Subido por bojorge

ETAP Power Flow Analysis Using ETAP Software

Anuncio
An-Najah National University
Faculty of Graduate Studies
Power Flow Analysis Using ETAP Software
By:
Tareq Foqha
Supervisor:
Dr. Maher Khammash
Nablus, Palestine
2020
ABSTRACT
Load flow is an important tool used by power engineers for planning, to determine the best
operation for a power system and exchange of power between utility companies. In order to
have an efficient operating power system, it is necessary to determine which method is
suitable and efficient for the system’s load flow analysis. This research will introduce a load
flow study and analysis for 36-bus power system using ETAP software to improve the power
factor and to reduce the electrical losses.
II
TABLE OF CONTENTS
Cover Page
I
Abstract
II
CHAPTER 1: INTRODUCTION…………………..….………………………..….…….....
1
1.1 Load Flow Studies …..….…….…………………..….……….……………..……..…..…..…
2
1.2 Newton-Raphson Power Flow Solution ………………..….……………..….……….…
4
1.3 Control of Power Flow …………………..…………………………………..…………....…
6
1.4 ETAP ………………………………………..……………..….…………………………....….…
7
CHAPTER 2: LOAD FLOW ANALYSIS .…..…..………..…..…..…..…...…...……...
8
2.1 Power System Description ……………….....….…………….……….…..……….….…….
9
2.2 Load Flow Analysis for the 36-Bus System (normal condition) …...…….………
9
2.3 Load Flow Analysis for the 36-Bus System (Maximum Load Condition) ….…
11
The Maximum Load Improvement ….………….………….………….……………...
12
2.3.1.1 Improvement by increasing the swing bus voltage ….……………..………
13
2.3.1.2 Improvement by Using Tap-Changing Transformers ….……………..……
15
2.3.1.3 Improvement by Using Shunt Capacitor Banks ….……………..………….
17
2.3.1.4 Comparison between the three cases ….……………..………….….………..
21
2.4 Load Flow Analysis For the 36-Bus System (Minimum Load Condition) …....
22
The Minimum Load Improvement ….………….………….………….………….…..
24
2.4.1.1 Improvement by increasing the swing bus voltage ….………….….……...
25
2.4.1.2 Improvement by Using Tap-Changing Transformers ….……….….……...
27
Load Flow Analysis For the 36-Bus System (Post Fault Condition) ..….……...….
28
The Post Fault Condition Improvement ….……………..………...….…………….....
31
2.5.1.1 Improvement by Using Shunt Capacitor Banks ….……………..………...
31
CHAPTER 3: CONCLUSION …………..…..…..…..…..…..…..…..…..…...…..…..……...
34
3.1 Conclusion …………………..….…………….……………....….…..……………….....………
35
BIBLIOGRAPHY ………..….……...…………………..…………....….…..……..………….....…….
36
APPENDICES …………..….……...………………………………....….…..……………….....………
37
2.3.1
2.4.1
2.5
2.5.1
III
CHAPTER ONE
INTRODUCTION
1
CHAPTER ONE
INTRODUCTION
1.1 Power Flow Studies:
Power flow (or load flow) is the solution for the normal balanced three-phase steady-state
operating conditions of an electric power system. In general, power flow calculations are
performed for power system planning and operational planning, and in connection with system
operation and control.
The data obtained from power flow studies are used for the studies of normal operating mode,
contingency analysis, outage security assessment, and optimal dispatching and stability [1].
The main objective of the load flow analysis is to identify the potential problems, in terms of
unacceptable voltage conditions, overloading of facilities, decreasing reliability, or any failure
of the transmission system to meet performance criteria. After this analysis stage, the planner
develops alternative plans or scenarios that not only will prevent the foreseen problems but
also will best meet the long-term objectives of system reliability and economy.
