERTIFICATION SECTION 6.0 GOC© AMERICAS EDITION REVISION: 1 MECHANICAL - HVAC 6.1 ACTIONS 6.1.1 General PAGE: 2 a) Input by the relevant discipline engineers is required during Quality Planning and the subsequent development of the Inspection Test Summary. b) HVAC shall be checked for compliance and other requirements as detailed in, but not limited to: • The latest revision of Issued For Construction (IFC) or Approved For Construction (AFC) Drawings and Schedules • • Codes and standards reference in this section Plant and Project Specifications • Equipment Specifications and Data sheets • • BP Engineering Installation and Design Specifications Local, state, country and international standards, codes, and regulations as appropriate • Offshore - Special Standards, i.e. USCG, ABS and MMS 6.1.2 Installation a) Equipment/Material shall be inspected on receipt on site. Any remedial work carried out on site by the vendor to correct transit damage or faulty workmanship will be supervised by the Construction Authority. b) Installation shall be carried out under supervision of the Construction Authority. c) On completion of construction activities, the Construction Authority shall advise the Technical Integrity Authority accordingly. Where required, the Technical Integrity Authority shall witness all inspections and tests which are to be recorded, unless the Technical Integrity Authority waives this requirement. GOC© BP Exploration 1989 – 2001 All Rights Reserved GUIDANCE ON CERTIFICATION SECTION 6.0 GOC© AMERICAS EDITION REVISION: 1 SUBJECT: MECHANICAL - HVAC PAGE: 3 The Technical Integrity Authority shall monitor construction activities wherever possible, so that inspection and testing can be carried out as work proceeds. d) Following the satisfactory completion of inspection and testing, the Construction Authority shall complete the relevant records, which shall be witnessed by the Technical Integrity Authority as appropriate. No further work shall be carried out by construction on this completed plant unless by agreement with the Technical Integrity Authority. e) Vendor’s assistance may be required during the pre-commissioning and/or commissioning of HVAC systems. f) Where required testing of HVAC systems will be witnessed by the Technical Integrity Authority. 6.1.3 Use Of Forms a) General Requirements For all HVAC works, all recording of inspection and tests shall be on the © In addition to the SP2 HVAC System GOC standard forms. Performance Test Certificate, the Technical Integrity Authority is particularly interested in the following test recording sheets and they will have to be retained and attached to the SP2 - System Performance Test Certificate. i) ii) iii) iv) TR1 TR2 TR16 TR17 HVAC System Installation & Function Test Certificate Fire Dampers Tests. Smoke Test. Room Pressurization Test (Part 1). All remaining rest record sheets are completed and used as part of the assessment process to establish if the HVAC system as a whole meets GOC© BP Exploration 1989 – 2001 All Rights Reserved GUIDANCE ON CERTIFICATION SECTION 6.0 GOC© AMERICAS EDITION REVISION: 1 SUBJECT: MECHANICAL - HVAC PAGE: 4 design criteria. When this is established and the SP2 is approved then the TR’s are superfluous and may be discarded with the exception of the TR1, TR2, TR16 and TR17. b) SP2: System Performance Test Certificate To be used by the Technical Integrity Authority to record satisfactory completion of HVAC installation and tests by individual sections. c) PL1: Punchlist To be used by Construction/Technical Integrity Authority by discipline, to record outstanding items/defects on installation Construction, prior to any Commissioning activities. d) completion by Test Recording Sheet No. 1: TR1 To be used by the Technical Integrity Authority for collating instrument installation and function test data. e) Test Recording Sheet No. 2: TR2 To be used by the Technical Integrity Authority for collating Damper Test data. f) Test Recording Sheet No. 3: TR3 To be used by the Technical Integrity Authority for collating Filter/ Coalescer/ Separator Test data. g) Test Recording Sheet No. 4: TR4 To be used by Technical Integrity Authority for collating Heating Coil test data. GOC© BP Exploration 1989 – 2001 All Rights Reserved GUIDANCE ON CERTIFICATION SECTION 6.0 GOC© AMERICAS EDITION REVISION: 1 SUBJECT: h) MECHANICAL - HVAC PAGE: 5 Test Recording Sheet No. 5: TR5 To be used by the Technical Integrity Authority for collating Centrifugal Fan Test data. i) Test Recording Sheet No. 6: TR6 To be used by the Technical Integrity Authority for collating Humidifier Test data. j) Test Recording Sheet No. 7: TR7 To be used by the Technical Integrity Authority for collating Constant Volume/ Terminal Re-Heat Unit Test data. k) Test Recording Sheet No. 8: TR8 To be used by the Technical Integrity Authority for collating Terminal Air Conditioning Unit Test data. l) Test Recording Sheet No. 9: TR9 To be used by the Technical Integrity Authority for collating Air Handling Unit Test Unit Test data. m) Test Recording Sheet No. 10: TR10 To be used by the Technical Integrity Authority for collating Cooling Coil Test data. n) Test Recording Sheet No. 11: TR11 To be used by the Technical Integrity Authority for collating Cooling Tower Test data. GOC© BP Exploration 1989 – 2001 All Rights Reserved SUBJECT: o) GUIDANCE ON CERTIFICATION SECTION 6.0 GOC© AMERICAS EDITION REVISION: 1 MECHANICAL - HVAC PAGE: 6 Test Recording Sheet No. 12: TR12 To be used by the Technical Integrity Authority for collating Grille & Diffuser Test data. p) Test Recording Sheet No. 13: TR13 To be used by the Technical Integrity Authority for collating Ductwork Air Leakage’s Rate Test data. q) Test Recording Sheet No. 14: TR14 To be used by the Technical Integrity Authority for collating System Balance Test data. r) Test Recording Sheet No. 15: TR15 To be used by the Technical Integrity Authority for collating Internal Conditions Test data. s) Test Recording Sheet No. 16: TR16 To be used by the Technical Integrity Authority for collating Smoke Test data. t) Test Recording Sheet No. 17: TR17 To be used by the Technical Integrity Authority for collating Room Pressurization data. u) Test Recording Sheet No. 18: TR18 To be used by the Technical Integrity Authority for collating Pressurization Unit Test data. GOC© BP Exploration 1989 – 2001 All Rights Reserved SUBJECT: GUIDANCE ON CERTIFICATION SECTION 6.0 GOC© AMERICAS EDITION REVISION: 1 MECHANICAL - HVAC PAGE: 7 6.1.4 Calibration a) Any test equipment, whether in-house or vendor supplied, used in the pre-commissioning and/or commissioning of HVAC systems, shall be accompanied by current Calibration Certificate stating that the test equipment has been calibrated to specified limits within the specified time limits. GOC© BP Exploration 1989 – 2001 All Rights Reserved SUBJECT: GUIDANCE ON CERTIFICATION SECTION 6.0 GOC© AMERICAS EDITION REVISION: 1 MECHANICAL - HVAC HVAC PROCEDURES Procedure No. 6.1 - General Requirements Procedure No. 6.2 - Dampers Procedure No. 6.3 - Filtration Procedure No. 6.4 - Heating and Cooling Coils Procedure No. 6.5 - Centrifugal Fans and Drivers Procedure No. 6.6 - Humidifiers Procedure No. 6.7 - Terminal Units, Grills & Diffusers Procedure No. 6.8 - Air Conditioning Units Procedure No. 6.9 - Air Handling Unit Procedure No. 6.10 - Ductwork Procedure No. 6.11 - Sound Attenuators Procedure No. 6.12 - Cooling Towers Procedure No. 6.13 - Areas Receiving HVAC Supply GOC© BP Exploration 1989 – 2001 All Rights Reserved PAGE: 8 SUBJECT: GUIDANCE ON CERTIFICATION SECTION 6.0 GOC© AMERICAS EDITION REVISION: 1 MECHANICAL - HVAC PAGE: 9 Procedure No. 6.1 1.1 General Requirements 1.1.1 General This Procedure lays down the checks that are required to ensure that the overall system is per project specifications and correctly installed prior to carrying out specific checks on individual parts of the installation. The Following points are to be checked: a) Check supplied equipment for damage. b) Check that nameplate is in a readable location and that the data corresponds with the relevant equipment index/specification/data sheet/drawing with regard to identification/tag number ratings and other data. c) Check that equipment has been installed as per the specifications, Issued for Construction (IFC) drawings and vendors instructions. d) By reference to the area classification drawing, check the classification of locations where electrical equipment is installed and ensure that equipment installed in hazardous locations carries the appropriate certification. e) Ensure that the applicable installation procedures, inspections, and tests have been carried out for mechanical, electrical and control equipment, compressors, fans, pumps, motors, cabling switchgear, instruments, etc. Refer to the appropriate section of the GOC© for guidance i.e., Mechanical Section 3.0, Control Section 8.0 and Electrical Section 9.0. GOC© BP Exploration 1989 – 2001 All Rights Reserved SUBJECT: f) GUIDANCE ON CERTIFICATION SECTION 6.0 GOC© AMERICAS EDITION REVISION: 1 MECHANICAL - HVAC Ensure that equipment is properly grounded: PAGE: 10 measure ground path resistance in accordance with the relevant Electrical Procedures reference in Section 9.0. g) Ensure that painting (Section 7) has been carried out in accordance with the project painting specification or to the manufacturers own agreed application, and that no damage has occurred during installation. h) Check that there is adequate space to maintain/inspect the equipment. i) Check that the equipment is internally and externally clean. 1.1.2 Certification a) With reference to e) above the relevant discipline inspection and test certificates shall be used to record that the applicable installation procedures, inspection and tests have been carried out and are acceptable. The SP2 Test Certificate shall be used for all HVAC procedures as detailed in this section, any items of non-conformance should be indicated on the particular certificate, relating to that part of the installation concerned, and also be fully identified on the relative discipline punchlist, Form PL1. GOC© BP Exploration 1989 – 2001 All Rights Reserved GUIDANCE ON CERTIFICATION SECTION 6.0 GOC© AMERICAS EDITION REVISION: 1 SUBJECT: MECHANICAL - HVAC PAGE: 11 Procedure No. 6.2 2.1 Dampers 2.1.1 General This procedure lays down the checks/tests that are required to ensure that all types of dampers in the HVAC system are per project specifications, correctly certified and installed correctly. Although the Technical Integrity Authority (TI) may demand additional tests for fire dampers, the following points are to be checked: a) Carry out the relevant checks listed in Procedure No. 6.1 - General Requirements. b) Check that access doors adjacent to the dampers are installed where applicable. c) Check that the damper blade clearance and sealing is satisfactory. d) Check that the damper blades move freely. e) Check that the blade position external indicator is fitted and gives correct indication. f) Check that the blade position locking quadrant is satisfactory. g) Check that movement of the damper corresponds to the type of control called for in the specification. h) Check that the damper blades are adequately supported where damper width exceeds 40 in. GOC© BP Exploration 1989 – 2001 All Rights Reserved SUBJECT: i) GUIDANCE ON CERTIFICATION SECTION 6.0 GOC© AMERICAS EDITION REVISION: 1 MECHANICAL - HVAC PAGE: 12 Check that the blades are enclosed within the casing with the damper in the fully open position. j) Check that the damper actuators are free to move and suitably enclosed. k) Ensure that damper controls move freely and are unobstructed for the purpose of routine maintenance and periodic certification inspections. l) Check that the local hand lever moves freely. m) Check visually that the damper is adequately supported and that the correct specification gaskets are fitted to the connecting ductwork. Ensure that the damper is bolted correctly and that any dissimilar metal isolation is achieved. n) Ensure that where required, the integrity of the bulkhead penetration is maintained. Ensure penetration has been properly sealed with fire stopping. o) Ensure that the tension spring is fitted, and that there is adequate space via the enclosure access plate to maintain tension spring adjustment for pressure setting. p) Check that the damper is internally clean and is left in the fully open position. q) Check that the access cover to the enclosure has been replaced. r) Check that the limit switches actuation is satisfactory. s) Check that instrument air supply tubing & piping is correctly fitted and function correctly. t) Check that the mechanical reset mechanism re-opens electric dampers. GOC© BP Exploration 1989 – 2001 All Rights Reserved GUIDANCE ON CERTIFICATION SECTION 6.0 GOC© AMERICAS EDITION REVISION: 1 SUBJECT: u) MECHANICAL - HVAC PAGE: 13 Check that a fusible link of the correct rating is fitted and accessible, and that the damper closes and seals correctly. Caution: Dampers are typically spring loaded and rapid closing! v) Check that the insulation, fire rated where specified, has been correctly fitted after ensuring that the damper material and finish are to specification and undamaged. w) Ensure that the fire dampers carry appropriate fire resistance test certificates and UL/NRTL listing and label. x) Ensure that where appropriate, dampers carry Technical Integrity Authority (TI) certification. 2.1.2 Damper Test a) Test recording sheet No. 2 (TR2) is provided for collation of test data, to enable subsequent signing of the applicable part of the SP2 Test Certificate. 2.1.3 Certification a) Form HVAC; TR2 shall be completed by the BP HVAC Representative and/or Vendor as appropriate, to record that all necessary inspections and tests relevant to either type of damper, have been carried out satisfactorily, to the requirements of HVAC Procedures 6.1 & 6.2. Any deviation to Design/Operating Parameters and Vendor instructions shall be recorded on the Test Record Sheet. GOC© BP Exploration 1989 – 2001 All Rights Reserved GUIDANCE ON CERTIFICATION SECTION 6.0 GOC© AMERICAS EDITION REVISION: 1 SUBJECT: MECHANICAL - HVAC PAGE: 14 Procedure No. 6.3 3.1 Filtration 3.1.1 General This procedure lays down the checks/tests that are required to ensure that the air filters and filter/coalescers are per project specifications and are correctly installed. The following points are to be checked as appropriate to the subject item of equipment. a) Carry out the relevant checks listed in Procedure 6.1 - General Requirements. b) Check visually that the equipment is adequately supported and that the correct specification gaskets are fitted to the connecting ductwork. Ensure that the equipment is bolted correctly and that any dissimilar metal isolation is achieved. c) Check that the filter elements and removal guide rails have been properly installed and ensure that there is adequate space to maintain/remove filters. d) Check that access doors adjacent to the unit have been installed where applicable. e) Check that the differential pressure indicator is located in a readable position and that all associated pipework is installed correctly. f) Check that the spray nozzles are clean. GOC© BP Exploration 1989 – 2001 All Rights Reserved SUBJECT: g) GUIDANCE ON CERTIFICATION SECTION 6.0 GOC© AMERICAS EDITION REVISION: 1 MECHANICAL - HVAC PAGE: 15 Check that drain connections and traps are located correctly and free of blockages and restrictions, and that traps can be visually checked for water level. h) Check that heat trace has been installed if required and that it has been inspected in accordance with the relevant Electrical Procedures (Section 9.0). 3.1.2 Filter/Coalescer/Separator Test a) Test recording sheet No. 3 (TR3) is provided for collation of test data, to enable subsequent signing of the applicable part of the SP2 Test certificate. 3.1.3 Certification a) Form HVAC; TR3 shall be completed by the BP HVAC Representative and/or Vendor as appropriate, to record that all necessary inspections and tests relevant to the subject equipment type have been carried out satisfactorily, to the requirements of HVAC Procedures 6.1 & 6.3. Any deviation to the Design/Operating Parameters and Vendor instructions shall be recorded on the Test Recording Sheet. GOC© BP Exploration 1989 – 2001 All Rights Reserved SUBJECT: GUIDANCE ON CERTIFICATION SECTION 6.0 GOC© AMERICAS EDITION REVISION: 1 MECHANICAL - HVAC PAGE: 16 Procedure No. 6.4 4.1 Heating and Cooling Coils 4.1.1 General This Procedure lays down the checks/tests that are required to ensure that the Heating and Cooling Coils are per project specifications and correctly installed. The following points are to be checked as appropriate to the subject item of equipment: a) Carry out the relevant checks listed in Procedure 6.1 - General Requirements. b) Check visually that the Heating and Cooling Coils are adequately supported and that correct specification gaskets have been fitted to connection ductwork. Ensure that components are bolted/fixed correctly and that any dissimilar metal isolation is achieved. c) Check that heating elements are clean, undamaged and readily accessible, and ensure that adequate space has been provided for element withdrawal/maintenance. d) Check that the cooling coil has been correctly installed, is undamaged, and that it is level and complete with guide rails to slide the coil section out of its holding frame. Ensure that adequate space is provided for coil withdrawal. e) Ensure that the high air temperature and high element temperature cutout thermostats are of the correct type and are accessible for resetting/maintenance where applicable. f) Check that all electrical connections to the heater have been terminated correctly and that all associated cables have been inspected and tested GOC© BP Exploration 1989 – 2001 All Rights Reserved SUBJECT: GUIDANCE ON CERTIFICATION SECTION 6.0 GOC© AMERICAS EDITION REVISION: 1 MECHANICAL - HVAC PAGE: 17 in accordance with the Electrical Procedures (Section 9.0). Ensure that the terminal box access cover is readily accessible. g) Check access cover installed in ductwork adjacent to heater. h) Check that distributors and all pipework has been correctly connected and that all interior connections are clean. i) Check that drain pan is correctly fitted, and if the coil is split vertically, ensure that both sections have pans fitted. j) Check that interconnecting pipework between upper and lower drain pans is installed and that a drain trap is correctly fitted with pipework routed to a suitable discharge. k) Check air venting facility if fitted. 4.1.2 Heating and Cooling Coil Tests a) Test recording sheet No. 4 (TR4) is provided for collation of Heating Coil test data, and No. 10 (TR10) for Cooling Coil test data, to enable subsequent signing of the applicable parts of the SP2 Test Certificate. 4.1.3 Certification a) Form HVAC; TR4 shall be completed by the BP HVAC Representative and/or Vendor as appropriate, to record that all necessary inspections and tests relevant to the subject equipment type have been carried out satisfactorily, to the requirements of HVAC Procedures 6.1 & 6.4. Any deviation to the Design/Operating Parameters and Vendor instructions shall be recorded on the Test Recording Sheet. GOC© BP Exploration 1989 – 2001 All Rights Reserved GUIDANCE ON CERTIFICATION SECTION 6.0 GOC© AMERICAS EDITION REVISION: 1 SUBJECT: MECHANICAL - HVAC PAGE: 18 Procedure No. 6.5 5.1 Centrifugal Fans and Drivers 5.1.1 General This procedure lays down the checks/tests that are required to ensure that the centrifugal fans and their drivers are per project specifications and have been correctly installed. a) Carry out the relevant checks listed in Procedure No. 6.1 - General Requirements. b) Check visually that the fan assembly is adequately supported and that the correct specification gaskets are fitted to the connecting ductwork. Ensure that all components are bolted/fixed securely and that any dissimilar metal isolation is achieved. c) Check that fan and motor are correctly mounted in the right angular position, and that the motor is level and aligned with the specified drive fitted. Ensure that the motor has been inspected in accordance with the Electrical Procedures (Section 9.0). d) Check that vibration isolators are installed and adjusted correctly for the specified deflection. Make sure shipping locks are removed. e) Check that inlet/outlet flexible connections are correctly fitted and do not take up offsets. f) Check that all internal shipping brackets/packings have been removed and that fan is internally and externally clean. g) Check that fan and motor bearings are lubricated and that the grease nipples are accessible. GOC© BP Exploration 1989 – 2001 All Rights Reserved SUBJECT: h) GUIDANCE ON CERTIFICATION SECTION 6.0 GOC© AMERICAS EDITION REVISION: 1 MECHANICAL - HVAC PAGE: 19 Remove fan belt drive guard and visually check fan shaft level and bearing alignment. Ensure that belts are correctly tensioned. i) Check free rotation of fan impeller, key secure and clearance satisfactory. j) Check that there is adequate space to withdraw impeller or motor assembly for maintenance. k) Check that fan belt guard is lined with nonferrous material. l) Check that fan guards are fitted securely. m) Check that the manually operated inlet guide vane control damper has been correctly fitted and that it has been inspected in accordance with Procedure 6.2. n) Check that the outlet non-return damper has been correctly fitted and that it has been inspected in accordance with Procedure 6.2. o) Check direction of rotation is correct. p) Verify AMCA B non-sparking construction, as applicable. Confirm absence of rubbing parts and/or possible contact between moving and stationary parts. 5.1.2 Centrifugal Fans and Drivers Test a) Test recording sheet No. 5 (TR5) is provided for collation of test data, to enable subsequent signing of the applicable part of the SP2 Test Certificate. GOC© BP Exploration 1989 – 2001 All Rights Reserved SUBJECT: GUIDANCE ON CERTIFICATION SECTION 6.0 GOC© AMERICAS EDITION REVISION: 1 MECHANICAL - HVAC PAGE: 20 5.1.3 Certification a) Form HVAC; TR5 shall be completed by the BP HVAC Representative and/or Vendor as appropriate, to record that all necessary inspections and tests relevant to the subject equipment type have been carried out satisfactorily, to the requirements of HVAC Procedures 6.1 & 6.5. Any deviation to the Design/Operating Parameters and Vendor instructions shall be recorded on the Test Recording Sheet. GOC© BP Exploration 1989 – 2001 All Rights Reserved GUIDANCE ON CERTIFICATION SECTION 6.0 GOC© AMERICAS EDITION REVISION: 1 SUBJECT: MECHANICAL - HVAC PAGE: 21 Procedure No. 6.6 6.1 Humidifiers 6.1.1 General This procedure lays down the checks/tests that are required to ensure that the humidifiers are per project specifications and correctly installed. The following points are to be checked on all humidifiers: a) Carry out the relevant checks listed in Procedure 6.1 - General Requirements. b) Check visually that mounting arrangements and supports to the humidifier and steam injection duct are adequate. c) Check that steam injection duct is installed to the manufacturers recommendations and that it drains back to the humidifier. d) Check that all ductwork is bolted correctly and that flanged connections have correct specification gaskets fitted. e) Check that balance pipe from humidifier to ductwork is installed and properly sealed. f) Check that utility pipework connections to humidifier are correctly installed and adequately supported. g) Check that the water inlet valve is fitted and operating correctly. h) Ensure that drain and overflow are fitted and piped to a suitable drain. i) Ensure that there is adequate space to maintain humidifier internals (i.e. water storage tank/steaming chamber etc.) GOC© BP Exploration 1989 – 2001 All Rights Reserved GUIDANCE ON CERTIFICATION SECTION 6.0 GOC© AMERICAS EDITION REVISION: 1 SUBJECT: j) MECHANICAL - HVAC PAGE: 22 Check that the heating elements are clean, undamaged and readily accessible. k) Check that the water and heater thermostats are fitted within the humidifiers integral electrical compartment and that a removable access cover is provided. l) Check that the water level in the storage tank is correct and that the level gauge reads correctly. m) Ensure that adjacent ductwork connections and traps are located correctly, are free of blockages and restrictions, and traps can be visually checked for water level. n) Check that the humidifiers are operable for the duct pressure (water lock). 6.1.2 Humidifier Test a) Test recording sheet No. 6 (TR6) is provided for collation of test data, to enable subsequent signing of the applicable part of the SP2 Test Certificate. 6.1.3 Certification a) Form HVAC; TR6 shall be completed by the BP HVAC Representative and/or Vendor as appropriate, to record that all necessary inspections and tests relevant to the subject equipment type have been carried out satisfactorily, to the requirements of HVAC Procedures 6.1 & 6.6. Any deviation to the Design/Operating Parameters and Vendor instructions shall be recorded on the Test Recording Sheet. GOC© BP Exploration 1989 – 2001 All Rights Reserved SUBJECT: GUIDANCE ON CERTIFICATION SECTION 6.0 GOC© AMERICAS EDITION REVISION: 1 MECHANICAL - HVAC PAGE: 23 Procedure No. 6.7 7.1 Constant Volume/Terminal Re-Heat Units, Grills & Diffusers 7.1.1 General This Procedure lays down the checks/tests that are required to ensure that the units are per project specifications and correctly installed. The following points are to be checked on all Terminal Units, Grilles and Diffusers: a) Carry out the relevant checks listed in Procedure No. 6.1 - General Requirements. b) Check visually that the Terminal Re-Heat Unit is properly aligned, adequately supported, and that the correct specification gaskets have been fitted to the connecting ductwork, ensuring that components are bolted/fixed correctly and that any dissimilar metal isolation is achieved. c) Check the free movement of valve linkage mechanism and ensure it is pre-set for the correct pressure drop rating. d) Check that there is adequate space to maintain the constant volume control valve via the access cover to damper section. e) Check that internal acoustic lining has been installed to prevent noise breakout. f) Check that heating elements are undamaged, readily accessible, and ensure that adequate space has been provided for element withdrawal/maintenance. g) Ensure that the high air temperature and high element temperature cutout thermostats are accessible for resetting/maintenance. GOC© BP Exploration 1989 – 2001 All Rights Reserved SUBJECT: GUIDANCE ON CERTIFICATION SECTION 6.0 GOC© AMERICAS EDITION REVISION: 1 MECHANICAL - HVAC PAGE: 24 h) Check that the unit is internally clean and free from moisture. 7.1.2 Constant Volume/Terminal Re-Heat Units Test a) Test recording sheet No. 7 (TR7) is provided for collation of test data, to enable subsequent signing of the applicable part of the SP2 Test Certificate. 7.1.3 Grilles and Diffusers Test a) Test recording sheet No. 12 (TR12) is provided for collation of test data, to enable subsequent signing of the applicable part of the SP2 Test Certificate. 7.1.4 Certification a) Form HVAC; TR7 and TR12 for Constant Volume/Terminal Re-Heat Units and Grilles and Diffusers shall be completed by the BP HVAC Representative and/or Vendor as appropriate, to record that all necessary inspections and tests relevant to the subject equipment type have been carried out satisfactorily, to the requirements of HVAC Procedures 6.1 & 6.7. Any deviation to the Design/Operating Parameters and Vendor instructions shall be recorded on the Test Recording Sheet. GOC© BP Exploration 1989 – 2001 All Rights Reserved SUBJECT: GUIDANCE ON CERTIFICATION SECTION 6.0 GOC© AMERICAS EDITION REVISION: 1 MECHANICAL - HVAC PAGE: 25 Procedure No. 6.8 8.1 Air Conditioning Units 8.1.1 General This procedure lays down the checks/tests that are required to ensure that Air Conditioning Units are per project specifications and correctly installed. The following points are to be checked on all Air Conditioning Units: a) Carry out the relevant checks listed in Procedure No. 6.1 - General Requirements. b) Check visually that the unit is adequately supported and that the correct specification gaskets are fitted to the connecting ductwork. Ensure that the equipment is bolted correctly and that any dissimilar metal isolation is achieved. c) Check that the fans and compressors are installed correctly with reference to Procedure 6.5 - Centrifugal Fans and Drivers (in the case of compressors - for fan read compressor). d) Check that the filters are installed correctly with reference to Procedure 6.3 - Filtration. e) Check that all pipework connections are correct and adequately supported. f) Check that the drain pan and drain pipes are installed correctly and that the drains are routed to a suitable location. g) Ensure that all inspection doors, hatches and locks are operable. h) Ensure that all valves are operable. GOC© BP Exploration 1989 – 2001 All Rights Reserved SUBJECT: i) GUIDANCE ON CERTIFICATION SECTION 6.0 GOC© AMERICAS EDITION REVISION: 1 MECHANICAL - HVAC PAGE: 26 Check that all insulation is to specification and correctly fitted and free of damage. j) Check that refrigeration charge is within specifications. 8.1.2 Terminal Air Conditioning Unit Test a) Test recording sheet No. 8 (TR8) is provided for collation of test data, to enable subsequent signing of the applicable part of the SP2 Test Certificate. 8.1.3 Certification a) Form HVAC; TR8 shall be completed by the BP HVAC Representative and/or Vendor as appropriate, to record that all necessary inspections and tests relevant to the subject equipment type have been carried out satisfactorily, to the requirements of HVAC Procedures 6.1, 6.3 & 6.5. Any deviation to the Design/Operating Parameters and Vendor instructions shall be recorded on the Test Recording Sheet. GOC© BP Exploration 1989 – 2001 All Rights Reserved SUBJECT: GUIDANCE ON CERTIFICATION SECTION 6.0 GOC© AMERICAS EDITION REVISION: 1 MECHANICAL - HVAC PAGE: 27 Procedure No. 6.9 9.1 Air Handling Unit 9.1.1 General This procedure lays down the checks/tests that are required to ensure that Air Handling Units are per project specifications and correctly installed. The following points are to be checked on all Air Handling Units: a) Carry out the relevant checks listed in Procedure No. 6.1 - General Requirements. b) Check that the Air Handling Units skid base holding down arrangement is correct. c) Check visually that all components are properly fitted together and that any dissimilar metal isolation is achieved. d) Check that all equipment installed within the Air Handling Unit is checked against the following procedures: i) ii) Fans Shut-off Dampers HVAC Procedure No. 6.5 HVAC Procedure No. 6.2 iii) iv) Heating and Cooling Coils Filters HVAC Procedure No. 6.4 HVAC Procedure No. 6.3 e) Check that all Ductwork connections to unit have the correct specification gasket fitted. f) Check that the Air Handling Unit equipment compartment sections are fitted with light fixtures as indicated in the project specification, and GOC© BP Exploration 1989 – 2001 All Rights Reserved SUBJECT: GUIDANCE ON CERTIFICATION SECTION 6.0 GOC© AMERICAS EDITION REVISION: 1 MECHANICAL - HVAC PAGE: 28 ensure the cabling and fittings are tested and inspected in accordance with the Electric Procedures. g) Check that inspection/access doors have been provided for the individual equipment compartments and that all handles, catches and locks are operable. 9.1.2 Air Handling Unit Test a) Test recording sheet No. 9 (TR9) is provided for collation of test data, to enable subsequent signing of the applicable part of the SP2 Test Certificate. 9.1.3 Certification a) Form HVAC; TR9 shall be completed by the BP HVAC Representative and/or Vendor as appropriate, to record that all necessary inspections and tests relevant to the subject equipment type have been carried out satisfactorily, to the requirements of HVAC Procedures 6.1, 6.2, 6.3, 6.4, 6.5 & 6.9. Any deviation to the Design/Operating Parameters and Vendor instructions shall be recorded on the Test Recording Sheet. GOC© BP Exploration 1989 – 2001 All Rights Reserved GUIDANCE ON CERTIFICATION SECTION 6.0 GOC© AMERICAS EDITION REVISION: 1 SUBJECT: MECHANICAL - HVAC PAGE: 29 Procedure No. 6.10 10.1 Ductwork 10.1.1 General This procedure lays down the checks and tests that are required to ensure that the system ductwork is per project specifications and correctly installed. The following points are to be checked on all system ductwork: a) Carry out the relevant checks listed in Procedure 6.1 - General Requirements. b) Ensure that ductwork systems are clearly identified and marked with directional flow arrows. c) Check flexible connections have been fitted and sealed correctly. Ensure that no flexible connection has been used to take up misalignment between sections of ductwork or connections to plant equipment. d) Check that the correct jointing and sealants have been used as specified in the project specification. e) Check that all flanged ductwork joints are bolted correctly and correct specification gaskets fitted. f) Check that location of ductwork doors/panels/hatches are correct and that they are properly fastened and sealed. g) Check that all stiffening and turning vanes have been correctly installed. h) Check that instrument test holes have been drilled and suitably plugged. GOC© BP Exploration 1989 – 2001 All Rights Reserved GUIDANCE ON CERTIFICATION SECTION 6.0 GOC© AMERICAS EDITION REVISION: 1 SUBJECT: i) MECHANICAL - HVAC PAGE: 30 Check that ductwork is supported correctly and that all ductwork is insulated from supports. Ensure insulator blocks are fitted to all supply ductwork. j) Ensure any dissimilar metal isolation is achieved. k) Check that all diffusers and grilles are installed and sealed correctly, and that diffusers/grilles and their associated volume control dampers are left in the open position. l) Check that all intake and discharge louvers have been installed correctly and that any necessary bird mesh protection screens have been fitted. m) Check that ductwork systems are internally clean and that no internal damage exists. n) Check that the air filter racks are fitted. o) Check that the fire dampers are installed in their correct location and that the correct fusible links have been fitted. p) Check that the filter/coalescer is loaded, separators clean, drains piped and traps functioning. q) Check that all sound attenuators are correctly installed. r) Ensure that the material, protective coatings/finish of ducting is in accordance with project specifications and in an undamaged condition. s) Ductwork systems shall be leak tested in accordance with the HVAC test classes as laid down in the project specifications and HVAC Procedure 6.13. GOC© BP Exploration 1989 – 2001 All Rights Reserved SUBJECT: t) GUIDANCE ON CERTIFICATION SECTION 6.0 GOC© AMERICAS EDITION REVISION: 1 MECHANICAL - HVAC PAGE: 31 Ductwork shall be insulated in accordance with project specifications. External insulation should be applied only after ensuring that a duct leakage rate test certificate has been accepted and signed. 10.1.2 Certification a) Form SP2 shall be completed by the BP HVAC Representative and/or Vendor as appropriate, to record that all necessary inspections and tests relevant to system Ductwork have been carried out satisfactorily, to the requirements of HVAC Procedures 6.1, 6.10 & 6.11, and within the Design/Operating Parameters and Vendor instructions. GOC© BP Exploration 1989 – 2001 All Rights Reserved GUIDANCE ON CERTIFICATION SECTION 6.0 GOC© AMERICAS EDITION REVISION: 1 SUBJECT: MECHANICAL - HVAC PAGE: 32 Procedure No. 6.11 11.1 Sound Attenuators 11.1.1 General This procedure lays down the checks that are required to ensure that the Sound Attenuators are per project specifications and correctly installed. The following points are to be checked on all Sound Attenuators: a) Carry out the relevant checks listed in Procedure 6.1 - General Requirements. b) Check location and orientation of the Sound Attenuator is correct, and ensure that the unit is installed for the correct air flow direction. c) Check that the Sound Attenuator is adequately supported, that the correct specification gaskets are fitted to the connecting ductwork, ensuring that the unit is bolted correctly and that any dissimilar metal isolation is achieved. d) Check that the Sound Attenuator is internally clean. Ensure that no damage exists to the acoustic lining or splitters, and that no moisture has entered the unit. e) Check that the fire/thermal insulation has been correctly fitted after ensuring that the Sound Attenuator material and finish are to specification, and that no damage has occurred during installation. f) Verify that installation configuration complies with manufacturer’s instructions and airflow direction. GOC© BP Exploration 1989 – 2001 All Rights Reserved SUBJECT: GUIDANCE ON CERTIFICATION SECTION 6.0 GOC© AMERICAS EDITION REVISION: 1 MECHANICAL - HVAC PAGE: 33 11.1.2 Certification a) Form SP2 shall be completed by the BP HVAC Representative and/or Vendor as appropriate, to record that all necessary inspections and tests relevant to the Sound Attenuators have been carried out satisfactorily, to the requirements of HVAC Procedures 6.1 & 6.11, and within the Design/Operating Parameters and Vendor information. GOC© BP Exploration 1989 – 2001 All Rights Reserved GUIDANCE ON CERTIFICATION SECTION 6.0 GOC© AMERICAS EDITION REVISION: 1 SUBJECT: MECHANICAL - HVAC PAGE: 34 Procedure No. 6.12 12.1 Cooling Tower 12.1.1 General This Procedure lays down the checks/tests that are required to ensure that the Cooling Towers are per project specifications and are correctly installed. The following points are to be checked on all Cooling Towers: a) Carry out the relevant checks listed in Procedure 6.1 - General Requirements. b) Fan Section: Refer to HVAC Procedure No. 6.5 - Centrifugal Fans and Drivers. c) Coil Section: Check that the spray nozzles are clean and that the eliminators are undamaged. d) Pan Section: undamaged. e) Check that spray pump is aligned and rotation is correct. f) Check that water level is correct. g) Check that the bleed line is operational. h) Check that strainer is clean. i) Check that corrosion inhibitor is installed. j) Check that the water make-up valve is open and float operational. GOC© Check that the immersion heater is installed and BP Exploration 1989 – 2001 All Rights Reserved SUBJECT: GUIDANCE ON CERTIFICATION SECTION 6.0 GOC© AMERICAS EDITION REVISION: 1 MECHANICAL - HVAC PAGE: 35 12.1.2 Cooling Tower Test a) Test recording sheet No. 11 (TR11) is provided for collation of test data, to enable subsequent signing of the applicable part of the SP2 Test Certificate. 12.1.3 Certification a) Form SP2 shall be completed by the BP HVAC Representative and/or Vendor as appropriate, to record that all necessary inspections and tests relevant to the Cooling Towers have been carried out satisfactorily, to the requirements of HVAC Procedures 6.1, 6.5 & 6.12, and within the Design/Operating Parameters and Vendor information. 12.1.4 Pipework a) Ensure that all associated pipework has been fabricated, inspected and tested in accordance with the project specification. Refer to the Pipe Testing Section 3.0. GOC© BP Exploration 1989 – 2001 All Rights Reserved GUIDANCE ON CERTIFICATION SECTION 6.0 GOC© AMERICAS EDITION REVISION: 1 SUBJECT: MECHANICAL - HVAC PAGE: 36 Procedure No. 6.13 13.1 Areas Receiving HVAC Supply 13.1.1 General The following HVAC tests will be required to be carried out by an HVAC Vendor/Engineer and the results recorded, to ensure that all necessary inspections and tests have been carried out. Any deviation to the Design/Operating Parameters and Vendor instructions shall be recorded on the appropriate Test Record Sheet. 13.1.2 Ductwork Leakage Rate Test Test recording sheet No. 13 (TR13) is provided for collation of test data, to enable subsequent signing of the applicable part of the SP2 Test Certificate. 13.1.3 System Balance Test Test recording sheet No. 14 (TR14) is provided for collation of test data, to enable subsequent signing of the applicable part of the SP2 Test Certificate. 13.1.4 Grille and Diffuser Test Test recording sheet No. 12 (TR12) is provided for collation of test data, to enable subsequent signing of the applicable part of the SP2 Test Certificate. 13.1.5 Internal Conditions Test Test recording sheet No. 15 (TR15) is provided for collation of test data, to enable subsequent signing of the applicable part of the SP2 Test Certificate. GOC© BP Exploration 1989 – 2001 All Rights Reserved GUIDANCE ON CERTIFICATION SECTION 6.0 GOC© AMERICAS EDITION REVISION: 1 SUBJECT: MECHANICAL - HVAC PAGE: 37 13.1.6 Smoke Test of Pressurized Room & Areas Protected by a Gaseous Inerting Agent Test recording sheet No. 16 (TR16) is provided for collation of test data, to enable subsequent signing of the applicable part of the SP2 Test Certificate. 13.1.7 Room Pressurization Tests (Parts 1 & 2) Test recording sheet No. 17 (TR17) is provided for collation of test data, to enable subsequent signing of the applicable part of the SP2 Test Certificate. 13.1.8 Room Pressurization Unit Test Test recording sheet No. 18 (TR18) is provided for collation of test data, to enable subsequent signing of the applicable part of the SP2 Test Certificate. GOC© BP Exploration 1989 – 2001 All Rights Reserved GUIDANCE ON CERTIFICATION SECTION 6.0 GOC© AMERICAS EDITION REVISION: 1 SUBJECT: MECHANICAL - HVAC PAGE: 38 Flowchart 6 • • Functional Certification Flowchart Discipline: Mechanical (HVAC) MM1 MM1: MC1: SP2: SH1: MC1 SP2 SH1 Machinery Installation Certificate Mechanical Completion Certificate System Performance Test(s) System Handover Certificate Note! Where Welding is carried out an MW1 - Welding Completion Summary is required - Refer to GOC© Section 2 GOC© BP Exploration 1989 – 2001 All Rights Reserved SUBJECT: GUIDANCE ON CERTIFICATION SECTION 6.0 GOC© AMERICAS EDITION REVISION: 1 MECHANICAL - HVAC PAGE: 39 EXHIBIT 6 STANDARD FORMS Form No. Form & Test Record Title SP2 System Performance Test TR1 Control Installation & Function Test Certificate TR2 - 18 HVAC Installation & Test Record (General HVAC Certificate to cover activities TR2 - TR18) DIS4 Data Input Sheet 4 – Section 6 HVAC GOC© BP Exploration 1989 – 2001 All Rights Reserved Project Title: Maintenance No: Work Pack No: SH1 No: MC1 No: FORM SP2 SITE: HVAC - SYSTEM PERFORMANCE CERTIFICATE EQUIPMENT No : SHT OF EQUIPMENT DESCRIPTION : LOCATION : SYSTEM : TEST RECORDING SHEET No TESTS APPLICABLE INSTRUMENTATION TR1 YES/NO * YES/NO * 6.1 & 6.2 DAMPERS TR2 YES/NO * YES/NO * 6.1 & 6.3 FILTRATION TR3 YES/NO * YES/NO * 6.1 & 6.4 HEATING & COOLING COILS TR4 YES/NO * YES/NO * 6.1 & 6.5 CENTRIFUGAL FANS TR5 YES/NO * YES/NO * 6.1 & 6.6 HUMIDIFIERS TR6 YES/NO * YES/NO * 6.1 & 6.7 TERMINAL RE-HEAT UNITS TR7 YES/NO * YES/NO * 6.1,6.3, 6.5 & 6.8 AIR CONDITIONING UNITS TR8 YES/NO * YES/NO * 1, 2, 3, 4, 5 & 9 AIR HANDLING UNITS TR9 YES/NO * YES/NO * 6.1,6.10 & 6.11 DUCTWORK & ATTENUATORS YES/NO * YES/NO * PROCEDURE Nos. SECTION 8.0 6.1 & 6.4 DESCRIPTION CONFORMITY ACCEPTANCE CHECK REVIEWED DATE COOLING COILS TR10 YES/NO * YES/NO * 6.1 -6.5 & 6.12 COOLING TOWERS TR11 YES/NO * YES/NO * 6.1 -6. 