Transport of BOP and LMRP offshore equipment in Las Palmas ALE has succesfully completed the transport manoeuvres of the BOP and LMRP equipment. The characteristics of the pieces were: 1 No. BOP: 5,080 x 5,080 x 11,463.4mm; 247t (including the transport skid). 2 No. LMRP: 5,080 x 5,080 x 8,387.4 mm; 135t (including the transport skid). To complete this work it was used a 4x6 SPMT configuration with a Power Pack. The operations performed by ALE for the transport of the modules, were: First movement: transport of the 1st LMRP from offshore platform to dock end. Second movement: transport of the 1st LMRP from dock end to the offshore platform. Third and fourth movement: transport of the new modules LMPR and BOP from the H/L ship to the platform Project: Transport of BOP and LMRP offshore equipment in Las Palmas Project Location: Las Palmas, Spain Equipment: 4x6 SPMT Weight: BOP 247 T, LMRP 135 T. ALE, P.I. Los Frailes. Ctra Alcalá de Henares a Daganzo, km 9. P 101-106 28814 Daganzo (Madrid), Spain Tel:+ 34 91 8845403 Fax:+ 34 91 8845840 Web:www.ale-heavylift.com ALE499SP