The effectiveness of the alternative plans is determined by load-flow, or power-flow studies
under both normal and emergency operations. The load-flow programs now in use by the
utilities allow the calculation of currents, voltages, and real and reactive power flows, taking
into account the voltage-regulating capability of generators, transformers, synchronous
condensers, specified generation schedules, as well as net interchange among interconnected
systems, automatically. By changing the location, size, and number of transmission lines, the
planner can achieve to design an economical system that meets the operating and design
criteria [2].
2
Successful power system operation under normal balanced three-phase steady-state conditions
requires the following:
1. Generation supplies the demand (load) plus losses.
2. Bus voltage magnitudes remain close to rated values.
3. Generators operate within specified real and reactive power limits.
4. Transmission lines and transformers are not overloaded.
The power-flow computer program is the basic tool for investigating these requirements. This
program computes the voltage magnitude and angle at each bus in a power system under
balanced three-phase steady-state conditions. It also computes real and reactive power flows
for all equipment interconnecting the buses, as well as equipment losses.
Both existing power systems and proposed changes including new generation and
transmission to meet projected load growth are of interest. Conventional nodal or loop analysis
is not suitable for power-flow studies because the input data for loads are normally given in
terms of power, not impedance. Also, generators are considered as power sources, not voltage
or current sources. The power-flow problem is therefore formulated as a set of nonlinear
algebraic equations suitable for computer solution [3].
Every power system have a special operation of the system depend on knowing the effects of
this power system with other power systems and we will have new loads ,new generating
stations and new transmission lines before they are installed. The required condition according
to load studies for any network which consider the most difficult are:
1. Maximum load;
2. Minimum load;
3. Faults.
3
1.2 Newton-Raphson Power Flow Solution:
It is an iterative method which approximates a set of non-linear simultaneous equations to a
set of linear simultaneous equations using Taylor’s series expansion and the terms are limited
to the first approximation. It is the most iterative method used for the load flow because its
convergence characteristics are relatively more powerful compared to other alternative
processes and the reliability of Newton-Raphson approach is comparatively good since it can
solve cases that lead to divergence with other popular processes. If the assumed value is near
the solution, then the result is obtained very quickly, but if the assumed value is farther away
from the solution then the method may take longer to converge. This is another iterative load
flow method which is widely used for solving nonlinear equation. The admittance matrix is
used to write equations for currents entering a power system.
Equation (1) is expressed in a polar form, in which j includes bus i
(1)
The real and reactive power at bus i is
(2)
Substituting for Ii in Equation (1) from Equation (2)
(3)
The real and imaginary parts are separated:
(4)
(5)
4
The above Equation (4) and (5) constitute a set of non-linear algebraic equations in terms of
|V| in per unit and δ in radians. Equation (4) and (5) are expanded in Taylor’s series about the
initial estimate and neglecting all higher order terms, the following set of linear equations are
obtained.
In the above equation, the element of the slack bus variable voltage magnitude and angle are
omitted because they are already known. The element of the Jacobian matrix are obtained after
partial derivatives of Equations (15) and (16) are expressed which gives linearized relationship
between small changes in voltage magnitude and voltage angle. The equation can be written in
matrix form as:
(6)
J1, J2, J3, J4 are the elements of the Jacobian matrix.
The difference between the schedule and calculated values known as power residuals for the
terms ∆Pi(k) and ∆Qi(k) is represented as:
(7)
5
(8)
The new estimates for bus voltage are [4]:
(9)
(10)
1.3 Control of Power Flow:
The following means are used to control system power flows:
1. Prime mover and excitation control of generators.
2. Switching of shunt capacitor banks, shunt reactors, and static var systems.
3. Control of tap-changing and regulating transformers.
From the power-flow standpoint, an increase in prime-move power corresponds to an increase
in P at the constant-voltage bus to which the generator is connected. The power-flow program
computes the increase in d along with the small change in Q. An increase in generator
excitation corresponds to an increase in voltage magnitude at the constant-voltage bus to
which the generator is connected. The power-flow program computes the increase in reactive
power Q supplied by the generator along with the small change in δ.