7 & 6.13 GRILLES & DIFFUSERS TR12 YES/NO * YES/NO * 6.13 AIR LEAKAGE RATE TR13 YES/NO * YES/NO * 6.13 SYSTEM BALANCE TR14 YES/NO * YES/NO * 6.13 INTERNAL CONDITIONS TR15 YES/NO * YES/NO * 6.13 SMOKE TEST TR16 YES/NO * YES/NO * 6.13 ROOM PRESSURIZATION TR17 YES/NO * YES/NO * 6.13 PRESSURIZATION UNIT TR18 YES/NO * YES/NO * THIS CERTIFICATE SHALL BE COMPLETED BY THE BP HVAC COMMISSIONING REPRESENTATIVE AND/OR VENDOR AS APPROPRIATE, TO RECORD THAT ALL NECESSARY INSPECTIONS AND TESTS HAVE BEEN CARRIED OUT SATISFACTORILY, TO THE REQUIREMENTS OF THE HVAC PROCEDURES AND WITHIN DESIGN/OPERATING PARAMETERS AND VENDOR INSTRUCTIONS. ANY VARIANCE SHALL BE DETAILED ON THE APPROPRIATE TEST RECORD SHEET AND ATTACHED TO THIS CERTIFICATE. COMPLETED BY APPROVED BY COMPANY SIGNATURE PRINT NAME DATE * DELETE AS APPLICABLE GOC© BP Exploration 1989 – 2001 All Rights Reserved Americas REV. 1 Project Title: Work Pack No: FORM TR1 Maintenance No: (SIDE 1) FUNCTION TEST REQUIRED? *YES / NO SH1 No: SITE: (IF YES, COMPLETE SIDE 2) MC1 No: HVAC SYSTEM - CONTROL COMPLETION CERTIFICATE & FUNCTION TEST CERTIFICATE SHT P&ID No: OF YES NO Loop Diagram Drawing No: Equipment Installed as per Design (If No, Raise an EQ) Area Classification Check - Electrical Procedure 9.15 Complete YES NO N/A Process Hook-Up Drawing No: Junction Box Inspection YES NO N/A Pneumatic Hook-Up Drawing No: Orifice Plate Measurement Completed (where appropriate) YES NO N/A Instrument Tie-in Point Number: Orifice Plate Measurement : Diameter NDE Location Drawing No: YES NO Impulse Line Welding *YES/NO if YES - is MW1 Complete? *YES/NO - Electrical Procedure 9.19 Complete ins / Check Flatness Record All Deviations/Comments: Loop Number Tag Number Procedure No. 8.1 Completed By Procedure No. 8.1 8.2 Manufacturer Model & Serial No Data Sheet No Calibrated Range/Setting Procedure No. 8.3 Asset Specific Procedure Approved By 8.3 Procedure No. 8.2 Company Signature Print Name Date • DELETE AS APPLICABLE GOC© BP Exploration 1989 – 2001 All Rights Reserved DOUBLE SIDED FORM Americas REV. 1 HVAC - SYSTEM CONTROL FUNCTION TEST RECORD EQUIPMENT No : FORM TR1 (SIDE 2) EQUIPMENT DESCRIPTION : LOCATION : SYSTEM : COMMISSIONING PROCEDURE NO : COMPLETED BY APPROVED BY COMPANY SIGNATURE PRINT NAME DATE GOC © BP Exploration 1989 – 2001 All Rights Reserved DOUBLE SIDED FORM Americas REV. 1 Project Title: Maintenance No: Work Pack No: SH1 No: MC1 No: FORM TR 2 - 18 SITE: HVAC - INSTALLATION & TEST RECORD EQUIP / TAG No : SHT OF LOCATION: CIRCLE BELOW THE TEST RECORDS (TRs) THIS REPORT COVERS TR2 TR3 TR4 TR5 TR6 TR7 TR8 TR9 TR10 TR11 TR12 TR13 TR14 TR15 TR16 TR17 TR18 DESCRIPTION : REPORT AND TEST RESULT: COMPLETED BY APPROVED BY COMPANY SIGNATURE PRINT NAME DATE GOC© BP Exploration 1989 – 2001 All Rights Reserved Americas REV. 1 DIS4 SHEET J.P NO. LOCATION : __________________ DATA INPUT SHEET 4 PROJECT : __________________ SECTION 6 - HVAC HANDOVER ID DESCRIPTION EQUIP NUMBER TAG NUMBER DRAWING NUMBER RAISED BY: __________________________________ DATE : ____________________ NOTE: JP No FOR INSTALLATION / TESTING GOC OF WORKSCOPE ID : ___________________ MAINTENANCE ID No : ______________ ASBUILT REQ'D (LAD) SPECIFY SP2 TEST RECORD SPECIFY SP2 TEST RECORD SPECIFY SP2 TEST RECORD SPECIFY SP2 TEST RECORD SPECIFY SP2 TEST RECORD DATA ENTERED BY : ____________________ © BP Exploration 1989 - 2001 All Rights Reserved SPECIFY SP2 TEST RECORD SPECIFY SP2 TEST RECORD DATE : ___________ Americas Rev. 1 GUIDANCE ON CERTIFICATION GOC© AMERICAS EDITION SUBJECT: MECHANICAL - ARCHITECTURAL SERVICES (PAINTING, COATING AND INSULATION) SECTION 7.0 ARCHITECTURAL SERVICES (PAINTING, COATING AND INSULATION) GOC © BP Exploration 1989 – 2001 All Rights Reserved SECTION 7.0 REVISION: 1 PAGE: 1 GUIDANCE ON CERTIFICATION GOC© AMERICAS EDITION SUBJECT: MECHANICAL - ARCHITECTURAL SERVICES (PAINTING, COATING AND INSULATION) SECTION 7.0 REVISION: 1 PAGE: 2 7.1 ACTIONS 7.1.1 General a) This section summarizes the recording procedure for certification relating to the surface preparation, internal and external paint coatings, linings, spray applied fire-proofing applications and all types of insulation. The construction or maintenance authority is responsible for issue of the work scope to the painting/insulation and protective coating contractor(s) who shall be responsible for management and inspection requirements. The contractor shall maintain reports which describe the preparation and environmental conditions during construction activities. b) Architectural Services (surface preparation, internal and external paint coatings, linings, spray applied fire-proofing applications and all types of insulation) shall be checked for compliance and other requirements as detailed in, but not limited to: • • • • • • • The latest revision of Issued For Construction (IFC) or Approved For Construction (AFC) Drawings and Schedules Codes and standards reference in this section Plant and Project Specifications Equipment Specifications and Data sheets BP Engineering Installation and Design Specifications Local, state, country and international standards, codes, and regulations as appropriate Offshore - Special Standards, i.e. USCG, ABS and MMS 7.1.2 Use Of Forms a) All reporting and recording of results of inspection shall be on the GOC© standard forms - see Exhibit 7 on the last page of this section. b) AS1: Final Paint Acceptance Certificate. Used to record acceptance on completion of painting. GOC © BP Exploration 1989 – 2001 All Rights Reserved GUIDANCE ON CERTIFICATION GOC© AMERICAS EDITION SUBJECT: c) MECHANICAL - ARCHITECTURAL SERVICES (PAINTING, COATING AND INSULATION) SECTION 7.0 REVISION: 1 PAGE: 3 AS2: This is a two-part certificate. Final Insulation/Coating Acceptance Certificate Covering Architectural and Structural Acceptance, (Paint, Linings and Fire Proofing) and is used for recording acceptance of fire proofing and related activities. The State Fire Marshall or authorized representative of the country or state whose jurisdiction the installation is subject, may be required to endorse this document for Passive Fire Protection. Piping/Equipment Insulation Acceptance Certificate Used to record insulation acceptance on completion of insulation applied to piping systems, mechanical equipment and vessels. Prior to acceptance of insulation, it shall be confirmed that all corrosion monitoring pockets have been identified and correctly installed. Note: Prior to acceptance of insulation, it shall be confirmed that all corrosion monitoring pockets have been identified and correctly installed. GOC © BP Exploration 1989 – 2001 All Rights Reserved SECTION 7.0 GUIDANCE ON CERTIFICATION GOC© AMERICAS EDITION SUBJECT: REVISION: 1 MECHANICAL - ARCHITECTURAL SERVICES (PAINTING, COATING AND INSULATION) PAGE: 4 Flowchart 7 • • • Functional Certification Flowchart Discipline: Mechanical (Architectural Services) (Painting, Coatings and Insulation) AS1 MC1 SH1 AS2 AS1: AS2: MC1: SH1: Final Paint Certficiate Final Coating / Insulation Certificate Mechanical Completion Certificate System Handover Certificate Architectural Services covers the following Sections: Section 3 Section 4 Section 5 Section 6 Pipe Testing Vessels and Tanks Machinery Mechanical Handling Structural HVAC GOC © BP Exploration 1989 – 2001 All Rights Reserved GUIDANCE ON CERTIFICATION GOC© AMERICAS EDITION SUBJECT: MECHANICAL - ARCHITECTURAL SERVICES (PAINTING, COATING AND INSULATION) SECTION 7.0 REVISION: 1 PAGE: 5 EXHIBIT 7 STANDARD FORMS Form No. Form Title AS1 Final Paint Acceptance Certificate AS2 Covering Architectural and Structural Acceptance Certificate, (Paint, Linings and Fire Proofing) and Piping/Equipment Insulation Acceptance Certificate. Note: Final acceptance of each report as complete and correct shall be authorized by the painting/insulation foreman or dedicated painting inspector. The AS2 may require to be endorsed by the State Fire Marshall or authorized representative of the country or state whose jurisdiction the installation is subject. GOC © BP Exploration 1989 – 2001 All Rights Reserved Project Title: Maintenance No: Work Pack No: SH1 No: MC1 No: FORM AS1 SITE: FINAL PAINT ACCEPTANCE CERTIFICATE CONTRACTOR: SHT OF CONTRACT NO: SCOPE OF CERTIFICATE REMARKS THIS IS TO CERTIFY THAT ALL PAINTING AS DEFINED ABOVE HAS BEEN COMPLETED IN ACCORDANCE WITH PAINT SPECIFICATION. INSPECTED BY APPROVED BY COMPANY SIGNATURE PRINT NAME DATE GOC© BP Exploration 1989 – 2001 All Rights Reserved Americas REV. 1 Project Title: Maintenance No: Work Pack No: SH1 No: MC1 No: FORM AS2 (SIDE 1) SITE: ARCHITECURAL INSULATION / COATINGS ACCEPTANCE CERTIFICATE AREA: SYSTEM: GRID REF: LOCATION: ELEVATION: P & I.D. NO: DRAWING NO: TEST PACK NO: SHT OF P & ID NO: PIPING/EQUIPMENT SPECIFICATION NO: LINE NUMBER OR EQUIPMENT NO. & DESCRIPTION FINAL PAINT ACCEPTED *YES/NO INSULATION TYPE (FIREPROOFING THERMAL, ACOUSTIC) INSULATION THICKNESS (Inches) INSULATION INSTALLED IN ACCORDANCE WITH SPECIFICATION YES NO FOR ITEMS MARKED 'NO' RAISE PUNCH LIST INSPECTED BY APPROVED BY COMPANY SIGNATURE PRINT NAME DATE * DELETE AS APPLICABLE GOC© BP Exploration 1989 – 2001 All Rights Reserved DOUBLE SIDED FORM Americas REV. 1 ARCHITECTURAL INSULATION / COATINGS ACCEPTANCE CERTIFICATE NORTH PROJECT TITLE: MAINTENANCE ID No: WORKPACK No: SH1 No: MC1 No: FORM AS2 (SIDE 2) SHT OF STRUCTURAL AND ARCHITECTURAL PRIMARY AND SECONDARY STEELWORK MODULE WALLS SOUTH EAST WEST ROOF DECK COATING DESCRIPTION SPECIFICATION LINING DESCRIPTION SPECIFICATION FIRE PROOFING DESCRIPTION SPECFICATION SURFACE PREPARATION & FINAL THICKNESS AVERAGE dft COMMENTS INSPECTED BY APPROVED BY AREA LOCATION GRID REF. ELEVATION COMPANY SIGNATURE PRINT NAME DATE GOC© BP Exploration 1989 – 2001 All Rights Reserved DOUBLE SIDED FORM Americas REV. 1 GUIDANCE ON CERTIFICATION SECTION 8.0 GOC© AMERICAS EDITION REVISION: 1 SUBJECT: CONTROL, INCLUDING INSTRUMENTATION FIRE AND GAS AND TELECOMMUNICATIONS SECTION 8.0 CONTROL GOC© BP Exploration 1989 – 2001 All Rights Reserved PAGE: 1 GUIDANCE ON CERTIFICATION SECTION 8.0 GOC© AMERICAS EDITION REVISION: 1 SUBJECT: CONTROL, INCLUDING INSTRUMENTATION FIRE AND GAS AND TELECOMMUNICATIONS PAGE: 2 8.1 ACTIONS 8.1.1 General a) This document details the certification requirements for the installation and testing of standard process control equipment as used in the petrochemical industry, including Fire & Gas detection/ protection and Telecommunications. Any special tests required to show conformance to specifications for specialized systems shall be agreed between the Supplier and BP or their Delegated Authority. The procedural requirements detailed herein are the recommended minimum requirements for the inspection and testing for Control including that used for Instrumentation, Fire and Gas detection/ protection and Telecommunications and must be carried out with due regard to the relevant manufacturers instructions. Full reference shall be made to Section 9.0 Electrical with respect to Equipment Classification (Electrical Procedure 9.15), Electrical Inspection (Electrical Procedure 9.19) and where the voltage demarcation between Control/Electrical is reached. For active fire protection, reference shall be made to Section 3 "Pipe Testing", refer to Procedure 3.1.7 Piping Completion (Fire & Gas). For passive fire protection, reference shall be made to Section 7 "Painting, Coating and Insulation", form AS2, "Architectural and Structural Acceptance Certificate, Paint, Lining, and Fire Proofing." b) Installation Process control equipment including Fire & Gas detection / protection and Telecommunications shall be checked for compliance and other requirements as detailed in but not limited to: GOC © BP Exploration 1989 – 2001 All Rights Reserved GUIDANCE ON CERTIFICATION SECTION 8.0 GOC© AMERICAS EDITION REVISION: 1 SUBJECT: CONTROL, INCLUDING INSTRUMENTATION FIRE AND GAS AND TELECOMMUNICATIONS • • • • • • • c) PAGE: 3 The latest revision of Issued For Construction (IFC) or Approved For Construction (AFC) Drawings and Schedules Codes and standards reference in this section Plant and Project Specifications Equipment Specifications and Data sheets BP Engineering Installation and Design Specifications Local, state, country and international standards, codes, and regulations as appropriate Offshore - Special Standards, i.e. USCG, ABS and MMS Inspection Package units and loose equipment received are to be visually inspected for damage and shortages. Any equipment/device not accompanied by the appropriate certification, or referenced as being reviewed and accepted on the appropriate Inspection and Test Summary (ITS), shall be quarantined until such time as the certification is available. d) Damage Any shipping damage shall be recorded and the condition of packaging noted by the Materials/Stores Department. Equipment, which is damaged or suspected to be faulty as a result of damage to either equipment or packaging, shall be quarantined pending assessment by the appropriate authority. The Engineering Authority shall determine whether the equipment may be: i) ii) iii) released without further action; returned to the vendor for repair; repaired, if possible without invalidating the vendor's warranty; The Engineering Authority will advise the materials department accordingly. GOC © BP Exploration 1989 – 2001 All Rights Reserved GUIDANCE ON CERTIFICATION SECTION 8.0 GOC© AMERICAS EDITION REVISION: 1 SUBJECT: CONTROL, INCLUDING INSTRUMENTATION FIRE AND GAS AND TELECOMMUNICATIONS e) PAGE: 4 Storage Devices and materials, as received, shall be stored as recommended by the supplier and protected against adverse weather conditions. Where special storage requirements are stipulated, they shall be stored under cover or in air-conditioned stores etc., with shipping stops and protective devices in place. Devices shall be examined, on receipt, to check that they are correctly tagged. To ensure early detection of damage, all equipment inherently suitable shall be calibrated in the workshop as soon as practicable after receipt into store and a calibration sticker showing calibrated range/setting; the date and responsible person attached to the equipment. The material control department shall be responsible for co-ordinating this activity. Refer to Project Procurement Plan for any deviations to above activities or for special storage requirements. 8.1.2 Use Of Forms a) General Requirements For on-site works, all reporting and recording of the results of inspections and tests shall be on the GOC© standard forms, listed in Exhibit 8 at the end of this section. b) Roles and Responsibilities Construction/Maintenance Authority The construction/maintenance authority will be responsible for the calibration and installation of all devices, their associated piping, pneumatic and electrical hook-up and all powered down loop checks relevant to the device, and completion of the relevant certificates. GOC © BP Exploration 1989 – 2001 All Rights Reserved GUIDANCE ON CERTIFICATION SECTION 8.0 GOC© AMERICAS EDITION REVISION: 1 SUBJECT: CONTROL, INCLUDING INSTRUMENTATION FIRE AND GAS AND TELECOMMUNICATIONS PAGE: 5 Commissioning Authority The commissioning authority will be responsible for powering up and completing the loop checking and all associated Function Testing. c) CC1 Control Acceptance Certificate The CC1 form is used to by the construction dept to confirm and record the following: That the Device(s) and the associated hook-up(s) have been supplied, calibrated, installed and tagged correctly as per relevant design drawings and specifications. Relevant Electrical certification has been completed. Pneumatic / Impulse lines have (where applicable) been blown through and pressure tested. Orifice plate inspection and dimensional checks carried out. d) SC1: System Control (Function Test) Certificate The SC1 form is used by Commissioning to record: i) ii) All powered loop tests and the associated function testing. Detail and record the test requirements for Programmable Logic Controller Panels as detailed on Procedure 8.7. Function testing will be carried out on all critical/complex loops (refer to Procedure 8.4). Items not requiring function testing which are solely covered by the CC1 form and Testing are typically: PI's, TI's and RO's i.e. completely local non-interactive items GOC © BP Exploration 1989 – 2001 All Rights Reserved GUIDANCE ON CERTIFICATION SECTION 8.0 GOC© AMERICAS EDITION REVISION: 1 SUBJECT: CONTROL, INCLUDING INSTRUMENTATION FIRE AND GAS AND TELECOMMUNICATIONS e) PAGE: 6 SP1: System Performance Certificate (HIPS) The SP1 form is used by Commissioning to record High Integrity Performance System (HIPS) Test(s). GOC © BP Exploration 1989 – 2001 All Rights Reserved GUIDANCE ON CERTIFICATION SECTION 8.0 GOC© AMERICAS EDITION REVISION: 1 SUBJECT: CONTROL, INCLUDING INSTRUMENTATION FIRE AND GAS AND TELECOMMUNICATIONS PAGE: 7 CONTROL PROCEDURES Procedure 8.1 Impulse Line Pressure Testing Procedure 8.2 Control Cable & Fiber Optic Cable Procedure 8.3 General/Calibration/Installation/Cold Loop Checking Procedure 8.4 Powered Up Loop and Function Testing Procedure 8.5 System Control (Function) Testing Procedure 8.6 System Performance "HIPS" Tests Procedure 8.7 Programmable Logic Controller Panels (PLCP) GOC © BP Exploration 1989 – 2001 All Rights Reserved Testing GUIDANCE ON CERTIFICATION SECTION 8.0 GOC© AMERICAS EDITION REVISION: 1 SUBJECT: CONTROL, INCLUDING INSTRUMENTATION FIRE AND GAS AND TELECOMMUNICATIONS PAGE: 8 PROCEDURE 8.1 1.1 Impulse Line Pressure Testing 1.1.1 General Ensure all air supply/transmission/process/hydraulic lines are correctly hooked up, as per relevant drawing. a) Instrument Air Distribution Systems Instrument air systems shall be checked for air leakage using dried, filtered, oil free air or N2 from a compressor or storage cylinder. Main air headers and branch lines to individual instrument isolating valves shall be tested to 110% of maximum working pressure. Devices should not be connected during this test. Service test the last joint after reconnection. Apply the required input pressure to the process connection, close the inlet and disconnect the pressure source. Observe the gauge on the inlet and ensure that there is no fall-off of pressure. Where leaks are evident these shall be eliminated and the test repeated. Tests shall have a duration of at least 10 minutes and a test gauge shall be observed to detect leakage. All joints shall be leak tested with a soap and water (bubble) solution, should the above test fail. Testing of pneumatic piping with liquids is not permitted. Instrument air tubing downstream of pressure regulators and instrument pneumatic signal lines shall be blown clear and leak tested using bubble solution. GOC © BP Exploration 1989 – 2001 All Rights Reserved GUIDANCE ON CERTIFICATION SECTION 8.0 GOC© AMERICAS EDITION REVISION: 1 SUBJECT: CONTROL, INCLUDING INSTRUMENTATION FIRE AND GAS AND TELECOMMUNICATIONS b) PAGE: 9 Instrument Piping/Tubing Systems Instrument piping/tubing systems may be categorised as either "Impulse Lines" or "Process Piping" as follows: "Impulse Line" (intermittent flow) means the whole of the instrument piping/tubing downstream of the process line isolating valve, but not instrument piping through which continuous process flow occurs, such as for on-stream analysers, which shall be treated as "Process Piping" (continuous flow) for the purposes of inspection and testing. Instrument piping classed as: i) "Process Piping" shall require full welding traceability, and form MW1 and associated NDT certificates completed where welding activities are performed (refer GOC© Manual Section 2.1); ii) "Impulse Piping" socket weld activities only require Magnetic Particle Inspection (MPI) or Dye Penetrant (DP) to be performed; all butt-welds require Ultrasonic Testing (UT) or radiographic testing and shall have full traceability as per process piping. conformation of completion of MW1 on the CC1; iii) Record Hydraulic Piping IP12 shall be cleaned in accordance with NAS 1638, “Cleanliness Requirements of Parts Used in Hydraulic Systems.” All instrument piping/tubing shall be flushed. Prior to flushing main process lines, all displacement meters, turbine meters, control valves soft-seated valves, orifice plates, etc., should be removed from the process lines and suitable spool pieces inserted. Instrument piping/tubing, during the testing of main process lines, should be positively isolated or removed from the device downstream of the first isolation valve. In the case of hydro testing against a positive isolation GOC © BP Exploration 1989 – 2001 All Rights Reserved GUIDANCE ON CERTIFICATION SECTION 8.0 GOC© AMERICAS EDITION REVISION: 1 PAGE: 10 SUBJECT: CONTROL, INCLUDING INSTRUMENTATION FIRE AND GAS AND TELECOMMUNICATIONS of an instrument, the instrument should be equalized and/or vented, or removed. All the instrument piping/tubing and manifold shall be tested separately from the process piping using a suitable test pump and calibrated test gauge. Testing of pneumatic piping with liquids is not permited. Instrument piping/tubing categorised as "Impulse Piping" shall be leak tested using a suitable test medium at 110% of the maximum working pressure, for a minimum period of 15 minutes, the limits of which will be indicated on the appropriate hook-up drawing. Where an “instrument manifold” valve is employed for primary isolation, the pressure test source shall be connected to the vent of the "instrument manifold" valve. The instrument piping shall be capped at the instrument end and vent valves shall be opened with the outlets blanked off. All pressure testing is the responsibility of the Construction/ Maintenance Authority, who shall sign as satisfactorily tested on the Final Control Completion Certificate CC1. For pressure testing of instrument piping and design requirements, refer to BP RP32-2 “Site Inspection, Testing & precommissioning of New Plant, BP RP42-1 “Piping Systems” and ANSI B31.3 “Process Piping” respectively. Where tubing and compression fittings are used (as opposed to Nominal Bore pipe), the Inspection and Test requirements in BP RP30-10, “Selection Suply & Installation of Compression Fittings”, shall be followed. GOC © BP Exploration 1989 – 2001 All Rights Reserved GUIDANCE ON CERTIFICATION SECTION 8.0 GOC© AMERICAS EDITION REVISION: 1 SUBJECT: CONTROL, INCLUDING INSTRUMENTATION FIRE AND GAS AND TELECOMMUNICATIONS PAGE: 11 The additional and specific requirements of testing instrument compression fittings on process pipe work are: i) 100 % inspection of fittings. ii) Training and Qualifications of installers. iii) iv) Maintain Training and Qualifications of qualified installers. Hydrostatic test pressure shall be 150% MAWP, which is the same v) as process pipe work, ANSI B31.3. Any equipment removed (breaking containment) and re-instated shall be subject to a formal Leak Test at 110% MAWP. GOC © BP Exploration 1989 – 2001 All Rights Reserved GUIDANCE ON CERTIFICATION SECTION 8.0 GOC© AMERICAS EDITION REVISION: 1 SUBJECT: CONTROL, INCLUDING INSTRUMENTATION FIRE AND GAS AND TELECOMMUNICATIONS PAGE: 12 PROCEDURE 8.2 2.1 Control Cable & Fiber Optic Cable Testing 2.2.1 General The following inspection and test procedures are applicable to all cable sizes and types. 2.2 Post - Installation Inspection a) Compare the cable size, type, routing and numbering with the cable schedule and relevant electrical drawings, paying particular attention to any special requirements, e.g. toxicity. Ensure that the core identification agrees with the connection diagrams. b) Ensure that the termination fitting certificates meet the area classification and specification requirements. c) Inspect the cable termination fitting for tightness and good workmanship. Ensure that the correct type of termination fitting has been used for the size and type of cable installed, and that, where specified, insulating termination fitting adapters have been installed. d) Ensure that the termination fitting plates for single-core cables have been manufactured from non-magnetic materials, where this is applicable. e) Where conductors have been terminated using crimped connections, ensure that the correct size and type of crimped connection has been used. f) Inspect the ground connections. GOC © BP Exploration 1989 – 2001 All Rights Reserved GUIDANCE ON CERTIFICATION SECTION 8.0 GOC© AMERICAS EDITION REVISION: 1 SUBJECT: CONTROL, INCLUDING INSTRUMENTATION FIRE AND GAS AND TELECOMMUNICATIONS g) PAGE: 13 For MI (mineral insulated) control cables, the additional inspection as listed below should be carried out: i) Check that the termination fittings is in accordance with the manufacturers' instructions and that grounding tails have been terminated at a suitable grounding terminal. ii) Check that surge suppression voltage dependent resistors, where specified, are correctly fitted and that the correct type has been fitted. iii) Where applicable, ensure the appropriate requirements of Electrical Procedures 9.15 and 9.19 are carried out. 2.3 Fiber Optic Cable Testing a) Check that the interconnection devices and passive components are installed as per the Manufacturer’s instructions and procedures. Fiber Optic Specialists will perform all the testing to the approved Vendor and/or Manufacturer’s specifications and procedures. b) Every strand of fiber shall be tested for attenuation, length and continuity. An Optical Time Division Reflectometer (ODTR) shall be performed to determine length and continuity. Hard copy plots of the tests results shall be printed and attached to Form EE16 Sheet 01. Attenuation tests shall be conducted by injecting a stabilized light source into one end of the fiber and measuring the optical loss with an optical power meter at the other end. Both sets of tests shall be performed at the 850 nanometer (nm) window in both directions. c) The fiber optic cable shall be pretested using optical power meters at 850 and 1300 nm to ensure that all fibers are acceptable and have not been damaged during shipping. A subsequent reading shall be taken with an OTDR, also at 850 and 1300 nm prior to installation of the cable. After installation is complete and connectors have been attached to GOC © BP Exploration 1989 – 2001 All Rights Reserved GUIDANCE ON CERTIFICATION SECTION 8.0 GOC© AMERICAS EDITION REVISION: 1 SUBJECT: CONTROL, INCLUDING INSTRUMENTATION FIRE AND GAS AND TELECOMMUNICATIONS PAGE: 14 each fiber, all links shall be tested and certified for attenuation utilizing the above two methods. d) The fiber optic cable testing shall verify that the minimum power budget requirements and maximum distance requirements for the installed fiber meet the manufacturer’s requirements and the listed standards requirements. e) Fiber Optic Specialists shall submit as part of the final documentation package test results taken before the installation (bare method) and after the installation (connectorized fiber cable). The date/time of the fiber optic installation/termination/testing, along with the testing equipment used (make, model, date of calibration) and the names of the person(s) doing the testing shall be included. f) Fiber Optic Specialists shall provide a sample results sheet for all tests. g) References: Electronic Industries Association (EIA)/Telecommunication Industry Association (TIA) EIA/TIA-526-7 Measurement of Optical Power Loss of Installed Single-Mode Fiber Cable Plant, EIA/TIA-526-14 Optical Power Loss Measurements of Installed Multi-Mode Fiber Cable Plant, EIA/TIA568 Commercial Building Telecommunications Cabling Standard and EIA/TIA-569 Commercial Building Standard for Telecommunications Pathways and Spaces. h) Form EE16 will be used as a carrier certificate for the Specialist’s installation, inspection, testing and certification of Fiber Optic Cables. The EE16 will be endorsed by the Fiber Optic Specialist’s representative and BP Commissioning and/or Operating Authority. i) In addition specifications, methods of test and certification, risk analysis statements should be understood with particular notice to the Material Safety Data Sheets (MSDS) relating to fiber shards and hazardous substances. GOC © BP Exploration 1989 – 2001 All Rights Reserved GUIDANCE ON CERTIFICATION SECTION 8.0 GOC© AMERICAS EDITION REVISION: 1 SUBJECT: CONTROL, INCLUDING INSTRUMENTATION FIRE AND GAS AND TELECOMMUNICATIONS PAGE: 15 2.4 Insulation Resistance Testing a) Before any cables are tested, check cables for damage during installation, and make sure all clamps, supports, etc. are completed. Intermediate insulation resistance tests shall be carried out before clamping. Before making any measurements, the inspector should ensure that one termination fitting of the cable has de-terminated and is clear of any metal. After measurements have been taken, a final test should be made when the termination fitting in question has been reterminated; i.e. conductor-to-conductor, conducto-to-shield, and conductor-to-ground. Measure the insulation resistance of the cable and record on the appropriate EE1 Sheet 1 or 2 test certificate. The table below gives the test voltages and minimum acceptable values of insulation resistance. Where necessary measure the conductivity of the ground conductor. For all multicore cables, insulation resistance should be measured conductor to conductor, conductor to ground and shield to armor. Only the lowest figure obtained shall be recorded. Cable Voltage (Working Range) Test Voltage (between Conductor and to ground) Minimum Insulation Resistance Volts 24 240/440 Volts 500 500 Meg-Ohms 10 10 After the above tests each cable shall be discharged and the conductors earthed until the cable is put into service. The test voltage are as tabulated above. GOC © BP Exploration 1989 – 2001 All Rights Reserved GUIDANCE ON CERTIFICATION SECTION 8.0 GOC© AMERICAS EDITION REVISION: 1 SUBJECT: CONTROL, INCLUDING INSTRUMENTATION FIRE AND GAS AND TELECOMMUNICATIONS PAGE: 16 2.5 Certification a) All cable testing is the responsibility of the Construction/Maintenance authority who shall sign Form EE1 Sheet 1 or 2. Form EE1 Sheet 1 or 2 is to be used to record the results of the testing and to confirm that all the requirements of this procedure, and Electrical Procedures 9.15 and 9.19, if appropriate, have been carried out. b) Form EE16 Sheet 01 is to be used as a carrier certificate for Fiber Optic Cables. The EE16 Sheet 01 will be endorsed by the Fiber Optic Specialists and BP Commissioning and/or Operating Authority. GOC © BP Exploration 1989 – 2001 All Rights Reserved GUIDANCE ON CERTIFICATION SECTION 8.0 GOC© AMERICAS EDITION REVISION: 1 SUBJECT: CONTROL, INCLUDING INSTRUMENTATION FIRE AND GAS AND TELECOMMUNICATIONS PAGE: 17 PROCEDURE 8.3 3.1 General Calibration / Installation / Cold Loop Checking 3.1.1 General Device calibration shall be carried out in a calibration workshop, except where devices form a part of an integrated system, in which case they shall be calibrated in place. Calibration shall be completed with due regard to the specific requirements of each type of device. A suitable means shall be made available for simulating the required process conditions and that test equipment is available with sufficient accuracy for the test to be performed. Construction/Maintenance shall provide current test certificates for all calibration equipment. Before calibration, all devices shall be visually inspected for damage (any damage being rectified before any tests are attempted). The data plate on the device, and the available power source, whether electric or pneumatic shall agree with that called for on the device specification sheet. The Supplier's Instruction Manual shall be made available. A label shall be attached to the device, giving details of the calibration check, including date test completed and the name of tester. GOC © BP Exploration 1989 – 2001 All Rights Reserved GUIDANCE ON CERTIFICATION SECTION 8.0 GOC© AMERICAS EDITION REVISION: 1 SUBJECT: CONTROL, INCLUDING INSTRUMENTATION FIRE AND GAS AND TELECOMMUNICATIONS PAGE: 18 3.1.2 Energy Supply Source and Output a) This procedure applies to all devices requiring a power supply and which generate a signal output. b) Pneumatic i) The air supply to pneumatic instruments shall be clean, dry and oil free. ii) Connect the air supply and adjust the air supply regulator to the correct setting, e.g. 20 psig for an operating range of 3-15 psig; 1.4 bar gauge for an operating range of 0.2 – 1.0 bar gauge. iii) Connect the output to a suitable test gauge via a capacity chamber. iv) Care should be taken to ensure that all pneumatic connections are leak free. If in doubt, leak test joints with soap and water (bubble) solution. c) Electronic i) Connect a suitable power supply. Electronic devices shall be energized for the minimum period as stated by manufacturers recommendations. Correct polarity of supply should be maintained at all times. ii) Connect the output to a suitable test meter. 3.1.3 Transmitters/Receivers a) This procedure applies to all transmitting, receiving and direct reading devices, other than local pressure/temperature gauges, and switches. GOC © BP Exploration 1989 – 2001 All Rights Reserved GUIDANCE ON CERTIFICATION SECTION 8.0 GOC© AMERICAS EDITION REVISION: 1 SUBJECT: CONTROL, INCLUDING INSTRUMENTATION FIRE AND GAS AND TELECOMMUNICATIONS b) PAGE: 19 Leak Test i) Apply the maximum signal input pressure to the process connection, close the inlet and disconnect the pressure source. Observe the gauge on the signal inlet and ensure that there is no fall-off of pressure over a given period. Where leaks are evident, these shall be eliminated and the test repeated. c) Calibration Test Check device at 'ZERO' reading and adjust if necessary. i) Raise the process input signal and record the corresponding output signal and/or scale readings at 0-25-50-75-100% of the device range. Differential pressure devices shall be subject to a static alignment check. Note: The readings should always be taken when the signal is in the 'rising' state. ii) Lower the process input signal and record the corresponding output signal and/or scale readings at 100-75-50-25-0%. Note: The readings should always be taken when the signal is in the 'falling' state. iii) The percentage error calculated for the above tests should not exceed the manufacturer's stated limits for accuracy and hysteresis. iv) Where necessary, adjustments should be made according to the manufacturer's instructions and the tests repeated. Accuracy of reading should be better than or equal to the accuracy limits stated in the manufacturer's specification. GOC © BP Exploration 1989 – 2001 All Rights Reserved GUIDANCE ON CERTIFICATION SECTION 8.0 GOC© AMERICAS EDITION REVISION: 1 SUBJECT: CONTROL, INCLUDING INSTRUMENTATION FIRE AND GAS AND TELECOMMUNICATIONS PAGE: 20 3.1.3 Controllers a) This procedure applies to conventional analog, field or panel mounted controllers, and would not apply to micro processor type controllers which form part of an integrated system. Such systems would usually be factory calibrated and any field tests or adjustment would be subject to special agreement with the engineer. 3.1.4 Receiver Controller (Closed Loop Method) a) Receiver controllers, either pneumatic or electronic should be tested by the closed loop method. This entails connecting the controller output to the process input connection and the following performed. i) Place controller action in reverse (decreasing output for increasing input), set Proportional Band to a low value, set Integral or Derivative action (if fitted) to minimum time values. ii) Check that the settings of any limit stops allow full scale pointer movement. iii) Adjust the set point to 50% of scale and set the Auto/Manual transfer switch to Auto. The controller output should now read 50%, if there is a deviation scale, it should be a null balance point (center scale). iv) Move the set-point upscale and down scale while observing the output meter. The output meter should continuously track the set point and deviation point should always read null. Always allow time at each set-point setting to permit the controller to balance correctly. v) With the controller set-point and output at 50% move the Proportional Band setting from minimum to maximum. During this GOC © BP Exploration 1989 – 2001 All Rights Reserved GUIDANCE ON CERTIFICATION SECTION 8.0 GOC© AMERICAS EDITION REVISION: 1 SUBJECT: CONTROL, INCLUDING INSTRUMENTATION FIRE AND GAS AND TELECOMMUNICATIONS PAGE: 21 movement, the output or null balance pointer should remain stationary. vi) Change the Auto/Manual transfer switch to ‘Manual’; it should be possible to vary the output manually from 0 to 100% of the output scale. In the event of the controller performing incorrectly adjustments should be made in accordance with the manufacturers' instructions until satisfactory test results are obtained. NOTE: The above procedure may vary from one manufacturer to another. 3.1.5 Direct Connected Controllers (Open Loop Method) a) For controllers connected directly to the process, connect a suitable signal generating source to the process connection together with a means of isolating and regulating the same, with a suitable accurate indicator. A power supply should be connected and an output gauge provided if one does not already exist on the controller. Checks should be made for controller alignment and synchronisation as follows. i) Controller Alignment Set the controller action to 'Direct', the Auto/Manual transfer switch to 'Auto', and the Proportional Band to a low value. Adjust the Integral and Derivative settings (if fitted) to minimum values. Set the set-point to 50% (mid-scale) and increase the process variable to mid-scale at which point the controller output should change from minimum to maximum. If this does not occur, make adjustments in accordance with manufacturers' instructions. GOC © BP Exploration 1989 – 2001 All Rights Reserved GUIDANCE ON CERTIFICATION SECTION 8.0 GOC© AMERICAS EDITION REVISION: 1 SUBJECT: CONTROL, INCLUDING INSTRUMENTATION FIRE AND GAS AND TELECOMMUNICATIONS PAGE: 22 When correct change-over occurs, reverse the controller action and re-check the operation to ensure the controller is correctly aligned. ii) Controller Synchronization Having checked the alignment set the controller action to the required mode for operation and set the Proportional band to 100% with the process variable and set point at 50% (mid-point). The controller is normally synchronized at 50% of the output range and should therefore indicate mid-output range when the set-point and process variables are at mid-scale. With the controller set up at mid-scale, adjust the Proportional Band setting from minimum to maximum, during which the output pointer should remain stationary. If the controller performs incorrectly, adjustment should be made in accordance with the manufacturers instructions, and the test repeated. Change the Auto/Manual transfer switch to 'Manual'; it should be possible to vary the output manually from 0 to 100% of the output scale. 3.1.6 Pressure Gauges a) Pressure gauges should be checked by means of a Hydraulic Pressure Gauge Comparator. The standard pressure gauge shall be calibrated on site against a Dead Weight Tester before initial use and then periodically. The date for such tests shall be recorded. The Gauge Comparator should be firmly fixed to a bench, and a test gauge of range comparable to the gauge being tested is fitted to the other branch with the hand pump on the comparator operated in order to check the gauge against the reading of the test gauge. GOC © BP Exploration 1989 – 2001 All Rights Reserved GUIDANCE ON CERTIFICATION SECTION 8.0 GOC© AMERICAS EDITION REVISION: 1 SUBJECT: CONTROL, INCLUDING INSTRUMENTATION FIRE AND GAS AND TELECOMMUNICATIONS PAGE: 23 Reading should be checked for pressure corresponding to 0-50-100% of the range of the gauge under test. Actual gauge readings shall be noted for both rising and falling signals. Gauges for use on oxygen service must be tested by oil-free means. 3.1.7 Pressure Switches a) Pressure switches shall be tested at their operating point using either a compressed air source or a dead-weight tester depending upon the range of the switch under test. A continuity test-circuit should be connected across the contacts to ensure correct operation. Care should be taken to ensure the switch operation is in the correct mode, i.e. with a rising or falling signal according to the device specification. When stated in the specification, the switching differential should also be checked and recorded. 3.1.8 Temperature Indicators a) Local temperature indicators (dial thermometers) shall be checked using a temperature bath. They should normally be checked at approximately 50% of the range unless otherwise agreed. During the test both shall be continuously stirred to ensure even temperature throughout. 3.1.9 Temperature Switches a) Temperature switches shall be tested at their operating point using a temperature bath. During the test both shall be continuously stirred to ensure even temperature throughout. A continuity test-circuit should be connected across the contacts to ensure correct operation. Care should be taken to ensure the switch operation is in the correct mode, i.e. with a rising or falling signal according to the device specification. GOC © BP Exploration 1989 – 2001 All Rights Reserved GUIDANCE ON CERTIFICATION SECTION 8.0 GOC© AMERICAS EDITION REVISION: 1 SUBJECT: CONTROL, INCLUDING INSTRUMENTATION FIRE AND GAS AND TELECOMMUNICATIONS PAGE: 24 Where the switching differential is stated in the specification, this should also be checked. 3.1.10 Level Switches a) Float switches should be tested mechanically prior to installation with a continuity test-circuit connected across the contacts to ensure correct operation. Care should be taken to ensure the switch operation mode is correct. Where possible all float or displacer elements shall be checked for pin hole leaks i.e. immerse element in bath of clear hot water and inspect for Air Bubble Streams. Before commissioning, water should be used to check the operation of the switch in place. 3.1.11 Solenoid Valves a) Connect an appropriate power supply via a switch and connect an air supply to the appropriate port or ports. The operation of the valve shall be checked by operating the switch and observing the change-over action. Tightness of shut-off shall be checked by connecting a flexible tube to the outlet port or ports and immersing the free end in water to ensure that the valve closure is bubble-tight at the stated design pressure. Where applicable, check electrical and manual reset, over-ride and time delay features as called for in the specification; that the coil resistance is correct and any bridge rectification is intact. Also check any internal suppression diodes. GOC © BP Exploration 1989 – 2001 All Rights Reserved GUIDANCE ON CERTIFICATION SECTION 8.0 GOC© AMERICAS EDITION REVISION: 1 SUBJECT: CONTROL, INCLUDING INSTRUMENTATION FIRE AND GAS AND TELECOMMUNICATIONS PAGE: 25 3.1.12 Flow Elements a) Flow elements, e.g. orifice plates, venturies, variable area meters, turbine meters etc., should not be installed until line flushing has been completed. Flow elements such as turbine meters, magnetic flow meters etc., cannot usually be tested in the field and manufacturers test certificates are normally accepted. Before installation, the flow element shall be inspected to ensure that the data and material specification stamped on the data plate or tab handle agrees with the specification. b) Orifice plates should be examined for flatness and to ensure that they are undamaged. The dimensions should be checked against the relevant data sheet with a Vernier and recorded on form CC1 by Construction/Maintenance, and upon installation Commissioning to ensure correct direction of flow. checked by Inspection of orifice flange installation shall be carried out to ensure adequate weld dressing and orientation of flange taps. Pipeline internal dimension measurement certificates shall be inspected. 3.1.13 Control Valves a) Diaphragm Valves (Without Positioner) Note the bench setting operating range of the diaphragm actuator from its data plate or specification sheet. Connect a suitable regulated air supply with an accurate test gauge to the diaphragm case connection. Increase the air pressure to load the diaphragm and check the valve spindle position from the valve stem position indicator. The travel should be checked at the following GOC © BP Exploration 1989 – 2001 All Rights Reserved GUIDANCE ON CERTIFICATION SECTION 8.0 GOC© AMERICAS EDITION REVISION: 1 SUBJECT: CONTROL, INCLUDING INSTRUMENTATION FIRE AND GAS AND TELECOMMUNICATIONS PAGE: 26 positions 0-25-50-75-100% of valve stroke. Where necessary, adjust the valve spring tension nut to obtain the correct start point and retest. When tight shut-off is specified, a test rig should be fabricated comprising of a blind flange on the valve outlet, fitted with a bleed pipe and a suitable rated isolation valve. The open end of the bleed pipe should be immersed in water so that discharge bubbles can be observed. The valve inlet should be connected to a source of pressure equal to the valve shut-off pressure. The specified signal corresponding to the valve closed position under normal operating conditions should be applied to the valve actuator and, if necessary, adjustments made to the valve, until the leakage bubblerate is within the specified tolerance. b) Diaphragm Valves (With Positioner) Note the bench setting operating range of the diaphragm actuator from its data plate or specification sheet, i.e. bench-set of actuator irrespective of positioner. Note the operating range of the positioner input and output. Where the positioner is fitted with a by-pass valve (omitted in split-range service) switch the valve to the signal input connection. If a positioner by-pass is not fitted, disconnect the air connection from the actuator case and connect the variable air supply, with test gauge, direct to the diaphragm head. The actuator should then be checked for travel, independent from positioner with rising and falling signals at 0-25-50-75-100% of valve stroke. After checking the valve stroke without positioner, the stroke should be checked with the positioner in service. Connect an air supply to the Positioner 'supply' connection and adjust to 5 psig above the maximum GOC © BP Exploration 1989 – 2001 All Rights Reserved GUIDANCE ON CERTIFICATION SECTION 8.0 GOC© AMERICAS EDITION REVISION: 1 SUBJECT: CONTROL, INCLUDING INSTRUMENTATION FIRE AND GAS AND TELECOMMUNICATIONS PAGE: 27 operating range of the actuator. Switch the positioner by-pass valve to the 'on' position. If no by-pass is fitted, re-connect the positioner output to the actuator and connect the variable air supply to the positioner signal connection. If necessary, adjust in accordance with manufacturers instructions and then re-test. Control valves with other types of actuator, e.g. piston operators, air cylinder operators, electro/hydraulic or electric motor operators should be tested for stroking and failure action in accordance with the manufacturer's instructions. All valve accessories shall be checked for correct function, this shall include limit switches, solenoid valves and any associated test over-ride facilities. c) Electrically Actuated Valve Testing Where actuators have not been tested with the valves in the Vendors' Works, consideration shall be given to testing the combined valve and actuator unit to demonstrate that the actuator will open the valve with the specified differential pressure in the associated pipework. Initial testing shall be performed by winding the valve by hand to the mid-position before operating the actuator to check that the motor phase rotation is correct, noting that incorrect rotation will damage the valve. The settings of torque and limit switches, valve position indicators, indicating lights and remote/locate controls shall be checked by a full operation test, using both the medium and low voltage supplies. Where more than one electrically operated valve is associated with a system of interlocks, all valves shall be operational to ensure that the required valves only are affected. GOC © BP Exploration 1989 – 2001 All Rights Reserved GUIDANCE ON CERTIFICATION SECTION 8.0 GOC© AMERICAS EDITION REVISION: 1 SUBJECT: CONTROL, INCLUDING INSTRUMENTATION FIRE AND GAS AND TELECOMMUNICATIONS PAGE: 28 Field installed powered -up testing shall only be carried out with the full involvement of the Operating Authority. 3.2 Fire & Gas and Telecommunications a) Due to the diverse nature of Fire & Gas and Telecomms equipment general calibration procedures are not recommended. Calibration were applicable shall be carried out in accordance with the individual manufactures instructions and conjunction with the relevant specialised vendor where applicable. 3.3 Certification a) Calibration Checks All calibration checks are the responsibility of the Construction / Maintenance, and shall be recorded on Form CC1. All devices are to be calibrated on receipt (refer to 8.1.1. d). b) Inspecting & Tests The following inspections and tests shall be completed the Construction / Maintenance before a loop is offered for acceptance. i) All supports for piping, tubing and cabling have been fitted. ii) Hydraulic/hydrostatic pressure testing (Procedure 8.1) has been completed. iii) All field/panel cabling has been installed as per appropriate drawing. Instrument (Procedure 8.2) completed. iv) General calibration/installation (Procedure 8.3) complete, where appropriate, and recorded on the CC1. GOC © BP Exploration 1989 – 2001 All Rights Reserved GUIDANCE ON CERTIFICATION SECTION 8.0 GOC© AMERICAS EDITION REVISION: 1 SUBJECT: CONTROL, INCLUDING INSTRUMENTATION FIRE AND GAS AND TELECOMMUNICATIONS v) PAGE: 29 All equipment is installed, tagged and located, as per design. vi) All equipment certification is correct for area classification. Electrical (Procedure 9.15) has been completed and recorded on the CC1. vii) All "cold" powered down continuity loop checks are completed inline with the relevant design drawings. viii) All associated junction boxes have been checked and electrical (Procedure 9.19) has been completed and recorded on form CC1. ix) Mechanical protection of equipment, particularly Fire and Gas, critical to the overall completion of the detection and protection systems the necessary precautions shall be taken to ensure the integrity of the installed equipment and systems is maintained. GOC © BP Exploration 1989 – 2001 All Rights Reserved GUIDANCE ON CERTIFICATION SECTION 8.0 GOC© AMERICAS EDITION REVISION: 1 SUBJECT: CONTROL, INCLUDING INSTRUMENTATION FIRE AND GAS AND TELECOMMUNICATIONS PAGE: 30 PROCEDURE 8.4 4.1 Powered Up Loop And Function Testing 4.1.1 General Loop Testing shall be completed for Control, Fire & Gas and Telecommunications Loop testing will be carried out by the Commissioning Authority. Prior to commencing with powered-up loop checks confirm the completion of Procedures 8.1, 8.2 & 8.3. Confirm all relevant certification is complete and available for inspection. Full regard shall be taken of all relevant documentation prior to commencing loop function testing including: manufacturers instructions, O & M manuals, Control and Shutdown Philosophy, Cause and Effect's, and specialised vendor input that may be required. 4.1.2 Loop Categories a) Loops are basically divided into 4 categories: i) Local non-interactive, e.g. PI, TI. This category does not require function testing; calibration and installation are covered by the CC1 as completed by Construction. ii) Local control and indication with no local/remote panel interaction, e.g. PT & PCV. This category requires loop function testing. iii) Control and Detection/Indication with local/remote interaction, no complex control functions or shutdown interface, e.g. PT-PIC-PCV and/or PT-PSL-PSH-PAL-PAH. This category requires loop function testing. GOC © BP Exploration 1989 – 2001 All Rights Reserved GUIDANCE ON CERTIFICATION SECTION 8.0 GOC© AMERICAS EDITION REVISION: 1 SUBJECT: CONTROL, INCLUDING INSTRUMENTATION FIRE AND GAS AND TELECOMMUNICATIONS iii) PAGE: 31 Control and Detection/indication with local/remote interaction, complex control functions or shutdown interface, e.g. from any High High / Low Low initiating devices, Fire & Gas detection & Executive action. This category initially requires the standard loop function test and then the system function test for the control/shutdown interfaces and should be tested in accordance with the relevant commissioning procedure, control philosophy and cause and effect. For instruments connected to the Distributed Control System (DCS) or safety systems, the loop shall include system measurement, processing, control action and display. This shall be achieved utilising the control system monitoring facilities provided for the purpose. The overall testing of the instrumentation system, which includes DCS/safety systems, shall be carried out in conjunction with the Vendor of the control system, under the supervision of the Construction control engineer and the Commissioning Authority. 4.1.3 Loop Function Testing Control a) General Loop testing is applicable to all devices: Control, Fire & Gas and Telecommunications, except were specialized vendor involvement is required; in these instances testing will be at the discretion of the Commissioning Authority. Ensure devices are powered-up and tested in accordance with manufacturers procedures. b) For Fire & Gas devices. i) Ensure correct operation of fire area override. ii) Ensure the area around the detector is free of gas. GOC © BP Exploration 1989 – 2001 All Rights Reserved GUIDANCE ON CERTIFICATION SECTION 8.0 GOC© AMERICAS EDITION REVISION: 1 SUBJECT: CONTROL, INCLUDING INSTRUMENTATION FIRE AND GAS AND TELECOMMUNICATIONS iii) PAGE: 32 Ensure that any optical surfaces and mirrors are clean. iv) Check alignment of detectors and reflector plates. c) Apply an appropriate signal to the device, i.e. typical but not limited to:pressure/temperature/digital/analog/UV-IR source/test sheet or injection of test gas. Check each loop component for correct action/operation. A check calibration/performance test shall be carried out over the range of each loop device. d) Check / set any trip / alarm in the loop, simulate process signal to initiate the transmitter/device and check the action, check for correct LEL readings, check zero readings, including displays, alarms etc. at operator console. All trips shall be set to the value on the data sheet. e) Check the action of the annunciator/LED or other indication against the specification i.e. momentary or maintained. The correct sequence of operation and all outputs shall be proven to work satisfactorily including audible and visible alarms. f) Thermowells shall be visually inspected for correct insertion depth. Thermal elements shall be inspected for damage and correct element length to ensure contact with the base of the well. g) Resistance thermometer elements and thermocouples should be checked at ambient, and at differing temperatures using suitable test equipment connected at the field terminals, and the corresponding output display and recorders checked over their range. h) Burn out features shall be checked where provided. i) Stroke valves by varying controller output. Check valve fail action and positioner action. j) Ensure devices are powered up in accordance with manufacturers procedures. GOC © BP Exploration 1989 – 2001 All Rights Reserved GUIDANCE ON CERTIFICATION SECTION 8.0 GOC© AMERICAS EDITION REVISION: 1 SUBJECT: CONTROL, INCLUDING INSTRUMENTATION FIRE AND GAS AND TELECOMMUNICATIONS PAGE: 33 k) All individual devices shall be checked as part of the loop function test. l) Shutdown input signals should be checked initially to the input LEDs and associated annunciator. m) Outputs from the shutdown system should be simulated initially from the output terminals to the field device. n) Shutdown inputs/outputs, Electrical, Fire & Gas, HVAC and Vendor packages interfaces should be checked to ensure system compatibility and correct function with the associated department in question. o) Analytical and special installations shall be tested in accordance with the manufacturers recommendations. p) Reference Procedure 8.5 for shutdown/complex loop functions q) Owing to the diversity of equipment involved in Telecommunications systems e.g. satellite communications, aeronautical radios, beacons, MF, HF, VHF, UHF communications equipment, antennae, TV, video, etc., it is impractical to produce in-house test record proformas to cover the full range of different manufacturers specialized equipment. The objective of providing the diverse range of telecommunications systems (Radio, Satellite, PA/GA, Telephone, etc.) is to ensure the operational integrity of the platform or facility. The basis for procuring the relevant telecommunications systems is to use appropriate proprietary systems, and system testing is carried out using manufacturer's procedures, with certification based on relevant industry standards. A system test is to be carried out for each system and all the devices connected to it, and a summary of the results recorded on Form SC1System Control Certificate. Telecom equipment can be placed in one of three categories for inspection and test purposed. GOC © BP Exploration 1989 – 2001 All Rights Reserved GUIDANCE ON CERTIFICATION SECTION 8.0 GOC© AMERICAS EDITION REVISION: 1 SUBJECT: CONTROL, INCLUDING INSTRUMENTATION FIRE AND GAS AND TELECOMMUNICATIONS I. PAGE: 34 General Bulk Field Equipment i) P.A. Speakers ii) P.A. Visual Lamps iii) Telephone Sockets iv) Exe Telephone Installation v) Data Sockets vi) Entertainment Distribution Components vii) Entertainment Office and Cabin Units viii) Fiber Optic Cable II. Specialist Field Equipment i) Muster Intercom Units ii) Operational Intercom Units iii) Hotline Telephones iv) CCTV Cameras and Monitors v) Meteorological Sensors vi) Antennas vii) Clocks viii) Drillers Intercom Units ix) x) xi) xii) xiii) xiv) xv) xvi) xvii) III. Crane Radios Aeronautical Non Directional Beacon Local Area Network (LAN) & Data Network Entertainment System Survival Craft Radios and Beacons P.A. Access Units PMS Line of Sight Radio Link Satellite System Central Telecoms Equipment - Located in Equipment Rooms, Radio Rooms and the CCR i) Public Address & General Alarm System ii) SITCOM Terminal iii) VHF Marine and Aeronautical Fixed Radios iv) MF/SSB Equipment GOC © BP Exploration 1989 – 2001 All Rights Reserved GUIDANCE ON CERTIFICATION SECTION 8.0 GOC© AMERICAS EDITION REVISION: 1 SUBJECT: CONTROL, INCLUDING INSTRUMENTATION FIRE AND GAS AND TELECOMMUNICATIONS PAGE: 35 v) NDB Beacon and Monitor vi) UHF Radio and Paging Equipment vii) Hotline Central Equipment viii) Telex ix) Inmarsat x) Meteorological Master and Salve Units xi) Weatherfac/Navfax/Fax xii) Shutdown System xiii) Master Supervisory xiv) Data Central Racks and Master Clock xv) Telephone Exchange System xvi) Emergency Muster Point System 4.1.4 General The foregoing requirements for equipment loop function testing by commissioning shall apply to Control, Instrumentation, Fire & Gas, Telecommunications equipment and systems as appropriate. Form SC 1 shall be used for this purpose. GOC © BP Exploration 1989 – 2001 All Rights Reserved GUIDANCE ON CERTIFICATION SECTION 8.0 GOC© AMERICAS EDITION REVISION: 1 SUBJECT: CONTROL, INCLUDING INSTRUMENTATION FIRE AND GAS AND TELECOMMUNICATIONS PAGE: 36 PROCEDURE 8.5 5.1 System Control (Function) Testing a) Function testing of the system control scheme and the shutdown system will be completed by Commissioning in accordance with relevant commissioning procedure, control philosophy and cause and effect for the system or part system, and SC1 certificate raised accordingly. System function testing will be carried out on receipt and acceptance of the Mechanical Completion Certificate (MC1). Programmable Logic Control Panel inspections, as detailed in Procedure 8.7, must be completed prior to the commencement of system control function testing. The SC1 shall be raised by the testing authority or nominated delegate. The originator and technical authority shall be detailed on the SC1. All relevant details of associated drawings and software that the system has been tested to shall be recorded on the SC1. The shutdown logic should be checked by the commissioning authority as a separate exercise and an SC1 raised to cover all actions as detailed in the associated Cause and Effect or logic diagram. All trip and interlock devices, system inhibits and over-rides shall be function tested. The function test will be simulated from the field in an end-to-end test. Signals will not be simulated by disconnection or by shorting; the control device in the field will be used to generate the trip signal. GOC © BP Exploration 1989 – 2001 All Rights Reserved GUIDANCE ON CERTIFICATION SECTION 8.0 GOC© AMERICAS EDITION REVISION: 1 SUBJECT: CONTROL, INCLUDING INSTRUMENTATION FIRE AND GAS AND TELECOMMUNICATIONS PAGE: 37 PROCEDURE 8.6 6.1 System Performance HIPS (High Integrity Performance System) Tests 6.1.1 Trip Testing Routine a) It is of paramount importance that systems installed for the protection of plant and personnel will operate correctly and reliably when a potentially dangerous condition is approached. Systems may remain static and may not be called on to operate for long periods of time. Failure of a component part of a system may not be apparent to the plant operator since the system does not play any part in the normal routine control of the plant. Trip testing routines shall be carried out for the following: 6.1.2 Category 1 Systems If testing of the system is required on-line, a complete system of at least single sensor, logic system, actuator and trip valve shall remain in commission during testing. Test facilities that prevent the system fulfilling its intended function should be avoided. The frequency and method of testing should be those, which have been shown by reliability analysis to give acceptable integrity. The trip testing routine shall be provided as part of the system design / commissioning procedure and shall be ratified by the relevant authorities, any required deviation from the routine due to operational circumstances should first be authorized by the engineering authority. GOC © BP Exploration 1989 – 2001 All Rights Reserved GUIDANCE ON CERTIFICATION SECTION 8.0 GOC© AMERICAS EDITION REVISION: 1 SUBJECT: CONTROL, INCLUDING INSTRUMENTATION FIRE AND GAS AND TELECOMMUNICATIONS PAGE: 38 6.1.3 Category 2A a) Category 2A systems with multiple sensors, logic and trip valves should be tested as for the Category 1 system. For 2A systems using single sensors and logic, the testing will be determined by the reliability requirements. The trip testing routine shall be provided as part of the system design / commissioning procedure and shall be ratified by the relevant authorities, any required deviation from the routine due to operational circumstances should first be authorized by the engineering authority. Form SP1 to be used to record the completion of the routine. 6.1.4 Category 2B a) Testing on line of the final actuator device may not be required. An adequate level of integrity may be achieved by testing at plant or spared equipment shutdown. The trip testing routine shall be provided as part of the system design / commissioning procedure and shall be ratified by the relevant authorities, any required deviation from the routine due to operational circumstances should first be authorized by the engineering authority. HIPS Testing 6.1.5 ESD Valve (Emergency Shutdown) a) Inspection and testing of primary platform isolations ESD valves shall be checked for correct position and orientation. Function Testing of these valves should be carried out using the platform ESD system. Form SP1 to be used to record the completion of the routine. Refer to SI 825 Pipeline and Safety Regulations. GOC © BP Exploration 1989 – 2001 All Rights Reserved GUIDANCE ON CERTIFICATION SECTION 8.0 GOC© AMERICAS EDITION REVISION: 1 SUBJECT: CONTROL, INCLUDING INSTRUMENTATION FIRE AND GAS AND TELECOMMUNICATIONS b) PAGE: 39 Offshore ESDV’s must be inspected and function tested to assets and statutory requirements of SI 1996 No 825 (formally SI 1029). SI 1996 No 825 details the intervals between partial and full closure test, for planned full closure tests it is recommended that a seal leak test, wherever possible, is conducted at the pipeline Maximum Allowable Operating Pressure (MAOP). If the MAOP cannot be achieved then an estimate of the leak rate at the MAOP should be made using the actual test pressure achieved. Form SP2 (side 2) to be used to record the valve closure test results. Refer to SI 1996 No 825 Pipeline Safety Regulations. Although SI 1996 No 825 does not apply to onshore ESDV’s it is recommended that onshore valves are also inspected and tested in accordance with this SI. 6.1.6 SSIV (Subsea Intervention Valve) a) Subsea Intervention Valves (SSIV) are not directly referred to in SI 825, however the following guidelines should be considered. i) SSIV testing should be scheduled to coincide with SI 825 closure tests. ii) Where the plant operability and control system design allows partial and full closure tests should be carried out including seat leakage rate test. iii) The time interval in seconds from the initiation of the shutdown sequence for the SSIV to travel to the closed position should be recorded and developed into a trend for use as a fault finding tool. The frequency and type of function testing should be determined based on the SSIV system reliability analysis, vendors recommendations, operational experience and in accordance with the Pipeline Operators Requirements. GOC © BP Exploration 1989 – 2001 All Rights Reserved GUIDANCE ON CERTIFICATION SECTION 8.0 GOC© AMERICAS EDITION REVISION: 1 SUBJECT: CONTROL, INCLUDING INSTRUMENTATION FIRE AND GAS AND TELECOMMUNICATIONS 6.1.7 PAGE: 40 ESDV (Emergency Shutdown Valve) Topside facility ESDV's as used for primary facility isolation shall be checked in accordance with the relevant Asset specific, Prevention of Fire and Explosion, and Emergency Response (PFEER) requirements. Full closure testing, partial closure testing and seat leakage testing shall be carried out in accordance with the relevant Commissioning / Maintenance Procedure. The time taken for ESD valves to stroke to their shutdown position shall be recorded. Valve installation shall be checked for correct position and orientation. Form SP1 should be used to record the completion of the routine. 6.1.8 a) Miscellaneous (Analysers, Special Installations) Analysis and sampling equipment shall be checked against their specification on receipt and shall be carefully examined for damaged glassware and other easily breakable components. Any defects shall be reported to the Technical Integrity Authority. Construction shall not attempt any analysis testing without prior consultation with the Integrity Authority. Commissioning in accordance with specific procedures. GOC © BP Exploration 1989 – 2001 All Rights Reserved GUIDANCE ON CERTIFICATION SECTION 8.0 GOC© AMERICAS EDITION REVISION: 1 SUBJECT: CONTROL, INCLUDING INSTRUMENTATION FIRE AND GAS AND TELECOMMUNICATIONS PAGE: 41 PROCEDURE 8.7 7.1 Programmable Logic Controller Panels (PLCP) These panels generally fall into three categories: i) ii) Emergency and Process Shutdown Systems (ESD / PSD) Distributed Control Systems (DCS) iii) Fire and Gas This is a generic procedure for the above systems, and covers the panel inspection / testing at the vendors prior to delivery (if applicable), preinstallation checks on site, and post installation checks and tests. Due to the wide variety of PLCPs, i.e. simplex, duplex etc., it is not possible to be specific as to the tests requirements. The procedure should be treated as a guide as to the test requirements, and it will be the responsibility of the construction and commissioning engineers, in liaison with the panel vendor as to what level of testing is required. Details of these test requirements should be listed on the relevant SC1 certificate. Test requirements for such generic panels should include as a minimum, but not limited to the following checks and tests. 7.1.1 Pre-Delivery Inspection / Testing at Vendors a) Ensure the panel conforms to the specified design drawings and documentation. b) Ensure that the panel certificates meet the area classification and design specification requirements. c) Compare the panel equipment with the equipment schedule and vendor documentation. Ensure that all power supply circuit ratings are GOC © BP Exploration 1989 – 2001 All Rights Reserved GUIDANCE ON CERTIFICATION SECTION 8.0 GOC© AMERICAS EDITION REVISION: 1 SUBJECT: CONTROL, INCLUDING INSTRUMENTATION FIRE AND GAS AND TELECOMMUNICATIONS PAGE: 42 as specified. Note any circuit or hardware changes, and ensure that they are covered by a project change notice, EQ, or similar. d) Vendor documentation shall be reviewed and validated against panel equipment. e) Produce a detailed commissioning and /or test procedure to cover the functionality of the panel equipment, taking into account: i) Power supply segregation / fusing ii) All inputs and outputs iii) iv) Controller functionality Full Cause and Effect testing 7.1.2 Pre installation and Inspection a) Remove any temporary weatherproofing and silica gel drying agents from the panel. Inspect the inside of the panel for cleanliness paying particular attention to the PLC racks and terminations. b) Check internal hardware is fixed securely, and adequate access is available to all panel equipment. c) Ensure panel is not damaged and all connection hardware and cables are included. 7.1.3 Post-Installation a) Inspect the entire panel assembly for alignment, level, tightness of anchor bolts and fastening in general. b) Ensure that all panel doors, racks and are bonded to panel structure. c) Ensure that all equipment installed in the panel is in good order and in clean condition. Verify bolt connections for tightness. GOC © BP Exploration 1989 – 2001 All Rights Reserved GUIDANCE ON CERTIFICATION SECTION 8.0 GOC© AMERICAS EDITION REVISION: 1 SUBJECT: CONTROL, INCLUDING INSTRUMENTATION FIRE AND GAS AND TELECOMMUNICATIONS PAGE: 43 d) Inspect panel grounding and earth connections for mechanical and e) electrical continuity. Ensure all single core panel wiring pins /crimps are secure. Check all terminals for tightness post field cable termination. 7.1.4 Panel Testing Before the function testing of any field device as detailed in Procedure 8.5 can be carried out, panel functionality tests must be completed. The detail and extent of such tests are the responsibility of the commissioning engineer, who should liase with the panel vendor to ensure adequate test requirements. Panel functionality testing can only commence on receipt and acceptance of the Mechanical Completion Certificate MC1 from the construction group. All AC / DC power supplies to the panel, including UPS supplies, are to be connected and operational and terminated within the panel, with their relevant cable test certificates completed and signed off. i) Ensure all breakers are switched off, and all main fuses are removed with-in the panel, switch on each power supply in turn and check for correct voltage and polarity. ii) Power-up the panel equipment in turn for each of the power supplies and ensure stable operation. If necessary current measurements are to be taken to ensure no overload condition exists. iii) Check all PLC LEDs for correct status, and confirm PLC healthy indication. Establish communications between the processor and the I/O racks and check that correct data is flowing. In the case of a dual redundant communication system, fail each comms link in turn and check for auto change-over. GOC © BP Exploration 1989 – 2001 All Rights Reserved GUIDANCE ON CERTIFICATION SECTION 8.0 GOC© AMERICAS EDITION REVISION: 1 SUBJECT: CONTROL, INCLUDING INSTRUMENTATION FIRE AND GAS AND TELECOMMUNICATIONS PAGE: 44 iv) Power-up the system monitors and confirm satisfactory operation. v) Examine the system status pages, and confirm that all PLC system alarms and faults are genuine and accounted for. vi) Select a random number of digital and analogue inputs and operate. Observe correct PLC I/O rack LED indication, and correct status on the system monitors. Note: These tests need not include full application logic tests as per the cause and effects. Full cause and effect function testing will be performed during each of the system control function tests as detailed in Procedure 8.5. GOC © BP Exploration 1989 – 2001 All Rights Reserved GUIDANCE ON CERTIFICATION SECTION 8.0 GOC© AMERICAS EDITION REVISION: 1 SUBJECT: CONTROL, INCLUDING INSTRUMENTATION FIRE AND GAS AND TELECOMMUNICATIONS PAGE: 45 Flowchart 8 • • Functional Certification Flowchart. Discipline: Control ( Includes Instrumentation, Fire & Gas and Telecoms) SP1 CC1 MC1 SH1 SC1 CC1 : Control Completion Certificate. MC1 : Mechanical Completion Certificate. SC1 : System Control (Function Test) Certificate SP1 : System Performance Certificate (HIPS) SH1 : System Handover Certificate. Note! Where Welding is carried out an MW1 - Welding Completion Summary is required - Refer to GOC Section 2 GOC © BP Exploration 1989 – 2001 All Rights Reserved GUIDANCE ON CERTIFICATION SECTION 8.0 GOC© AMERICAS EDITION REVISION: 1 SUBJECT: CONTROL, INCLUDING INSTRUMENTATION FIRE AND GAS AND TELECOMMUNICATIONS PAGE: 46 EXHIBIT 8 Standard Forms CC1 Control Completion Certificate SC1 System Control (Function Test) Certificate SP1 System Performance Certificate (HIPS) DIS5 Data Input Sheet 5 – Section 8 Controls Note: Final acceptance of each form as complete and correct shall be approved by the Construction and/or Commissioning Authority as appropriate. GOC © BP Exploration 1989 – 2001 All Rights Reserved Project Title: FORM CC1 Work Pack No: Maintenance No: SITE: SH1 No: MC1 No: SHT CONTROL COMPLETION CERTIFICATE P&ID No: OF Equipment Installed as per Design (If No, Raise an NCR or EQ ) Area Classification Check - Electrical Procedure 9.15 Complete YES NO Loop Diagram Drawing No: YES NO N/A Process Hook-Up Drawing No: Junction Box Inspection YES NO N/A Pneumatic Hook-Up Drawing No: Orifice Plate Measurement Completed (where appropriate) YES NO N/A Instrument Tie-in Point Number: Orifice Plate Measurement : Diameter NDE Location Drawing No: YES NO Impulse Line Welding *YES/NO if YES - is MW1 Complete? *YES/NO - Electrical Procedure 9.19 Complete ins / Check Flatness Record All Deviations/Comments: Loop Number Tag Number Procedure No. 8.1 Completed By Procedure No. 8.1 8.2 Manufacturer Model & Serial No Data Sheet No Calibrated Range/Setting Procedure No. 8.3 Asset Specific Procedure Approved By 8.3 Procedure No. 8.2 Company Signature Print Name Date * DELETE AS APPLICABLE GOC© BP Exploration 1989 – 2001 All Rights Reserved Americas REV. 1 Project Title: Maintenance No: Work Pack No: SH1 No: MC1 No: FORM SC1 Sheet 01 SITE: SYSTEM CONTROL FUNCTION TEST CERTIFICATE EQUIPMENT No : SHT OF EQUIPMENT DESCRIPTION : LOCATION : SYSTEM : COMMISSIONING PROCEDURE NO : IS RUNNING LOG REQUIRED? * YES * NO IF "YES" ATTACH THE APPROPRIATE COMMISSIONING RUNNING LOG COMPLETED BY APPROVED BY COMPANY SIGNATURE PRINT NAME DATE * DELETE AS APPLICABLE GOC© BP Exploration 1989 – 2001 All Rights Reserved DOUBLE SIDED FORM Americas REV. 1 Project Title: Maintenance No: Work Pack No: SH1 No: MC1 No: FORM SC1 Sheet 02 SITE: SYSTEM CONTROL FUNCTION TEST INSTRUMENT TUBING LEAK TEST CERTIFICATE SHT EQUIPMENT No : EQUIPMENT DESCRIPTION : LOCATION : TYPE OF TEST : SYSTEM : TYPE OF TUBING : COMMISSIONING PROCEDURE NO : TEST MEDIUM : TAG No. INSPECTED DATE INITIAL TEST PRESSURE COMPLETED BY LEAK TESTED DATE DURATION OF INSPECTION COMPLETE INITIAL APPROVED BY COMPANY SIGNATURE PRINT NAME DATE * DELETE AS APPLICABLE GOC© BP Exploration 1989 – 2001 All Rights Reserved DOUBLE SIDED FORM Americas REV. 1 Project Title: Maintenance No: Work Pack No: SH1 No: MC1 No: FORM SP1 (SIDE 1) SITE: HIPS PERFORMANCE CERTIFICATE (CONTROL FUNCTION TEST) EQUIPMENT No : SHT OF EQUIPMENT DESCRIPTION : LOCATION : SYSTEM : COMMISSIONING PROCEDURE NO : COMPLETED BY APPROVED BY COMPANY SIGNATURE PRINT NAME DATE GOC© BP Exploration 1989 – 2001 All Rights Reserved DOUBLE SIDED FORM Americas REV. 1 FORM SP1 HIPS PERFORMANCE CERTIFICATE (VALVE CLOSEURE/LEAK TESTS) (SIDE 2) Name and Identification of Installation: SHT 0F Name and Identification of Pipeline: TAG Identification: Actuator Identification: Name of Installation Owner: Description Of Test Select & Date INSPECTION RECORD LEAKAGE RATE RECORD PARTIAL CLOSURE RECORD FULL CLOSURE RECORD TRIP TESTING ROUTINE RECORD Particulars Of Procedures Used External Leaks Revealed External Damage Revealed External Corrosion Revealed Closure Time (actual mechanical movement time) Seat Leakage Rate Sec’s Oil lb/min or gal/min Gas SCF/Min Trip Testing Routine Carried Out Other Observations Recommended Remedial Work I Certify the Above Particulars Are Correct Technician Who Carried Out Test & Inspection Control Supervisor Production Supervisor OIM or Nominated Authority Signature Name Date Designation GOC© BP Exploration 1989 – 2001 All Rights Reserved DOUBLE SIDED FORM Americas REV. 1 DIS5 HANDOVER No : _______________ PROJECT : ___________ J.P NO. TAG No LOCATION : _______________ LOOP DIAGRAM No RAISED BY: ___________________________________ NOTE: JP No FOR (LOOP) TESTING DATA INPUT SHEET 5 P&ID No WELL No LOOP No DATE : _________________________________ GOC© OF WORKSCOPE ID : ______________________ SECTION 8 - CONTROL SLOT No SHEET MAINTENANCE ID No : ______________________ CC1 SP1 SC1 * SC1 REF DRGS TO BE AS-BUILT (LAD) COMMENTS DATA ENTERED BY : ________________ DATE : __________ BP Exploration 1989 - 2001 All Rights Reserved Americas Rev. 1 GUIDANCE ON CERTIFICATION SECTION 9.0 GOC© AMERICAS EDITION REVISION: 1 SUBJECT: ELECTRICAL SECTION 9.0 ELECTRICAL GOC© BP Exploration 1989 - 2001 All Rights Reserved PAGE: 1 GUIDANCE ON CERTIFICATION SECTION 9.0 GOC© AMERICAS EDITION REVISION: 1 SUBJECT: 9.1 ELECTRICAL PAGE: 2 ACTIONS 9.1.1 General a) This document details the on-site and off-site inspection and testing procedures for the Electrical Discipline and includes standard forms which are to be used to accurately record the results of the inspection and tests. It also provides written evidence that all electrical equipment and circuits comply with design parameters, and will function correctly. b) The procedures cover the inspection of electrical equipment prior to installation and the inspection and testing of installed equipment and circuits before and after energization. Although the inspection and test procedures in this section are comprehensive, they may not necessarily cover all electrical equipment and circuits included in the design. It is the responsibility of the Construction/Commissioning Group to confirm all electrical inspections and tests. Also, it is to ensure that any further procedures, additional to those included in this document, are developed in order to give complete coverage and confirm that electrical circuits in all respects are fit for energization and service. c) The Engineering & Procurement Group shall ensure that prior to inspection and testing activities, a comprehensive component or equipment list and cable schedule is available. All the required test certificates will be checked against this list to give a concise cross reference for the completion of system testing. These lists will form the index of the Certification Database for the electrical discipline. (Refer to Section 1.0). d) The Supplier may be required to carry out final inspection and functional testing on-site after installation. Such inspection and tests are to be recorded on GOC© test certificates unless specific test certificates are prepared by the Supplier and agreed by the Witnessing Authority prior to use. GOC© BP Exploration 1989 - 2001 All Rights Reserved GUIDANCE ON CERTIFICATION SECTION 9.0 GOC© AMERICAS EDITION REVISION: 1 SUBJECT: e) ELECTRICAL PAGE: 3 The requirements described herein which apply to equipment specified to be installed in ‘Class 1 Division 1 hazardous locations, shall also apply to equipment specified suitable for use in ‘Class 1 Division 1 hazardous locations but to be installed in ‘Class 1 Division 2 or non-hazardous areas, at the approval of BP or the Delegated Authority. 9.1.2 Installation a) The installation of electrical equipment and circuits will be checked for compliance with good engineering practice and other requirements as detailed in: • The latest revision of IFC Drawings and Schedules • • • Plant and Project Specifications Equipment Specifications and Data sheets National Electrical Code (NFPA-70) • National Electric Safety Code (ANSI C-2) • NFPA 70E, Standard for Electrical Safety Requirements for Employee Workplaces • NFPA 72, ANSI / IEEE Standards and NEMA Standards • API RP 14F, Recommended Practice for Design & Installation of Electrical Systems for Fixed and Floating Offshore Petroleum Facilities for Unclassified and Class I, Division 1 and 2 Locations API RP 540, Electrical Installations in Petroleum Processing Plants Nationally Recognized Testing Lab Standards, e.g. UL, FM, CSA BP Engineering Installation and Design Specifications Offshore - Special Standards of ABS and USCG in addition to those above • • • • b) Electrical equipment and the electrical content of mechanical equipment packages will be inspected on receipt on-site. Any remedial work carried out on-site by the supplier to correct transit GOC© BP Exploration 1989 - 2001 All Rights Reserved GUIDANCE ON CERTIFICATION SECTION 9.0 GOC© AMERICAS EDITION REVISION: 1 SUBJECT: ELECTRICAL PAGE: 4 damage or faulty workmanship not previously detected, will be supervised by the Construction Authority. c) Any final inspection and testing of electrical equipment and systems carried out on-site by the supplier’s representatives will be witnessed and formally accepted by the Construction/Commissioning Group Electrical Engineer. Prior to performing the above inspections or tests, the Witnessing Authority shall be informed and shall identify those inspections and tests that are required to be witnessed. 9.1.3 Pre-Acceptance Procedure a) Prior to energizing, when Construction considers that the installation of an electrical circuit or parts thereof is complete, and is of such a standard that pre-acceptance inspection and testing can commence, he shall advise The Witnessing Authority accordingly. Unless said Authority gives a specific waiver, a representative of The Witnessing Authority shall witness all inspection and tests, which are to be recorded in the HCP. Construction must provide adequate notice of their intention to commence these activities so that The Witnessing Authority has time to allocate necessary personnel. b) The Witnessing Authority shall monitor construction activities so that inspection and testing can be carried out as work proceeds. The need for disconnecting of cables for testing purposes after the installation has been completed, is to be avoided. c) Wherever possible, final inspection and testing should be carried out immediately prior to acceptance for energization. Where this is not possible, The Witnessing Authority may call for re-inspection and re-testing. GOC© BP Exploration 1989 - 2001 All Rights Reserved GUIDANCE ON CERTIFICATION SECTION 9.0 GOC© AMERICAS EDITION REVISION: 1 SUBJECT: d) ELECTRICAL PAGE: 5 Following the satisfactory completion of the inspection and testing of a system or circuit, Construction or the Witnessing Authority shall complete the appropriate test certificate(s). These shall be witnessed as appropriate by The Witnessing Authority, and submitted prior to formal notification that work on the circuit is complete. No further work whatsoever shall be carried out on a completed circuit by Construction, subsequent to this certificate submittal, unless The Witnessing Authority or the Commissioning authority agrees in writing to full details of all such works. The further work description shall contain full details of all branch circuits not covered, and include the means by which not covered circuits will be isolated during this added work. e) Equipment used for testing such as meggers, DC high potential test sets and current injection test sets shall be calibrated every six months. Certificates of calibration shall be included with the SH1 package and identified to matching serial numbers on the equipment used for the tests. f) Module or work enclosure internal ambient temperature shall be maintained at 40oF to 80oF during all testing. The ambient temperature shall be recorded at the beginning of each test, along with the percent relative humidity. g) The Commissioning and Witnessing Authority Tests (Items Marked **) Certain Certificates shown at the end of each Procedure, detail tests that are to be carried out after energization. The Commissioning & Witnessing Authorities will therefore complete these Certificates. The areas to be completed by The Commissioning & Witnessing Authorities will be indicated by a double asterisk (**). GOC© BP Exploration 1989 - 2001 All Rights Reserved GUIDANCE ON CERTIFICATION SECTION 9.0 GOC© AMERICAS EDITION REVISION: 1 SUBJECT: ELECTRICAL PAGE: 6 The Construction work scope will therefore be completed where the non-asterisks part of the form is indicated. See the following listing: The sheets affected by this work delineation are: EE2 Sheet 01 & 02 − EE3 Sheet 01 EE4 Sheet 01 − − MCC Inspection for Bus Duct Phase rotation Circuit Breaker Tests for Trip circuit operation Contactor Starter for Trip circuit operation and breaker status remote indication EE4 Sheet 03 − Load testing Variable Speed Drives EE13 Sheet 01 − Phase rotation and run testing of motors EE15 Sheet 01 − UPS performance testing EE8 Sheet 02 − Heat Trace performance test EE16 Sheet 01 − General Test Certificate & Attachments (when required) h) The Witnessing Authority Tests (Electrical Procedures Marked “Witnessing Test”) The electrical procedures also detail tests that are to be carried out after energization and will therefore be completed by The Witnessing Authority. These tests have been indicated by placing “Witnessing Authority” at the end of the test clause on the appropriate certificate. i) The Witnessing Authority (Electrical Procedures Marked “Witnessing Authority to Verify”) The electrical procedures detail required witnessing points during construction/pre-commissioning. The witnessing points have been indicated by placing “Witnessing Authority to Verify” at the end of the test description clause on the appropriate procedure. GOC© BP Exploration 1989 - 2001 All Rights Reserved GUIDANCE ON CERTIFICATION SECTION 9.0 GOC© AMERICAS EDITION REVISION: 1 SUBJECT: ELECTRICAL PAGE: 7 9.1.4 Energization and Commissioning a) Construction will notify The Witnessing Authority that work is complete; arrangements will be made to energize the circuit at a mutually convenient time. The energization and commissioning of the circuit will be carried out by, and be the responsibility of, The Commissioning Authority and the Operator’s Electrical Supervisor as shown below: Up to 480VAC, by the Commissioning Authority. Over 480VAC, by the Operator’s Electrical Supervisor b) Under no circumstances may a circuit be energized or commissioned prior to it being inspected and tested, and the relevant certificate as identified on the appropriate Inspection and Test Summary (ITS), has been completed and approved. Prior to initial energizing, a Unit Work Permit shall be obtained. c) Under no circumstances may any test be carried out on cables or equipment without the agreement and in the presence of a representative of the Construction Authority or The Witnessing Authority. If the results of the tests and checks carried out after energization are not satisfactory, the circuit will be de-energized, locked-out and handed back to the Construction for remedial action. d) If the results of the energization tests are satisfactory, the circuit will be accepted by the Witnessing Authority, subject to any minor modifications specified by them. Thereafter, the circuit will become the responsibility of The Commissioning Authority or Operations and no further work may be carried out on it without their prior approval. Access to live parts or the energization of branch circuits must thereafter have the express approval of The Operating Authority by means of the Permit to Work system. GOC© BP Exploration 1989 - 2001 All Rights Reserved GUIDANCE ON CERTIFICATION SECTION 9.0 GOC© AMERICAS EDITION REVISION: 1 SUBJECT: ELECTRICAL PAGE: 8 9.1.5 Permit to Work Procedures In order to achieve a safe coordinated approach to electrical commissioning, the following procedural steps shall be followed: i) All commissioning will be carried out in accordance with the Operator’s HSE Regulations and Permit to Work requirements. ii) All feeders to switchgear and motor control centers will always be the responsibility of the Operation’s Electrical Supervisor as the Facility Authorized person. iii) Before disconnecting any feeder cables to switchgear and motor control centers, the Construction Authority, must provide the Electrical Supervisor with a full scope of work including procedures on re-instatement as well as effects on equipment in service or being disconnected. iv) Energization of pre-commissioned equipment up to 480VAC, such as MCC’s and distributing panels for lighting and heating, shall only be approved by mutual consent of the Construction Authority and Commissioning Authority. v) The custody of energized pre-commissioned equipment shall be with the Commissioning Authority. All feeder and branch circuit breakers not in use shall be locked-out and tagged-out. GOC© BP Exploration 1989 - 2001 All Rights Reserved GUIDANCE ON CERTIFICATION SECTION 9.0 GOC© AMERICAS EDITION REVISION: 1 SUBJECT: ELECTRICAL PAGE: 9 9.1.6 Safety Precautions a) In no circumstances may any test be carried out in such a manner as to cause danger to personnel. All due safety precautions must be taken. b) No test should be undertaken until it has been confirmed that the equipment to be tested is properly isolated, has been effectively discharged, and a UNIT WORK PERMIT obtained. c) Areas where High Voltage (HV) testing is to take place must be roped off prior to and during testing. Cautionary notices shall be displayed at all points of access. Similar precautions are to be taken in all other instances where danger could arise, e.g. motor running tests. d) All equipment is to be effectively discharged at the completion of testing; where necessary, e.g. in the case of large cables and motors. A grounding jumper shall be applied, and left connected until any residual voltage is fully discharged. In no case is this to be less than 5 minutes. GOC© BP Exploration 1989 - 2001 All Rights Reserved GUIDANCE ON CERTIFICATION SECTION 9.0 GOC© AMERICAS EDITION REVISION: 1 SUBJECT: ELECTRICAL PAGE: 10 Electrical Procedures List 9.1 Power, Control and Instrument Cables 9.2 Switchgear, Motor Control Centers and Metal Enclosed Bus Duct 9.3 Circuit Breakers - Air, Molded Case and Vacuum Oil Immersed 9.4 Contactor Starters and Variable Frequency Drives 9.5 9.6 Medium Voltage Air Switches Power Transformers; Oil Filled and Dry Type 9.7 Motors, A.C. Induction 9.8 9.9 Batteries and Battery Chargers U.P.S. 9.10 Lighting and Small Power Distribution System 9.11 9.12 9.13 Navigation Aids (Nav-aids) Neutral Grounding Resistors Heat Trace Cables and Circuits 9.14 9.15 9.16 Grounding/Bonding Equipment for use in Hazardous Locations Oil Insulation Tests 9.17 9.18 Drying of Electrical Rotating Machinery Instrument Transformer Verfications 9.19 9.20 9.21 Junction Box Inspection Protective Relay Testing and Metering Circuits A.C. Generators GOC© BP Exploration 1989 - 2001 All Rights Reserved GUIDANCE ON CERTIFICATION SECTION 9.0 GOC© AMERICAS EDITION REVISION: 1 SUBJECT: ELECTRICAL PAGE: 11 ELECTRICAL PROCEDURES Procedure No. 9.1 1.1 Power, Control and Instrument Cables 1.1.1 General The following inspection and test procedures are applicable to all cable sizes and types. 