The addition of a shunt capacitor bank to a load bus corresponds to the addition of a negative
reactive load, since a capacitor absorbs negative reactive power. The power-flow program
computes the increase in bus voltage magnitude along with the small change in δ. Similarly,
the addition of a shunt reactor corresponds to the addition of a positive reactive load, wherein
the power-flow program computes the decrease in voltage magnitude.
6
Tap-changing and voltage-magnitude-regulating transformers are used to control bus voltages
as well as reactive power flows on lines to which they are connected. Similarly, phase-angle
regulating transformers are used to control bus angles as well as real power flows on lines to
which they are connected. Both tap-changing and regulating transformers are modeled by a
transformer with an off-nominal turns ratio c. A change in tap setting or voltage regulation
corresponds to a change in c. The power-flow program computes the changes in Ybus, bus
voltage magnitudes and angles, and branch flows [3].
1.4 ETAP:
Electrical Transient Analyzer Program (ETAP) is the foremost-integrated for electrical
systems allowing to have multiple representations of a power system for different analysis and
design purpose. This research will introduce the load flow studies for various conditions by
Electrical Transient Analyzer Program (ETAP) application software as a successful and
accurate tool to conduct load flow study of complex electrical power systems within the
minimum time period.
7
CHAPTER TWO
LOAD FLOW ANALYSIS
8
CHAPTER TWO
LOAD FLOW ANALYSIS
2.1 System Description:
The one line diagram of a 36-bus system is shown in Figure 1. The System data needed for
power flow are shown in appendix A. In this system one generator placed at bus number 36. In
short, this network consists of 36 buses, 35 branches, and 35 loads as presented in table (1).
Buses
Branches
Generators
System Description
Swing
Regulated
Load
Transmission Lines
Transformers
1
Loads
1
0
35
18
17
30
2.2 Load Flow Analysis For the 36-Bus System (normal condition):
For load flow analysis we used the Newton Raphson method with max number of iterations of
50 and precision of 0.0001. Figure 2 shows the normal load flow analysis, after we run the
program the results are obtained from ETAP are shown in tables 2 and 3. Other results are
shown in Appendix A.
Bus Number
Bus Type
1
2
3
4
5
6
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Nominal Voltage
%
Angle
89.078
-5.6
86.527
-5.2
86.193
-5.1
86.193
-5.1
86.132
-5.1
86.098
-5.1
9
PF
69.9
69.9
70.4
75.5
64.6
73.9
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Slack Bus
86.106
86.202
86.321
86.170
86.393
85.526
86.495
85.558
86.007
85.129
85.116
85.110
85.416
76.747
81.932
82.863
80.874
79.266
77.474
79.511
80.147
79.804
78.101
78.909
78.488
78.444
76.979
76.674
77.168
100.00
-5.1
-5.1
-5.1
-5.1
-5.1
-5.0
-5.1
-4.9
-5.0
-4.8
-4.8
-4.9
-4.9
-9.3
-6.7
-5.7
-7.2
-9.1
-9.5
-8.8
-7.5
-8.4
-10.2
-8.7
-9.5
-8.9
-9.5
-9.5
-9.8
0.0
66.9
74.4
60.8
68.7
71.4
67.5
68.6
68.0
67.5
68.0
66.6
70.9
61.5
67.4
70.7
75.5
65.6
78.4
70.7
72.9
64.0
70.7
74.6
70.7
70.7
71.5
72.0
70.7
74.9
62.3
Table (2)
Summary of total generation, loading and demand are shown in the following table:
Source (Swing Bus)
Total Demand
Total Losses
MW
143.465
143.465
8.407
Mvar
180.335
180.335
48.888
Table (3)
MVA
230.440
230.440
PF
62.26 lagging
62.26 lagging
We conclude that all voltages are less than the nominal voltage. And there is a high voltage
drop and transmission losses.
10
Figure (1): 36-bus power system.
2.3 Load Flow Analysis For the 36-Bus System (Maximum Load
Condition):
In this section maximum load state will be studied and we will see the optimization problems
and will search solution for this optimization problem; and obtain results and make
recommendations.