1.1.2 Inspection 1.1.2.1 Pre-Installation Verify the cable to be installed is of the proper type, size and rating for the designated application. Also verify that all required manufacturing data and standards labeling are clearly visible on the cable per NEC. 1.1.2.2 Post-Installation a) Compare the cable size, type, routing and numbering with the cable schedule and relevant electrical drawings. Pay particular attention to any special requirements noted, such as: chemical environment, voltage of service, or area classification. Verify that the color code and wire numbers match connection diagrams and phase sequence. b) Ensure that cable termination and fittings meet area classification and specification requirements. c) Inspect the cable termination fittings for tightness and good workmanship. Ensure that the correct type of termination fitting has been used for the size and type of cable installed and the connection landed. GOC© BP Exploration 1989 - 2001 All Rights Reserved GUIDANCE ON CERTIFICATION SECTION 9.0 GOC© AMERICAS EDITION REVISION: 1 SUBJECT: d) ELECTRICAL PAGE: 12 Where 3 phase loads are served by either single conductor or parallel conductors for each phase, all phase conductors shall be grouped (A, B, C, N) per NEC. [Prevents induction heating of conduit or enclosure.] e) Where conductors have been terminated using compression connectors, check that the correct size and type of connector has been used. The crimp tool and dies used must be listed and labeled for the particular connector, and must be of the type requiring a full compression stroke before release. Ensure cable connections are tight and torque values verified with a calibrated torque wrench. f) Inspect all grounding connections, for control as well as power cables. Refer to manufacturers instructions for proper ground connections for the type of cable in use. g) For MV cables, be sure that the cables have been terminated in accordance with the cable manufacturer’s instructions, including shield grounding. In particular, check that any support or clamping measures required have been incorporated for strain relief. Note stress cones may be required depending on voltage and type of cable. h) For Mineral Insulated Cable (type MI): i) Check that all termination fittings are per the manufacturer’s instructions and that insulating sleeves are undamaged. ii) Verify pigtails are stranded wire and that pigtail length and root length meet drawing requirements per NEC. iii) Megger test insulation resistance on individual MI cable sets. iv) Verify MI cable is installed with vibration suppression loops. GOC© BP Exploration 1989 - 2001 All Rights Reserved GUIDANCE ON CERTIFICATION SECTION 9.0 GOC© AMERICAS EDITION REVISION: 1 SUBJECT: i) ELECTRICAL PAGE: 13 Inspect conduit, cable trays and cabling systems for NEC compliance and installation in accordance with Issued For Construction (IFC) drawings. Record inspection data on the applicable conduit, cable or cable tray checkout forms per pages 14 thru 17 following. j) Inspect cable blocking kit installation where required in hazardous locations. Record data on the Cable Blocking Kit Inspection Checkout form (page 18) and attach to EE16 Sheet 1. k) Ensure cable installation bends meet the manufacture’s and NEC minimum allowable bending radius. Pay particular attention to such standards for cables pulled into or through pull boxes and panels. l) Note and be certain the installation complies with the requirements for Hazardous Locations (Procedure 9.15) and Junction Box Standards (Procedure 9.19) for conduit seals and other details. m) Inspection Checkout Refer to Inspection Checkout forms on following pages 1418. These forms are to be attached to the EE16 Sheet 1 Certificate. These will assist in the organization of data and acceptance of the EE16 Sheet 1, General Test Certificate: • Conduit Installation Inspection • Conduct or Cable Seal Inspection • Cable Inspection • Cable Tray Installation Inspection • Cable Blocking Kit Installation Inspection Note: Complete conduit, cable and cable tray Inspections prior to executing insulation tests (megger or H.V. DC). Insulation tests (beginning with Part 1.1.3 following) are to be conducted with cables installed, but with end terminals still open. GOC© BP Exploration 1989 - 2001 All Rights Reserved GUIDANCE ON CERTIFICATION SECTION 9.0 GOC© AMERICAS EDITION REVISION: 1 SUBJECT: ELECTRICAL CONDUIT INSTALLATION INSPECTION CHECKOUT (Procedure 9.1) PAGE: 14 SLD No SHT DATE: JOB NO: LOCATION: MODULE: CONDUIT NO: SIZE: FROM: TO: of Initials/Date 1. Conduit fittings and junction boxes correct type for area of classification. 1 2. Aluminum or galvanized steel conduit installed where specified on drawings. 2 3. Supports installed and spacing as per drawings/specs/NEC. 3 4. Supports adjacent to terminal boxes/devices as per NEC. 4 5. Conduit is correct size per drawings/NEC fill requirements. 5 6. Conduit field cut is correctly threaded per NEC. 6 7. Conduit installed wrench tight with minimum 5 threads engaged. 7 8. Conduit installed plumb and level, at right angles to structure. 8 9. Conduits clean, stub-ups protected, open ends plugged, and free of obstructions. 10. Conduit bending radius is correct as per specs and NEC. Bends free of deformities with full diameter throughout. 9 11. Installation is neat and conduct runs evenly spaced. 11 12. Spacing between instrument and power conduits is per project specs. 12 13. Spacing from hot piping/equipment is in accordance with project specs. 13 14. Adequate clearance maintained from walls, ladders, railings, ceilings, etc. 14 15. Conduit is permanently and effectively grounded per NEC and Procedure 9.14. 15 16. Threaded Bushings installed on all conduits entering boxes, fittings per NEC. 16 17. Seals and drains installed as per drawings/specs/NEC. 17 18. Union installed between seal and devices or boxes. 18 19. No fittings installed between seals and crossover area classification boundaries. 20. Junction boxes level and supported per drawings with proper hubs, locknuts and bushings installed. 19 21. Junction boxes properly labels and grounded. 22. Number of pulling points adequate; number of bends does not exceed NEC. Flexible conduit installed with correct bending radius. 21 10 20 22 REMARKS REV. 1 GOC© BP Exploration 1989 - 2001 All Rights Reserved GUIDANCE ON CERTIFICATION SECTION 9.0 GOC© AMERICAS EDITION REVISION: 1 SUBJECT: ELECTRICAL CONDUIT OR CABLE SEAL INSTALLATION INSPECTION CHECKOUT (Procedure 9.1) DATE: JOB NO: PAGE: 15 SLD No LOCATION: Conduit or Cable number and Location SHT MODULE: Type (eys, stx, ect) Size Verify Initials/Date 1. Temperature suitable for pour __________ Record # degrees °C or °F. 1 2. Temperature maintained for seal cure as per manufacturers requirements. 2 3. Seal(s) properly sized as per specifications and codes. 3 4. Seal(s) properly located per code. 4 5. Packing material type & installation per vendor required. 5 6. Conductors properly separated. 6 7. Proper compound type and mixed per manufacturers requirements. 7 8. Seals checked for leak through after pour. 8 9. Seals plugs painted red. 9 10. Seal or STX initialed and dated by BP QA. of 10 REMARKS REV. 1 GOC© BP Exploration 1989 - 2001 All Rights Reserved GUIDANCE ON CERTIFICATION SECTION 9.0 GOC© AMERICAS EDITION REVISION: 1 SUBJECT: ELECTRICAL CABLE (INSTALLED WITHOUT CONDUIT) INSPECTION CHECKOUT (Procedure 9.1) PAGE: 16 SLD No SHT DATE: JOB NO: LOCATION: MODULE: CABLE NO: SIZE: FROM: TO: Verify of Initials/Date 1. Cable, fittings and junction boxes labeled/listed for the area classification. 1 2. Supports installed as per drawings/specs/NEC. 2 3. Supports installed at terminal boxes/devices as per NEC. 3 4. Cable is sized as per drawings. 4 5. Cable terminators packed and sealed as required. 5 6. Terminators are wrench tight with minimum 5 threads engaged. 6 7. Cables are installed plumb and neatly arranged. 7 8. Cable bending radius is correct as per specs and NEC. 8 9. Cable installation is neat and evenly spaced. 9 10. Spacing between instrument and power cables is as per project specs. 10 11. Spacing from hot piping/equipment is in accordance with project specs. 12. Adequate clearance maintained from walls, ladders, railings, ceilings and any sharp edges. 11 13. Cable is permanently and effectively grounded/bonded as per NEC. 13 14. Hubs/bushings installed for cable terminations as required. 14 15. No fittings installed between seals and area classification boundaries. 16. Junction boxes properly installed with proper hubs, bushings installed, labeled and grounded. 15 12 16 REMARKS REV. 1 GOC© BP Exploration 1989 - 2001 All Rights Reserved GUIDANCE ON CERTIFICATION SECTION 9.0 GOC© AMERICAS EDITION REVISION: 1 SUBJECT: ELECTRICAL CABLE TRAY INSTALLATION INSPECTION CHECKOUT (Procedure 9.1) PAGE: 17 SLD No SHT DATE: JOB NO: LOCATION: MODULE: TRAY NO: SIZE: FROM: TO: Verify of Initials/Date 1. All braces and supports installed are as per drawing/specs/NEC/VE-1. 1 2. Aluminum or galvanized conduit attachments are installed when specified on drawings. 2 3. Tray size and fill in accordance with specs/NEC/VE-1. 3 4. Tray hold downs and guides properly installed/located as per design, NEMA and NEC requirements. 4 5. No sharp edges left and round carriage bolts are installed with head to inside of tray. 5 6. Field bends/transitions provide continuous bonding for ground path and proper support for cables. 6 7. Bonding jumpers installed as required at all sections junction points. 7 8. All non-conductive coatings removed at ground/bond connections as required. 8 9. Cable tray grounded/bonded as required. 9 10. Proper clearances provided as required for installing cable runs in tray. 10 11. Expansion joints located as required properly installed and bonded. 11 12. Damaged coatings repaired as required. 12 13. Spacing between power and instrument trays maintained as per specs. 13 14. Proper spacing from heat sources as per specs. 14 15. All dividers, covers and fire stops installed as required by specs and NEC. 15 REMARKS REV. 1 GOC© BP Exploration 1989 - 2001 All Rights Reserved GUIDANCE ON CERTIFICATION SECTION 9.0 GOC© AMERICAS EDITION REVISION: 1 SUBJECT: ELECTRICAL CABLE BLOCKING KIT INSTALLATION INSPECTION CHECKOUT (Procedure 9.1) PAGE: 18 SLD No SHT DATE: JOB NO: LOCATION: MODULE: TRAY NO: SIZE: FROM: TO: Verify of Initials/Date 1. Cable jacket and shield(s) properly prepared for blocking. 1 2. Aluminum or galvanized conduit fittings installed when specified on drawings. 2 3. Drain wire(s) insulated with clear heat-shrink tubes. 3 4. Proper gap (1/2”) between drain heat-shrink tubing and end of shield foil. 4 5. Proper number of sealant sleeves used as per vendor requirements. 5 6. Individual drain wires grouped in common with their conductors. 6 7. No visible cracks or defects in sleeves or fittings. 7 8. No share bends at block mounting. 8 9. Hot melt sealant evenly distributed. 9 10. Hot melt sealant visible at both ends. 10 11. No individual conductors or shield wire showing. 11 12. Overall heat shrink is properly positioned. 12 13. Overall heat shrink length is per manufacturer’s specification. 13 14. Check cable type(s) to be compatible with blocking. 14 REMARKS REV. 1 GOC© BP Exploration 1989 - 2001 All Rights Reserved GUIDANCE ON CERTIFICATION SECTION 9.0 GOC© AMERICAS EDITION REVISION: 1 SUBJECT: ELECTRICAL PAGE: 19 1.1.3 Testing Cables a) Before any cables are tested, all cable supports, strain reliefs or clamping blocks and pull box or termination cabinets must be installed. All final cable tests are to be made with cable runs essentially in place, and before final terminations are made up. b) Prior to final megger test application, the inspector should ensure that the open end of the cable is isolated from conducting material, and all three phases (plus neutral if used) are prepared and accessible at the testing end. c) Perform the megger test on one phase conductor to ground with other conductors grounded, and shields (if used) grounded. Rotate test conductor so as to test all three phases individually in the same manner. d) On multi-conductor cables, insulation resistance tests are to be from conductor to other conductors - grounded one at a time with shields grounded, similar to c) above. An additional test is to confirm isolation between shield and armor where both are in the same cable. Record the lowest test value obtained on each of these tests. 1.1.4 Insulation Resistance Test for Installed Cable a) Measure insulation resistance of the cable and record data on the proper EE1 Test Certificate located in Exhibit 9 at the end of this section. [EE1-SHT01 and SHT02.] b) See Table 1.1.4 a) for test voltage and minimum resistance acceptable. (This is a one minute test to verify cable minimum insulation prior to any further HV tests required.) GOC© BP Exploration 1989 - 2001 All Rights Reserved GUIDANCE ON CERTIFICATION SECTION 9.0 GOC© AMERICAS EDITION REVISION: 1 SUBJECT: ELECTRICAL PAGE: 20 Witnessing Authority to Verify Table 1.1.4 a) Cable AC Test Voltage* Minimum Insulation Voltage Rating (Between Conductors Resistance (Operating Range) and to Ground) (60 seconds) Volts Volts DC Meg-Ohms 300V 500 50 600V 5KV 600 2500 50 5 15KV 5000 15 * Test time is one minute at these voltages 1.1.5 High Voltage Acceptance Test (DC) for MV and HV Cable [See IEEE-576-1989, “Recommended Practice for Installation, Termination and Testing of Insulated, Power Cable for use in the Petroleum Chemical Industry] a) Perform insulation resistance test as described in section 1.1.4, prior to high voltage testing. Ground and discharge residual voltage from those tests prior to applying HV test voltages. b) Per Table 1.1.5 a), apply a DC high voltage test between each conductor and ground, with other conductors and all shields grounded. Record test voltage, time and value of test voltage, record the leakage current and compute resistance from measured V/I. Repeat the test for each conductor of each cable and record. This test also confirms resistance of conductor to conductor and conductor to shield as being satisfactory. Should any readings be unsatisfactory, it will be necessary to selectively test each conductor to its shield and conductor to conductor to isolate the fault. [See Certificate EE1 - SHT03 and SHT04]. c) For acceptance of newly installed cable systems, apply full test voltage per Table 1.1.5 a). Subsequent re-tests due to failure and after repair, or tests made on a cable system consisting of new GOC© BP Exploration 1989 - 2001 All Rights Reserved GUIDANCE ON CERTIFICATION SECTION 9.0 GOC© AMERICAS EDITION REVISION: 1 SUBJECT: ELECTRICAL PAGE: 21 and previously in-service cable, shall be made at 80% of the acceptance test values. Each cable shall be discharged after the above tests, and the conductors grounded and tagged until the cable is ready to be terminated on both ends. Witnessing Authority to Verify Table 1.1.5 a) Cable System Acceptance Voltage (Operating BIL Range) Maintenance Step Test Test Voltage Test Voltage (Conductor (Conductor to Duration (5KV Voltage Duration at to Ground) Ground) Steps) Max Volts Volts Volts DC Volts DC Minutes Minutes 5KV 15KV 75KV 110KV 25KV 55KV 20KV 40KV 1 1 15 15 35KV 200KV 100KV 75KV 1 15 Record all readings for each step and at Max Volts. Procedure shall be per IEEE-400, 1991 Edition. [NOTE: If Doble Power Factor Testing is to be conducted, it should be done after all high potential testing is completed and the cables are fully discharged.] d) For cable systems with a number of splices, each cable segment between splices shall be tested as an individual cable before making up splices. Each splice shall then be individually tested at the rated operating voltage of the cable for one minute, or until the leakage current stabilized, to ensure splice integrity. e) The completed cable run, including the end service terminations shall be tested at 100% of cable rated voltage (the acceptance test) for 15 minutes. [Load circuit must be open for this test.] GOC© BP Exploration 1989 - 2001 All Rights Reserved GUIDANCE ON CERTIFICATION SECTION 9.0 GOC© AMERICAS EDITION REVISION: 1 SUBJECT: 1.16 a) ELECTRICAL PAGE: 22 Conductor Continuity Test Perform a precision continuity test on all conductors including medium voltage shield with a volt-ohm meter or potentiometer to ensure conductor integrity. b) Measure shield resistance by looping shield on two adjacent conductor shields together at one end. Measure and record the loop resistance with an accurate volt-ohm meter. Repeat for each conductor pair combination and record. Witnessing Authority to Verify 1.1.7 Where Cable Blocking kits are required to seal cables leaving hazardous locations; the kits shall be inspected for correct installation. Witnessing Authority to Verify 1.1.8 Where conduit seals are required in hazardous locations, the correct materials and methods for installing, sealing and packing shall be verified prior to pouring of any seals. Poured seals shall be inspected, then, if satisfactory, marked by painting seal plugs red with plugs tight. Witnessing Authority to Verify 1.1.9 Certification Attached Certificate Forms: EE1, Sheets 01 & 02, EE1, Sheets 03 & 04 and EE16, Sheet 01 are to be used to record the results of the inspections and testing. These Sheets must be endorsed by the Witnessing Authority to confirm all the requirements of this procedure, and 9.15 (HAZ Area) and 9.19 (Junction Boxes) if applicable, have been satisfactorily carried out. GOC© BP Exploration 1989 - 2001 All Rights Reserved GUIDANCE ON CERTIFICATION SECTION 9.0 GOC© AMERICAS EDITION REVISION: 1 SUBJECT: ELECTRICAL PAGE: 23 ELECTRICAL PROCEDURES Procedure No. 9.2 2.1 (A) Switchgear , (B) Motor Control Centers and (C) Metal Enclosed Bus Duct 2.1.1 a) Inspection Pre-Installation - All items (A), (B) and (C) i) Ensure the equipment documents certify that the area classification and specification requirements have been met. ii) Remove any temporary weatherproofing and silica gel drying materials from enclosures. Inspect the inside of the equipment for cleanliness and signs of moisture, paying particular attention to insulators and bus bracing. iii) Compare the equipment with drawing schedules, paying particular attention to ratings and circuit designations. iv) Ensure that the equipment meets environmental specifications, including weather, dust and vermin-proofing. v) Ensure equipment is not damaged, and any required connection and detail hardware is included in the shipment. (See shipping documents.) b) Post Installation (See Inspection check out Sheets following) i) Inspect the switchgear and MCC assemblies for alignment, plumb and level. Check tightness of anchor bolts. Se that assembly hardware is installed and torqued to specified values per vendor drawings. GOC© BP Exploration 1989 - 2001 All Rights Reserved GUIDANCE ON CERTIFICATION SECTION 9.0 GOC© AMERICAS EDITION REVISION: 1 SUBJECT: ii) ELECTRICAL PAGE: 24 Ensure that all panel doors and termination plates are bonded to their enclosure structures. iii) Ensure that all equipment installed in the enclosure is new and in good, clean condition. Verify bolt torque at bus connection points with calibrated torque wrench. Witnessing Authority to Verify iv) Inspect the equipment grounding bus and grounding electrode conductors for electrical and mechanical continuity. Verify connections meet NEC requirements. v) Inspect bus, insulation and supports for tightness. Ensure joint insulation is in place where specified. Verify housing and bus connections are in proper alignment. Check bolts at bus connection points with calibrated torque wrench. Witnessing Authority to Verify vi) Verify proper operation of any interlock system (Kirk Key or Electrical) between main and tie circuit breakers on installed switchgear or transfer schemes in MCCs. vii) c) Ensure the appropriate requirements of Procedure 9.15 (Hazardous Locations) are carried out as applicable. Inspection Check Out The following inspection check out lists are to be followed to assist in completing the requirements for acceptance certificates: A) B) C) Electrical Switchgear Motor Control Center Bus Duct GOC© Certificate EE2, Sheet 01 Certificate EE2, Sheet 02 Certificate EE16, Sheet 01 BP Exploration 1989 - 2001 All Rights Reserved GUIDANCE ON CERTIFICATION SECTION 9.0 GOC© AMERICAS EDITION REVISION: 1 SUBJECT: ELECTRICAL ELECTRICAL SWITCHGEAR INSPECTION CHECKOUT (Procedure 9.2.1 (A)) DATE: JOB NO: TAG NO. PAGE: 25 SLD No LOCATION: SHT of MODULE: SYSTEM VOLTAGE Initials/Date 1. Remove shipping supports. 1 2. Check phasing of bus connections prior to assembly. 2 3. Check and inspect for completeness of all components. 3 4. All devices are installed such as: ground fault relays, volt meters, ammeters, breakers. 4 5. Inspect control wiring, especially field connections at shipping splits. 5 6. Insulation Resistance Test buses and DC Proof Test buses per 9.2.1.1 (d). 6 7. Insulation Resistance Test control and potential transformer primary windings. 7 8. Verify control transformer fuses, type and size per drawings. 8 9. Verify potential transformer fuses, type and size per drawings. 9 10. Check primary and secondary ratings of all transformers including control transformers. 10 11. Check for proper equipment grounding connections at both ends of assembly. 12. Check ground bus bar continuity and ensure connection has been made at shipping split points. 11 13. See that nameplates and device tags are complete and correct. 13 14. Cubicles clean, dry and dust free. 14 15. Space heaters are connected and operable, including thermostat controls. 15 16. Terminals and connections tight and secure. 16 17. Main bus and taps sized per vendor drawings. 18. Insulation Resistance Test the DC and AC controls circuits, with main and outgoing control disconnect devices open [Caution: check electronic device limitations]. 19. Check incoming power cables insulation Resistance Test prior to connection to switchgear [See Section 9.1.1.2 (l)]. 17 20. Check DC High Potential Testing Data for incoming power cables [See Section 9.1.1.4]. 21. Incoming feeder terminations properly made-up, after cable insulation tests are completed. 22. Vendor Representative provided service/supervision for this equipment. Vendor certified test reports are to be attached to this Inspection Report. 20 23. Final inspection complete. Punch list items cleared, see Certificate required. 23 24. Verify protective relay testing requirements per 9.20, if applicable. 24 12 18 19 21 22 REMARKS REV 1 GOC© BP Exploration 1989 - 2001 All Rights Reserved GUIDANCE ON CERTIFICATION SECTION 9.0 GOC© AMERICAS EDITION REVISION: 1 SUBJECT: ELECTRICAL MOTOR CONTROL CENTER INSPECTION CHECKOUT (Procedure 9.2.1(B)) DATE: JOB NO: TAG NO: PAGE: 26 SLD No LOCATION: SHT MODULE: VOLTAGE: 1. Inspect assembly for damage and missing parts. Remove shipping blocks and/or of INITIAL/DATE 1 supports. 2. All changes recorded for as-built drawings. 2 3. Inspect bus taps and torque connection bolt joints per manufacturer’s instruction. 3 4. Check equipment nameplate data in accordance with manufacturer’s drawings and per 4 job specifications. 5. Check for correct ratings of circuit breakers, switches, fuses, contactors, protective 5 relays, other components against one line diagrams and Manufacturer’s drawings. 6. Inspect equipment grounding, connections and conductor sizes, including internal 6 grounds for plug-in units. 7. Megger main bus, phase to phase and phase to ground, per 9.2.1.1 (d). 7 8. ** Check phase sequence across the tie breaker connected between the normal bus 8 and the emergency bus. [Verify before buses are energized.] 9. ** Check that overload reset button is functional on each starter. 10. Perform manual operation of breakers, switches, and contactors in accordance with 9 10 Manufacturer’s instructions. 11. Three-phase connections and phasings are in accordance with drawing color code 11 requirements. REMARKS ** Witness Authority to Verify REV 1 GOC© BP Exploration 1989 - 2001 All Rights Reserved GUIDANCE ON CERTIFICATION SECTION 9.0 GOC© AMERICAS EDITION REVISION: 1 SUBJECT: ELECTRICAL BUS DUCT INSPECTION CHECKOUT (Procedure 9.2.1(C)) DATE: JOB NO: PAGE: 27 SLD No LOCATION: SHT of MODULE: INITIAL/DATE 1. Inspect entire assembly, including auxiliary equipment, for any apparent damage or 1 missing parts. 2. Remove shipping blocks and supports. 2 3. Torque bus segment connections per manufacturer recommendations. NOTE: bus 3 insulation tests must be completed prior to bolting connector at either end. 4. Drain holes unplugged? See manufacturer drawings and instructions. 4 5. Gaskets installed? (if required). Check wall and/or vapor seal offs to be properly 5 installed. 6. Megger bus, and record on Field Inspection Record. See 9.2.1.1 (d). 6 7. **Check for proper phasing after installation. 7 8. Connect space heaters and check operability (where applicable), including temperature 8 controls. REMARKS ** Witnessing Authority to Verify REV. 1 GOC© BP Exploration 1989 - 2001 All Rights Reserved GUIDANCE ON CERTIFICATION SECTION 9.0 GOC© AMERICAS EDITION REVISION: 1 SUBJECT: d) ELECTRICAL PAGE: 28 Testing Note: Inspection checkout sheets require following tests for data to be entered: i) Test the Switchgear (A) and MCC (B) Ground system for electrical and mechanical continuity. Measure the ground path resistance from each equipment ground bus to earth ground or the grounding electrode. Witnessing Authority to Verify ii) Check to see that all metering and protective relaying devices have been tested in accordance with the requirements of the appropriate E12 test certificate, supplier’s instructions and Procedure 9.20. Witnessing Authority to Verify iii) Measure the insulation resistance of the main bus section. Also, test the control wiring, after ensuring any sensitive equipment has been disconnected, and insuring control wiring is not subjected to bus test voltages. This test should be carried out prior to the Dielectric withstand voltage testing and before energizing the equipment. The minimum acceptable resistance together with the relevant test voltage is given in the table below. Switchgear or MCC Voltage Test Voltage Minimum Insulation Resistance Meg-Ohms Volts Volts Meg-Ohms 600V 5KV 15KV 1000 5000 5000 10 200 200 Witnessing Authority to Verify iv) Perform a Dielectric Withstand voltage test (pressure test) on each bus section when required, between phases and phase to ground. The following conditions must be adhered to for the tests: GOC© BP Exploration 1989 - 2001 All Rights Reserved GUIDANCE ON CERTIFICATION SECTION 9.0 GOC© AMERICAS EDITION REVISION: 1 SUBJECT: ELECTRICAL PAGE: 29 All current transformer secondaries will be short-circuited for the test. All voltage transformers shall be disconnected by removal of primary and secondary fuses for the duration of the test. One pole of the testing supply shall be grounded and bonded to the frame of the assembly, for the phase to ground test. v) For low voltage switchgear (600V), refer to ANSI/IEEE C37.20. Section 5.5,”Field Tests.” The switchgear shall not be tested at greater than 75% of the test values in the table below. *Voltage and Insulation Levels, AC LV Switchgear Rated Maximum Voltage Volts (rms) Insulation Levels Low-Frequency AC Reference DC Withstand KV Withstand KV (rms) 600 * NOTE: 2.2 3.1 See Table in paragraph 9.2.1.1 d)iii for minimum insulation resistance acceptable. vi) For medium voltage switchgear (1000 volts or greater), refer to ANSI/IEEE C37.20.2, Section 5.5 “Fields Test.“ The switchgear shall not be tested at greater than 75% of the test values given in the table below. Voltage and Insulation Levels, MV Switchgear Rated Maximum Voltage Volts (rms) Insulation Levels Low-Frequency AC Withstand KV (rms) Impulse Withstand (KV) Reference DC Withstand (KV) 4.76 19 60 27 15 36 95 50 38 80 150 * GOC© BP Exploration 1989 - 2001 All Rights Reserved GUIDANCE ON CERTIFICATION SECTION 9.0 GOC© AMERICAS EDITION REVISION: 1 SUBJECT: ELECTRICAL PAGE: 30 vii) Repeat step (i) viii) Upon the completion of all tests, reconnect all cables and ensure that shorting links are removed and fuses are replaced. Witnessing Authority to Verify ix) Carry out any required testing of protective relaying and/or meter circuitry in accordance with Procedure 9.20 using primary and secondary injection methods as appropriate. Witnessing Authority to Verify x) Measure and record the closing and tripping supply voltages. Witnessing Authority to Verify xi) Energize switchgear or MCC and verify correct phase rotation. Verify phase sequence across tie circuit breaker to normal and emergency bus when required. Witnessing Authority to Verify xii) For Bus Duct (C), prior to making up final end connections, and assembly of covers, measure the insulation resistance of each run, phase to phase and phase to ground. Test each phase to ground with other two-phases grounded, then test each phase to the other two phases. Test values shall be in accordance with the following table: Insulation Resistance Test Voltage Bus Duct Voltage Rating DC Test Voltage 150-600 1000 601-5000 2500 & Above 5000 Witnessing Authority to Verify GOC© BP Exploration 1989 - 2001 All Rights Reserved GUIDANCE ON CERTIFICATION SECTION 9.0 GOC© AMERICAS EDITION REVISION: 1 SUBJECT: xiii) ELECTRICAL PAGE: 31 When required, perform a DC over-potential test on each run of Bus Duct, phase to phase and phase to ground. Potential application shall be in accordance with the following table: Over-potential Test Voltage Rated kV DC Test Voltage KV 5 20.0 15 37.5 35 55.0 Witnessing Authority to Verify Test results are evaluated on a pass/fail basis by slowly raising the test voltage to the required value and holding the final test voltage for one minutes, then reducing test voltage slowing to zero. Record data. 2.1.2 Certification Certificates EE2 Sheet 01 and 02 and EE16 Sheet 01 are to be used for recording the results of the testing and requires endorsement to confirm that all the requirements of this procedure, and Procedure 9.15 if appropriate, have been performed satisfactorily. Originals of test certificates generated by implementing Procedure 9.20 (Protective Relay Testing) must be attached to EE2 Sheet 01. NOTE: See Bus Duct Inspection Checkout Sheet for megger test and bus phasing required for Witnessing Authority to Verify. GOC© BP Exploration 1989 - 2001 All Rights Reserved GUIDANCE ON CERTIFICATION SECTION 9.0 GOC© AMERICAS EDITION REVISION: 1 SUBJECT: ELECTRICAL PAGE: 32 ELECTRICAL PROCEDURES Procedure No. 9.3 3.1 Circuit Breakers - Air, Molded Case, Vacuum and Oil Immersed 3.1.1 General a) Refer to manufacturer’s test specs. b) The following procedures are applicable to circuit breakers in metal clad switchgear, Motor Control Centers, or dedicated enclosures. This procedure should follow after Procedure 9.2 tests are completed so main bus and control circuits can be safely energized. 3.1.2 a) Inspection Pre-Installation i) Carry out the Pre-installation checks of Procedure 9.2, to be sure all required materials and parts required have been accounted for and installed. b) Inspection Check Out The following inspection check out for Draw-out Air Circuit Breaker can assist in the realization and acceptance of the EE3 Sheet 01 Certificate. NOTE: The Inspection Checkout must be completed prior to final tests under EE3 Sheet 01 Certificate, for all draw-out circuit breakers. c) Testing required by EE3 Sheet 01 must be completed on every draw-out breaker and trip unit prior to placing same in service. Witnessing Authority to Verify GOC© BP Exploration 1989 - 2001 All Rights Reserved GUIDANCE ON CERTIFICATION SECTION 9.0 GOC© AMERICAS EDITION REVISION: 1 SUBJECT: ELECTRICAL PAGE: 33 DRAW-OUT AIR CIRCUIT BREAKER INSPECTION CHECKOUT (Procedure 9.3) DATE: PROJECT NO: SLD No LOCATION: SHT MODULE: INITIAL/DATE TAG NO: __________________________________________________ One at a time, insert breakers into their respective cubicles and check the following: (TURN ON CONTROL POWER SOURCE) 1. Roll breaker into the “TEST” position. The spring charging mechanism should engage 1 to charge the closing spring (on electrically operated mechanisms). 2. Withdraw breaker to the “DISCONNECT” position. 2 3. Roll breaker into the ‘TEST” position. Close breaker using door switch and check 3 indication light for operation. Close breaker from remote control station where applicable, using “Local/Remote” switch set to “Remote.” 4. ** Trip breaker and check indication light. Trip from door switch and remote control 4 station. 5. ** Trip each breaker from each protective device and check relay targets for operation. 5 Test proper operation of lockout device in closing circuit. NOTE: Observe manufacturer’s instructions on limiting consecutive close operations. 6. ** Trip each breaker with its mechanical trip device. 6 7. Check contact alignment and wipe clean (air break only). 7 8. Perform Insulation Resistance Test (megger) between each phase and across open 8 pole to frame and ground with breaker withdrawn. Repeat test between each phase with breaker closed. Record below. Ground all poles not being tested. 9. Perform contact resistance test and record below. 9 10. Roll breaker into “CONNECTED” position and test operation of latch check switch, if 10 provided, and verify control interlocks are operable. 11. Verify nameplate data is in accordance with vendor drawing (continuous amperes, 11 interrupting amps, insulation resistance, contact resistance, etc.). Insulation Resistance: ∅A to G (closed) ∅B to G (closed) ∅C to G (closed) A B ∅AA to A (open) ∅BB to B (open) ∅CC to C (open) AA BB ∅A to ∅B ∅B to C ∅C to ∅A ∅A ∅B ∅C C Contact Resistance: CC (Micro Ohms) REMARKS: This inspection and test checkout is required for every draw-out breaker installed in an operating assembly. ** See Certificate Required (EE3 Sheet 01) and Witnessing Authority to Verify. GOC© BP Exploration 1989 - 2001 All Rights Reserved of GUIDANCE ON CERTIFICATION SECTION 9.0 GOC© AMERICAS EDITION REVISION: 1 SUBJECT: ELECTRICAL PAGE: 34 Post-Installation (After all breakers have been inspected and tested per the checkout sheet.) *NOTE: Carry out mechanical operation checks to ensure: i) Correct contact alignment and all breaker stab or cluster connections to the power bus for in-service positioning; Witnessing Authority to Verify Correct alignment and connection of all main and secondary plug and socket connectors for control and/or interlocking circuits; Correct operation of bus shutters and energy isolation mechanism; Correct fitting and operation of any special grounding features for the breaker frame. ii) Check operation of circuit breaker close and trip mechanism, manually and electrically. Witnessing Authority to Verify iii) Check the operation of all local and remote, mechanical and electrical interlocks and trip systems, including functions of selector switches. Witnessing Authority to Verify * NOTE: Some power breakers may not be draw-out type. ALL breakers except molded case require mechanical operation checks. Use D.O. Checkout List for guidance. iv) Ensure the appropriate requirements of Procedure 9.15 (Hazardous Locations) have been carried out if applicable. Witnessing Authority to Verify GOC© BP Exploration 1989 - 2001 All Rights Reserved GUIDANCE ON CERTIFICATION SECTION 9.0 GOC© AMERICAS EDITION REVISION: 1 SUBJECT: v) ELECTRICAL PAGE: 35 Check operation of grounding switch if this forms a part of the circuit breaker assembly. Witnessing Authority to Verify vi) Verify tightness of cable and bus connections with a calibrated torque wrench. Witnessing Authority to Verify vii) e) Check arc chute alignment and grounding Witnessing Authority to Verify Testing-Low Voltage (Molded Case) i) Refer to UL 489 “Circuit Breakers, Molded Case, and Circuit Breaker Enclosures,” and NEMA AB2 “Procedures for Field Inspection and Performance Verification of Molded Case Circuit Breakers Used in Commercial and Industrial Applications” for testing guidelines. ii) The following tests are to be performed as required by BP and per Certificate EE3 Sheet 02. • Contact resistance shall be measured. Resistance shall be compared to adjacent poles and similar breakers. Deviations of more than 50% shall be investigated. • Time-current characteristic tests shall be performed by passing 300% rated current through each pole separately, except wherein breaker is equipped with ground fault protection. (See manufacturer’s information for test method for breakers with built-in GFP.) Trip times shall fall within the values in the table below: Witnessing Authority to Verify GOC© BP Exploration 1989 - 2001 All Rights Reserved GUIDANCE ON CERTIFICATION SECTION 9.0 GOC© AMERICAS EDITION REVISION: 1 SUBJECT: ELECTRICAL PAGE: 36 Values for Overcurrent Trip Test (at 300% of rated continuous current of breaker) Tripping Time, Seconds Minimum Maximum Range or Voltage, Volts ∗ Rated Cont. Thermal Breakers Magnetic Breakers Maximum Maximum Trip Times Current for Cable Amperes Protection* 240 15-45 3 - 50 100 sec 240 50-100 5 - 70 200 sec 600 15-45 5 5 80 100 sec 600 50-100 5 5 150 200 sec 240 110-225 10 5 200 300 sec 600 110-225 10 - 200 300 sec 600 250-450 25 - 250 300 sec 600 500-600 25 10 250 350 sec 600 700-1200 25 10 450 600 sec 600 1400-2500 25 10 600 750 sec These values are based on heat tests conducted by circuit breaker manufacturers on conductors in conduit. NEMA Reference. • Instantaneous pickup current shall be determined by pulse method. Clearing times should be within four cycles. Instantaneous pickup current levels should be within 20% of manufactures published values. Witnessing Authority to Verify • Insulation resistance tests shall be performed pole to pole, across open pole and pole to ground. Test voltage shall be 1000VDC. Witness Authority to Verify GOC© BP Exploration 1989 - 2001 All Rights Reserved GUIDANCE ON CERTIFICATION SECTION 9.0 GOC© AMERICAS EDITION REVISION: 1 SUBJECT: f) ELECTRICAL PAGE: 37 Testing - Low Voltage (Air) Refer to ANSI/IEEE C37.13, “IEEE Standard for Low-Voltage AC Power Circuit Breakers Used in Enclosures” for testing guidelines. Also, see Certificate EE3 Sheet 01. The following tests are to be performed as required by BP: • Contact resistance shall be measured. Resistance values greater than 200 micro-ohms or any value deviating from adjacent poles or similar breakers more than 50% should be investigated. Witnessing Authority to Verify • Insulation resistance tests shall be performed from pole to pole, pole to ground and across the open contacts of each phase at 1000VDC. Insulation resistance shall not be less than 50 megohms. • Minimum pick-up current shall be determined by primary current injection. Witnessing Authority to Verify • Long time delay shall be determined by primary injection at 300% of pick-up current. Witnessing Authority to Verify • Short time pick-up and time delay shall be determined by primary injection at intended settings per specs. Witnessing Authority to Verify • Instantaneous pick-up current shall be determined by primary injection. Witnessing Authority to Verify GOC© BP Exploration 1989 - 2001 All Rights Reserved GUIDANCE ON CERTIFICATION SECTION 9.0 GOC© AMERICAS EDITION REVISION: 1 SUBJECT: ELECTRICAL • PAGE: 38 Trip unit reset characteristics shall be verified by test per manufacturer’s instructions. Witnessing Authority to Verify • Auxiliary protective devices, such as ground fault or under voltage relays, shall be activated and simulate operation of shunt trip devices to verify operation. Witnessing Authority to Verify • Minimum pickup current, trip times and instantaneous pick-up values shall be set per the settings reflected by the IFC data sheets. Test values should fall within the Manufacturer’s published time-current characteristic tolerance band for all settings and curves applicable. Witnessing Authority to Verify g) Testing - Medium Voltage (Air) i) Refer to ANSI/IEEE C37.09 “Test Procedures for AC HighVoltage Circuit Breakers Rated on a Symmetrical Current Basis” for testing guidelines. Also, see Certificate EE3 Sheet 03 required. ii) The following tests are to be performed as required by BP: • Measure contact resistance. Resistance values shall not exceed 500 micro-ohms. Consult the manufacturers recommendations for acceptable range. Witnessing Authority to Verify • Perform minimum pick-up voltage tests on trip and close coils with calibrated voltmeter and adjustable source. Record data. Witnessing Authority to Verify GOC© BP Exploration 1989 - 2001 All Rights Reserved GUIDANCE ON CERTIFICATION SECTION 9.0 GOC© AMERICAS EDITION REVISION: 1 SUBJECT: ELECTRICAL • PAGE: 39 Circuit breaker shall be tripped by operation of each protective device by simulation. Witnessing Authority to Verify • Perform insulation resistance test pole-to-pole, pole-toground and across the open contacts of each phase. Use 2500 V.D.C. megger. Witnessing Authority to Verify • Perform insulation resistance test at 1000VDC on all control wiring. Use care to isolate electronics as necessary per manufacturer instructions. Witnessing Authority to Verify • Perform over-potential tests, or power factor test with breaker in the open and closed position. All arc chutes shall be tested for watt loss. Power factor and arc chute watt loss must be no greater than manufacturers allowable values. (see Section 9.2.1.c) ii) for overpotential test voltages) Witnessing Authority to Verify h) Testing - Medium Voltage (Oil) The following tests are to be performed as required by BP: (Refer to N.E.T.A. Acceptance Testing Specs for M.V. Oil breakers. Also refer to Certificate EE3 Sheet 04 required.) • Measure contact resistance on each breaker pole. Contact resistance shall not be greater than 500 microohms. Witnessing Authority to Verify • Perform insulation resistance test pole to pole, pole to ground and across the open contacts of each phase. Witnessing Authority to Verify GOC© BP Exploration 1989 - 2001 All Rights Reserved GUIDANCE ON CERTIFICATION SECTION 9.0 GOC© AMERICAS EDITION REVISION: 1 SUBJECT: ELECTRICAL • PAGE: 40 Perform over-potential tests, or power factor test with breaker in the open and closed position. All arc chutes shall be tested for watt loss. Power factor and arc chute watt loss must be no greater than manufacturers allowable values. (See Section 9.2.1.c)ii) for over- potential test voltages.) Witnessing Authority to Verify • Draw oil samples. Perform dielectric strength tests. The dielectric strength of each sample shall not be less than 26KV when tested with the 0.1 inch gap in accordance with ANSI/IEEE Standard C-57.106 (Guide for Acceptance and Maintenance of Insulating Oil in Equipment). Witnessing Authority to Verify • Circuit breaker shall be tripped by manual and/or electrical operation of each protective device. Witnessing Authority to Verify i) Testing - Medium Voltage (Vacuum) i) Refer to ANSI/IEEE C37.09 “Test Procedures for AC HighVoltage Circuit Breakers Rated on a Symmetrical Current Basis” for testing guidelines. NOTE: recommended checks for proper contact travel and perform same. ii) The following tests are to be performed as required by BP: • Measure contact resistance. Resistance values shall not exceed 500 micro-ohms. Consult the manufacturers recommendations for acceptable range. Witnessing Authority to Verify • Perform minimum pick-up voltage tests on trip and close coils. Witnessing Authority to Verify GOC© BP Exploration 1989 - 2001 All Rights Reserved GUIDANCE ON CERTIFICATION SECTION 9.0 GOC© AMERICAS EDITION REVISION: 1 SUBJECT: ELECTRICAL • PAGE: 41 Circuit breaker shall be tripped by operation of each protective device. Witnessing Authority to Verify • Perform insulation resistance test pole-to-pole, pole-toground and across the open contacts of each phase. Witnessing Authority to Verify • Perform insulation resistance test at 1000VDC on all control wiring. Witnessing Authority to Verify • Perform over-potential tests, with breaker in the open and closed position. Apply test voltages per manufacturer’s recommendations. Witnessing Authority to Verify • 3.1.3 Perform vacuum integrity tests per manufacturer’s specifications. Witnessing Authority to Verify Certification a) Form EE3 Sheets 1 - 4 are to be used for recording the results of the testing and requires endorsement to confirm that all the requirements of this procedure and Procedures 9.3 and 9.15, if appropriate, have been performed satisfactorily. Originals of test certificates generated by implementing Procedure 9.20 for protective relays must be attached to EE3. GOC© BP Exploration 1989 - 2001 All Rights Reserved GUIDANCE ON CERTIFICATION SECTION 9.0 GOC© AMERICAS EDITION REVISION: 1 SUBJECT: ELECTRICAL PAGE: 42 ELECTRICAL PROCEDURES Procedure No. 9.4 4.1 (a) Contactor Starters and (b) Variable Frequency Drives 4.1.1 Inspection 4.1.1.1 Pre-Installation (After Shipping Inspection) a) Remove packing material from contactors and drives, including silica gel, taping and /or binding materials from moving parts/assemblies. b) Inspect and clean out enclosures. Initiate damage repairs if required. c) Locate and check parts, devices, instructions and/or special tools required for assembling equipment or installation in assigned enclosures. 4.1.1.2 Post-Installation a) Compare unit descriptions with the IFC data sheets and Vendor drawings, and perform the following inspections: i) Ensure that the isolating switch can be locked in the ‘off’ position and that operating handle is mechanically interlocked with the door. ii) Inspect and check the operation of the isolator and any auxiliary switches or contacts mounted with it. iii) For draw-out or plug-in starters, check the fit of the withdrawal unit and alignment of main and auxiliary circuit contacts, including plug-ins. GOC© BP Exploration 1989 - 2001 All Rights Reserved GUIDANCE ON CERTIFICATION SECTION 9.0 GOC© AMERICAS EDITION REVISION: 1 SUBJECT: iv) ELECTRICAL PAGE: 43 Test the mechanical operation of all contactors and relays including alignment of moving contacts. v) Compare the main and control fuse ratings with the drawings and/or fuse tables in the equipment specs. vi) Examine the internal wiring for security and ensure that it is not being caught or damaged by the door or draw-out unit. vii) Make sure that the door is bonded to the enclosure and the enclosure is properly grounded. viii) Ensure the position and operation of control switches, lamps and push buttons is satisfactory and that the colors are per code. ix) Check any meters for correct/suitable scales. x) Ensure that any space heaters, if required, are in the correct position, not too close to any internal wiring or heat sensitive devices. Verify voltage and wattage rating. xi) Examine arc chutes, phase separators and other insulating components to be clean and in good condition. xii) Ensure the appropriate requirements of Procedure 9.15 for Hazardous Locations have been met (if required). xiii) Perform inspection of associated field equipment. xiv) Check VSD equipment for any special devices or auxilliary requirements needed. GOC© BP Exploration 1989 - 2001 All Rights Reserved GUIDANCE ON CERTIFICATION SECTION 9.0 GOC© AMERICAS EDITION REVISION: 1 SUBJECT: 4.1.1.3 ELECTRICAL PAGE: 44 Testing a) Contactor Starters i) Test overloads by primary injection through the load bus and monitoring trip time. Overload test should be performed at 300% of motor full load current. Trip times shall be in accordance with manufacturer’s tolerances. Record the results on the relevant Test Certificate EE4 Sheet 01. Witnessing Authority to Verify ii) Test the overload relay for single phasing by passing 80% of full load current through two phases only and record the result on Test Certificate EE4 Sheet 01. Witnessing Authority to Verify iii) Test the calibration of any local/remote ammeters by primary injection; secondary injection shall only be used for circuits outside the range of primary injection sets. Record on Test Certificate EE4 Sheet 01. Witnessing Authority to Verify iv) v) Test and record the starter insulation resistance using: • 1000V test for power wiring - minimum value should be 10 Megohms. Use same technique as in 9.1.1.d. • 500V test for control wiring - minimum value should be 5 Megohms. (Isolate electronic devices per manufacturer’s instructions). Witnessing Authority to Verify Function test control circuit operations and indications from local and remote locations. Witnessing Authority to Verify GOC© BP Exploration 1989 - 2001 All Rights Reserved GUIDANCE ON CERTIFICATION SECTION 9.0 GOC© AMERICAS EDITION REVISION: 1 SUBJECT: vi) ELECTRICAL PAGE: 45 Perform any required testing of protective relaying or meter circuitry in accordance with Procedure 9.20 - attach test sheets to EE4 Sheet 01. Witnessing Authority to Verify vii) Where test certificates are available for tests performed by the vendor, these should be attached to the EE4 Certificates, or identified as being performed with comments in the appropriate ITS against the EE4 requirement. The original vendor test certificate remains in the vendor dossier. In cases where vendor testing was not performed, the following should be completed: • Check the thermal overloads and ground fault relays against the starter tabulations to ensure that the installed relays have the correct setting range and set point adjustments. • The setting range and set point should be noted on Certificate EE4 Sheet 01 in the “overload trip setting” column. • Where changes to the overloads have been made, or the markings have been lost, a complete re-test shall be performed. • In other cases sample points can be performed to ensure the device is still within manufacturers tolerances. GOC© BP Exploration 1989 - 2001 All Rights Reserved GUIDANCE ON CERTIFICATION SECTION 9.0 GOC© AMERICAS EDITION REVISION: 1 SUBJECT: b) ELECTRICAL PAGE: 46 Variable Speed Drive (VSD) Tests For new installations involving VSDs, motors and drives should be tested at the Manufacturer’s shop in accordance with a testing program which is required by the Project specifications. Including any tests appropriate to the VSD in the Manufacturer’s shop, Variable Speed Drives incorporating solid state variable speed controllers should be tested together with their motors as installed/applied. Tests must include driven equipment at either the driven equipment manufacturer’s shop or other suitable location, after completion of the individual component tests. In some cases, if approved by Project specifications, VSD protype testing may be allowed to demonstrate an acceptable application. This does not eliminate the need for field testing with the driven equipment. Additional tests should include: i) Motor temperature rise test under load, across the specific speed range required. (BP shall, subject to approval of the testing methods by an Independent Certifying Authority, approve certification of the motor for variable speed duty in a hazardous area. The VSD unit itself must also be considered.) Witnessing Authority to Verify ii) Motor vibration test across the required speed range at no load. Witnessing Authority to Verify iii) Motor noise test across the speed range shall be in accordance to BP’s RP 14-1 Guide to Noise Control. Witnessing Authority to Verify GOC© BP Exploration 1989 - 2001 All Rights Reserved GUIDANCE ON CERTIFICATION SECTION 9.0 GOC© AMERICAS EDITION REVISION: 1 SUBJECT: ELECTRICAL PAGE: 47 Prior to On-site test runs, the installation checks for the fixed power supply portion of the VSD should be completed as required by Procedure 9.4. Form EE4 - Sheet 03 to cover additional Vendor checks for On-site testing of the motor with the VSD permanent controller. NOTE: Load banks may be required for complete VSD testing. Reference to Amoco’s A EL-VFD-00-G Electrical - AC Variable Frequency Drives Guide and/or BP’s RP 12-12 Electrical Vazriable Speed Drives should be made for additional information on installation and testing requirements. 4.1.2 Certification Form EE13 and EE4 Sheet 03 shall be used for recording the results of the testing and requires endorsement to confirm that the requirements of this procedure, (and Procedure 9.15 if appropriate), have been performed satisfactorily. If applicable, the results of the drying out motor windings, Procedure 9.17, are to be attached to Form EE13, together with any certificates generated by implementing Procedure 9.20. For Variable Speed Drives, EE4 for power supply refer to Procedure 9.4 and Form EE16 to cover additional Vendor checks for On-site testing of the motor with the VSD permanent controller. Originals of test certificates generated by implementing Procedure 9.20 (Protection Relay and Metering Circuit Testing) must be attached to EE4. NOTE: Form EE4 verifies that the contactor/starter circuit including remote field equipment forming part of the circuit is installed and tested satisfactorily. GOC© BP Exploration 1989 - 2001 All Rights Reserved GUIDANCE ON CERTIFICATION SECTION 9.0 GOC© AMERICAS EDITION REVISION: 1 SUBJECT: ELECTRICAL PAGE: 48 ELECTRICAL PROCEDURES Procedure No. 9.5 5.1 Medium Voltage Air Switches 5.1.1 a) Inspection Pre-Installation i) Note the nameplate ratings of the air switch. Compare these ratings with those on the approved drawings, and be sure the switch installation instructions are included. ii) Remove any transit packing materials (where used). iii) Ensure that the fuse switch unit has been labeled correctly. iv) Check that the interior of the unit has been cleaned and any silica gel drying agents have been removed. v) b) Verify shipment includes all necessary field assembly parts and detail items. Post-Installation Refer to ANSI/IEEE C37.34 “American National Standard Test Code for High-Voltage Air Switches” for testing guidelines. i) Verify switch unit is mounted level and plumb, and inspect the air switch compartment for any signs of damage during installation. [Initiate any necessary repair action, check and torque bus connections.] ii) Inspect the mechanical operation of the air switch. Check for any required, mechanical or key interlocks installed in the GOC© BP Exploration 1989 - 2001 All Rights Reserved GUIDANCE ON CERTIFICATION SECTION 9.0 GOC© AMERICAS EDITION REVISION: 1 SUBJECT: ELECTRICAL PAGE: 49 air switch cubicle or cover. Inspect the equipment lock-out mechanism for proper operation. iii) Verify external wiring for electrical interlocks, remote indications, and/or electric space heater power is installed. iv) Verify the contact alignment of the air switch and the mechanical operation of the on-off indication. Make any adjustment checks per manufacturer’s instructions. v) Verify all necessary operating handles are provided, and properly stowed or retracted. vi) Ensure all necessary grounding bus and/or cables are installed and properly connected. vii) Measure one minute insulation resistance through the closed switch (phase to phase and each phase to ground), and pole to pole across the open switch. [Use megger voltage per 9.2.1.1 d).] Witnessing Authority to Verify viii) Perform DC contact resistance test across each switch blade (closed), when directed by BP. Any value exceeding 50 micro-ohms or any values that deviate from adjacent poles or similar switchs by more than 50% shall be investigated. Witnessing Authority to Verify ix) Verify the bus connections and mechanical throat alignment from switch to load (i.e., transformer) are properly made up after all switch testing is completed. Witnessing Authority to Verify GOC© BP Exploration 1989 - 2001 All Rights Reserved GUIDANCE ON CERTIFICATION SECTION 9.0 GOC© AMERICAS EDITION REVISION: 1 SUBJECT: x) ELECTRICAL PAGE: 50 Perform any required testing of associated protective relaying and/or meter circuitry in accordance with Procedure 9.20. If switch is supplied with internal C.T.’s, verify ratings and test as done for MV switchgear C.T.’s 5.1.2 a) xi) Ensure the appropriate requirements of Procedure 9.15 are performed if applicable, for Hazardous Locations. xii) Check to see correct MV fuses are available per circuit requirements on approved drawings. Certification Form EE5 Sheet 01 is to be used for recording the results of the testing and requires endorsement to confirm that the requirements of this procedure, and Procedure 9.15 if appropriate, have been performed satisfactorily. Originals of test certificates generated by implementing Procedure 9.20 must be attached to EE5 Sheet 01. GOC© BP Exploration 1989 - 2001 All Rights Reserved GUIDANCE ON CERTIFICATION SECTION 9.0 GOC© AMERICAS EDITION REVISION: 1 SUBJECT: ELECTRICAL PAGE: 51 ELECTRICAL PROCEDURES Procedure No. 9.6 6.1 Power Transformers; Oil Filled and Dry Type 6.1.1 a) Inspection Pre-Installation (Oil Filled and Dry Type) i) Inspect unit for any physical damage including dents or scraped paint. If unit is shipped with an impact recorder, check data before unloading transformer. ii) Ensure equipment certification meets the area and specification requirements. Review nameplate data and information on special attachments or auxiliary devices. Compare all with approved drawings. b) Post-Installation (Oil Filled) i) Inspect the transformer and auxiliary equipment for alignment and tightness of anchor bolts and fasteners in general. Inspect the installation and weatherproofing of the terminal boxes. Verify auxiliary device operation (fans, pumps, sudden pressure device, indicators, tap changer and gas pressurization system). Complete all items on Inspection Checkout sheets. ii) Inspect the lock out provisions for unit mounted disconnect switches and tap change. iii) Inspect the grounding pads and the grounding connections to the ground grid per installation drawings, verifying proper bolts, cable size and type, and connectors. GOC© BP Exploration 1989 - 2001 All Rights Reserved GUIDANCE ON CERTIFICATION SECTION 9.0 GOC© AMERICAS EDITION REVISION: 1 SUBJECT: iv) ELECTRICAL PAGE: 52 Inspect the “XO” connection. If neutral grounding resistors have been installed, refer to Procedure 9.12 for detailed requirements. If no resistor, ensure that grounding cable or straps from “XO” to grid are per specifications. v) Check for proper oil level at ambient temperature. Check gasketed covers, radiator flanges and plugs, and auxiliary devices for any sign of leaks or seepage. vi) Check tank pressure/vacuum relief device (if supplied). Inspect the inert gas alarm device (i.e. nitrogen regulator for tank pressure) if used. vii) Inspect the mechanical pressure relief device (required on oil filled units). viii) Inspect tightness of bus bar connections and bracing from bushing terminals to bus bars of switchgear. Ensure adequate separation distances between high voltage cables for the terminal box connections. Verify terminations are per unit manufacturer’s drawings and installation specifications. c) Inspection Check Out The following Inspection Check Out for Liquid Filled Transformers is to assist in the realization and acceptance of the EE6 Sheets 01 & 03 Certificates. GOC© BP Exploration 1989 - 2001 All Rights Reserved GUIDANCE ON CERTIFICATION SECTION 9.0 GOC© AMERICAS EDITION REVISION: 1 SUBJECT: ELECTRICAL LIQUID FILLED TRANSFORMER INSPECTION CHECKOUT (Procedure 9.6) DATE: JOB NO: PAGE: 53 SLD No LOCATION: SHT 1 of 2 MODULE: INITIAL/DATE TAG NO: __________________________________________________ 1. Receiving Operations / Inspection complete, including any required details shipped with 1 the ordered unit. 2. Verify tag number, HV/LV ratings and KVA rating per plant drawings and one-line 2 diagram. 3. Check transformer nameplate against the purchase order and specifications. 3 4. Verify location, mountings and bushing orientation per drawings. 4 5. Visually inspect for cleanliness. No chips, cracks or other apparent damage to 5 bushings, radiators and tanks. Any paint scuffs or scratches must be repaired with approved methods and materials. 6. Check lubrication and freedom of operation and rotation of cooling fans. 6 7. Check lubrication and freedom of motion of no-load tap changers and control 7 accessories. 8. Inspect fuses, disconnect switches and lightning arrester installations as required. 8 9. Inspect for liquid leakage around tank, radiators and accessories. 9 10. Collect samples of insulating liquid per manufacturer’s instructions and verify dielectric 10 strength of insulating liquid. Take laboratory samples for complete analysis of insulating liquid. 11. Check for nameplate winding continuity between bushings. 11 12. Verify neutral wire size, insulation and color per drawings / schedule. 12 13. Verify case ground (and grounding resistor if required) correctly installed. Measure, 13 bonding resistance of connections and record a Test Certificate. 14. Check that incoming feeders have had all insulation Resistance Tests performed, and 14 verify test data as acceptable per Certificate. 15. Check inert gas pressure gauge (pressure should be in accordance with manufacturers 15 instructions), and verify pressure relief settings. 16. Check temperature gauge for proper operation. 16 17. Check liquid level gauge for proper operation and proper level of liquid in all oil filled 17 compartments. REV. 1 GOC© BP Exploration 1989 - 2001 All Rights Reserved GUIDANCE ON CERTIFICATION SECTION 9.0 GOC© AMERICAS EDITION REVISION: 1 SUBJECT: ELECTRICAL LIQUID FILLED TRANSFORMER INSPECTION CHECKOUT (Procedure 9.6) DATE: JOB NO: PAGE: 54 SLD No LOCATION: SHT 2 of 2 MODULE: INITIAL/DATE 18. Measure primary and secondary voltages with tap changer in each position and verify 18 that voltage ratios are per transformer nameplate. [Apply 480V construction power to transformer primary (HV) connections and measure secondary (LV) voltages. Primary voltage rating shall not be exceeded.] 19. Record transformer tap setting below. Set at mid-tap unless otherwise directed. 19 20. Check sudden pressure relay and connections (if supplied). 20 21. Verify alarm and control circuits connected and complete. Verify alarm, trip, and fan 21 start contacts are operational. High winding and/or liquid temperature alarm set at 90°C, or in accordance with manufacturer’s instructions. 22. Primary/secondary cables/bus duct properly supported, insulated and protected against 22 mechanical damage. Bolted connections torqued in accordance with manufacturer’s recommendations. 23. Check conductor size, insulation class and type for incoming/outgoing cables. 23 24. Check conductor phasing and identification. 24 25. Check conduit connections - need to be tight, sealed and oriented properly. 25 26. Perform Insulation Resistance Test of transformer primary and secondary windings, 26 and record reading on Test Record (Megger tests). (See 6.1.1.d). 27. Perform Insulation Power Factor Test, required by specifications (Doble or equal). 27 28. Check to assure connections are tight and secure after testing. 28 29. Verify mechanical relief device is reset. 29 30. Verify spare control/alarm conductors taped or capped, and tagged. 30 31. Verify spare hubs or knockouts plugged with seals intact. 31 32. Verify paint scratches refinished. 32 33. Verify access covers tightly secured, with gaskets all in place. 33 34. Vendor Representative provided service supervision for this equipment Vendor test 34 reports attached to this Inspection Record. 35. Final inspection complete. Punch list items cleared. Transformer Tap GOC© BP Exploration 1989 - 2001 All Rights Reserved 35 GUIDANCE ON CERTIFICATION SECTION 9.0 GOC© AMERICAS EDITION REVISION: 1 SUBJECT: d) ELECTRICAL PAGE: 55 Testing (Oil Filled) i) Test the alarm and trip circuits of all protective devices on the unit. Witnessing Authority to Verify ii) Ensure that all cables have been tested and checked in accordance with the cable Certificate required (See EE1 Sheets 01 thru 03) Witnessing Authority to Verify iii) Measure ground continuity, XO, Resistor and tank to ground grid. Witnessing Authority to Verify iv) Breakdown Voltage tests, when required, shall be made on two oil samples from each transformer and each barrel, container or fraction thereof used to fill the transformer with oil. The dielectric strength of each sample shall not be less than 26KV when tested with the 0.1 inch gap in accordance with ANSI/IEEE Standard C-57.106, “Guide for Acceptance and Maintenance of Insulating oil in Equipment.” Witnessing Authority to Verify v) Measure the insulation resistance for both the HV and LV windings. Test primary (HV) winding insulation to ground with the tank and secondary (LV) winding grounded using a battery or motor operated megger. Test secondary winding insulation to ground with the tank and primary winding grounded. Test the primary winding to secondary winding. The minimum acceptable insulation resistance in megohms is 8 times the KV rating of the winding under test. Megger test voltages shall be in accordance with the values for bus duct in the table in section 9.2.1.c).i) and corrected for ambient temperature in accordance with the conversion table at the end of this section. Ground all terminals to fully discharge any residual voltage after completing tests. GOC© BP Exploration 1989 - 2001 All Rights Reserved GUIDANCE ON CERTIFICATION SECTION 9.0 GOC© AMERICAS EDITION REVISION: 1 SUBJECT: ELECTRICAL PAGE: 56 Witnessing Authority to Verify vi) A dielectric absorption test, when required, shall be made winding-to-winding and winding to ground for 10 minutes. The polarization index shall be computed. Test voltage and minimum acceptance values shall be in accordance with the Manufacturer’s recommendations and corrected for ambient temperature in accordance with the conversion table at the end of this section. The absorption test polarization index should be above 2.0 unless the scale value on the available test equipment prevents a meaningful ratio. Witnessing Authority to Verify vii) An AC over-potential test, when required, shall be made on all high and low voltage windings to ground. The AC high potential test voltage shall not exceed 75% of the factory test voltage for a one minute duration. (See following table for factory test voltages). Witnessing Authority to Verify NOTE: When performing all high voltage insulation tests, a regulated power supply for the test equipment shall be provided and used. Variations in operating power during test runs may result in exceeding the recommended high limit for testing. GOC© BP Exploration 1989 - 2001 All Rights Reserved GUIDANCE ON CERTIFICATION SECTION 9.0 GOC© AMERICAS EDITION REVISION: 1 SUBJECT: ELECTRICAL PAGE: 57 Over-Potential Test Voltage for Power and Distribution Transformers Nominal System Voltage* Insulation Class AC Factory Test (KV) Oil (KV) Immersed ** 1.2 1.2 10 2.4 2.5 15 4.8 5.0 19 8.32 8.7 26 14.4 15.0 34 18.0 18.0 40 25.0 25.0 50 34.5 34.5 70 46.0 46.0 95 69.0 69.0 140 * Intermediate voltage ratings are placed in the next higher insulation class. ** Also Applies to silicone or other liquid immersed, following manufacturer’s recommendations. viii) No-load tap changer settings on all transformers shall be set in accordance with the engineers instructions, or on mid-tap if not otherwise instructed. Witnessing Authority to Verify ix) Power factor test results corrected to 20° C should not exceed: 1 percent for distribution transformers (up to 500 KVA). ½ percent for power transformers of 500 KVA and above. Bushing P.F. tests results (hot collar or ungrounded tests) should be within manufacturers published tolerances. x) Turns ration test results (required for each tap position) should not deviate more than ½ percent from the GOC© BP Exploration 1989 - 2001 All Rights Reserved GUIDANCE ON CERTIFICATION SECTION 9.0 GOC© AMERICAS EDITION REVISION: 1 SUBJECT: ELECTRICAL PAGE: 58 calculated ratio, and phases should all correlate for each tap setting. Witnessing Authority to Verify e) Post Installation (Dry Type) i) Note the nameplate ratings of the transformers, and any special instructions concerning auxiliary apparatus. Compare these ratings with those on the approved drawings. Inspect for any internal damage. ii) Ensure equipment certification specification requirements. meets the area and iii) Verify proper auxiliary device operation such as fans, indicators and tap changer are provided per specifications. iv) Check tightness of accessible bolted electrical joints with a calibrated torque wrench. v) Verify ‘clear space’ requirements for proper cooling provided on transformer nameplate with measured clearances as installed. f) Testing (Dry Types) Refer to ANSI/IEEE C57.12.01, “General requirements for DryType Distribution and Power Transformers” for testing guidelines. i) Measure the insulation resistance for both the HV and LV windings. Test primary winding insulation to ground with the tank and secondary winding grounded using a 1000V (battery or motor operated), megger. Test secondary winding insulation to ground with the enclosure and primary winding grounded. Test the primary winding to secondary winding. GOC© BP Exploration 1989 - 2001 All Rights Reserved GUIDANCE ON CERTIFICATION SECTION 9.0 GOC© AMERICAS EDITION REVISION: 1 SUBJECT: ELECTRICAL PAGE: 59 The minimum acceptable insulation resistance in megohms is 8 times the KV rating of the winding under test. Test voltages shall be in accordance with the values for bus duct in the table in section 9.2.1.c).i) and corrected for ambient temperature in accordance with the conversion table at the end of this section. Winding resistance test results should compare within 1% of adjacent windings. Witnessing Authority to Verify ii) A dielectric absorption test, when required, shall be made winding-to-winding and winding to ground for 10 minutes. The polarization index shall be computed. Test voltage and minimum acceptance values shall be in accordance with the Manufacturer’s recommendations. Test voltages shall be in accordance with the values for bus duct in the table in section 9.2.1.c).i) and corrected for ambient temperature in accordance with the conversion table at the end of this section. The absorption test polarization index should be above 2.0 unless an extremely high value is obtained at the end of one such that additional time value will not yield a meaningful result with the available test equipment. Witnessing Authority to Verify iii) When required, a turns ratio test shall be performed between windings for all tap positions. The final tap setting to be left is to be determined by the engineer. Turns ratio test results should not deviate more than (½ %) from the calculated ratio. Phase test data should agree also. Witnessing Authority to Verify iv) An AC over-potential test, when required, shall be made on all high and low voltage windings to ground. The AC high potential test voltage shall not exceed 75% of the factory test voltage for a one minute duration. Evaluation shall be on a go no-go basis. NEMA Standard ST-20. GOC© BP Exploration 1989 - 2001 All Rights Reserved GUIDANCE ON CERTIFICATION SECTION 9.0 GOC© AMERICAS EDITION REVISION: 1 SUBJECT: ELECTRICAL PAGE: 60 Witnessing Authority to Verify Applied Potential Test Voltages Nameplate Winding v) Factory Test Voltage Rating Potential Volts A.C. (KV) A.C. 0 - 250 2.5 251 1201 2501 - 1200 2500 5,000 4.0 10.0 12.0 5001 8661 - 8660 15,000 19.0 31.0 As an alternative to the AC over-potential test, when required, insulation power factor tests shall be made from each winding to each other winding and from each winding to ground. Power factor test values in excess of 3% should be investigated. (Test equipment must be Doble type or equivalent.) vi) 6.1.2 Winding resistance tests, when required, shall be made for each winding at full turns. Witnessing Authority to Verify Certification for Transformers Forms EE6 sheets 1 thru 3 are to be used for recording the results of the testing and requires endorsement to confirm that the requirements of this procedure have been performed satisfactorily. All supplementary procedures should be completed as reference on the appropriate Certificates EE6 Sheet 01 , 02 & 03 and EE7 Sheet 01, namely neutral grounding resistors Procedure 9.12, GOC© BP Exploration 1989 - 2001 All Rights Reserved GUIDANCE ON CERTIFICATION SECTION 9.0 GOC© AMERICAS EDITION REVISION: 1 SUBJECT: ELECTRICAL PAGE: 61 transformer and link box oil testing Procedure 9.16 and Certificates generated by implementing Procedure 9.20 for protective relays. Witnessing Authority to Verify Insulation Resistance Conversion Factors for Conversion of Test Temperature to 20°°C Transformer Temperature °C 0 °F 32 Oil 0.25 Dry 0.40 5 41 0.36 0.45 10 50 0.50 0.50 15 59 0.75 0.75 20 68 1.00 1.00 25 77 1.40 1.30 30 86 1.98 1.60 35 95 2.80 2.05 40 104 3.95 2.50 45 113 5.60 3.25 50 122 7.85 4.00 55 131 11.20 5.20 60 140 15.85 6.40 65 149 22.40 8.70 70 158 31.75 10.00 75 167 44.70 13.00 80 176 63.50 16.00 GOC© BP Exploration 1989 - 2001 All Rights Reserved GUIDANCE ON CERTIFICATION SECTION 9.0 GOC© AMERICAS EDITION REVISION: 1 SUBJECT: ELECTRICAL PAGE: 62 ELECTRICAL PROCEDURES Procedure No. 9.7 7.1 Motors, A.C. Induction 7.1.1 a) Inspection Pre-Installation i) Check nameplate data on the motor(s) and compare with approved drawings and motor schedule. Tag motors for location code. ii) Ensure requirements for Hazardous Locations, per 9.15 have been meet, as indicated on motor nameplate. iii) Inspect for shipping damages and take any necessary corrective action. b) Post-Installation i) Ensure that any shaft blocking or shipping packing has been removed. Rotate shaft by hand to check freedom of movement. ii) Without dismantling the motor, inspect as far as possible, oil rings, oil levels, grease packing and bearings. Inspect for signs of leakage. Note manufacturer’s instructions may require flushing bearings prior to start up. iii) Inspect the paint finish of the motor for damage during installation. Any damage areas are to be repainted with compatible to original paint. GOC© BP Exploration 1989 - 2001 All Rights Reserved GUIDANCE ON CERTIFICATION SECTION 9.0 GOC© AMERICAS EDITION REVISION: 1 SUBJECT: iv) ELECTRICAL PAGE: 63 Inspect the weatherproofing and bolting of the connection boxes. This must not be dependent upon the application of paint, tape or plastic compounds for any sealing of the covers. Confirm conduit entry provisions are per installation drawings and schedules. v) Inspect the stator winding connection leads and verify star or delta terminals are per system supply. vi) Inspect frame grounding terminal and the connection to the ground grid system, including terminal lug and cable inside the connection box. c) Inspection Check Out The following inspection check out for Electric Motor Inspection is to be done to assist in the realization and acceptance of the EE13 Sheet 01 Certificate. GOC© BP Exploration 1989 - 2001 All Rights Reserved GUIDANCE ON CERTIFICATION SECTION 9.0 GOC© AMERICAS EDITION REVISION: 1 SUBJECT: ELECTRICAL ELECTRIC MOTOR INSPECTION CHECKOUT (Procedure 9.7) DATE: JOB NO: PAGE: 64 SLD No LOCATION: SHT of MODULE: INITIAL/DATE MOTOR TAG NO: ______________________ FUNCTION: __________________________ 1. Nameplate data agrees with motor list, plan drawings and one-line diagram. 1 2. Motors type is suitable for use in area classification. 2 3. Maximum Temperature Code, Per nameplate: 3 4. Check that the power and control cable insulation resistance tests are complete prior to 4 connection to motor. (See 9.2.1 d)). 5. For induction motors, perform insulation resistance test, using battery or motor operated 5 megger, 1000 V.D.C. 6. Grounding conductors installed, connected and bonded to frame, terminal box and grid. 6 7. Motor splices and terminations complete. Spare wires (pigtails) on multiple voltage 7 motors are properly insulated and tagged. 8. Motor electrical accessories are properly connected, such as space heaters, 8 thermocouples, vibration switches, RTDs. 9. Maximum overtemperature switch (such as a Klixon switch) is wired into the control 9 circuit, where such is required by drawings. 10. Ground bonding jumper installed, bolts and nuts are tightened at terminals. 10 11. Control station and motor lockout switch are installed and nameplate supplied. 11 12. Covers are installed, bolts and nuts are tightened. 12 13. Rotation checks OK. 13 14. Final inspection Complete. Punch list items cleared. 14 REMARKS REV. 1 GOC© BP Exploration 1989 - 2001 All Rights Reserved GUIDANCE ON CERTIFICATION SECTION 9.0 GOC© AMERICAS EDITION REVISION: 1 SUBJECT: d) ELECTRICAL PAGE: 65 Testing Procedures i) Refer to NEMA MG-1, Latest version, “Motors and Generators” for testing guidelines. ii) Ensure that all motor power cables have been certified in accordance with the cable test procedures. Check phase sequence and polarity of all connections for correct shaft rotation. iii) Motor insulation resistance shall be megger tested for one minute, and the values as calculated below shall be recorded per Checkout Sheet: • The minimum acceptable insulation resistance shall be determined by the formula: o C RM40 = kV + 1 megohm o Where RM40 C = minimum insulation resistance of the entire o machine winding in megohm at 40 C and kV = Rated machine potential in kilo-volts. Measure and record motor winding temperature by portable RTD meter, or by enclosure temperature by thermometer if no RTD’s are provided. Convert to 40°C value. • The observed resistance reading may be corrected to 40oC by applying the following formula and temperature coefficients: RM40oC = RM x T x Tc Where RM = insulation resistance in megohm, by test GOC© BP Exploration 1989 - 2001 All Rights Reserved GUIDANCE ON CERTIFICATION SECTION 9.0 GOC© AMERICAS EDITION REVISION: 1 SUBJECT: ELECTRICAL T= Tc = T Tc • PAGE: 66 winding temperature coefficient in oC, as measured temperature coefficient for the winding temperature 30 0.5 40 1.0 50 2.0 60 4.0 70 8.0 = = Temp. of winding Temp. Coefficient o Cold coil resistance (20 C and below) shall not be used. If winding is 20 oC or below, a heat source shall be used as hereinafter described to raise the internal temperature to 20 oC+. Witnessing Authority to Verify iv) If the insulation resistance is below the minimum value, the machine shall be dried out or replaced. Machine windings can be dried out by supplying heat from electric strip heaters, from heat lamps or by passing current through machine windings. Heat and some circulating air should be maintained until insulation resistance is acceptable - as corrected to 40oC. The winding temperature maintained during the drying-out process shall not exceed the following: • Class A Insulation (Class A is no longer in use.) Use Class B, F or H as applicable o By thermometer 80 C By resistance bridge or thermal sensing o resistor circuit (RTD) 90 C • Class B or F Insulation By thermometer 90 oC By resistance bridge or thermal sensing resistor circuit (RTD) 110 oC • GOC© The insulation resistance shall be taken at intervals of 2-3 hours during the drying-out process until a fairly BP Exploration 1989 - 2001 All Rights Reserved GUIDANCE ON CERTIFICATION SECTION 9.0 GOC© AMERICAS EDITION REVISION: 1 SUBJECT: ELECTRICAL PAGE: 67 constant value is reached. This value shall be a o minimum of, at 40 C: 1 Megohm per RATED KV of Motor +1 Witnessing Authority to Verify v) If special motor thermal sensing devices (e.g. RTD’s) have been installed, test their circuit continuity with a portable meter and record. Megger tests on RTD insulation resistance shall not exceed 250 V.D.C. for 15 seconds. NOTE: Thermocouples may be continuity checked by multi-meter battery only. permitted. vi) No ringer type testers are Measure the resistance and insulation resistance of motor winding space heaters and circuits (where specificed). Witnessing Authority to Verify vii) Verify that the motor starter, or variable frequency drive and associated protective relaying have been tested in accordance with Procedure 9.4. Witnessing Authority to Verify viii) Start the motor to determine the direction of rotation and compare this with the required rotation of the driven unit. Switch leads to correct if necessary, and record data. Witnessing Authority to Verify ix) Have the coupling open to separate the motor from the drive unit or the belts removed from the belt driven equipment. Ensure that the motor rotates freely by hand. Manually turn the shaft and check end play to be within tolerance. Motors shall be started and “run-in” uncoupled for 30 minutes for GOC© BP Exploration 1989 - 2001 All Rights Reserved GUIDANCE ON CERTIFICATION SECTION 9.0 GOC© AMERICAS EDITION REVISION: 1 SUBJECT: ELECTRICAL PAGE: 68 motors rated 200 horsepower and below, and for 2 hours for motors above 200 horsepower. Perform vibration tests on all 460V and higher voltage motors rated 200 horsepower and larger. Vibration amplitude values shall not exceed the values reflected by the NEMA Standard. Witnessing Authority to Verify NOTE: In some cases it may be impractical to run the motor uncoupled. Verify if the motor can be run driving the equipment, (e.g., flange mounted motors, axial fans, etc.) and run for the requested length of time if ok. x) Measure and record the line current of the free running motor. Readings taken on load to be noted on the Certificate applicable. Witnessing Authority to Verify xi) Have the coupling reassembled and the alignment of the coupling and end play checked (or have the belts put back on if belt driven) after the run test. Tag unit completed. Witnessing Authority to Verify 7.1.2 Certification Form EE13 Sheets 01 & 02 are to be used for recording the results of the testing and require endorsement to confirm that the requirements of this procedure and Procedure 9.15, if appropriate, have been performed satisfactorily. If applicable, the results of drying out motor windings, Procedure 9.17, are to be attached to Form EE13, together with any certificates generated by implementing Procedure 9.20. GOC© BP Exploration 1989 - 2001 All Rights Reserved GUIDANCE ON CERTIFICATION SECTION 9.0 GOC© AMERICAS EDITION REVISION: 1 SUBJECT: ELECTRICAL PAGE: 69 ELECTRICAL PROCEDURES Procedure No. 9.8 8.1 Batteries and Battery Chargers 8.1.1 a) Inspection Pre-Installation i) Note the nameplate rating of the charger(s), and number, type and rating of the batteries supplied. Compare with the ratings stated on the approved drawings for the equipment. ii) Ensure that the equipment Certificates meet the area classification and specification requirements, including any ventilation required. iii) Inspect the chargers and battery hardware for completeness of materials for assembly required. b) Post-Installation i) Inspect battery racks and batteries for proper assembly per manufacturer’s instructions. ii) Check grounding cables and terminations from charger frame to grid, and assembled racks to grid and bonding between per NEC and approved drawings. Torque all rack assembly bolts and grounding connections. iii) Ensure that all site installed cables have been tested in accordance with the Cable Test Certificate, see Procedure 9.1, EE1 Sheet 01 & 02. GOC© BP Exploration 1989 - 2001 All Rights Reserved GUIDANCE ON CERTIFICATION SECTION 9.0 GOC© AMERICAS EDITION REVISION: 1 SUBJECT: iv) ELECTRICAL PAGE: 70 Check cleanliness of battery rooms. Inspect and clean the interiors of all control panels and chargers. Remove any temporary silica-gel drying agents from panels and/or enclosures. v) Note the type, size and rating of all associated fuses and protective devices, and compare with those shown on the approved drawings and schedules. vi) Inspect all batteries for cracks, leaks or other damage. Check tightness and cleanliness of terminals, and connection, jumpers and straps. vii) Remove any shipping supports and store with the battery tools for possible future use. Maintain secure storage for all such items. viii) Inspect all bolted connections between individual cells in each bank of batteries. Ensure that all battery terminals, straps, posts, bolts, nuts, washers and cable lugs have been coated with anti-oxidizing compound. c) ix) Where applicable, inspect the battery electrolyte level in all cells after filling. Verify specific gravity and adjust electrolyte per manufacturer’s instructions. x) Where sealed, gas recombination, lead acid cells are used, check that cells have been trickle charged in accordance with manufacturers recommendations during storage. xi) Ensure that battery spaces are well ventilated and ventilation systems are operating properly where applicable. Inspection Check Out GOC© BP Exploration 1989 - 2001 All Rights Reserved GUIDANCE ON CERTIFICATION SECTION 9.0 GOC© AMERICAS EDITION REVISION: 1 SUBJECT: ELECTRICAL PAGE: 71 The following inspection check out for Battery and Battery Charger Inspection can assist in the realization and acceptance of EE14 Sheets 01 & 02 Certificates. GOC© BP Exploration 1989 - 2001 All Rights Reserved GUIDANCE ON CERTIFICATION SECTION 9.0 GOC© AMERICAS EDITION REVISION: 1 SUBJECT: ELECTRICAL BATTERY AND BATTERY CHARGER INSPECTION CHECKOUT (Procedure 9.8) DATE: JOB NO: PAGE: 72 SLD No LOCATION: SHT of MODULE: INITIAL/DATE TAG NO: ______________________ SYSTEM VOLTS: ____________________________ 1. Receiving Inspection complete. 1 2. Batteries and racks installed and checked for proper mechanical installation, including 2 connections and number of cells. 3. Grounding connection checked. ( MFS/ FCO) 4. Battery charger checked for proper installation, wiring complete and properly 3 4 connected. 5. Check charger nameplate against approved vendor drawings and site specific 5 specifications. 6. Accessory equipment accounted for, and itemized. 6 7. Batteries, battery racks and charger cleaned. 7 8. Terminals and interconnectors covered with protective compound. 8 9. Connection nuts and bolts torqued to XX foot pounds, per vendor instructions. 9 10. Fuses and circuit breakers in accordance with vendor drawings. 10 11. Final inspection complete. Punch list items cleared. 