11
Figure (2): Load Flow Analysis in normal condition.
2.3.1 The Maximum Load Improvement
When the original condition analyzed we noticed that there is a drop voltage in most of the
buses. The calculated voltages shown in the table are not acceptable because of the extra drop
voltage in the networks; and the voltages should be adjusted to Vmax = (105% - 110%)
Vnominal. This is required in max load for better performance of the network, because of the
drop in voltage; we have three methods to increase the voltage on the buses:
12
1. Increasing the swing bus voltage;
2. Tap changing Transformers;
3. Addition of a shunt capacitor bank to a load bus
2.3.1.1 Improvement by increasing the swing bus voltage:
For this network we assume that we can increase the voltage on the swing bus up to 5% from
the nominal voltage (220 kV), the new value of the swing bus voltage will be (231 kV), After
running the ETAP the load flow results obtained are shown in the tables 4 and 5, other results
are shown in the appendix B, Figure 3 shows the load flow analysis after increasing the swing
bus voltage by 5%.
Bus Number
Bus Type
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Nominal Voltage
%
Angle
94.680
-5.6
92.246
-4.7
91.926
-4.7
91.926
-4.7
91.868
-4.6
91.838
-4.7
91.845
-4.6
91.935
-4.7
92.049
-4.7
91.905
-4.6
92.117
-4.7
91.292
-4.5
92.214
-4.6
91.322
-4.5
91.763
-4.6
90.928
-4.4
90.917
-4.4
90.911
-4.4
91.203
-4.4
83.043
-8.3
87.870
-6.1
88.750
-5.2
86.873
-6.5
85.379
-8.2
13
PF
70.1
70.2
70.4
75.5
64.7
74.4
67.4
74.7
61.1
68.9
71.7
67.9
68.9
68.4
68.0
68.4
67.1
71.4
62.2
67.4
70.7
75.5
65.6
78.4
25
26
27
28
29
30
31
32
33
34
35
36
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Slack Bus
83.709
85.603
86.192
85.875
84.303
85.036
84.656
84.606
83.260
82.977
83.440
105.000
-8.5
-7.9
-6.8
-7.6
-9.2
-7.8
-8.6
-8.1
-8.6
-8.6
-8.9
0.0
70.7
72.9
64.0
70.7
74.6
70.7
70.7
71.5
72.0
70.7
74.9
63.2
Table (4)
Figure (3): Load flow analysis after increasing the swing bus voltage by 5%.
14
Summary of total generation, loading and demand are shown in the following table:
MW
145.585
145.585
7.598
Source (Swing Bus)
Total Demand
Total Losses
Mvar
178.444
178.444
44.148
Table (5)
MVA
230.440
230.440
PF
63.22 lagging
63.22 lagging
The increasing of the swing bus voltage by 5% didn’t achieve the required, so we have to
change the tap changer.
2.3.1.2 Improvement by Using Tap-Changing Transformers:
In this network the max tap of the transformer T20 is +1 x 5% and the rest of the transformers
have max tap of +1 x 2%, so we put the settings of the transformers tap’s as shown in the
following table:
Transformer
Tap Settings
T20
-4% on the primary Side
Other transformers
-1% on the primary Side
Table (6)
After running the ETAP the load flow results obtained are shown in the tables 7 and 8, other
results are shown in the appendix C, Figure 4 shows the load flow analysis after changing the
tap as shown in table 6.
15
Figure (4): Load flow analysis after Changing the Tap of the transformers.