11 REMARKS REV. 1 GOC© BP Exploration 1989 - 2001 All Rights Reserved GUIDANCE ON CERTIFICATION SECTION 9.0 GOC© AMERICAS EDITION REVISION: 1 SUBJECT: d) ELECTRICAL PAGE: 73 Testing Battery Systems Refer to NEMA PE-1-1983, “Uninterruptible Power Systems” and NEMA PW-5-1985 “Utility Type Battery Chargers” for performance and testing guidelines. i) Measure the ground path resistance from the main ground terminal to the ground grid electrode. Note that special care must be taken when making tests with charger electronics connected, due to susceptibility to damage by over-voltages, and/or harmonics in test power supply. ii) For non-sealed cells, measure and record the specific gravity of the electrolyte in each cell and compare this with the recommended values. Inspect the closing plugs to ensure the vent holes are able to vent properly. Witnessing Authority to Verify iii) Measure the voltage at the terminal of each cell and compare with the recommended values. Tabulate the results and ensure that a copy of the checklist remains with the batteries. (See Certificate EE14 Sheet 01.) Witnessing Authority to Verify iv) When all inspection and tests have been performed, the batteries may be given their initial charge. This may be performed under the supervision of the vendor’s representative on site. (Vendor’s set-up charge instructions must be followed.) The boost and float charge voltage settings should be noted. Confirm the current limit settings and record values. Witnessing Authority to Verify Note: Under NO circumstances whatsoever are sealed cells to be boost charged. GOC© BP Exploration 1989 - 2001 All Rights Reserved GUIDANCE ON CERTIFICATION SECTION 9.0 GOC© AMERICAS EDITION REVISION: 1 SUBJECT: v) ELECTRICAL PAGE: 74 Check the operation of the battery ground fault alarm (where installed), and measure the ground current amperes for a zero impedance ground fault. Ensure that the measured value is below the drop off current level for all shutdown relays. Witnessing Authority to Verify vi) Check the operation of all alarms and trips including the main supply and charge failure alarms. Witnessing Authority to Verify vii) Check the operation of the battery charger rectifier failure alarms and trips (where installed). Witnessing Authority to Verify viii) Measure the level of output voltage ripple at normal load. Check the load manufacturer’s data that this is within tolerance. Witnessing Authority to Verify Note: Batteries should never be disconnected with charger(s) on-line, unless charger is approved for such service. ix) Check the operation of the DC over and under voltage alarms and trips (where installed). Witnessing Authority to Verify x) Perform a battery discharge test using a procedure acceptable to the Vendor and BP or delegated authority. Record the results, including decay graphs, on Vendor test sheets, and log per Certificate EE14 Sheet 01. Witnessing Authority to Verify xi) Recharge the battery at completion of discharge test, record the SG of the electrolyte (where applicable), and cell volts. Copies of these records must remain with the battery bank GOC© BP Exploration 1989 - 2001 All Rights Reserved GUIDANCE ON CERTIFICATION SECTION 9.0 GOC© AMERICAS EDITION REVISION: 1 SUBJECT: ELECTRICAL PAGE: 75 for maintenance records. Use Battery Test Certificate EE14 Sheet 02. Witnessing Authority to Verify 8.1.2 Certification Form EE14 Sheets 01 & 02 are to be used for recording results of the testing and require endorsement to signify the inspection requirements of the procedure have been performed satisfactorily. Supplier test sheets are to be attached to Form EE14 for filling in the Handover Certification Pack (HCP) or, where Vendor Data is provided, it shall form part of the project dossier. GOC© BP Exploration 1989 - 2001 All Rights Reserved GUIDANCE ON CERTIFICATION SECTION 9.0 GOC© AMERICAS EDITION REVISION: 1 SUBJECT: ELECTRICAL PAGE: 76 ELECTRICAL PROCEDURES Procedure No. 9.9 9.1 Uninterruptable Power Supplies 9.1.1 General The procedure is preliminary to the inspection and test to be performed by the equipment Vendor on-site. 9.1.2 a) Inspection Post-Installation i) Note the nameplate ratings of the equipment and any auxiliary apparatus and compare with the ratings given on the approved drawings. ii) Inspect the installed equipment for alignment, plumb and level, check tightness of anchor bolts and supports and verify shims are in place, where needed. iii) Inspect the grounding lugs and cables for the connection to the grounding system(s). Verify continuity to the system ground grid. iv) Ensure that all on-site installed cables have been tested in accordance with the electrical Procedure 9.1 and Test Certificates (Forms EE1 Sheet 01 thru Sheet 04). v) Note the type, size and rating of all fuses and protective devices and compare with requirements shown on the approved drawings. GOC© BP Exploration 1989 - 2001 All Rights Reserved GUIDANCE ON CERTIFICATION SECTION 9.0 GOC© AMERICAS EDITION REVISION: 1 SUBJECT: vi) ELECTRICAL PAGE: 77 Check for cleanliness and where necessary, clean the interiors of all control panels and enclosures. Remove any temporary silica-gel drying agents. vii) Perform inspection of the battery charger and batteries in accordance with Procedure 9.8. b) Testing i) Perform testing of batteries and battery charger in accordance with Procedure 9.8. Complete Certificates EE14 Sheet 01 & 02 prior to placing UPS in service. Witnessing Authority to Verify ii) Connect UPS output for load to be supplied, in order to verify UPS capabilities and transfer functions. If loads are not ready, temporary load banks may be necessary for these tests. Witnessing Authority to Verify iii) Perform all testing required on form EE15 Sheet 01 and sign off Certificate. Witnessing Authority to Verify iv) 9.1.3 Ensure that all vendor site tests have been completed and all results recorded on vendor test sheets. Witnessing Authority to Verify Certification Form EE15 Sheet 01 is to be used for recording the results of the testing and required endorsement to signify that the inspection requirements of the procedure have been performed satisfactorily. Certificates for batteries and battery charge tests, together with originals of Vendor test certificates should be attached to EE15 Sheet 01. GOC© BP Exploration 1989 - 2001 All Rights Reserved GUIDANCE ON CERTIFICATION SECTION 9.0 GOC© AMERICAS EDITION REVISION: 1 SUBJECT: ELECTRICAL PAGE: 78 ELECTRICAL PROCEDURES Procedure No. 9.10 10.1 Lighting and Small Power Distribution System 10.1.1 a) Inspection Post-Installation i) Verify that the equipment meets the area classification and specification requirements as described in the design specification and drawings. ii) Note the location and elevation of the lighting fixtures, panelboards, receptacles, and wall switches. Compare with the approved drawings. Note that wiring may have to be field verified for multi-voltage rated lighting fixtures (i.e., combination 230/277/480 volt sodium vapor fixtures). iii) Note distribution panel labeling and circuit numbering. Check fuse and/or breakers ratings of the circuits and compare with the approved drawings. Verify the operation of any safety features such as mechanical interlocks, circuit lock-out devices and door switches. iv) Ensure that the distribution panel and power supply cable has been tested and relevant test certificates completed. v) Check the grounding bus bar and wire and cable grounding connections inside the distribution panels. Be sure there are grounding connections from individual items of equipment to the grounding bus where detailed on drawings. Verify the grounding bus bar is properly connected to the grounding grid per NEC. GOC© BP Exploration 1989 - 2001 All Rights Reserved GUIDANCE ON CERTIFICATION SECTION 9.0 GOC© AMERICAS EDITION REVISION: 1 SUBJECT: vi) ELECTRICAL PAGE: 79 Inspect lighting fixtures, receptacles and switches for neatness, weather-proofing, cable connections, terminations and general good installation workmanship. vii) As each branch circuit from a distribution panel is inspected, complete an inspection tag and attach it to the branch circuit over current device where visible. Tag shall contain the date, circuit number and name of the inspector. viii) All equipment in hazardous locations should be inspected in accordance with the requirements of Procedure 9.15. ix) Perform an inspection of junction boxes in accordance with Procedure 9.19. b) Inspection Check Out The following inspection check out for Panel Board Inspection and Lighting and Receptacle Inspection can assist in the realization and acceptance of the EE16 Sheet 01 Certificate. GOC© BP Exploration 1989 - 2001 All Rights Reserved GUIDANCE ON CERTIFICATION SECTION 9.0 GOC© AMERICAS EDITION REVISION: 1 SUBJECT: ELECTRICAL PANELBOARD INSPECTION CHECKOUT (Procedure 9.10) DATE JOB NO PAGE: 80 SLD No LOCATION SHT of MODULE INITIAL/DATE TAG NO: ____________________ VOLTS: ________________ AMPS: _______________ 1. Receiving Inspection complete. 1 2. Check assembly for any missing parts. 2 3. Enclosure approved for classification of the area installed. 3 4. Panelboard circuit schedule correctly filled out and installed. 4 5. Correct circuit breakers installed (including GFCI) and correct fuse size (if applicable) 5 per drawing schedules. 6. Neutral wire correctly color coded. 6 MFS Contractors Installation 7. Grounding installed and connected (wiring is green color coded). MFS 7 Contractors Installation 8. Seals installed (if required). 8 9. Check for breather and drain (if required). 9 10. Check color coding of branch circuit conductors. 10 11. Panel board has been cleaned. 11 12. Mounting and supports adequate per specification and NEC. 12 13. Nameplate, number of circuits and panelboard location in accordance with approved 13 drawings. 14. Final inspection complete. Punch list items cleared. 14 REMARKS – See Lighting & Receptacle Inspection Check Out for additional circuit requirements on Lighting and Receptacles REV. 1 GOC© BP Exploration 1989 - 2001 All Rights Reserved GUIDANCE ON CERTIFICATION SECTION 9.0 GOC© AMERICAS EDITION REVISION: 1 SUBJECT: ELECTRICAL LIGHTING & RECEPTACLE INSPECTION CHECKOUT (Procedure 9.10) DATE JOB NO PAGE: 81 SLD No LOCATION SHT of MODULE INITIAL/DATE TAG NO: ____________________ VOLTS: ________________ AMPS: _______________ 1. Receiving Inspection complete. 1 2. Check assembly for any missing parts. 2 3. Enclosure approved for classification of the area installed. 3 4. Panelboard and circuit identification referenced. 4 5. Neutral wire correctly color-coded. 5 6. Grounding installed and connected (wiring is green color coded). 6 7. Seals installed (if required). 7 8. Check for breather and drain (if required). 8 9. Check color-coding of branch circuit conductors. 9 10. Mounting and supports adequate per specification and NEC. 10 11. Fixtures and receptacles are correct type and installed in accordance with drawings. 11 12. Fixtures and receptacles on correct circuit and working; receptacle polarity is correct. 12 13. Ensure tight fit of gaskets on lighting fixtures and that guards and reflectors are fitted 13 and securely fastened in place. 14. Verify minimum lighting levels per specification and NEC.** 14 15. Verify emergency lighting is functional per specification.** 15 16. Final inspection complete. Punch list items cleared. 16 REMARKS REV. 1 GOC© BP Exploration 1989 - 2001 All Rights Reserved GUIDANCE ON CERTIFICATION SECTION 9.0 GOC© AMERICAS EDITION REVISION: 1 SUBJECT: c) ELECTRICAL PAGE: 82 Testing i) Measure branch circuit insulation resistance to ground. Observe manufacturer’s instructions for light fixtures that incorporate electronic systems. Witnessing Authority to Verify ii) Test the voltage and polarity of each receptacle, and verify ground continuity. ground connectors. All receptacles must have polarized Witnessing Authority to Verify iii) Carry out illumination tests. Illumination levels are to comply with the NEC code for interior lighting where no other statutory or contract illumination levels are specified. Witnessing Authority to Verify iv) Carry out any required testing of protection and/or metering circuitry in accordance with Procedure 9.20. Witnessing Authority to Verify v) Test operation of emergency lighting systems and prove battery capacity to sustain lighting for the specified period (i.e. 1 hour). Witnessing Authority to Verify 10.1.2 Certification Results of illumination level checks should be recorded on the electrical layout drawings and attached to form EE16 Sheet 01. Form EE16 Sheet 01 is to be endorsed to signify that the requirements of this procedure, and Procedures 9.15 and 9.19 if appropriate, have been performed satisfactorily. Witnessing Authority to Verify GOC© BP Exploration 1989 - 2001 All Rights Reserved GUIDANCE ON CERTIFICATION SECTION 9.0 GOC© AMERICAS EDITION REVISION: 1 SUBJECT: ELECTRICAL PAGE: 83 Originals of test certificates generated by implementing Procedure 9.20 must be attached to EE16 Sheet 01. NOTE: On occasions where additional light fixtures are tied into existing circuits, an EE16 form may be used to record that Procedures 9.10, 9.15 and 9.19 have been performed for the new installed light fixtures. This avoids the need to re-test the whole circuit. GOC© BP Exploration 1989 - 2001 All Rights Reserved GUIDANCE ON CERTIFICATION SECTION 9.0 GOC© AMERICAS EDITION REVISION: 1 SUBJECT: ELECTRICAL PAGE: 84 ELECTRICAL PROCEDURES Procedure No. 9.11 11.1 Navigation Aids (Navaids) 11.1.1 General This procedure is preliminary to the inspection and testing performed by the equipment supplier at the site. 11.1.2 a) Inspection Post-Installation i) Note the nameplate rating of the supplied equipment and compare this rating with that on the approved drawings. ii) Check the equipment certification meets classification and specification requirements. iii) Inspect the installation of equipment for alignment, level and plumb. Check tightness of anchors and supports. iv) Ensure that the insides of control panels and enclosures have been cleaned out. Remove any temporary weatherproofing and silica gel from the equipment. v) Remove any transit blocking or and binding materials from the contactors and relays supplied with the equipment. vi) Inspect the equipment grounding connections. enclosures are all bonded to the ground grid. GOC© BP Exploration 1989 - 2001 All Rights Reserved the area Verify the GUIDANCE ON CERTIFICATION SECTION 9.0 GOC© AMERICAS EDITION REVISION: 1 SUBJECT: vii) ELECTRICAL PAGE: 85 Note the size, type and rating of all fuses and protective devices. Compare with the values stated on the approved drawings. viii) Ensure that all site installed cables have been certified in accordance with the relevant electrical procedure and test certificate completed. Ensure that the installation is suitable for the location of the equipment. ix) Ensure that the standby power systems have been tested, and tagged as such. x) Inspect the paint finish, paying particular attention to externally located equipment. Any damaged areas are to be corrected. xi) Inspect the weatherproofing and bolting of the connection boxes. Weatherproofing should not be dependent upon the application of paint, tape or plastic compounds. xii) Ensure the appropriate requirements of Procedure 9.15 are carried out if applicable. xiii) When floating platform/barge moors up to fixed installation, Nav-aid lights are to be synchronized (see applicable Maritime Laws). b) Testing i) Perform all testing as required by form EE17 Sheet 01. Witnessing Authority to Verify ii) If applicable, perform testing of batteries and battery chargers in accordance with Procedure 9.8. GOC© BP Exploration 1989 - 2001 All Rights Reserved GUIDANCE ON CERTIFICATION SECTION 9.0 GOC© AMERICAS EDITION REVISION: 1 SUBJECT: iii) ELECTRICAL PAGE: 86 Ensure that all supplier site tests have been completed to the satisfaction of any appropriate Statutory Authority and all results recorded on supplier tests sheets. Witnessing Authority to Verify 11.1.3 Certification Form EE17 Sheet 01 is to be used for recording the results of the testing and requires endorsement to confirm that the requirements of the procedure, and Procedure 9.15 if appropriate have been performed satisfactorily. Originals of Vendor test sheets and test records for batteries and battery chargers shall be attached Certificate EE17 Sheet 01. A Vendor Data Book is to be provided, this will form part of the project dossier. GOC© BP Exploration 1989 - 2001 All Rights Reserved GUIDANCE ON CERTIFICATION SECTION 9.0 GOC© AMERICAS EDITION REVISION: 1 SUBJECT: ELECTRICAL PAGE: 87 ELECTRICAL PROCEDURES Procedure No. 9.12 12.1 Neutral Grounding Resistors 12.1.1 a) b) Inspection Pre-Installation i) Note the nameplate ratings of the grounding resistors and compare with the approved drawings. ii) Ensure the equipment certificate meet the area classification and specification requirements. iii) Remove any temporary weather-proofing and any drying agents (e.g. silica-gel). Post-Installation i) Inspect the neutral grounding resistors for alignment, tightness of anchor bolts and supports. ii) Verify stand-off insulators are correct type, clean and undamaged. iii) Inspect the connections to the neutral grounding resistor being certain cables are correct size; and terminals are tightly clamped. iv) Inspect the equipment grounding conductor connections, being certain of correct size cable and connections. v) Warning labels are required, advising sudden temperature of the resistor in event of a ground fault. GOC© BP Exploration 1989 - 2001 All Rights Reserved high GUIDANCE ON CERTIFICATION SECTION 9.0 GOC© AMERICAS EDITION REVISION: 1 SUBJECT: c) ELECTRICAL PAGE: 88 Testing i) Measure the insulation resistance of the resistor to ground with incoming and outgoing connections disconnected. Use 1000V D.C. megger, one minute reading. Measure the value of the neutral grounding resistor. Witnessing Authority to Verify ii) Test the space heater and circuits where installed. Witnessing Authority to Verify iii) If current transformers have been installed, check that Vendor test certificates and magnetizing curves are available, if not, perform tests in accordance with Procedure 9.18. Witnessing Authority to Verify iv) Measure the equipment ground path resistance at the main grounding terminal to the system ground. Value must be less than 2 ohms from resistor connection to EARTH including ground electrode. Witnessing Authority to Verify v) Perform required testing of protective relaying and/or meter circuitry in accordance with Procedure 9.20. Witnessing Authority to Verify vi) 12.1.1 Upon completion of tests, reconnect the incoming and outgoing cables to bushing to resistor, and resistor to ground grid. Witnessing Authority to Verify Certification Form EE7 Sheet 01 must be endorsed to confirm that the requirements of this procedure have been carried out satisfactorily. GOC© BP Exploration 1989 - 2001 All Rights Reserved GUIDANCE ON CERTIFICATION SECTION 9.0 GOC© AMERICAS EDITION REVISION: 1 SUBJECT: ELECTRICAL PAGE: 89 Any supporting Vendor test certificates for the current transformer certificates should be supplied in the Vendor Data Book which forms part of the Project Dossier. If they are shipped loose, they should be attached to EE7, together with originals of test certificates generated by implementing Procedure 9.20. GOC© BP Exploration 1989 - 2001 All Rights Reserved GUIDANCE ON CERTIFICATION SECTION 9.0 GOC© AMERICAS EDITION REVISION: 1 SUBJECT: ELECTRICAL PAGE: 90 ELECTRICAL PROCEDURES Procedure No. 9.13 13.1 Heat Trace Cables and Circuits 13.1.1 a) Inspection Pre-Installation i) Check that the supplied heater cable is correct as noted in the design drawings and is rated for the area classification where it is installed. b) ii) Check that the heater cable is of the correct length. iii) Check that the circuit is correct for the voltage rating of the heater cable. iv) Perform insulation tests while cable is on the reel. See EE8 Sheet 02. Post-Installation i) Check that the fuse or breaker rating is correct for the total circuit loading. ii) Check that the heater cable is installed correctly, especially as applied to high point vents, low point drains, dead legs, flanges and removable items, such as valves and instrument or control devices. GOC© BP Exploration 1989 - 2001 All Rights Reserved GUIDANCE ON CERTIFICATION SECTION 9.0 GOC© AMERICAS EDITION REVISION: 1 SUBJECT: iii) ELECTRICAL PAGE: 91 Check that the mounting and grounding of the junction boxes and thermostats are correct. NOTE: ALL devices such as separately mounted controllers, sensors and mounting materials must also be grounded per applicable codes. iv) Perform inspection and tests detailed in Procedures 9.1, 9.15 and 9.19 as required. (Cable wiring and testing, Hazardous Area Classification and J-Box termination.) v) Insulation resistance measurements shall be performed while the heater cable is on the reel, after initial installation and upon completion of the of piping or vessel insulation. c) Inspection Check Out The following checkout and Inspection sheets for Heat Trace Components will assist in the realization and acceptance of the equipment as required by EE8 Sheet 01 & 02. GOC© BP Exploration 1989 - 2001 All Rights Reserved GUIDANCE ON CERTIFICATION SECTION 9.0 GOC© AMERICAS EDITION REVISION: 1 SUBJECT: ELECTRICAL HEAT TRACE COMPONENTS INSPECTION CHECKOUT (Procedure 9.13) DATE: JOB NO: Line Number Manufacturer PAGE: 92 SLD No SHT 1 of 2 LOCATION: Heater Number Model/Cat. Number MODULE: Service Voltage Wattage Watts/Foot INITIAL/DATE Construction Inspection - General 1. Inspect control panel to ensure proper installation per drawings and specifications. 1 Check circuit breaker ratings and fuse ratings. 2. Verify that installation and connection of the temperature controller is in accordance 2 with the manufacturer’s instructions and wiring diagram, and per project approved drawings. 3. Inspect the entire assembly for damage and/or missing parts. 3 4. Verify that heat tracing cable ends are properly protected from physical damages and 4 moisture contamination. 5. Inspect for apparent damages such as cuts, cracks or moisture spots. 5 6. Verify that all heat tracing cables are provided with tin plated copper grounding braid 6 and Teflon outer jacket, or equal. Verify catalog type, wattage, voltage rating, and area classification ratings are correct. 7. Verify that all grommets, connection boxes, end seals and other connection hardware 7 are furnished with correct type and size per manufacturer’s drawings, and per project approved drawings as applicable. 8. Verify heat tracing power connection/splicing and wiring color code to ensure that phase 8 connections are correct as per drawings, proper connection hardware is used as shown in drawings, all connection boxes are installed on upper quadrant of the pipe, and heat shrink boots instead of electrical tape are used for insulating the heat trace core material. 9. Verify that armored cables for power feeders are adequately supported. 9 10. Verify that heat trace power supply panels are equipped with correct breaker ratings 10 including GFCI’s needed. REMARKS REV. 1 GOC© BP Exploration 1989 - 2001 All Rights Reserved GUIDANCE ON CERTIFICATION SECTION 9.0 GOC© AMERICAS EDITION REVISION: 1 SUBJECT: ELECTRICAL HEAT TRACE COMPONENTS INSPECTION SUMMARY (Procedure 9.13) DATE: JOB NO: Line Number PAGE: 93 SLD No LOCATION: Heater Number Manufacturer SHT 2 of 2 Model/Cat. Number MODULE: Service Voltage Wattage Watts/Foot Power Connections, Splices and Tees 1. Power to heater connections, heat trace splices and tees per design drawings, and INITIAL/DATE 1 correct voltage source. 2. All changes recorded on as-built drawings. 2 3. Correct identification tags installed. 3 4. Junction box and lid gaskets correctly installed. 4 5. Proper grommets installed. 5 6. Outer jacket extends completely through grommet (CT heaters). 6 7. Shield pigtail tight (no loose strands or “whiskers”). 7 8. ½ inch minimum distance between shield and inner jacket cutback. 8 9. Heater bus wires properly stripped (no loose or broken strands). 9 10. Heater bus wires insulated up to terminal block (NOTE: Electrical tape is not 10 acceptable, only heat shrink material is acceptable). 11. Three-phase connections in accordance with manufacturers color code. 11 Transmitter, End Terminations INITIAL/DATE 1. Correct identification tag installed on each unit. 1 2. Proper sealing gasket installed between transmitter box and base. 2 3. Proper grommets installed. 3 4. Outer Jacket extends completely through grommet (CT heaters). 4 5. Bus wires properly connected to transmitter. 5 a) Insulated with heat shrinkable tubing. b) #14 AWG insulated wire with butt splice properly crimped. 6. ½ inch minimum distance between shield and outer jacket cutback. 6 7. Heater shield properly insulated with heat shrink tubing. 7 8. Heater shield connected to RTD shield (or green wire) with properly crimped wire joint 8 (T&B #RP-12). 9. Monitor wire cutback, if present (not to be utilized). REMARKS GOC© BP Exploration 1989 - 2001 All Rights Reserved 9 GUIDANCE ON CERTIFICATION SECTION 9.0 GOC© AMERICAS EDITION REVISION: 1 SUBJECT: d) ELECTRICAL PAGE: 94 Testing i) Each heater cable shall be subject to an insulation resistance test when installation is complete. (500V. Megger per Procedure 9.1.) Witnessing Authority to Verify ii) After all the heater cables on a circuit are installed the complete circuit shall have its insulation resistance tested and recorded. Witnessing Authority to Verify iii) After completion of the thermal insulation the circuit should have its insulation resistance re-checked to ensure no damage has occurred. Witnessing Authority to Verify iv) 13.1.1 The Commissioning Authority shall perform functional Checkout of the heat trace failure alarm and a SC1 form filled out. Certification Form EE8 Sheets 01 & 02 are to be used for recording the results of the testing, together with Form EE1 Sheet 02 for cable testing in accordance with Procedure 9.1. The forms require endorsement to confirm that the requirements of the procedure, and Procedures 9.1, 9.15 and 9.19 as appropriate, have been carried out satisfactorily. GOC© BP Exploration 1989 - 2001 All Rights Reserved GUIDANCE ON CERTIFICATION SECTION 9.0 GOC© AMERICAS EDITION REVISION: 1 SUBJECT: ELECTRICAL PAGE: 95 ELECTRICAL PROCEDURES Procedure No. 9.14 14.1 Grounding / Bonding 14.1.1 a) Inspection Post-Installation i) Compare the ground connection type and size with the schedule, drawings and specifications. ii) Where conductors have been terminated using crimped connections ensure that the correct size and type of crimped connection has been used. The crimp tool must also be listed for use with the compression lugs, and must be of the racket type which releases only after complete compression. b) iii) Ensure all connections are tight and anti-oxidizing grease applied. iv) Be sure all metal assemblies, conduits and J-Box are bonded together and to ground. Testing i) Each separate grounding point, which may consist of one or more electrodes, shall be verified with a ground resistance instrument, certified for accuracy down to 1 ohm or less. The resistance of each point must not exceed, the figures stated in paragraph 14.1.1 b) iv) following. GOC© BP Exploration 1989 - 2001 All Rights Reserved GUIDANCE ON CERTIFICATION SECTION 9.0 GOC© AMERICAS EDITION REVISION: 1 SUBJECT: ii) ELECTRICAL PAGE: 96 Perform Fall Of Potential test for soil resistance per IEEE Standard No. 81, Section 9.04, when required by the Authority in Charge. Witnessing Authority to Verify iii) Perform the two point method test per IEEE No. 81, Section 9.03, to determine the ground resistance between the grid connected grounding electrode and all major electrical equipment frames, system neutral or derived neutral points. iv) Alternate Method: Perform ground continuity test, when required, between grounding electrode and equipment frame, system neutral and/or derived neutral point. This test shall be made by passing a minimum of 10 amperes DC current between the grounding electrode (at system grid) and the ground point to be tested. Voltage drop shall be measured and the resistance calculated by voltage drop method. v) The resistance as measured from any part of the system to the main ground grid shall not exceed the values noted below and tests shall be carried out to confirm this: • • • 14.1.2 Electrical Grounding - 1 ohm Lightning Protection - 7 ohms Static Bonding - 10 ohms Certification Form EE9 Sheets 01 & 02, are to be used for recording the results of the grounding tests. GOC© BP Exploration 1989 - 2001 All Rights Reserved GUIDANCE ON CERTIFICATION SECTION 9.0 GOC© AMERICAS EDITION REVISION: 1 SUBJECT: ELECTRICAL PAGE: 97 ELECTRICAL PROCEDURES Procedure No. 9.15 15.1 Equipment for Use in Hazardous Locations 15.1.1 a) Inspection Post-Installation The following is a general inspection guide for all types of equipment installed in hazardous locations (or specified and installed in unclassified locations). The particular requirements for special equipment used in these locations will be listed individually hereafter and should be read in conjunction with BP Specification E-309 and Article 500, 501 and 505 of NFPA-70 (N.E.C.). i) Check to see that the equipment is listed and labeled for use in the installed area classification, the surface temperature (T rating) is correct and any special considerations on the Vendor data have been confirmed and accepted by the Witnessing Authority. ii) Ensure that all bolts, cable terminations, conduit seals and plugs are wrench tight and the enclosure gaskets are installed in good condition. iii) Inspect and clean the interior of the equipment of dust or dirt accumulation. Ensure that all electrical connections are tight. A check should also be made that any needed protection is adequate for the equipment rating. iv) Where applicable, ensure that cable and conduit sealing compound is correctly applied to avoid ingress of hazardous material. Inspect seal packing to ensure adequate GOC© BP Exploration 1989 - 2001 All Rights Reserved GUIDANCE ON CERTIFICATION SECTION 9.0 GOC© AMERICAS EDITION REVISION: 1 SUBJECT: ELECTRICAL PAGE: 98 separation of conductors, and the compound installed is per manufacturer’s specifications. v) Inspect the equipment grounding for integrity and all joints are properly tightened. vi) Ensure there is no damage to the equipment and it is adequately protected against corrosion, weather, vibration and other adverse factors pertaining to the installation. Check and inspect any electrical cables for sign of distress or damage. vii) Ensure that lamp rating and type are correct for any lighting fixtures installed. viii) Where guards are used, ensure that they are correctly located and secure. Verify motor fans and/or couplings are not rubbing or contacting housings or guard covers. b) Additional Checks The following additional checks are required on special equipment as listed: Explosion Proof Enclosures (Class 1 Division 1 or “Zone” Equivalent): i) Obstructions in the vicinity of the equipment do not block the path of door openings or impede air ventilation around the equipment. ii) All cover door gaps (per machining tolerance) are correct and free from corrosion, dirt and paint. iii) All conduit runs are wrench tight, free from corrosion, and meet classification requirements per NEC. GOC© BP Exploration 1989 - 2001 All Rights Reserved GUIDANCE ON CERTIFICATION SECTION 9.0 GOC© AMERICAS EDITION REVISION: 1 SUBJECT: iv) ELECTRICAL PAGE: 99 All unused conduit or fitting openings are plugged and sealed. NOTE: Any spare conduits must be sealed off the same as if there were wiring installed in it. c) Intrinsically Safe Installations (See NEC-Article 504) NOTE: Any equipment used as “Intrinsically Safe” must be so labeled and certified to meet this standard. i) All installations should be inspected to ensure that any cable or wiring shields are grounded in accordance with the relevant standard drawings. No “floating” shields are permissible. ii) All diode safety barrier installations are to be inspected to ensure that the correct type of barriers have been installed. They must remain firmly fixed to the barrier ground bus. iii) Boxes containing diode safety barriers and junction boxes must be inspected to make sure that they do not contain wiring other than that specified in the documentation for the intrinsically safe system. All such wiring must be segregated from any non-intrinsically safe wiring. iv) All installations should be inspected to ensure that relays and similar devices, which act as safety barriers between circuits, have not become damaged by repeated operation or vibration. Such damage may reduce the segregation afforded, causing loss of the safety intended. v) The ground path resistance must be measured from the safety barrier to a certified grounding conductor. GOC© BP Exploration 1989 - 2001 All Rights Reserved GUIDANCE ON CERTIFICATION SECTION 9.0 GOC© AMERICAS EDITION REVISION: 1 SUBJECT: d) ELECTRICAL PAGE: 100 Purged Pressurized Equipment (See NEC 500-4, and NFPA-496): i) The purge medium must be from an uncontaminated source, which is isolated from any hazardous material. ii) Any filters are clean and accessible, and approved for the area and enclosure. In-line filters only are permitted. iii) The purge system should be thoroughly checked to ensure that the purge pressure, cycle times, interlocks, lock-out sequence, and alarm provisions are intact and operating properly. iv) All purged pressurized equipment shall meet the requirements of NFPA-496. e) General The described grounding requirements of any of the classified equipment described must meet the requirements of Article 250 of the National Electric Code, as well as Articles 500-505 as applicable. f) Testing The diversity of equipment and special components, which are contained in a particular type of apparatus, does not permit a generalization of the testing required to demonstrate suitability for service in a hazardous location. Special requirements for testing may be contained in BP Specification E-327 or specific IEEE standards and should be compiled, prior to final energization of the circuit. Vendor documentation shall be examined to ensure that electrical components and equipment are listed and labeled for the use specified as required by the National Electrical Code, U.L., F.M. or appropriate NRTL standards. GOC© BP Exploration 1989 - 2001 All Rights Reserved GUIDANCE ON CERTIFICATION SECTION 9.0 GOC© AMERICAS EDITION REVISION: 1 SUBJECT: 15.1.1 ELECTRICAL PAGE: 101 Certification There is no specific standard form for recording that the requirements of the procedure have been implemented; Form EE10 Sheet 01 should be used to record the results of any testing required by BP Specification E-327, specific IEEE Standards or applicable NRTL standards. All Certificates necessary for approval by the Witnessing Authority, refer to the requirement that all equipment be certified as approved for the Area Classification in which it is installed. GOC© BP Exploration 1989 - 2001 All Rights Reserved GUIDANCE ON CERTIFICATION SECTION 9.0 GOC© AMERICAS EDITION REVISION: 1 SUBJECT: ELECTRICAL PAGE: 102 ELECTRICAL PROCEDURES Procedure No. 9.16 16.1 Oil Insulation Tests 16.1.1 General A separate procedure for oil-filled electrical equipment will be produced, if any new Projects have oil-filled electrical equipment in their work scope. Local site procedures will be used when any project interfaces with existing oil filled equipment. See Section 9.6 for transformer oil testing requirements. GOC© BP Exploration 1989 - 2001 All Rights Reserved GUIDANCE ON CERTIFICATION SECTION 9.0 GOC© AMERICAS EDITION REVISION: 1 SUBJECT: ELECTRICAL PAGE: 103 ELECTRICAL PROCEDURES Procedure No. 9.17 17.1 Drying of Electrical Rotating Machinery 17.1.1 a) Drying of Windings in Rotating Electrical Machinery Following testing per Procedure 9.7.1.1 (d), if motor test data reveals of P.I. of 2.5 or less, and insulation resistance is less than ( b) Rated Volts + 1 megohms, drying out may be necessary. 1000 ) i) The application of drying heat to the winding must be carefully controlled. The use of high intensity heat sources must be avoided at all times due to possible damage to insulation. ii) Heat must be applied gradually, regardless of the method used. The internal winding temperature should not be increased more rapidly than about 5°C per hour. A means of temperature monitoring, either by thermometer or RTD’s attached to the winding, (and to bearings to prevent overtemperatures there!) must be provided. Readings every 30 minutes to 1 hour are to be taken, along with insulation tests to track improvement. (See typical curve in 17.1.2). iii) Internal space heaters for the unit should be energized for the drying period, but they will not be effective for drying. The purpose of these heaters is only to inhibit condensation while the unit is not energized, and they will not provide sufficient heat for drying out insulation. iv) Regardless of the heating method for drying, clean air circulating through or over the unit is essential for purging damp air out of the winding. Drying of Motors Using Internal Heating i) Internal heating is obtained by circulating a low voltage AC or DC current through windings. The circulating current should not exceed 25% of the rated full load AC current and GOC© BP Exploration 1989 - 2001 All Rights Reserved GUIDANCE ON CERTIFICATION SECTION 9.0 GOC© AMERICAS EDITION REVISION: 1 SUBJECT: ELECTRICAL PAGE: 104 the allowable must be adjustable to maintain the desired level of current. NOTE: Necessity to monitor winding temperature rise per 17.1.1 a) i). ii) If AC is used for drying larger squirrel cage induction motors, the rotor temperature also shall be monitored. If the rotor temperature rise is too rapid, it may be advisable to remove the rotor from the assembly. Wound rotors need not be removed, but the end turns of the rotor windings shall be monitored for undue temperature increase. iii) When using the current circulated method of drying the winding, initial measurement of temperature shall be taken every 15 minutes during the first 2-3 hours to detect any undue temperature rises before damage occurs. For wound rotor motors, which are dried by current circulation, the drying current shall not be applied to the rotor via the brushes. This could cause hot spots at the contact areas between the brushes and slip-rings or commutator. iv) c) Dry, clean air must be constantly circulated to assist in purging moisture. Witnessing Authority to Verify Drying of Motors Using Internal Heating i) When drying equipment using external heaters, the machinery should be and clean air ventilated through appropriate in and out openings. ii) The size of the heater used is dependent upon the machine frame, and surrounding ambient conditions. As an approximate guide, the following relationship may be used: GOC© BP Exploration 1989 - 2001 All Rights Reserved GUIDANCE ON CERTIFICATION SECTION 9.0 GOC© AMERICAS EDITION REVISION: 1 SUBJECT: ELECTRICAL PAGE: 105 Heater Size (KW) = Weight of Machine (Kg) or Weight in Pounds 1000 2500 Witnessing Authority to Verify iii) It is also acceptable to use baking ovens, such as is available at motor repair facilities. Heat temperature in a well equipped, thermally controlled oven with venting and circulating air can be set to 115°C max. The entire motor with access covers and plugs removed can be set inside the oven while drying out. 17.1.2 Typical Drying Curve R3 Insulation Resistance ------------------------- R1 (MEG OHMS) R2 R1 = Time (Hours) Resistance of windings at start of drying out process. R2 = Minimum resistance of windings (due to vaporization, etc.). R3 = Final resistance of windings. 17.1.3 Certification Is to be used to record results. All results are to be recorded, retained with the graphs and attached to the motor test Certificates, Form EE13 Sheets 01 & 02. GOC© BP Exploration 1989 - 2001 All Rights Reserved GUIDANCE ON CERTIFICATION SECTION 9.0 GOC© AMERICAS EDITION REVISION: 1 SUBJECT: ELECTRICAL PAGE: 106 ELECTRICAL PROCEDURES Procedure No. 9.18 18.1 Instrument Transformer Verifications 18.1.1 a) Inspection Post-Installation i) Check the nameplates on the current transformers to make sure they are the correct class, type and ratio for the duty called for on the IFC and Vendor drawings. Verify they are mounted in the locations per drawings. ii) Inspect the mounting brackets for the C.T.’s insuring that they are securely fixed. Check to be sure of no damage during transportation. Also be sure that adequate clearance is given to the C.T.’s from moving parts of switchgear, and from possible interference with cables scheduled for installation in the gear. iii) Confirm electrical polarity marks are visible on all current and potential transformers, or such is shown on transformer nameplates. iv) Verify C.T.’s are equipped with secondary shorting terminal blocks and they are in the shorted position until circuits are complete. Also check to be sure the secondary wiring from the C.T.’s are terminated in short circuiting, type terminal strips, accessible to technicians. GOC© BP Exploration 1989 - 2001 All Rights Reserved GUIDANCE ON CERTIFICATION SECTION 9.0 GOC© AMERICAS EDITION REVISION: 1 SUBJECT: b) ELECTRICAL PAGE: 107 Testing i) Measure insulation resistance of transformer secondary winding and leads with 1000V megger, with ground lead lifted and electronic devices protected. (Both C.T.’s and P.T.’s) Witnessing Authority to Verify ii) Measure transformer primary insulation with applicable overpotential tests. Consult manufacturer for proper voltage and procedure. Witnessing Authority to Verify iii) Verify wiring at the C.T. secondary leads by connecting a low value of current through the leads, and taking readings at the applicable relaying and metering devices connected to the transformer secondary circuit. A low range clamp on ammeter may be used to read currents. Witnessing Authority to Verify iv) After pulling primary P.T. fuses, proceed to verify wiring of the P.T. secondary leads by applying a low voltage to the leads and checking for this voltage at the potential input terminals of metering and/or protective devices. Witnessing Authority to Verify v) Replace P.T. primary fuses after these tests. When P.T. circuits are fully energized, check for P.T. KVA load with secondary voltage and current measurements, when required. Load must be less than the Volt-Amp capacity of the P.T. Witnessing Authority to Verify vi) Testing, to determine the magnetizing characteristics of current transformers is performed by the Supplier after assembly. Supplier test certification should be checked for GOC© BP Exploration 1989 - 2001 All Rights Reserved GUIDANCE ON CERTIFICATION SECTION 9.0 GOC© AMERICAS EDITION REVISION: 1 SUBJECT: ELECTRICAL PAGE: 108 completeness and accuracy. ANSI characteristics must be supplied by certified test data from the manufacturer. It is not necessary to perform such testing on-site. If C.T. test data is not given, the vendor will be responsible to provide the certified data, or perform the tests, or secure services of the manufacturer to do so. Witnessing Authority to Verify c) Test Procedure i) Any magnetizing curve testing must be done by the vendor/manufacturer of the transformers. This would only be required if insufficient certified test date is provided with the equipment. ii) Verifying ratio of P.T.’s and C.T.’s can be done with variable voltage and/or variable current sources commonly available with portable test sets for metering and/or protective relay checks. 18.1.2 Certification Form EE11 Sheet 01 is to be used for recording the results of ratio testing, and requires endorsement to confirm that all requirements of the procedure have been performed satisfactorily. GOC© BP Exploration 1989 - 2001 All Rights Reserved GUIDANCE ON CERTIFICATION SECTION 9.0 GOC© AMERICAS EDITION REVISION: 1 SUBJECT: ELECTRICAL PAGE: 109 ELECTRICAL PROCEDURES Procedure No. 9.19 19.1 Junction Box Inspection 19.1.1 a) Inspection Post-Installation i) Ensure that the junction box location is correct as reflected by IFC drawings. ii) Check that the J-Box is suitable for the Area Classification specified. iii) Ensure that the junction box is adequately supported and permanently labeled for cable i.d., drawing numbers, and source location. iv) Check internal terminal types, size, support and identification. Be sure all are correct, listed and labeled for the use specified. Verify all wiring is tagged and color-coded per specs and/or drawings. v) Ensure that the grounding connections, internal and external, are correct and all connections are tight. vi) Inspect to see that cable terminations and accessories are correctly installed, and any unused cable entries are plugged and sealed per area classification needs. vii) Ensure that gaskets are correctly installed, as required, with proper lubricant for preserving gasket quality. GOC© BP Exploration 1989 - 2001 All Rights Reserved GUIDANCE ON CERTIFICATION SECTION 9.0 GOC© AMERICAS EDITION REVISION: 1 SUBJECT: viii) ELECTRICAL PAGE: 110 Check that the box covers are correctly sealed, and all bolts, latches and/or clamps are in place and tight. ix) For hazardous area locations, Procedure 9.15 must be followed. b) Testing No testing of junction boxes is required, with the exception that a ground continuity test must be performed, and results logged in Inspection Check Out. 19.1.1 Certification There is no specific standard form for recording that the requirements for the procedure have been implemented. The following forms however, make reference to relevant procedures and require endorsement to confirm that the junction boxes and the standard of installation is suitable for the intended service: EE1, EE8 and EE16 Sheet 1 General Test Certificate (For Panel Board Inspection checkout). GOC© BP Exploration 1989 - 2001 All Rights Reserved GUIDANCE ON CERTIFICATION SECTION 9.0 GOC© AMERICAS EDITION REVISION: 1 SUBJECT: ELECTRICAL PAGE: 111 ELECTRICAL PROCEDURES Procedure No. 9.20 20.1 Protective Relay and Metering Circuit Testing 20.1.1 a) General The equipment covered by the following procedures may require testing of protective relaying and/or meter circuitry by means of primary and/or secondary injection, as required by the Witnessing Authority. Form EE12 Sheet 01 and/or Sheet 02 required. Procedure: • 9.2 - Switchgear, Motor Control Centers and Metal Enclosed Bus Duct • • 9.3 - Circuit Breakers - Air, Molded Case and Oil Immersed 9.4 - Contactor Starters • 9.5 - Medium Voltage Air Switches • • • • 9.6 - Power Transformers - Oil Filled and Dry Type 9.7 - Motors 9.10 - Lighting and Small Power Distribution 9.12 - Neutral Grounding Resistors Owing to both the variety of schemes and the diverse types of relays in use, no attempt has been made to produce a standard testing procedure. Each relay requires an Inspection Report, Form EE12 Sheet 03. Witnessing Authority to Verify b) Testing i) All relay tests shall be made by, or under the supervision of, a qualified electrical engineer (typically from a specialty GOC© BP Exploration 1989 - 2001 All Rights Reserved GUIDANCE ON CERTIFICATION SECTION 9.0 GOC© AMERICAS EDITION REVISION: 1 SUBJECT: ELECTRICAL PAGE: 112 contractor, or technical testing service, equipped and experience to do this work). ii) Every protective relay shall be inspected, tested, tagged and dated by the service company performing the work. iii) Records on all relay and/or meter tests shall be completed and made a part of the equipment Certificate record for that equipment. iv) Relay test Certificates are required for each protective relay, according to the application type per Forms EE12 Sheet 04 thru EE12 Sheet 10. If the relay is of a type not covered by the Forms, the installer/tester is to provide a suitable form with typical format. It may also be expedient to use one furnished Form by changing the title and adding new sheet numbers. Witnessing Authority to Verify 20.1.2 Certification i) Certification of protective relay testing and calibration shall be documented on forms EE12 Sheet 01 thru EE12 Sheet 10. GOC© BP Exploration 1989 - 2001 All Rights Reserved GUIDANCE ON CERTIFICATION SECTION 9.0 GOC© AMERICAS EDITION REVISION: 1 SUBJECT: ELECTRICAL PAGE: 113 ELECTRICAL PROCEDURES Procedure No. 9.21 21.1 Generators, AC 21.1.1 a) Inspection Pre-Installation i) Note the nameplate ratings of the generator(s) and compare with those given in the approved drawing and generator data sheets. Note any special instructions regarding auxiliary equipment. Be sure all material is on hand per the installation drawings, including any auxiliary items such as surge packs, terminal boxes, connection lugs and bearing probes shipped with the unit. ii) Ensure equipment certification (nameplate data) meets the appropriate area requirements. b) classification and specification Post-Installation i) Ensure that any shaft blocking or shipment packing has been removed. Rotate shaft by hand prior to energizing the drive unit. ii) Without dismantling the generator, inspect as far as possible: through bearing sight glass for oil rings, oil levels if required, and other lubricant needs such as grease packing for bearings. Inspect for any signs of lubricant leakage, and provide report data on such. Follow manufacturer’s instructions for “flushing” bearings prior to starting. GOC© BP Exploration 1989 - 2001 All Rights Reserved GUIDANCE ON CERTIFICATION SECTION 9.0 GOC© AMERICAS EDITION REVISION: 1 SUBJECT: iii) ELECTRICAL PAGE: 114 Inspect the paint finish of the generator for damage during installation. Any damaged areas are to be repainted, using the BP approved process per purchase specifications. iv) Inspect the weatherproofing and bolting of all connection boxes. Sealing shall not be dependent upon the application of paint, tape or plastic compounds. All bolts must be in place and torqued to the proper tightness, except when covers need to be open for work in progress. Supervisor is responsible to see that the covers are all secured and bolts in place during the time there is no work being done. v) Inspect the stator winding connections: Check to see if the line connections needed are for star or delta connection, and be sure the correct terminal access is available for that configuration. vi) Inspect the grounding terminals and the connections for the ground grid system, including those inside the terminal box. There must be at least two provisions on the generator frame (on alternate corners) for attaching grounding cables. Terminal box grounding lugs must be bonded to the frame ground and incoming line ground conductors. vii) Check to see that all requirements of Procedure 9.15 (Hazardous Location Classifications) have been met for the performing of electrical tests, and will overall satisfy the installation requirements. c) Complete the “AC Generator Inspection Checkout” list after performing the winding insulation tests in Section 9.21.1.2 following. 21.1.2 Testing Prior to Connecting Power Cables (See IEEE-43, 1991; Recommended Practices for Testing Insulation Resistance of Rotating Machinery, and NEMA MG-1 for Factory Test Standards.) GOC© BP Exploration 1989 - 2001 All Rights Reserved GUIDANCE ON CERTIFICATION SECTION 9.0 GOC© AMERICAS EDITION REVISION: 1 SUBJECT: a) ELECTRICAL PAGE: 115 Megger test winding by the following table for voltage and minimum values, holding voltage one minute before reading the final value. All RTDs should be shorted to ground during these tests. Generator Volts Winding Type Megger Volts Minimum Megohms 480-600 3ph ungrd. Wye 500v all leads 1.0 at 40°C 2300-4160 3ph ungrd. Wye 1kv, all leads Kv + 1.0 at 40°C 2300-4160 13.2Kv-13.8Kv 3ph, 6 leads 3ph, 6 leads 1kv, 1ph w/2 gnd* 5kv min, 1ph w/2 g* Kv + 1.0 at 40°C Kv + 1.0 at 40°C * Denotes energizing one phase while grounding the other two. Rotate connections to finally test all three phases, one at a time. Record each reading and winding temperature, and correct to 40°C. b) Correcting megger readings to 40°C The observed resistance reading may be corrected to 40°C by applying the following formula and temperature coefficients: RM 40°C = RM x Tc Where T= TC= RM = insulation resistance in megohm as read winding temperature in °C temperature coefficient for the winding temperature Winding Temperature Temperature Coefficient (°C) (T C) 30 0.5 40 1.0 50 2.0 60 4.0 70 ** 8.0 ** Cold coil resistance (20°C and below) shall not be used, and a heat source shall be used as hereinafter described to raise the machine temperature to a minimum of 20°C. Witnessing Authority to Verify c) For large units, performance of an insulation polarization index (PI) test is advised as part of the procedure for megger testing, especially if the unit winding has been exposed to moist or contaminated air. (See Section 4.5 of IEEE 43.) If the insulation GOC© BP Exploration 1989 - 2001 All Rights Reserved GUIDANCE ON CERTIFICATION SECTION 9.0 GOC© AMERICAS EDITION REVISION: 1 SUBJECT: ELECTRICAL PAGE: 116 resistance is below the minimum allowed value, the machine shall be dried out or replaced. Machine windings shall be dried out by: supplying heat from electric strip heaters, from heat lamps or by passing current through machine windings until a sufficient insulation resistance is obtained. It may be necessary to circulate dry, warm air through the winding or bore during the drying out process. d) The temperature maintained during the drying-out process shall not exceed the following: • Class B or F insulation by thermometer • By resistance bridge or thermal sensing resistor circuit (RTD) 90°C 110°C • The insulation resistance shall be taken at intervals of 4-5 hours during the drying-out process until an acceptable value is reached. This value in megohms shall be at least equal to 1 megohm per Kv of voltage rating, with a minimum of 1 megohm. Witnessing Authority to Verify e) If special generator protective devices (e.g. thermo-couples or RTD’s) have been installed, test their circuit continuity to the terminal blocks mounted on the frame, or to the connection end of the wires from each. Verify insulation integrity on ungrounded leads, by applying resistance-measuring meters. (Special precautions are necessary before attempting to apply more than 250V D.C. megger voltage to RTD’s. Never attempt higher than ohmmeter voltages to check thermocouples.) Measure the circuit resistance and insulation resistance of generator space heaters. Witnessing Authority to Verify f) Verify that the excitation system, prime mover protection and associated protective devices have all been tested in accordance GOC© BP Exploration 1989 - 2001 All Rights Reserved GUIDANCE ON CERTIFICATION SECTION 9.0 GOC© AMERICAS EDITION REVISION: 1 SUBJECT: ELECTRICAL PAGE: 117 with Procedure 9.20 and industry standards (i.e., NEMA MG-1 & IEEE). g) MV and/or HV generator windings may require Doble (or equal) power factor testing as part of acceptance. If the manufacturer at their plant does this, test data must be part of the documents provided with the unit. If Doble tests are done in the field, Certificate EE18 Sheet 02 is required. On units rated at 6000 volts or above, PDA testing is also required and is tabulated on the same sheet. Special test equipment and technicians are required for these tests. 21.1.3. a) AC Generator Inspection Check At this point, review the items on the “AC Generator Checkout” sheet, on the following page and execute the items required to complete. Witnessing Authority to Verify b) After completion of the Checkout items, proceed with the following: i) ii) Have the coupling disconnected to separate the generator from the drive unit, or the belts removed from the belt driven equipment. Ensure that the generator rotor can be turned freely and the rotor endplay is within tolerance. Verify alignment to the prime mover is within tolerance. After the unit is connected and the prime mover running, perform vibration tests on all 460V and 4000V generators rated 200 kilowatts and larger. Vibration amplitude values shall not exceed the values reflected by the NEMA MG-1 Standard. Witnessing Authority to Verify GOC© BP Exploration 1989 - 2001 All Rights Reserved GUIDANCE ON CERTIFICATION SECTION 9.0 GOC© AMERICAS EDITION REVISION: 1 SUBJECT: c) ELECTRICAL PAGE: 118 Certification Form EE18 Sheets 01 & 02 are to be used for recording the results of testing. These pages require endorsement to confirm that the requirements of this procedure and Procedure 9.15, if appropriate, have been performed satisfactorily. If applicable, the results of drying out generator windings, Procedure 9.17, are to be attached to Form EE18 Sheet 01. Also include and attach any certificates generated by implementing Procedure 9.20 (Metering and Relay Testing) for generator devices supplied by the vendor. GOC© BP Exploration 1989 - 2001 All Rights Reserved GUIDANCE ON CERTIFICATION SECTION 9.0 GOC© AMERICAS EDITION REVISION: 1 SUBJECT: ELECTRICAL AC GENERATOR INSPECTION CHECKOUT (Procedure 9.21) DATE JOB NO PAGE: 119 SLD No LOCATION SHT of MODULE INITIAL/DATE GENERATOR TAG NO: ____________________ FUNCTION: ____________________ 1. Nameplate data agrees with specifications, plan drawings & one-line diagram. 1 2. Frame type is suitable for use in area classification required. 2 3. Maximum Temperature Code: 3 4. Check that the power and control cables insulation resistance tests are complete prior 4 to connection to generator. (Megger & Hi-Pot as required.) NOTE: If winding hi-pot is required - follow manufacturer’s recommended procedure to maintain in warranty. 5. Review generator insulation resistance test data at Procedure 21.1.2 . 5 6. Grounding conductors installed, connected and bonded per NEC. 6 7. Generator splices and terminations complete. Unused cables or leads on multiple 7 voltage generators are properly insulated and/or terminated. 8. Generator electrical accessories are properly connected, such as space heaters, 8 thermocouples, RTDs, vibration switches, or auxiliary devices 9. Maximum overtemperature switch (if provided) is wired into control circuit of the 9 generator circuit breaker. 10. Grounding bond jumpers installed, bolts and nuts are tightened. Grounding 10 connections properly made up to equipment and plant grid ring. 11. Control station nameplate installed, including identification of all external wiring sources 11 and power provisions. 12. Covers are installed, bolts and nuts are tightened. 12 13. Final inspection Complete. Punch list items cleared. 13 REMARKS (clarification of instructions or comments): See 21.1.2 g) for other tests on MV & HV generators. Add remarks regarding any special tests required (such as EE17 Sheet 01 for example). REV. 1 GOC© BP Exploration 1989 - 2001 All Rights Reserved GUIDANCE ON CERTIFICATION SECTION 9.0 GOC© AMERICAS EDITION REVISION: 1 SUBJECT: ELECTRICAL PAGE: 120 • Functional Certification Flowchart 9 • Discipline: Electrical Equipment & Cables (includes Control Cables) POWER DOWN POWER UP EE1 EE2 EE3 EE13 EE4 EE14 EE5 MC1 EE15 SC1 SH1 EE6 EE16 EE7 EE17 EE8 EE18 EE9 EE10 EE11 EE12 For Certificate title refer to Exhibit 9 EE1 EE2 EE3 EE4 EE5 EE6 EE7 EE8 EE9 LV & MV Cables, all Switchgear, MCC, Bus Duct LV & MV Circuit Breakers Contactor Starters & VSD’s M.V. Fused Air Sws. Power Transformers Neutral Grounding Resistors Heat Trace Electrical Grounding EE10 Hazardous Locations EE11 Instrument Transformers EE12 Primary & Secondary Injection Relay Tests EE13 Electrical Motors & Rotating Machinery EE14 Battery Tests EE15 UPS Load Test EE16 General Test Certificate ** EE17 Navigational Aids EE18 AC Generators ** Can be used in both Construction & Commissioning Phases GOC© BP Exploration 1989 - 2001 All Rights Reserved GUIDANCE ON CERTIFICATION SECTION 9.0 GOC© AMERICAS EDITION REVISION: 1 SUBJECT: ELECTRICAL PAGE: 121 EXHIBIT 9 STANDARD FORMS Form Number Test Certificate Description EE1 LV / Shielded Instrument Cable Cable and Wire Insulation, Insulation Resistance EE2 SHT 01 02 03 Cable D.C. High Potential Step Voltage 04 Insulation Resistance and DC Hi-Pot Graph SHT 01 02 EE3 SHT 01 Switchgear Bus Insulation and Phasing MCC Bus Insulation and Phasing LV Power Circuit Breaker 02 Molded Case Breakers 03 04 Med. Voltage Circuit Breaker High Voltage Limited Oil Interrupter EE4 SHT 01 02 03 Contactor Type Starter Motor Thermal Overload Relay Variable Speed Drives EE5 SHT 01 Medium Voltage Air Switch Inspection EE6 SHT 01 02 03 Two Winding Power Transformer Transformer Turns Ratio (Requires Sketch on Back) Three Winding Power Transformer EE7 SHT 01 Neutral Grounding Resistor EE8 SHT 01 02 Heat Trace Tape Inspection (Electrical) Heat Trace Performance (Electrical) EE9 SHT 01 02 Electrical Ground System Test Grounding Resistance Test (Individual Electrodes) GOC© BP Exploration 1989 - 2001 All Rights Reserved GUIDANCE ON CERTIFICATION SECTION 9.0 GOC© AMERICAS EDITION REVISION: 1 SUBJECT: ELECTRICAL PAGE: 122 STANDARD FORMS Form Number Test Certificate Descriptoin EE10 SHT 01 Hazardous Location Certificate EE11 SHT 01 Instrument Transformer Ratio Tests EE12 SHT 01 02 Primary Injection Test Secondary Injection Test EE13 03 Relay Inspection (Individual units) 04 Overcurrent Relay Test 05 Instantaneous Overcurrent Relay Test 06 Over/Under Voltage Relay Test 07 Power Factor Relay Test 08 09 Frequency Relay Test Transformer Differential Relay Test 10 Reverse Power Relay Test SHT 01 02 Motors and Motor Circuits, Phase Rotation & Tests Rotating Machinery EE14 SHT 01 02 Battery Load Test (Bank) Individual Battery Test Log EE15 SHT 01 UPS Power Supply EE16 SHT 01 General Test Certificate EE17 SHT 01 Navigational Aids EE18 SHT 01 02 AC Generator and Generator Circuits Test Rotating Machinery (AC Generator) Test (Individual Unit P.F. and PDA tests) GOC© BP Exploration 1989 - 2001 All Rights Reserved GUIDANCE ON CERTIFICATION SECTION 9.0 GOC© AMERICAS EDITION REVISION: 1 SUBJECT: ELECTRICAL PAGE: 123 STANDARD FORMS DIS6 Data Input Sheet 6 – Electrical Cables DIS7 Data Input Sheet 7 – Electrical Equipment GOC© BP Exploration 1989 - 2001 All Rights Reserved Project Title: SH1 No: Maintenance No: MC1 No: Work Pack No: Package No: FORM EE1 – SHT 01 (SIDE 1) SITE: Source/Equipment No: LV / SHIELDED INSTRUMENT CABLE TEST CERTIFICATE CABLE VOLTAGE RATING MEGGER USED/CAL. DATE MEGER VOLTAGE ENVIRONMENTAL CABLE No. DRAWING REFERENCE(s) CORES SIZE MODEL NO. TEMP/HUMIDITY/AMB IR TEST CABLE SCHEDULE INFORMATION SHT CONTINUITY CORE CORE TO CORE SCREEN TO CORE ARMOUR SCREEN OHMS ARMOUR OHMS MOHMS* MOHMS* SCREEN ARMOUR CONTINUITY TO EARTH OHMS OF SERIAL NO. *MINIMUM RESISTANCE VALUE IN MEG OHMS PROCEDURE COMPLETE (DELETE AS APPROPRIATE) 9.1 9.15 9.19 YES/NA YES/NA YES/NA YES/NA YES/NA YES/NA YES/NA YES/NA YES/NA YES/NA YES/NA YES/NA YES/NA YES/NA YES/NA YES/NA YES/NA YES/NA YES/NA YES/NA YES/NA YES/NA YES/NA YES/NA YES/NA YES/NA YES/NA YES/NA YES/NA YES/NA YES/NA YES/NA YES/NA YES/NA YES/NA YES/NA YES/NA YES/NA YES/NA YES/NA YES/NA YES/NA YES/NA YES/NA YES/NA YES/NA YES/NA YES/NA COMPLETED BY DATE APPROVED BY DATE USUALLY INDIVIDUAL CONDUCTORS IN A CABLE WILL HAVE SIMILAR VALUES OF INSULATION RESISTANCE. HOWEVER, WHERE THEY DIFFER, THE VALUE STATED ABOVE SHOULD BE THE LOWEST. IF THEY DIFFER BY A SIGNIFICANT AMOUNT, THIS COULD BE AN INDICATION OF DAMAGE OR POOR WORKMANSHIP AND SHOULD BE INVESTIGATED. GOC© BP Exploration 1989 – 2001 All Rights Reserved DOUBLE SIDED FORM Americas REV. 1 IR TEST CABLE No. DRAWING REFERENCE(s) CABLE SCHEDULE INFORMATION CORES SIZE CONTINUITY CORE CORE TO CORE SCREEN TO CORE ARMOUR SCREEN OHMS ARMOUR OHMS MOHMS* MOHMS* SCREEN ARMOUR CONTINUITY TO EARTH OHMS PROCEDURE COMPLETE (DELETE AS APPROPRIATE) 9.1 9.15 9.19 YES/NA YES/NA YES/NA YES/NA YES/NA YES/NA YES/NA YES/NA YES/NA YES/NA YES/NA YES/NA YES/NA YES/NA YES/NA YES/NA YES/NA YES/NA YES/NA YES/NA YES/NA YES/NA YES/NA YES/NA YES/NA YES/NA YES/NA YES/NA YES/NA YES/NA YES/NA YES/NA YES/NA YES/NA YES/NA YES/NA YES/NA YES/NA YES/NA YES/NA YES/NA YES/NA YES/NA YES/NA YES/NA YES/NA YES/NA YES/NA YES/NA YES/NA YES/NA YES/NA YES/NA YES/NA YES/NA YES/NA YES/NA YES/NA YES/NA YES/NA YES/NA YES/NA YES/NA YES/NA YES/NA YES/NA YES/NA YES/NA YES/NA YES/NA YES/NA YES/NA YES/NA YES/NA YES/NA YES/NA YES/NA YES/NA COMPLETED BY DATE APPROVED BY DATE USUALLY INDIVIDUAL CONDUCTORS IN A CABLE WILL HAVE SIMILAR VALUES OF INSULATION RESISTANCE. HOWEVER, WHERE THEY DIFFER, THE VALUE STATED ABOVE SHOULD BE THE LOWEST. IF THEY DIFFER BY A SIGNIFICANT AMOUNT, THIS COULD BE AN INDICATION OF DAMAGE OR POOR WORKMANSHIP AND SHOULD BE INVESTIGATED. GOC© BP Exploration 1989 – 2001 All Rights Reserved DOUBLE SIDED FORM Americas REV. 1 Project Title: Maintenance No: Work Pack No: SH1 No: MC1 No: CABLE AND WIRE INSULATION INSULATION RESISTIVITY CERTIFICATE DATE JOB NO. FORM EE1 - SHT 02 SITE: SHT of SLD No: LOCATION MODULE CABLE VOLTAGE RATING MEGGER USED/CAL.DATE MEGGER VOLTAGE MODEL NO. SERIAL NO. ACCURACY/FULL SCALE READING REFERENCES: ENVIRONMENTAL TEMP. MINIMUM RESISTANCE VALUE IN MEG OHMS ONE MINUTE TESTS SEALS CABLE BLOCK CONTINUITY CABLE/CONDUIT NO./TO-FROM COMPLETE COMPLETE CHECKED COMPLETED BY WITNESSED BY ACCEPTED BY RACEWAY SYSTEM INSPECTED CONDUCTORS TO OVERALL SHIELD CONDUCTORS TO CONDUCTORS APPROVED BY COMPANY SIGNATURE PRINT NAME DATE GOC© BP Exploration 1989 – 2001 All Rights Reserved Americas REV. 1 Project Title: Maintenance No: Work Pack No: SH1 No: MC1 No: FORM EE1 - SHT 03 SITE: CABLE DC HIGH POTENTIAL STEP VOLTAGE TEST CERTIFICATE DATE JOB NO. LOCATION CONDUIT CABLE NO. RATED KV CABLE INSULATION SHT of SLD No MODULE CABLE SIZE MANUFACTURER REEL NO. FROM CABLE LENGTH TO EQUIPNT USED (FOR TEST) AMBIENT TEMPERATURE SERIAL NO. MODEL NO. HUMIDITY ENVIRONMENTAL CONDITIONS NO. OF TYPE OF TERMINATION NO. OF °F TYPE OF SPLICE TEST KV 5 KV 15 KV CABLE CABLE TIME LEAKAGE CURRENT TIME VS. CURRENT DATA INT. (MICRO-AMPS) FOR GRAPH 15 MIN. MAX. PHASE A PHASE B PHASE C LEAKAGE CURRENT TO SHIELD TO SHIELD TO SHIELD PHASE A 5 15 15 SEC. 10 20 30 SEC. 15 25 45 SEC. 20 30 1 MIN. 23 35 2 MIN 25 40 3 MIN. 45 4 MIN. 50 5 MIN. 53 6 MIN. 55 PHASE B PHASE C 7 MIN. REMARKS: 8 MIN. 9 MIN. 10 MIN. 11 MIN. 12 MIN. 13 MIN. 14 MIN. 15 MIN. 16 MIN. COMPLETED BY WITNESSED BY ACCEPTED BY APPROVED BY COMPANY SIGNATURE PRINT NAME DATE GOC© BP Exploration 1989 - 2001 All Rights Reserved Americas REV. 1 Project Title: SH1 No : Maintenance No: MC1 No : FORM EE1 SHT 04 SITE: Work Pack No: Source/Equipment No: INSULATION RESISTANCE AND DC HIGH POTENTIAL GRAPH OF TEST DATA DATE MANUFACTURER CABLE MFR TEMPRETURE JOB NO. LOCATION MODULE MODEL NO CABLE RATING HUMIDITY SETTING INSULATION TYPE VOLTAGE INCREMENTS SHT OF EQUIPMENT NO SERIAL NO CONDUCTOR SIZE STABILIZATION TIME ACCURACY MICROAMPS M IN U T E S ___ ____ (1 vs. T IM E ) D C T E S T V O LT A G E , K V COMPILED BY APPROVED BY LEAKAGE CURRENT AT FULL TEST DISCHARGE TIME VOLTAGE AFTER COMPANY DOWN TO ______________KV DOWN TO ________KV I MIN. DISCHARGE SIGNATURE PHASE A _______________µA _________________SEC ________________KV NAME PHASE B _______________µA _________________SEC ________________KV DATE PHASE C _______________µA _________________SEC ________________KV GOC© BP Exploration 1989 – 2001 All Rights Reserved Americas REV. 1 Project Title: Maintenance No: Work Pack No: SH1 No: MC1 No: FORM EE2 - SHT 01 SITE: SWITCHGEAR BUS INSULATION AND PHASING TEST CERTIFICATE DATE JOB NO. LOCATION MODULE EQUIPMENT DESCRIPTION MANUFACTURER MODEL NO. SERIAL NO. TAG NO. TYPE VOLTAGE RATING SHT of SLD No CURRENT RATING POWER RATING EQUIPMENT USED (FOR TEST) MANUFACTURER MODEL NO. VOLTAGE SERIAL NO. ACCURACY/FULL SCALE ENVIRONMENTAL CONDITIONS TEMPERATURE RESISTANCE VALUE IN MEG OHMS PHASE TO PHASE A-B B-C C-A EQUIPMENT INSPECTION COMPLETED PHASE TO GROUND A B INSPECTORS INITIALS MECHANICAL COMPLETION NEC COMPLIANCE C DATE DWG AND STD COMPLIANCE VERIFIED REMARKS: Check Bus Phasing COMPLETED BY WITNESSED BY ACCEPTED BY APPROVED BY COMPANY SIGNATURE PRINT NAME DATE GOC© BP Exploration 1989 – 2001 All Rights Reserved Americas REV. 1 Project Title: Maintenance No: Work Pack No: SH1 No: MC1 No: FORM EE2 - SHT 02 SITE: M.C.C. BUS INSULATION AND PHASING TEST CERTIFICATE DATE JOB NO. LOCATION MODULE EQUIPMENT DESCRIPTION MANUFACTURER MODEL NO. SERIAL NO. TAG NO. TYPE VOLTAGE RATING SHT of SLD No CURRENT RATING POWER RATING EQUIPMENT USED (FOR TEST) MANUFACTURER MODEL NO. VOLTAGE SERIAL NO. ACCURACY/FULL SCALE ENVIRONMENTAL CONDITIONS TEMPERATURE RESISTANCE VALUE IN MEG OHMS PHASE TO PHASE A-B B-C EQUIPMENT INSPECTION COMPLETED PHASE TO GROUND C-A A B INSPECTORS INITIALS MECHANICAL COMPLETION NEC COMPLIANCE C DATE DWG AND STD COMPLIANCE VERIFIED REMARKS: Check Bus Phasing COMPLETED BY WITNESSED BY ACCEPTED BY APPROVED BY COMPANY SIGNATURE PRINT NAME DATE GOC© BP Exploration 1989 - 2001 All Rights Reserved Americas REV. 1 Project Title: Maintenance No: Work Pack No: SH1 No: MC1 No: FORM EE3 - SHT 01 SITE: CIRCUIT BREAKER, LV POWER TEST CERTIFICATE DATE: JOB NO. SLD No. SHT of LOCATION Equipment Used (for test) Manufacturer Model No. Setting Serial No. Accuracy MODULE Feeder Identification Cubicle Number Trip Units - Type or Style Number Substation Switchgear Unit Number Trip Coil Rating Breaker Type Style or Serial Number Time Delay Range Breaker Manufacturer Instantaneous Setting Interrupting Capacity Short Time Delay Setting Procedure 9.2 Initial: Pre-Installation Complete Date: Long Time Delay Setting Procedure 9.3 - Drawout Air Initial: Circuit Inspection Complete Date: Published Trip Time Min. Trip Unit Setting 1. Instantaneous Trip Setting Max. Phase A Phase B Phase C 2. Inverse Time Setting 3. Instantaneous Pick-up (Amps) 4. Normal Pick-Up (Amps) 5. Inverse Time at % current Min. Sec. Min. Sec. Min. Sec. Inverse Time at % current Min. Sec. Min. Sec. Min. Sec. Inverse Time at % current Min. Sec. Min. Sec. Min. Sec. 6. Contact Resistance 7. Others: REMARKS: COMPLETED BY WITNESSED BY ACCEPTED BY APPROVED BY COMPANY SIGNATURE PRINT NAME DATE GOC© BP Exploration 1989 – 2001 All Rights Reserved Americas REV. 1 Project Title: SH1 No : Maintenance No: MC1 No : FORM EE3 SHT 02 SITE: Work Pack No: Source/Equipment No: MOLDED CASE BREAKER TEST REPORT per 9.3.1.2 d SHT OF DATE JOB NO. LOCATION MODULE MCC TAG NO. MCC MANUFACTURER MCC DESCRIPTION MCC RATINGS TRIP TIME 300% OF RATED CURRENT BREAKER NO. TYPE & MFG. INFORMATION POLES/ RATING SERVICE PHASE A PHASE B PHASE C INST. TRIP TIME REMARKS COMPILED BY APPROVED BY COMPANY SIGNATURE NAME DATE GOC © BP Exploration 1989 – 2001 All Rights Reserved Americas REV. 1 Project Title: Maintenance No: Work Pack No: SH1 No: MC1 No: FORM EE3 - SHT 03 SITE: MEDIUM VOLTAGE CIRCUIT BREAKER TEST CERTIFICATE DATE JOB NO. SLD No LOCATION MODULE Equipment Used (for test) Manufacturer Model No. Setting Serial No. Accuracy Switchgear/MCC Tag No. Switchgear Manufacturer Switchgear Description Switchgear Voltage Circuit Number Trip Device Type Circuit Breaker Manufacturer Circuit Breaker Type Serial No. Model No. Long Time Range Short Time Range SHT of Instantaneous Range Environmental Condition Panel Temp. Procedure 9.2 Initial: Pre-Installation Complete Date: Procedure 9.3 - Drawout Air Initial: Circuit Inspection Complete Date: SETTINGS Phase A S/T L/T Phase B Inst. L/T S/T Phase C Inst. L/T S/T Inst. RESULTS L/T S/T Instantaneous Phase Current Current Current A Time Time Time Phase Current Current Current B Time Time Time Phase Current Current Current C Time Time Time WITNESSED BY ACCEPTED BY REMARKS: COMPLETED BY APPROVED BY COMPANY SIGNATURE PRINT NAME DATE GOC© BP Exploration 1989 - 2001 All Rights Reserved Americas REV. 1 Project Title: Maintenance No: Work Pack No: SH1 No: MC1 No: FORM EE3 - SHT 04 SITE HIGH VOLTAGE LIMITED OIL INTERRUPTER TEST REPORT DATE JOB NO. Equipment (used for tests) SLD No SHT of LOCATION Manufacturer MODULE Model Number Serial Number Control Device: Trip Coil Ohms Amps Close Ohms Amps Motor Volts Amps (normal running current) Amps (starting current) Mechanical Operation Open and Close operation at Minimum control voltage: Volts Open and Close operation at Minimum control voltage: Volts Time Test: A Phase B Phase C Phase Trip Time MS. MS. MS. Close time MS. MS. MS. √ _________ √ _________ √ _________ Current Path Resistance (DC Micro Ohms at 100 Amps minimum) Low Frequency Withstand (1 Minute) Major Insulating Components: kV. Control Wiring Volts Insulation Oil: Dielectric Breakdown Voltage kV. at °C REMARKS: COMPLETED BY WITNESSED BY ACCEPTED BY APPROVED BY COMPANY SIGNATURE PRINT NAME DATE GOC© BP Exploration 1989 - 2001 All Rights Reserved Americas REV. 1 Project Title: Maintenance No: Work Pack No: SH1 No: MC1 No: FORM EE4 - SHT 01 SITE: CONTACT STARTER TEST CERTIFICATE DATE: SLD No JOB NO: SHT of LOCATION: MODUL Switchboard Number: Location: Circuit Title: System: Win. Overcurrent Trip Setting Amps Seconds Drive Full Load Current Amps Amps Motor Fuse Ratings Amps Volts System Voltage Timer T. Setting Control Fuse Size Control Voltage Insulation Resistance Megohms Subsystem: Volts Test Volts Volts Yes No Control Circuits correct to Schematic Diagram Number Remote Control and Annunciation Tested and Correct * * Space Heater Circuit Tested Thermal Overload Test Results Current %FLC Trip Time (secs) Amp L1 L2 Single Phase Testing Result (80% FLC) Remarks L3 115 No Trips 200 Hot/ Cold 600 Hot/ Cold Circuit Amps L1-L2 L1-L3 L2-L3 Trip Time (Secs) Ground Fault Test Results Circuit L1 L2 L3 Min. Amps to Operate Trip Time Set CT Ratio (Protection): Ammeter Test Results Location Test Amps CT Ratio (Metering): Reading Reading Reading REMARKS: COMPLETED BY WITNESSED BY ACCEPTED BY APPROVED BY COMPANY SIGNATURE PRINT NAME DATE ** Witnessing Authority to Perform Test GOC© BP Exploration 1989 - 2001 All Rights Reserved Americas REV. 1 Project Title: Maintenance No: Work Pack No: SH1 No: MC1 No: FORM EE4 - SHT 02 SITE: MOTOR THERMAL OVERLOAD RELAY TEST CERTIFICATE Date Project Number SLD No Location Module Equipment Used (for test) Manufacturer Model Number Setting Serial Number Accuracy Motor Tag Number H.P. Service MCC Number Circuit Breaker Trip Starter Size SHT of F.L. Amps Volts RPM Motor Manufacturer O.L. Heater Control Device Interlocks Mechanical Cond. Motor Bearing Lube Contact Align Conduit Rotation Run % Rated Current High Speed A B C Low Speed Time At: Time At: Should be: Should be: Actual: Actual: A B C REMARKS: COMPLETED BY WITNESSED BY ACCEPTED BY APPROVED BY COMPANY SIGNATURE PRINT NAME DATE GOC© BP Exploration 1989 - 2001 All Rights Reserved Americas REV. 1 Project Title: Maintenance No: Work Pack No: SH1 No: MC1 No: FORM EE4 - SHT 03 SITE: VARIABLE SPEED DRIVES TEST CERTIFICATE DATE: SLD No JOB NO: Manufacturer Power Semiconductors Input Diode SHT of LOCATION: Tag Number MODULE Model Number Volts Amperes Volts Amperes Hz Running Hours Volts Amperes Hz Power Factor dV/dt dl/dt Service PIV Output Transistor Complete Controller Unit Functional Test Load Test * * 100% Load Efficiency Running Time * * 50% Load * * 25% Load Control Print Circuit Boards Burn-In Test (0ºC - 60ºC - 0ºC 22 Hours Minimum) One Hour at Each Temperature: ºC To ºC Back To ºC Total Hours: REMARKS: COMPLETED BY WITNESSED BY ACCEPTED BY APPROVED BY COMPANY SIGNATURE PRINT NAME DATE ** Witnessing Authority to perform test. GOC© BP Exploration 1989 - 2001 All Rights Reserved Americas REV. 1 Project Title: Maintenance No: Work Pack No: SH1 No: MC1 No: FORM EE5 - SHT 01 SITE: MEDIUM VOLTAGE AIR SWITCH INSPECTION CERTIFICATE Date SLD No Project Number Location Module Equipment Used (for test) Manufacturer Model Number Setting Serial Number Accuracy Switchgear Tag Number SHT of Feeder Identification Other Identification Air Switch Data Manufacturer Type Style/ Serial No. Current Rating Fuse Information Voltage Rating System Voltage Inspection Check Point Condition Check Point Notes Physical Damage Contact Alignment Cleanliness Contact Wipe Mechanical Operator Contact Pressure Main Contacts Phase Barriers Arc Contacts Hardware Tightness Arc Chutes Fuse Holders Arc Interrupter Sequence Interlocks C.T.’s, No ____ Ratio ___:5 Metering Condition Notes Electrical Tests Contact Resistance in Milliohms Insulation Resistance: Ø AØ Switch Closed A-GND B-GND C-GND A-B BØ B-C CØ C-A A Switch Open B C Volts REMARKS: Switch assembly to Transformer throat checked. COMPLETED BY WITNESSED BY ACCEPTED BY APPROVED BY COMPANY SIGNATURE PRINT NAME DATE GOC© BP Exploration 1989 - 2001 All Rights Reserved Americas REV. 1 Project Title: Maintenance No: Work Pack No: SH1 No: MC1 No: FORM EE6 - SHT 01 SITE: TWO-WINDING POWER TRANSFORMER TEST CERTIFICATE DATE: JOB NO: SLD No SHT LOCATION: Equipment Used (for test) Model Number Serial Number MODULE: Initial: Procedure 9.6 - Liquid Filled Transformer Inspection Complete Oil Mineral Oil Other Air Location of Tests Transformer Age Sealed Gas Top Oil Temperature Weather % Humidity High Side KV Low Side KV Y Y Gas Blanketed B U S H I N G S ∆ ∆ Neutral Date: Air Temperature Type/ Class Free Breathing Manufacturer of KVA Conservator Type Class Gallons of Oil DWG. No. Cat. No. KV Year Date Last Test Over-All Tests (Doble or Equal) Equivalent 10 KV Readings Milliamperes Watts Test Connections Test Winding Energized Winding Grounded 1 High Low 2 High 3 Low 4 Low Winding Guarded Test KV Meter Multiplier Reading Meter Milliampere Reading Multi-plier Key to Insulation Rating % Power Factor Watts Measured Cor. 20° G=Good C I=Investigate ---- ---- ---- ---- Low D=Deteriorated B=Bad (remove or Insulation Rating CH High High Calculated Results ---- ---- ---- ---- ---- ---- ---- ---- CL CHL ---- (Test 1 minus Test 2) ---- (Test 3 minus Test 4) - Bushing Tests (Doble or Equal) Equivalent 10 KV Readings Milliamperes Watts Test Connections Line No. Bush. No Phase Bushing Serial No. Test KV Meter Multiplier Reading Meter Milliampere Reading Multi-plier % Power Factor Watts Measured Cor. 20° C Collar Tests (Watts / Current) Top Insulation Rating HIGH SIDE 1 2 3 4 SIDE 6 LOW 5 7 8 9 10 11 12 REMARKS: Oil Sample Tests: COMPLETED BY WITNESSED BY ACCEPTED BY APPROVED BY COMPANY SIGNATURE PRINT NAME DATE GOC© BP Exploration 1989 - 2001 All Rights Reserved Americas REV. 1 Project Title: Maintenance No: Work Pack No: SH1 No: MC1 No: FORM EE6 - SHT 02 (SIDE 1) SITE: TRANSFORMER TURNS RATIO TEST CERTIFICATE SLD No JOB No: DATE: LOCATION: Equipment Used (for test) Setting Serial Number Accuracy Manufacturer Model Number Class Insulation Type Dry MODULE: Manufacturer Model Number KVA SHT of Phase Mineral Oil Serial Number Hertz __________ Temperature Rise Voltage Impedance % at H.V. °C L.V. Winding Configuration On Back Of This Sheet Taps Available Tap Position Primary Voltage As Found Tap: As Left Tap: Voltage Measurements Initial Secondary (Tap ) Final Secondary (Tap ) Primary Voltage A-B A-N A-B A-N A-B B-C B-N B-C B-N B-C A-C C-N A-C C-N A-C Turns Ratio Determination As Left Primary Nameplate Secondary Calculated Jumper Ratio Tap Megger Readings High to Low & Ground Megohms Low to High & Ground Megohms High to Low Megohms REMARKS: COMPLETED BY WITNESSED BY ACCEPTED BY APPROVED BY COMPANY SIGNATURE PRINT NAME DATE GOC© BP Exploration 1989 - 2001 All Rights Reserved DOUBLE SIDE FORM Americas REV. 1 Sketch Winding Configuration & Vector Diagram Below GOC © BP Exploration 1989 - 2001 All Rights Reserved DOUBLE SIDE FORM FORM EE6 - SHT 02 (Side 2) Americas REV. 1 Project Title: Maintenance No: Work Pack No: SH1 No: MC1 No: FORM EE6 - SHT 03 SITE: 3-WINDING POWER TRANSFORMER TEST CERTIFICATE DATE PROJECT No. Manufacturer Serial Number Tag. Number KVA SLD No SHT of LOCATION MODULE Procedure 9.6 - Liquid Filled Initial: Date: Transformer Inspection Secondary Voltage Primary Voltage Test Equipment Type Manufacturer Model Number Serial number 1 2 3 4 Rating Type Phase Frequency Hertz Temperature Rise Insulating Liquid Class H. Winding X. Winding V. kVA kVA kVA Y. Winding V. kVA kVA kVA V. kVA kVA kVA Additional Tap Voltages H Winding X Winding Connections for Operation Transformers in Bank To Transformer Phase Connected Transformers in Performance Dielectric Tests Based on a Applied Loading of: H. Winding X Winding kVA kVA Y Winding kVA To Transformer To Phase Connected Insulation Levels kV Basic Lightning Low Frequency Voltage** X Winding kV Voltage Y Winding kV Impulse insulation Level H. Winding Items Insulation Level ----------- H Line Induced Line to Line kV H Neutral Voltage Line to Ground kV X Line ** To other windings and ground X Neutral Y Line COMPLETED BY WITNESSED BY ACCEPTED BY ----------------------------------------APPROVED BY COMPANY SIGNATURE PRINT NAME DATE GOC© BP Exploration 1989 - 2001 All Rights Reserved Americas REV. 1 Project Title: Maintenance No: Work Pack No: SH1 No: MC1 No: FORM EE7 - SHT 01 SITE: NEUTRAL GROUNDING RESISTOR TEST CERTIFICATE DATE: System SLD No JOB NO: LOCATION: Subsystem Location SHT of MODULE: Equipment Description: Transformer Mount Switchgear Mount C.T. Resistor: Ratio _________________ OHMS _________________ Stand Alone Mount Rated Volts Rated Amps Description of Tests and/or Inspections carried out: Per Procedure 9.12 _________________ Contin. 10 Sec. Megger Volts _______________ D.C. Ohms resistance, to frame and ground with “IN” and “OUT” leads disconnected ____________________ Verified by _____________________________ Witnessing Authority Test Certificate Numbers: For C.T. (If applicable) REMARKS COMPLETED BY WITNESSED BY ACCEPTED BY APPROVED BY COMPANY SIGNATURE PRINT NAME DATE GOC© BP Exploration 1989 - 2001 All Rights Reserved Americas REV. 1 Project Title: Maintenance No: Work Pack No: SH1 No: MC1 No: FORM EE8 - SHT 01 SITE: HEAT TRACE TAPE INSPECTION CERTIFICATE DATE SLD No PROJECT No Line Number LOCATION Heater Number Manufacturer SHT of Model / Cat. Number MODULE Service Voltage Wattage Watts/Foot Equipment Used (for test) Manufacturer of Megger Model Number Serial Number Setting Accuracy Environmental/Area Classification Temperature Circuit Breaker Number: Procedure 9.13 - Heat Trace Component Inspection Complete Initial: Date: Reading / Remarks Date Initials Megger Test on Reel (Before Installation) Continuity Test on Reel (Before Installation) Piping Completed (Ready to Install Heat Tape) Megger Before Insulation Continuity Test Before Insulation General Heat Tape Inspection Complete (Release for Insulation) Insulation Completed and Inspected Megger After Insulation System Inspection Conduit Seals Mechanical Completion Code Compliance DWG & STD Compliance Date Verified Wire Seals Power and Splice Connections Transmitter and RTD Remarks: COMPLETED BY WITNESSED BY ACCEPTED BY APPROVED BY COMPANY SIGNATURE PRINT NAME DATE GOC© BP Exploration 1989 - 2001 All Rights Reserved Americas REV. 1 Project Title: Maintenance No: Work Pack No: SH1 No: MC1 No: FORM EE8 - SHT 02 SITE: ELECTRICAL HEAT TRACE PERFORMANCE CERTIFICATE DATE SLD No PROJECT NO. TEST EQUIPMENT SHT of LOCATION MANUFACTURER MODULE MODEL NO. SERIAL NO. DIGITAL VOLT-OHM METER CURRENT PROBE/METER TEMPERATURE PROBE HEATER NO. PANEL NO. CKT. BKR. NO. SERVICE DESCRIPTION END OF LINE LOCATION EL. HEATER MFG. HEATER TYPE BREAKER TYPE GND. FLT. DET. 30 10 HEATER SIZE BREAKER SIZE TOTAL CKT. LOAD DESIGN HTR. VOLT DESIGN FT. HTR. TOT. LGT. INSTALL VAC INSULATION TYPE NORM. LINE TEMP. W/FT. A. AREA CLASSIFICATION CL. W. HTR. TOT. LGT. DESIGN COL. DIV. FT. INSULATION THICKNESS °F MAINTAIN DESIGN TEMP. °F MAX. OPER. TEMP. °F CONTROL THERMOSTAT AMBIENT LINE MFG. MOD. NO. SET DEC. °F RESET INC. °F LOW TEMP. ALARM SW. MFG. MOD. NO. SET DEC. °F RESET INC. °F END OF LINE MONITOR MFG. MOD. NO. TYPE VOLTS A.C. * * PERFORMANCE DATA CURRENT AMPS PANEL E.O LINE A0 B0 C0 POWER WATTS TEMPERATURE N TOTAL PER FT. PIPE AMB. START UP AFTER 10 MIN AFTER 4 HRS REF. DWG. NO'S. (VOLT)(AMP) HRT.LGT. = WATT / FT REMARKS COMPLETED BY WITNESSED BY ACCEPTED BY APPROVED BY COMPANY SIGNATURE PRINT NAME DATE ** Witnessing Authority to perform test. GOC© BP Exploration 1989 - 2001 All Rights Reserved Americas REV. 1 Project Title: Maintenance No: Work Pack No: SH1 No: MC1 No: ELECTRICAL GROUND SYSTEM TEST CERTIFICATE DATE: JOB NO. FORM EE9 - SHT 01 SITE: SLD No SHT of LOCATION Equipment Used (for test) Manufacturer Model Number Setting Serial Number Accuracy MODULE Note: This Test and Inspection Report is for the * Main Electrical Ground System (*check as appropriate) * Isolated Instrument Ground System Reference Drawings: 1. Verify Primary grid conductors are correct size and type in accordance with drawings. 2. Verify ground conductor burial depth and routing per drawings and specifications. 3. Check thermal and/or compression connections checked (no cold joints or burn outs.) INITIALS/DATE 1 2 3 4. Check thermal and/or compression connection for application of anti corrosion compound. 4 5. Verify ground rod locations diameter, length and material and installation per drawings. 5 6. Check ground rod connections to verify integrity and tightness. 6 7. Verify location, type, size and insulation color of equipment taps per drawings. Be sure all are protected form physical damage during work. 7 8. Verify system ground rod resistance-to-earth checked and recorded. 8 9. Verify all field revisions are recorded on “as-built” drawings. 9 Connection: Tag Number or Ground Point Conductor Size and Type Resistance to Ground Ambient Temperature Environmental Conditions Taps (9) Initials / Date ohms ohms ohms ohms ohms ohms COMPLETED BY WITNESSED BY ACCEPTED BY APPROVED BY COMPANY SIGNATURE PRINT NAME DATE GOC© BP Exploration 1989 - 2001 All Rights Reserved Americas REV. 1 Project Title: Maintenance No: Work Pack No: SH1 No: MC1 No: FORM EE9 - SHT 02 SITE: GROUNDING RESISTANCE TEST CERTIFICATE DATE: JOB NO: SLD No LOCATION: Equipment Used (for test) Manufacturer Model Number Setting Serial Number Accuracy Electrode Number & Location (From Approved Drwgs.) Ground Resistance 1. ohms 2. ohms 3. ohms 4. ohms 5. ohms 6. ohms 7. ohms 8. ohms 9. ohms 10. ohms 11. ohms 12. ohms SHT of MODULE: Conductor Size and Type Remarks REMARKS: COMPLETED BY WITNESSED BY ACCEPTED BY APPROVED BY COMPANY SIGNATURE PRINT NAME DATE GOC© BP Exploration 1989 - 2001 All Rights Reserved Americas REV. 1 Project Title: Maintenance No: Work Pack No: SH1 No: MC1 No: FORM EE10 - SHT 01 SITE: HAZARDOUS LOCATIONS TEST CERTIFICATE DATE: System SLD No JOB NO: LOCATION: Subsystem Location SHT of MODULE: Equipment Description: Description of Tests and/or Inspections carried out: Test Certificate Numbers: REMARKS: This form is to be used to denote any equipment departure from the standards required. Any such entry must be resolved with the Witnessing Authority for approval or correction before it is considered for Certification. COMPLETED BY WITNESSED BY ACCEPTED BY APPROVED BY COMPANY SIGNATURE PRINT NAME DATE GOC© BP Exploration 1989 - 2001 All Rights Reserved Americas REV. 1 Project Title: Maintenance No: Work Pack No: SH1 No: MC1 No: FORM EE11 - SHT 01 SITE: INSTRUMENTS TRANSFORMER RATIO TEST CERTIFICATE DATE: JOB NO: SLD No LOCATION: MODULE: Switchboard Number Location System Subsystem Circuit Title Data Sheet Compartment number Protection Type Ratio Class Line 1 SHT of Line 2 Line 3 Serial Numbers: Procedure 9.18 completed: Signed: Line 1 Volts Date: Line 2 Amps Volts COMPLETED BY WITNESSED BY Line 3 Amps Volts ACCEPTED BY Amps APPROVED BY COMPANY SIGNATURE PRINT NAME DATE GOC© BP Exploration 1989 - 2001 All Rights Reserved Americas REV. 1 Project Title: Maintenance No: Work Pack No: SH1 No: MC1 No: PRIMARY INJECTION TEST REPORT DATE: FORM EE12 - SHT 01 SITE: SLD No JOB NO: LOCATION: Switchboard Number: SHT of MODULE: System: Circuit Title: Subsystem: Compartment Number: Data Sheet: Serial Number: Manufacturer: Location: Relay Type: C.T. Ratios: Protection Type: C.T. Ratios: C.T. Serial Numbers: C.T. Test Certificates Available: Yes No Signature Date Primary Injection Test Phase Injected Primary Current & Phase Secondary Current & Spill Current & Phase Phase Comments Circuit Injected (Sketch: Use Extra Sheet if Necessary) REMARKS: COMPLETED BY WITNESSED BY ACCEPTED BY APPROVED BY COMPANY SIGNATURE PRINT NAME DATE GOC© BP Exploration 1989 - 2001 All Rights Reserved Americas REV. 1 Project Title: Maintenance No: Work Pack No: SH1 No: MC1 No: FORM EE12 - SHT 02 SITE: SECONDARY INJECTION TEST REPORT DATE: SLD No JOB NO: LOCATION: Switchboard Number: System: Circuit Title: Subsystem: Compartment Number: Data Sheet: Serial Number: Manufacturer: Location: Relay Type: C.T. Ratios: Protection Type: Element % Setting P.U. D.O. SHT of MODULE: Time Set Inj. Sec.Current Curve Time Actual Time Relay Setting Current Volts: Permanent Aux. Supply: Sign: Time Date: Circuit Injected (Sketch: Use Extra Sheet if Necessary) COMPLETED BY WITNESSED BY ACCEPTED BY APPROVED BY COMPANY SIGNATURE PRINT NAME DATE GOC© BP Exploration 1989 - 2001 All Rights Reserved Americas REV. 1 Project Title: Maintenance No: Work Pack No: SH1 No: MC1 No: FORM EE12 - SHT 03 SITE: RELAY INSPECTION REPORT DATE: SLD No JOB NO: LOCATION: SHT of MODULE: EQUIPMENT USED (FOR TEST) MANUFACTURER MODEL NO. SETTING SERIAL NO. ACCURACY CIRCUIT LOCATON CIRCUIT DESIGNATION TYPE PHASE OR LOCATION INPANEL MFG STYLE NO FUNCTION C.T. RATIO P. T. RATIO SHUNT TAP RANGE INSTANTANEOUS RANGE TIME OPERATIONS INDICATOR INSTANTANEOUS OPERATIONS INDICATOR AMPS RELAY MODEL NO & SERIAL NO. SERIAL OR CIRCUIT AMPS RELAY MODEL NO & SERIAL NO CONTACTS COVER DIRTY GLASS TIGHT PITTED GLASS CLEAN OPERATIONS INDICATOR GASKET TIGHT ARMATURE FREE CONDITION TARGET FREE DUST INSTANTANEOUS ATTACHMENT RUST ARMATURE FREE IRON FILINGS TARGET FREE GEARINGS / PIVOTS DISC. OPERATION SHORTING BARS IN PLACE OTHERS: CONNECTIONS TIGHT COMPLETED BY WITNESSED BY ACCEPTED BY APPROVED BY COMPANY SIGNATURE PRINT NAME DATE GOC© BP Exploration 1989 - 2001 All Rights Reserved Americas REV. 1 Project Title: SH1 No : Maintenance No: MC1 No : FORM EE12- SHT 04 SITE: Work Pack No: Source/Equipment No: OVER CURRENT RELAY TEST REPORT SHT EQUIPMENT USED (FOR TEST) MANUFACTURER MODEL NO. SETTING SERIAL NO. ACCURACY OF COMPLETE NAMEPLATE DATA NUMBER OF POINTS TO BE INSPECTED LOCATION SERIAL NUMBER STYLE NUMBER RELAY VALUES SETTINGS TAP (AMPS) TIME DIAL INST. PICKUP AMPS 1.5X 2X 2.5X 3X 5X 7X INSTRUMENT (AMPS) TARGET OPERATIONS (AMPS DC) INSULATION TEST (MEGOHMS) REMARKS COMPILED BY APPROVED BY COMPANY SIGNATURE NAME DATE GOC© BP Exploration 1989 - 2001 All Rights Reserved Americas REV. 1 Project Title: Maintenance No: Work Pack No: SH1 No: MC1 No: FORM EE12 - SHT 05 SITE: INSTANTANEOUS OVER CURRENT RELAY TEST REPORT DATE: JOB NO: SLD No LOCATION: MODULE: EQUIPMENT USED (FOR TEST) MANUFACTURER MODEL NO. SETTING SERIAL NO. ACCURACY EQUIPMENT BP RELAY IDENTIFICATION IDENTIFICATION NAME-PLATE DATA PHASE DATE INST. TRIP AMPS SETTING INS. RES. VOLTS DC INST. TRIP AMPS OPER. IND. AMPS SHT of TEST WITHIN LIMITS SERIAL NO. CURVE REMARKS A B C COMPLETED BY WITNESSED BY ACCEPTED BY APPROVED BY COMPANY SIGNATURE PRINT NAME DATE GOC© BP Exploration 1989 - 2001 All Rights Reserved Americas REV. 1 Project Title: Maintenance No: Work Pack No: SH1 No: MC1 No: FORM EE12 - SHT 06 SITE: OVER VOLTAGE OR UNDER VOLTAGE RELAY TEST REPORT DATE: JOB NO: SLD No SHT of LOCATION: MODULE: EQUIPMENT USED (FOR TEST) MANUFACTURER MODEL NO. SETTING SERIAL NO. ACCURACY EQUIPMENT BP RELAY IDENTIFICATION IDENTIFICATION NAME-PLATE DATA POINTS TO BE TESTED LOCATION SERIAL NO. SETTING STYLE NO. TAP VOLTS CURVE RELAY TESTS TIME DIAL PICK-UP VOLTS % % % % % % TARGET OPER. INSUL. TEST AMPS DC MEGOHMS REMARKS: COMPLETED BY WITNESSED BY ACCEPTED BY APPROVED BY COMPANY SIGNATURE PRINT NAME DATE GOC© BP Exploration 1989 - 2001 All Rights Reserved Americas REV. 1 Project Title: Maintenance No: Work Pack No: SH1 No: MC1 No: FORM EE12 - SHT 07 SITE: POWER FACTOR RELAY TEST REPORT DATE: SLD No JOB NO: SHT of LOCATION: MODULE: EQUIPMENT USED (FOR TEST) MANUFACTURER MODEL NO. SETTING SERIAL NO. ACCURACY EQUIPMENT BP RELAY IDENTIFICATION IDENTIFICATION NAME-PLATE DATA SPECIFIED RELAY SETTINGS TAP SETTING DATE ZERO ADJ. TEST AMPS OTHER INS. RES. POWER FACTOR TO CLOSE CONTACTS VOLTS AC AS FOUND AS LEFT COMPLETED BY CURVE WITNESSED BY SERIAL NO. ACCEPTED BY REMARKS APPROVED BY COMPANY SIGNATURE PRINT NAME DATE GOC© BP Exploration 1989 - 2001 All Rights Reserved Americas REV. 1 Project Title: Maintenance No: Work Pack No: SH1 No: MC1 No: FORM EE12 - SHT 08 SITE: FREQUENCY RELAY TEST REPORT DATE: SLD No JOB NO: SHT of LOCATION: MODULE: EQUIPMENT USED (FOR TEST) MANUFACTURER MODEL NO. SETTING SERIAL NO. ACCURACY EQUIPMENT BP RELAY IDENTIFICATION IDENTIFICATION NAME-PLATE DATA CURVE SETTING LOCATION SERIAL NO. STYLE NO. TYPES SET FREQ. TIME DIAL FROM CYCLES RELAY TESTS TO CYCLES TIME TO CLOSE (CYCLE) OPER. TARGET INSUL. FREQ. OPER. TEST AMPS MEGOHMS DC REMARKS: COMPLETED BY WITNESSED BY ACCEPTED BY APPROVED BY COMPANY SIGNATURE PRINT NAME DATE GOC© BP Exploration 1989 - 2001 All Rights Reserved Americas REV. 1 Project Title: Maintenance No: Work Pack No: SH1 No: MC1 No: FORM EE12 - SHT 09 SITE: TRANSFORMER DIFFERENTIAL RELAY TEST REPORT DATE: JOB NO: SLD No SHT of LOCATION: MODULE: EQUIPMENT USED (FOR TEST) MANUFACTURER MODEL NO. SETTING SERIAL NO. ACCURACY EQUIPMENT BP RELAY IDENTIFICATION IDENTIFICATION NAME-PLATE DATA LOCATION SERIAL NO. STYLE NO. 1 TAP AMPS 2 TAP AMPS COMPLETED BY 3 TAP AMPS 4 TAP AMPS WITNESSED BY MIN. TRIP AMP CURVE DIFFERENTIAL CHARACTERISTICS A B ACCEPTED BY HARMONIC REST. TARGET OPER INSUL TEST CHAR AMP DC MEGOHMS APPROVED BY COMPANY SIGNATURE PRINT NAME DATE GOC© BP Exploration 1989 - 2001 All Rights Reserved Americas REV. 1 Project Title: SH1 No : Maintenance No: MC1 No : FORM EE12 SHT 10 SITE: Work Pack No: Source/Equipment No: REVERSE POWER RELAY TEST REPORT DATE SHT JOB NO. LOCATION EQUIPMENT USED (FOR TEST) MANUFACTURER MODEL NO. SETTING SERIAL NO. ACCURACY EQUIPMENT IDENTIFICATION BP IDENTIFICATION NUMBER OF POINTS TO BE INSPECTED LOCATION SERIAL NUMBER STYLE NUMBER TAP (AMPS) MODULE RELAY NAME PLATE DATA SETTINGS OF CURVE RELAY TEST VALUES PICK-UP WATTS 2X 4X 6X 8X 10X 12X TARGET OPER (AMPS DC) INSUL TEST (MEGOHMS) SECONDS-CYCLE REMARKS COMPILED BY APPROVED BY COMPANY SIGNATURE NAME DATE GOC© BP Exploration 1989 - 2001 All Rights Reserved Americas REV. 1 Project Title: Maintenance No: Work Pack No: SH1 No: MC1 No: FORM EE13 - SHT 01 SITE: MOTORS AND MOTOR CIRCUITS TEST CERTIFICATE DATE: SLD No JOB NO: LOCATION: EQUIPMENT USED (FOR TEST) MANUFACTURER SHT of MODULE: ELEC. DATA SHEET NUMBER MODEL NO. SERIAL NO. VOLTAGE ACCURACY (FULL SCALE READING) MEG OHMS ENVIRONMENTAL CONDITIONS TEMP POWER SYSTEM VOLTS FREQUENCY & PHASE °F AMPS MOTOR NO. HP. FL AMPS VOLTS SERVICE TEMP CODE MCC NO. MOTOR MFG CIRCUIT BREAKER TRIP STARTER SIZE C L HEATER CONTACT RMP ALIGN CONTROL DEVICE INTERLOCKS CONDUIT SEALS MECH COND MOTOR BEARING LUBE ROTATION * * PROCEDURE 9.7 - ELECTRIC MOTOR INSPECTION COMPLETE INITIAL: RUN * * DATE: MEGGER PHASE TO PHASE DESCRIPTION AB BC CA PHASE TO NEUTRAL A/B/C TO NEUTRAL PHASE TO GROUND A B C NEUTRAL MOTOR WINDINGS POWER LEADS CONTROL CIRCUIT REMARKS: NOTE: Ungrounded Star or Delta wound motors with no access to neutral, require only one megger reading: all 3 phases together to ground. Phase to phase requires precision resistance readings comparison. COMPLETED BY WITNESSED BY ACCEPTED BY APPROVED BY COMPANY SIGNATURE PRINT NAME DATE ** Witnessing Authority to perform test. GOC© BP Exploration 1989 - 2001 All Rights Reserved Americas REV. 1 Project Title: Maintenance No: Work Pack No: SH1 No: MC1 No: FORM EE13 - SHT 02 SITE: ROTATING MACHINERY TEST CERTICATE DATE: SLD No JOB NO: SHT of LOCATION: EQUIPMENT USED (FOR TEST) MODULE: MODEL NO. MANUFACTURER (Requires Doble or Equiv. Mfr.) SETTING SERIAL NO. ACCURACY EQUIPMENT TESTED MANUFACTURER MODEL NO. SERIAL NO. SERVICE FACTOR STATOR TEMP KV RPM KVA HP PF TYPE FORM AGE MFR. DATE LAST TEST LAST TEST SHEET NO. ROTOR KW INSULATION CLASS STATOR CORONA CONTROL CLASS EQUIVALENT 10 KV READINGS MILLIAMPERES LINE NO. PHASE TEST METER KV READING WATTS MILLI- MULTIPLIER AMPERES METER % % POWER PF TEST TIP UP KV READING MULTIPLIER WATTS FACTOR RIV MEASUREMENTS MICROVOLTS 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 COMPLETED BY WITNESSED BY ACCEPTED BY APPROVED BY COMPANY SIGNATURE PRINT NAME DATE GOC© BP Exploration 1989 - 2001 All Rights Reserved Americas REV. 1 Project Title: SH1 No : Maintenance No: MC1 No : FORM EE14 SHT 01 SITE: Work Pack No: Source/Equipment No: BATTERY LOAD TEST DATA CERTIFICATE DATE SHT OF JOB NO. LOCATION MODULE Battery Manufacturer Type Start Time Finish Time Float / Voltage Discharge Current Procedure 9.8 - Battery & Battery Charger Inspection Complete Initial: Min. Term. Volts Min. Volts / Cell Average Cell Temp. Date: Time Cell Initial Volts Volts Volts Volts Volts Volts Volts Volts Volts Volts Volts Volts Volts Volts Initial Hyd. Reading Final Hyd. Reading Remark Load Current Terminal Voltage COMPILED BY APPROVED BY COMPANY SIGNATURE NAME DATE GOC© BP Exploration 1989 - 2001 All Rights Reserved Americas REV. 1 Project Title: Maintenance No: Work Pack No: SH1 No: MC1 No: FORM EE14 - SHT 02 SITE: BATTERY TEST CERTIFICATE DATE: SLD No JOB NO: SHT of LOCATION: MODULE: Battery Information Test Cell Number Number of Cells Volts Procedure 9.8 - Battery & Battery Charger Inspection Complete Initial: Type Sp. Gr. Date: Normal Sp. Gr. Battery Area Ambient Temperature Manufacturer Charge Equalized initiated Type of Cell Date Time Electrolyte Level: As Found: Water Added: Quarts Total: Battery Term. Volt Average Volt / Cell Recorded Date: Term Float Volts Cell Volts 1. 2. 3. 4. 5. 6. 7. 8. 9. 10. 11. 12. 13. 14. 15. 16. 17. 18. 19. 20. Hydro Meter Temp Cell °F 21. 22. 23. 24. 25. 26. 27. 28. 29. 30. 31. 32. 33. 34. 35. 36. 37. 38. 39. 40. COMPLETED BY Volts Hydro Meter Temp °F Cell Volts Volts Hydro Meter Temp °F Rem. 41. 42. 43. 44. 45. 46. 47. 48. 49. 50. 51. 52. 53. 54. 55. 56. 57. 58. 59. 60. WITNESSED BY ACCEPTED BY APPROVED BY COMPANY SIGNATURE PRINT NAME DATE GOC© BP Exploration 1989 - 2001 All Rights Reserved Americas REV. 1 Project Title: Maintenance No: Work Pack No: SH1 No: MC1 No: FORM EE15 - SHT 01 SITE: UNINTERRUPTED POWER SUPPLY (UPS) TEST CERTIFICATE DATE: JOB NO: SLD No SHT of LOCATION: Equipment Number Location System Subsystem Rating MODULE: Data Sheet K.V.A. Serial Number Voltage In D.C. Volts Inverter Number Voltage Out A.C. Volts Battery Charger Type Manufacturer Static Switch Type Ground Resistance Ohms Minimum I.R. Inverter Test Certificate * * D.C. Volts In D.C. Amps In A.C. Volts Out A.C. Amps Out Megohm s H2 Output Amps Limit Distortion % Static Switch Test Result* * Maximum Load Transferred to Mains: Maximum Load Transferred Mains to Inverter: Maximum Load Transferred to Bypass Supply: Amps Amps Amps Control System Function Tested to Drwg. Number: Revision: Alarms Completed and Function Tested to Drwg. Number: Revision: List Alarms Tested: Vendors Test Sheet Completed: Signed: Date: Remarks: COMPLETED BY WITNESSED BY ACCEPTED BY APPROVED BY COMPANY SIGNATURE PRINT NAME DATE ** Witnessing Authority to perform test. GOC© BP Exploration 1989 - 2001 All Rights Reserved Americas REV. 1 Project Title: Maintenance No: Work Pack No: SH1 No: MC1 No: FORM EE16 - SHT 01 SITE: GENERAL TEST CERTIFICATE DATE: System SLD No JOB NO: LOCATION: Subsystem Location SHT of MODULE: General Electrical Equipment - Procedural Acceptance Procedure 9.1 - Conduit Inspection Complete YES/NO* Initial Date Procedure 9.2 - Bus Duct Inspection Complete YES/NO* Initial Date Procedure 9.1 - Cable Inspection Complete YES/NO* Initial Date Procedure 9.10 - Panel Board Insp. Complete YES/NO* Initial Date Procedure 9.1 - Cable Tray Inspection Complete YES/NO* Initial Date Procedure 9.10 – Lighting & Receptacle Insp. Compl. YES/NO* Initial Date Procedure 9.1 - Cable Blocking Inspection Complete YES/NO* Initial Date Procedure YES/NO* Initial Date Procedure 9.1 Conduit & Seal Inspection Complete YES/NO* Initial Date Procedure YES/NO* Initial Date Equipment Description: Description of Tests and/or Inspections carried out: Test Certificate Numbers: REMARKS COMPLETED BY WITNESSED BY ACCEPTED BY APPROVED BY COMPANY SIGNATURE PRINT NAME DATE GOC© BP Exploration 1989 - 2001 All Rights Reserved Americas REV. 1 Project Title: Maintenance No: Work Pack No: SH1 No: MC1 No: NAVIGATIONAL AIDS TEST CERTIFICATE DATE: FORM EE17 - SHT 01 SITE: SLD No JOB NO: SHT of LOCATION: Equipment Number Location System Subsystem Serial Number MODULE: K.V.A. Data Sheet Model / Type Number Supply Voltage Battery Charger Type Manufacturer Volts Procedure 9.11 Completed: Signature: Date: Procedure 9.15 Completed: Signature: Date: Ohms Ground Path Resistance: Minimum I.R. Megohms Control Circuits Tested to Drwg. Number: Revision: Alarm Circuits Tested to Drwg. Number: Revision: Procedure 9.8 Completed: Signature: Date: Vendors Test Sheets Completed: Signature: Date: REMARKS: COMPLETED BY WITNESSED BY ACCEPTED BY APPROVED BY COMPANY SIGNATURE PRINT NAME DATE GOC© BP Exploration 1989 - 2001 All Rights Reserved Americas REV. 1 Project Title: Maintenance No: Work Pack No: SH1 No: MC1 No: FORM EE18 - SHT 01 SITE: A.C. GENERATORS AND GENERATOR CIRCUITS TEST CERTIFICATE DATE: JOB NO: SLD No LOCATION: TEST EQUIPMENT USED MANUFACTURER SHT of MODULE: ELEC. DATA SHEET NUMBER MODEL NO. SERIAL NO. VOLTAGE ACCURACY (FULL SCALE READING) MEG OHMS ENVIRONMENTAL CONDITIONS TEMP POWER SYSTEM VOLTS FREQUENCY & PHASE GENERATOR SERIAL NO. KVA/P.F./KW SERVICE TEMP CODE (INSULATON) SWGR. MECH COND GEN BEARING PROCEDURE 9.7 - ELECTRIC GEN’R. INSPECTION COMPLETE AMPS FL AMPS CIRCUIT BREAKER TRIP SET BREAKER °F VOLTS RMP GEN. MFR. SYNCH. CONTACT ALIGN INTERLOCKS FOR SYNCH’R CONDUIT SEALS LUBE TYPE ROTATION * * RTDs RUN * * DATE: MEGGER PHASE TO PHASE DESCRIPTION AB BC CA PHASE TO NEUTRAL A/B/C TO NEUTRAL PHASE TO GROUND A B C NEUTRAL GEN. STATOR WINDINGS EXCITER LEADS STATOR CONTROL CIRCUIT REMARKS: Comments on excitation system components/assembly: COMPLETED BY WITNESSED BY ACCEPTED BY APPROVED BY COMPANY SIGNATURE PRINT NAME DATE ** Witnessing Authority to Perform Test GOC© BP Exploration 1989 - 2001 All Rights Reserved Americas REV. 1 Project Title: Maintenance No: Work Pack No: SH1 No: MC1 No: FORM EE18 - SHT 02 SITE: ROTATING MACHINERY (GENERATOR) TEST CERTIFICATE DATE: JOB NO: SLD No LOCATION: TEST EQUIPMENT USED MANUFACTURER MODEL NO. SETTING SERIAL NO. ACCURACY EQUIPMENT TESTED MANUFACTURER MODEL NO. SERIAL NO. SHT of MODULE: SERVICE FACTOR STATOR TEMP KV RPM KVA HP PF TYPE FORM AGE MFR. DATE LAST TEST LAST TEST SHEET NO. ROTOR KW INSULATION CLASS STATOR CORONA CONTROL CLASS EQUIVALENT 10 KV READINGS MILLIAMPERES LINE NO. PHASE TEST METER KV READING WATTS MILLI- MULTIPLIER AMPERES METER % % POWER PF TEST TIP UP KV READING MULTIPLIER WATTS FACTOR PDA MEASUREMENTS MICROVOLTS 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 COMPLETED BY WITNESSED BY ACCEPTED BY APPROVED BY COMPANY SIGNATURE PRINT NAME DATE NOTE: THIS IS A DOBLE TEST SHEET! GOC© BP Exploration 1989 - 2001 All Rights Reserved Americas REV. 1 DIS6 SHEET HANDOVER No : _______________ PROJECT : ___________ JP No. CABLE No EE1 LOCATION : ___________ EE16 RAISED BY : _____________________________ NOTE: JP No FOR TESTING CABLE DATA INPUT SHEET 6 SECTION 9 ELECTRICAL CABLES FROM TO DATE : _______________________________ GOC© OF WORKSCOPE ID : ______________________ MAINTENANCE ID No : ______________________ DRG No DRGS TO BE AS-BUILT (LAD) DATA ENTERED BY : ______________________ BP Exploration 1989 - 2001 All Rights Reserved COMMENTS DATE : __________________ Americas Rev. 1 DIS7 HANDOVER No : _______________ DATA INPUT SHEET 7 PROJECT : ___________ LOCATION : ___________ ______________________ JP No HANDOVER ID EQUIPMENT No EE2 EE3 EE4 RAISED BY: ___________________________________ NOTE: JP No FOR TESTING EE5 EE6 EE7 EE8 DATE : ________________ GOC© EE10 EE11 EE12 EE13 EE14 OF WORKSCOPE ID : ______________________ SECTION 9 - ELECTRICAL EQUIPMENT EE9 SHEET EE15 EE16 MAINTENANCE ID No : EE17 DATA ENTERED BY : ______________________________ BP Exploration 1989 - 2001 All Rights Reserved EE18 SC1 SC1 REF. Drawing No ASBUILT REQ' D DATE : ____________________ Americas Rev. 1 SUBJECT: GUIDANCE ON CERTIFICATION SECTION 10 GOC© AMERICAS EDITION REVISION: 1 CIVIL CONSTRUCTION SECTION 10 CIVIL CONSTRUCTION GOC© BP Exploration 1989 - 2001 All Rights Reserved PAGE: 1 SUBJECT: 10.1 GUIDANCE ON CERTIFICATION SECTION 10 GOC© AMERICAS EDITION REVISION: 1 CIVIL CONSTRUCTION PAGE: 2 ACTION 10.1.1 General The scope of the Civil Construction covers civil and buildings (architecture) activities in general and as such may not be applicable to all project activities, however the applicable requirements of this procedure shall be included within any procedure for civil or architectural inspection and acceptance produced by the Construction Authority. All on-site and off-site activities and operations shall be planned and performed in accordance with agreed procedures. The agreed procedures shall define the sequence, methods, controls, criteria for acceptance, inspection and testing, recording of test results, and their evaluation. The frequency of tests should take into account the consistency of test results and changes in characteristics. Civil Construction shall be checked for compliance and other requirements as detailed in but not limited to: • • • • • • • The latest revision of Issued For Construction (IFC) or Approved For Construction (AFC) Drawings and Schedules Codes and standards reference in this section Plant and Project Specifications Equipment Specifications and Data sheets BP Engineering Installation and Design Specifications Local, state, country and international standards, codes, and regulations as appropriate Offshore - Special Standards, i.e. USCG, ABS and MMS GOC© BP Exploration 1989 - 2001 All Rights Reserved GUIDANCE ON CERTIFICATION SECTION 10 GOC© AMERICAS EDITION REVISION: 1 SUBJECT: 10.2 CIVIL CONSTRUCTION PAGE: 3 CIVIL WORK 10.2.1 Scope The civil work scope, as defined by the contract drawings, shall be divided into discrete civil construction work packages. Each work package shall cover all civil works within a specified area of the site and be clearly identified on the applicable drawings. For convenience of site inspection and testing the work package may be further sub-divided. The Construction Authority shall be responsible for raising and documenting requests for inspection, certificates, with all necessary supporting documentation, prior to submitting to BP for acceptance. 10.2.2 General Construction Management responsibilities and associated Quality Planning for civil activities, is normally categorized and managed, but not limited to the following: a) On-Site: The Construction Authority is responsible for the Inspection and Test activities and management of the construction Contractor who provides labor and equipment only; b) Off-Site: The Construction Authority monitors the performance of the Management Contractor who is directly responsible for the fabrication and Inspection and Test activities. c) For on-site, those Inspection and Test activities that require to be performed and recorded to fulfill the minimum quality control requirements, are clearly defined on the specified Inspection and Test Schedule (ITS) for the work. GOC© BP Exploration 1989 - 2001 All Rights Reserved SUBJECT: d) GUIDANCE ON CERTIFICATION SECTION 10 GOC© AMERICAS EDITION REVISION: 1 CIVIL CONSTRUCTION PAGE: 4 For off-site, those Inspection and Test activities performed by the Managing Contractor that are deemed by BP or their delegated authority to be at critical stages in the fabrication process and require to be witnessed before the Contractor can proceed, will be clearly defined within the Managing Contractor's quality plan (QP), and/or the supplied ITS. e) The acceptance of structural works is a composite function of Fabrication, and Inspection (Section 2). Input by the relevant discipline engineer is required in quality planning and subsequent development of an ITS for both off-site and on-site work. f) Flow charts give guidelines on handover of on-site work. g) All reporting and recording of inspection and acceptance of civil work shall be on the GOC© standard forms or alternatives where agreed by BP or their delegated authority. h) The Construction Authority shall exercise sufficient dimensional control over the civil work and shall monitor or conduct surveys throughout pre-fabrication, fabrication, construction and installation stages of the work to ensure that the specified design tolerances are achieved. The contractor, prior to installation, shall establish reference marks and levels. i) The Construction Authority shall prepare, maintain and issue reports which describe the extent, and contain the results, of all dimensional surveys carried out on-site and shall monitor reports produced. j) The construction authority shall ensure that all applicable permits are obtained and approved. The permits may be, but are not limited to, Area Civil Work Requests (ACWR), Tundra Access Permits and U.S. Civil Corp. of Engineers Gravel Placement Permits. The general source shall be an approved and permitted pit. GOC© BP Exploration 1989 - 2001 All Rights Reserved SUBJECT: GUIDANCE ON CERTIFICATION SECTION 10 GOC© AMERICAS EDITION REVISION: 1 CIVIL CONSTRUCTION PAGE: 5 10.2.3 Soils and Earthwork The control of soils and earthwork operations shall ensure that the site sub-grade is prepared suitably free of extraneous materials, voids, excess moisture, etc. and that fill operations are not carried out in inclement weather. Soil compaction activities should be carried out such that the fill material will not separate when applied and spread in accordance with specified lift thickness and appropriate watering and compaction is carried out. Appropriate tests for compaction, grain size, plasticity, field density, etc. shall be carried out during the course of construction. The Construction Authoritys Civil Engineer should ensure that the frequency of the tests is dependent upon consistency of results and changes in material characteristics. 10.2.4 Piling Operations Piling operations shall be subject to controls and inspections that ensure that the type, location and position of the piles are verified, and pile hammer, cushion material, and driving procedure and sequence are adequately described and recorded. The Construction Authorities Civil Engineer shall ensure that a suitable record of the number of pile driving strokes for each pile is maintained. Cast in piles shall be checked to confirm the alignment is correct. 10.2.5 Concrete Site control procedures shall ensure that adequate inspection and testing for all aspects of concrete construction are performed. The extent of control will be dependent upon the structural function of the concrete structure. GOC© BP Exploration 1989 - 2001 All Rights Reserved GUIDANCE ON CERTIFICATION SECTION 10 GOC© AMERICAS EDITION REVISION: 1 SUBJECT: PAGE: 6 CIVIL CONSTRUCTION The controls employed for the material storage and handling techniques should ensure the cement storage facilities are suitably weather tight, and the type and age of cement is verified. Aggregates stockpiles should be inspected to ensure temperature and moisture controls are in operation and that storage and handling techniques prevent contamination. facilities should be inspected contamination are prevented. These inspections should The admix storage and handling to include verify water that deterioration quality and and concrete temperatures. Measuring and mixing operations should be monitored to ensure cement, water, and aggregate proportions are checked and recorded. Aggregate moisture compensation measures, temperature controls should also be verified. mixing time, and Placement operations should be monitored to ensure the preparations are checked to confirm that specified material has been used and the condition of the material, gradation, and compaction are correct. Inspections should be carried out prior to concrete placement to confirm the location and configuration of formwork, and size, orientation and installation of reinforcing steel is correct. Concrete placement inspection should confirm that specified testing of concrete is performed and adequate concrete consolidation equipment and techniques are used. Appropriate cube/cylinder testing should be carried out and results recorded. Finished construction should be inspected to check for any voids or contamination. Where the Construction Authorities Civil Engineer considers it necessary physical removal of concrete may he necessary to determine the extent. GOC© BP Exploration 1989 - 2001 All Rights Reserved SUBJECT: 10.3 GUIDANCE ON CERTIFICATION SECTION 10 GOC© AMERICAS EDITION REVISION: 1 CIVIL CONSTRUCTION PAGE: 7 STEEL CONSTRUCTION 10.3.1 General Steel construction, including related items, such as anchor bolts and base plates, forming part of a supporting structure should be inspected at appropriate stages of construction. Anchor bolts and base plates should be checked for correct type, location, orientation, and bolt hole alignment prior to erection. 10.4 PIPING 10.4.1 General Piping activities associated with civil work shall be subject to controls and inspections that ensure the location and construction methods adopted are verified. Pipe testing (metallic) to be in accordance with Section 3 Pipe Testing. Work shall be performed in accordance with procedures that adequately take account of the complexity, uniqueness, or novelty of the item, and the need for any special controls or surveillance over processes, methods, or equipment. Particular attention shall be made to ensure laying, jointing and backfill operations do not jeopardise the integrity of non-metallic piping. GOC© BP Exploration 1989 - 2001 All Rights Reserved GUIDANCE ON CERTIFICATION SECTION 10 GOC© AMERICAS EDITION REVISION: 1 SUBJECT: 10.5 CIVIL CONSTRUCTION PAGE: 8 Use of Forms a) Off-Site Civil Acceptance The CW6 will certify that all off-site fabrication activities for a discrete structure or its component parts, complies with the design requirements and all specified inspection and testing is completed and accepted. As a minimum, all sub-assemblies will require a CW6 Civil Completion Certificate before they can be installed in to an assembly. All assemblies will require a CW6 Civil Completion Certificate before they can be installed into the discrete structure. All discrete structures will require a CW6 Civil Completion Certificate before they can be released for shipment onsite for installation. b) On-Site Civil Acceptance The CW6 Civil Completion Certificate will certify that all on-site activities relating to the onsite fabrication and installation of civil work have been completed and comply with the approved design, fabrication and installation specifications and that all specified inspection and testing is completed and accepted. c) Concealed / Covered Work Where subsequent work will prohibit further access, all items of work concealed in finished work, either underground or by closure or as a result of gravel installation, covering filler fabric, drainage structures or other work, shall be inspected immediately prior to being covered/concealed. GOC© BP Exploration 1989 - 2001 All Rights Reserved SUBJECT: GUIDANCE ON CERTIFICATION SECTION 10 GOC© AMERICAS EDITION REVISION: 1 PAGE: 9 CIVIL CONSTRUCTION The inspection and testing shall be recorded on the CW6 Civil Completion Certificate, which must identify clearly the area that was inspected prior to filling and back filling. “As-built” drawing data will also be recorded and relevant coordinates confirmed. d) Protective Coatings Painting, coating of items or surfaces for which the coating is essential to the preservation of the item quality, including its safety, e.g. fire proofing, shall be performed and inspected in accordance with approved procedures. Refer to the AS2 Final Coating / Insulation Certificate as detailed in Section 7.0 - Architectural Services (Painting, Coating and Insulation). e) Civil Work Civil work shall be accepted by using the forms listed below. The Construction Authority using their own suite of forms will record piling activities. The Construction Authorities Civil Engineer will record acceptance on these forms which will form part of the permanent Record Documents. civil standard forms is given over. GOC© Guidance on the application of BP Exploration 1989 - 2001 All Rights Reserved SUBJECT: i) GUIDANCE ON CERTIFICATION SECTION 10 GOC© AMERICAS EDITION REVISION: 1 CIVIL CONSTRUCTION PAGE: 10 CW1 - CW4 For Civil Work CW1 to CW4 Inspection Certificates are available: CW1 - Reinforced Concrete Works CW2 - Underground Services / Drainage CW3 - Earthworks, Roads, Flexible Paving CW4 - Transportation / Placement of Concrete ii) CW5 - Concrete Test Cube/Cylinder Summary CW5 is available for use as a summary record sheet for all concrete testing results. iii) CW6 - Civil Construction Completion Certificate CW6 certificate to be used for the acceptance of on-site and off-site work, assemblies, sub-assemblies or discrete structures and/or the acceptance of areas or sub-areas that are required to be handed over and made available to another contractor. The CW6 certificate shall only be accepted when all relevant supporting documentation is available and accepted. Acceptance of the CW6 by the Construction Authority, Commissioning Authority and/or the Operating Authority, only confirms that the area or collective areas are ready for SH1 System Handover, (refer to Flowchart 10). The acceptance of the CW6 certificate on its own does not constitute system handover or acceptance by the operator. GOC© BP Exploration 1989 - 2001 All Rights Reserved SUBJECT: 10.6 10.6.1 GUIDANCE ON CERTIFICATION SECTION 10 GOC© AMERICAS EDITION REVISION: 1 CIVIL CONSTRUCTION PAGE: 11 Buildings, Fittings and Furnishings (Architectural) General The requirements of this procedure should apply to the architectural acceptance of areas used as permanent offices, control rooms, laboratories, or rest rooms. These requirements should be included within any procedure for inspection and acceptance of architectural works produced by the Construction Authority. The acceptance of associated services, e.g. fire and gas detection, electrical power and lighting, and HVAC is contained within the relevant sections of the GOC©. The inspection of the areas should be carried out after installation of all items and the completion of testing of services and utilities to the area by the appropriate disciplines. It should be noted that within control rooms, completion activities will normally continue until final handover to the operator, and a handover program should be agreed between the Construction Authority, Commissioning Authority and Operations. The overall standard of workmanship of the areas should be considered in addition to the minimum inspection points contained within this section. GOC© BP Exploration 1989 - 2001 All Rights Reserved GUIDANCE ON CERTIFICATION SECTION 10 GOC© AMERICAS EDITION REVISION: 1 SUBJECT: CIVIL CONSTRUCTION PAGE: 12 10.6.2 Inspection Requirements The Construction Authority shall ensure the following inspections and/or tests have been completed prior to submitting the building, for approval to the Commissioning Authority. All inspection and testing to be carried in accordance with design requirements, specifications, approved drawings and to national and/or state statutory regulations and codes of the country or state the facility is subject. 10.6.3 Surface Finish Surface Finish to be checked to ensure: a) The surface finish is as per the design and specification requirements; e.g. tiled, screeded, aluminium, Formica, wood, painted, etc. b) The surface coating is correct for quality and color of finish, and has no scratches, blemishes, or defects. Attention should be paid to recessed items such as light switches, socket outlets, louvers, or where tiles are fitted. c) All access hatches to concealed areas are correctly fixed, accessible, labelled, including warning notices where necessary. d) All mouldings on skirting boards, ceiling, and wall joints are correctly fitted. e) All ceiling tiles are in place and undamaged and for suspended ceilings, all suspension ties and supports are correctly installed. f) Where applicable the floor slope or camber to drains is correct. GOC© BP Exploration 1989 - 2001 All Rights Reserved SUBJECT: GUIDANCE ON CERTIFICATION SECTION 10 GOC© AMERICAS EDITION REVISION: 1 CIVIL CONSTRUCTION PAGE: 13 10.6.4 Windows and Doors All Windows and Doors are to be checked to ensure: a) The correct fire rated items have been fitted. b) The finish around door and window frames is correct and complete. c) All doors and opening windows function correctly and when closed are correctly sealed. d) All hinges, locks, handles etc. are fitted and function correctly. e) The glazing is not damaged in any way. 10.6.5 Fittings All permanent fittings, other than control panels, are to be checked to ensure: a) Sanitary ware is undamaged. b) Sealant, plugs, covers, taps, handles, etc. are correctly fitted and operational. c) Mirrors are correctly installed and undamaged. d) Wardrobe units, cupboards, and working surfaces are correctly aligned and doors function correctly. All locks, where fitted, have keys and function correctly. e) Edges around wardrobe units, cupboards, and working surfaces are correctly sealed and undamaged. GOC© BP Exploration 1989 - 2001 All Rights Reserved GUIDANCE ON CERTIFICATION SECTION 10 GOC© AMERICAS EDITION REVISION: 1 SUBJECT: CIVIL CONSTRUCTION PAGE: 14 10.6.6 Safety Items All Safety Items are to be checked to ensure: a) Fire extinguisher brackets are installed in agreed locations with unrestricted access at all times, are of the correct type and size, and correctly marked. It should be noted that the operator may carry out the installation of the extinguisher. b) Deluge, fire water and sprinkler systems will be inspected and tested in accordance with Section 3 - Pipe Testing. c) Hose reels are and associated valves are correctly installed and operate freely, and correctly tagged. Hoses are to be run out to ensure they are undamaged. Ensure they are correctly re-rolled after checking. d) All doors, covers etc. associated with the hose reels freely operate. e) All emergency exit signs are of the correct type and correctly located. f) All escape routes are clearly marked and maps installed. g) Muster point cabinet locations are installed in agreed locations. GOC© BP Exploration 1989 - 2001 All Rights Reserved SUBJECT: GUIDANCE ON CERTIFICATION SECTION 10 GOC© AMERICAS EDITION REVISION: 1 CIVIL CONSTRUCTION PAGE: 15 10.6.7 Soft Furnishings All Soft Furnishings are to be checked to ensure: a) All curtain rods, hooks, curtains, blinds are installed and operate correctly, and are of the correct color. b) All carpeting is of the correct color and installed correctly. c) Loose furniture, chairs etc. is as per the requirements. 10.6.8 Buildings, Fittings and Furnishings Certificate (Architectural) BF1 - Building Area Acceptance Certificate - for modules, buildings, permanent offices, control rooms, rest rooms, medical rooms and associated facilities shall be used to record the results of inspections and surveys. The acceptance of the BF1 by the Construction Authority, Commissioning Authority and/or the Operating Authority, only confirms that the area or collective areas are ready for SH1 - System Handover, (Refer to Flowchart 11). The acceptance of the BF1 certificate on its own does not constitute system handover or acceptance by the operator. GOC© BP Exploration 1989 - 2001 All Rights Reserved GUIDANCE ON CERTIFICATION SECTION 10 GOC© AMERICAS EDITION REVISION: 1 SUBJECT: PAGE: 16 CIVIL CONSTRUCTION FLOWCHART 10 • Functional Certification Flowchart • Discipline: Civil Construction CW1 CW2 CW4 CW5 CW6 SH1 CW3 CW1 CW2 : : Reinforced Concrete Work Underground Services/Drainage CW3 CW4 CW5 : : : Earthwork/Roads/Flexible Paving Transportation/Placing of Concrete Concrete Test Cube/Cylinder Summary CW6 SH1 : : Civil Completion Certificate System Handover Certification NOTE! Electrical, Control and Mechanical disciplines will be handed over on system basis. Refer to the appropriate section for relevant procedures and certificates. GOC© BP Exploration 1989 - 2001 All Rights Reserved GUIDANCE ON CERTIFICATION SECTION 10 GOC© AMERICAS EDITION REVISION: 1 SUBJECT: PAGE: 17 CIVIL CONSTRUCTION FLOWCHART 11 • Functional Certification Flowchart • Discipline: Civil – Buildings, Fittings and Furnishings (Architectural) BF1 BF1 SH1 : : SH1 Building Area Acceptance Certificate. System Handover Certificate Note! Electrical, Control and Mechanical disciplines will be handed over on a system basis. Refer to the appropriate section for relevant procedures and certificates. GOC© BP Exploration 1989 - 2001 All Rights Reserved GUIDANCE ON CERTIFICATION SECTION 10 GOC© AMERICAS EDITION REVISION: 1 SUBJECT: CIVIL CONSTRUCTION PAGE: 18 EXHIBIT 10 STANDARD FORMS Form No. Form Title CW1 Reinforced Concrete Work CW2 Underground Services / Drainage CW3 CW4 CW5 Earthwork, Roads, Flexible Paving Transportation / Placement of Concrete Concrete Test Cube / Cylinder Summary CW6 BF1 Civil Completion Certificate Buildings Area Acceptance Certificate DIS8 Data Input Sheet 08 – Civil Construction Note: Final acceptance of the CW6 - Civil Completion Certificate will be by the Civil Engineer authorized by BP or their Delegated Authority. GOC© BP Exploration 1989 - 2001 All Rights Reserved Project Title: Maintenance No: Work Pack No: SH1 No: MC1 No: FORM CW1- SHT 01 SITE: REINFORCED CONCRETE WORK INSPECTION REPORT DATE: JOB NO. SHT of LOCATION CONTRACTOR Description: The works referenced have been inspected in accordance with Contract requirements and are in accordance with the Project design criteria, drawings and specifications. All outstanding work to be detailed on the agreed joint Punch List. INITIALS/DATE INSPECTION STAGE * 1. Excavation 1 2. Formation 2 3. Blinding 3 4. Impermeable membrane 4 5. Reinforcement 5 6. HD Bolts 6 7. Built-in Items (Details) 7 8. Form work 8 9. Line and level 9 10. Cleanliness 10 11. Manholes sealed 11 12. Curing (requirements) 12 13. Water Proofing 13 14. Backfilling 14 15. Testing (Type & Results) 15 16. Piling 16 17. Survey layout 17 COMPLETED BY WITNESSED BY ACCEPTED BY APPROVED BY COMPANY SIGNATURE PRINT NAME DATE * Delete as appropriate GOC© BP Exploration 1989 - 2001 All Rights Reserved Americas REV. 1 Project Title: Maintenance No: Work Pack No: SH1 No: MC1 No: FORM CW2- SHT 01 SITE: UNDERGROUND SERVICES/DRAINAGE INSPECTION REPORT DATE: SHT of JOB NO. LOCATION CONTRACTOR Pipe/Drain: (Size & Type) Jointing/Fittings: Manhole/Gully: (Chamber No & Type) Description: Service Function: The works referenced have been inspected in accordance with Contract requirements and are in accordance with the Project design criteria, drawings and specifications. All outstanding work to be detailed on the agreed joint Punch List. INITIALS/DATE INSPECTION STAGE * 1. Excavation 1 2. Formation 2 3. Bedding 3 4. Invert Levels 4 5. Test calculations 5 6. Protective Coatings 6 7. Testing (Type of tests and results) 7 8. Backfill/Surround 8 9. Flushing 9 10. Visual Inspection (Obstructions) 10 11. Manholes sealed 11 12. Gratings fitted REMARKS 12 COMPLETED BY WITNESSED BY ACCEPTED BY APPROVED BY COMPANY SIGNATURE PRINT NAME DATE * Delete as appropriate GOC© BP Exploration 1989 - 2001 All Rights Reserved Americas REV. 1 Project Title: Maintenance No: Work Pack No: SH1 No: MC1 No: FORM CW3 - SHT 01 SITE: EARTHWORK/ROADS/FLEXIBLE PAVING INSPECTION REPORT DATE: JOB NO. SHT of LOCATION CONTRACTOR Description: The works referenced have been inspected in accordance with Contract requirements and are in accordance with the Project design criteria, drawings and specifications. All outstanding work to be detailed on the agreed joint Punch List. INSPECTION STAGES * INITIALS/DATE 1. Set-out/Grid Reference/ Bench marks 1 2. Excavation/Formation level 2 3. Fill/Formation level 3 4. Impermeable membrane 4 5. Sub-base/Graded fill 5 6. Asphalt/Macadam (pavement) 6 7. Testing (summary of test results) 7 8. Kerbing/Curbing 8 9. Finish level 9 10. Landscaping Note! 10 Where additional excavation/fill is required because of unsuitable material/soft spots, these areas to be clearly identified on the drawing and entered on the Punch List proforma. Drawing Nos. Drawing Nos. Drawing Nos. REMARKS COMPLETED BY WITNESSED BY ACCEPTED BY APPROVED BY COMPANY SIGNATURE PRINT NAME DATE * Delete as appropriate GOC © BP Exploration 1989 - 2001 All Rights Reserved Americas REV. 1 Project Title: Maintenance No: Work Pack No: SH1 No: MC1 No: FORM CW4- SHT 01 SITE: TRANSPORTATION/PLACING OF CONCRETE INSPECTION REPORT DATE: SHT of JOB NO. LOCATION CONTRACTOR Central Batching Plant: In-Situ Batching: Ticket No/Truck No: Time of loading: Time of Arrival: (at Location) Description: Ready Mix: (name depot) Concrete:(Grade & Description): Quantity: INITIALS/DATE INSPECTION STAGE * 1. Check delivery details 1 2. Check stage inspection form CW1 2 3. Permission to commence (time and date) 3 4. Testing (type of test) 4 5. Number of cubes/cylinders taken 5 6. Protective Coatings 6 7. Cubes Reference No (tests results) 7 8. Time of Completion REMARKS 8 COMPLETED BY WITNESSED BY ACCEPTED BY APPROVED BY COMPANY SIGNATURE PRINT NAME DATE * Delete as appropriate GOC© BP Exploration 1989 - 2001 All Rights Reserved Americas REV. 1 Project Title: Maintenance No: Work Pack No: SH1 No: MC1 No: FORM CW5- SHT 01 SITE: CONCRETE TEST CUBE / CYLINDER SUMMARY DATE: JOB NO. SHT of LOCATION CONTRACTOR Description: Cylinder No. Location / Identification COMPLETED BY Date Cast Date Test WITNESSED BY No. of Days PSI Design ACCEPTED BY PSI Actual APPROVED BY COMPANY SIGNATURE PRINT NAME DATE * Delete as appropriate GOC© BP Exploration 1989 - 2001 All Rights Reserved Americas REV. 1 Project Title: Maintenance No: Work Pack No: SH1 No: MC1 No: FORM CW6 - SHT 01 SITE: CIVIL COMPLETION CERTIFICATE DATE: SHT of JOB NO. LOCATION MODULE Description: The works referenced have been inspected in accordance with Contract requirements and are in accordance with the Project design requirements, drawings and specifications. All outstanding work to be detailed on an agreed joint Punch List. Yes No N/A INSPECTION STAGES * INITIALS/DATE 1. Site preparation complete, buried utilities located and documented. 1 2. Geotechnical liners/filter/drainage fabrics installed. 2 3. Drainage culverts/structures installed. 3 4. Trenching completed to specified grades. 4 5. Backfill installed and compacted. 5 6. Structural fills installed and compacted. 6 7. Guard rails, fences, gates and bollards installed. 7 8. Finish grading complete to plan. 8 9. Erosion control and re-seeding complete. 10. Piles (USM) installed as per design location and in accordance with specification. 11. Excess materials returned to warehouse, construction debris properly disposed and work/site area cleaned up. 9 10 11 12. Roads and kerbing/curbing complete. 12 13. Road markings and road signs complete. 13 14. Landscaping complete. Drawing Nos. 14 Drawing Nos. Drawing Nos. REMARKS COMPLETED BY WITNESSED BY ACCEPTED BY APPROVED BY COMPANY SIGNATURE PRINT NAME DATE * Delete as appropriate GOC© BP Exploration 1989 - 2001 All Rights Reserved Americas REV. 1 Project Title: Maintenance No: Work Pack No: SH1 No: MC1 No: FORM BF1- SHT 01 SITE: BUILDINGS - AREA ACCEPTANCE CERTIFICATE DATE: SHT of JOB NO. LOCATION CONTRACTOR Description: Boundary Wall Disciplines North South East West (Initial & Date) (Initial & Date) (Initial & Date) (Initial & Date) 1. Electrical Services 2. HVAC Services 3. Fire & Gas 4. Finish - Walls 5. Finish - Floor 6. Finish - Ceiling 7. Doors & Windows Complete Yes No Room No: _______ 1. Electrical Services 2. HVAC Services 3. Fire & Gas 4. Finish - Walls 5. Finish - Floor 6. Finish - Ceiling 7. Doors & Windows Yes No Yes No 1.2 Light Fittings No Outstanding Work INSPECTION POINTS * 1.1 Power Points Yes (Circle Item Number) 1.3 Ariel Sockets 1.1 1.2 1.3 1.5 1.6 1.4 Trunking 1.5 Telecoms 1.6 Network Sockets 1.4 2.1 H/C Water System 2.2 LTHW System 2.3 Louvers/Vents 2.1 2.2 2.3 2.4 A/C System 2.5 CHW System 2.6 Ducting 2.4 2.5 2.6 3.1 Detectors 3.2 Extinguish System 3.6 Sprinkler System 3.1 3.2 3.6 3.4 Dampers 3.5 Fire 3.4 3.5 3.7 4.1 Paint 4.2 Curtain Rails 4.6 Picture Rails 4.1 4.2 4.6 4.4 Wall Covering 4.5 Coat Hooks 4.7 Skirting 4.4 4.5 4.7 5.1 Paint 5.2 Carpet 5.6 Boards 5.1 5.2 5.6 5.4 Screed/Concrete 5.5 Tiles 5.7 Floor Covering 5.4 5.5 5.7 6.1 Paint 6.2 Suspended 6.6 Hessian Covering 6.1 6.2 6.6 6.4 Tiles 6.5 Boards 6.7 Hatches 6.4 6.5 6.7 7.1 Fittings 7.2 Fastening (Windows) 7.6 Locks (Doors) 7.1 7.2 7.6 7.4 Glazing 7.5 Finish 7.4 7.5 7.7 Water Hose 3.7 Alarms 7.7 Handles (Doors) REMARKS COMPLETED BY WITNESSED BY ACCEPTED BY APPROVED BY COMPANY SIGNATURE PRINT NAME DATE * Delete as appropriate GOC© BP Exploration 1989 - 2001 All Rights Reserved Americas REV. 1 DIS8 LOCATION : __________________ DATA INPUT SHEET 8 PROJECT : ____________________ J.P NO. RAISED BY: HANDOVER ID ____________________________________ NOTE: JP No FOR INSTALLATION DRAWING No DATE : __________________ GOC OF WORKSCOPE ID : ______________________ SECTION 10 CIVIL CONSTRUCTION DESCRIPTION SHEET CW1 MAINTENANCE ID No : ______________________ CW2 CW3 Civil CW4 CW5 CW6 BF1 DATA ENTERED BY : ____________________ © BP Exploration 1989 - 2001 All Rights Reserved COMMENTS DATE : ___________ Americas Rev. 1