Bus Number
Bus Type
1
2
3
4
5
6
7
8
9
10
11
12
13
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Nominal Voltage
%
Angle
99.474
-4.7
97.123
-4.4
96.813
-4.3
96.813
-4.4
96.757
-4.3
96.730
-4.3
96.736
-4.3
96.822
-4.3
96.933
-4.3
96.793
-4.3
96.998
-4.4
96.201
-4.2
97.092
-4.3
16
PF
70.4
70.4
70.4
75.5
64.8
74.8
67.7
74.9
61.4
69.1
71.9
68.2
69.1
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Slack Bus
96.231
96.663
95.859
95.848
95.842
96.124
89.357
93.912
94.748
92.965
91.561
89.990
91.772
92.323
92.026
90.564
91.222
90.891
90.819
89.556
89.290
89.728
105.00
-4.2
-4.3
-4.1
-4.1
-4.2
-4.1
-7.6
-5.6
-4.8
-6.0
-7.5
-7.8
-7.3
-6.2
-6.9
-8.4
-7.2
-7.8
-7.4
-7.9
-7.8
-8.1
0
68.7
68.4
68.8
67.5
71.8
62.7
67.4
70.7
75.5
65.6
78.4
70.7
72.9
64.0
70.7
74.6
70.7
70.7
71.5
72.0
70.7
74.9
63.9
Table (7)
Summary of total generation, loading and demand are shown in the following table:
Source (Swing Bus)
Total Demand
Total Losses
MW
147.947
147.947
7.045
Mvar
177.921
177.921
40.817
Table (8)
MVA
231.396
231.396
PF
63.94 lagging
63.94 lagging
The changing of the tap on the transformers still didn’t achieve the required, so we have to add
shunt capacitor banks.
2.3.1.3 Improvement by Using Shunt Capacitor Banks:
After running the ETAP the load flow results obtained are shown in the tables 9 and 10, other
results are shown in the appendix D, Figure 5 shows the network after adding the capacitor
bank and Figure 6 shows the load flow analysis after installing the capacitor banks.
17
This equation will be used to calculate the reactive power needed from the capacitors:
Qc= P(tan cos-1 (PFold) - tan cos-1(PFnew))
PFnew (desired) = 0.94 lag
Table (9) shows the voltage level before and after adding the capacitors:
Bus
Number
Bus Type
QC
Mvar
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Slack Bus
1.9111
1.7980
1.3399
1.7840
3.1000
1.9110
8.6389
1.95556
9.3594
2.0613
2.2910
2.4210
2.0778
5.2780
0.3824
0.1163
1.0947
1.0291
3.5689
1.7164
0.8376
1.7207
4.4229
3.9067
4.6842
4.1007
4.5665
4.8434
4.1664
-
Nominal Voltage
before adding
capacitor bank
%
99.474
97.123
96.813
96.813
96.757
96.730
96.736
96.822
96.933
96.793
96.998
96.201
97.092
96.231
96.663
95.859
95.848
95.842
96.124
89.357
93.912
94.748
92.965
91.561
89.990
91.772
92.323
92.026
90.564
91.222
90.891
90.819
89.556
89.290
89.728
105.00
Table (9)
18
Nominal Voltage
after adding
capacitor bank
%
105.570
103.875
103.654
103.641
103.606
103.568
103.568
103.668
104.018
103.750
103.710
103.130
103.834
103.202
103.527
102.936
102.937
102.904
103.152
101.519
102.914
102.778
102.944
101.417
101.565
102.186
102.881
102.431
101.700
101.938
102.198
101.779
101.093
101.104
100.877
105.000
PFold
PFnew
70.4
70.4
70.4
75.5
64.8
74.8
67.7
74.9
61.4
69.1
71.9
68.2
69.1
68.7
68.4
68.8
67.5
71.8
62.7
67.4
70.7
75.5
65.6
78.4
70.7
72.9
64.0
70.7
74.6
70.7
70.7
71.5
72.0
70.7
74.9
63.9
94.6
94.7
94.9
94.8
88.7
92.4
93.4
99.0
94.2
94.0
94.0
93.6
94.1
93.5
92.9
93.1
93.2
92.9
92.5
94.5
94.9
94.6
95.1
94.3
94.5
94.6
95.2
94.7
94.8
94.6
94.7
94.5
94.3
94.3
94.2
90.7
Summary of total generation, loading and demand are shown in the following table:
Source (Swing Bus)
Total Demand
Total Losses
MW
149.626
149.626
3.595
Mvar
71.177
71.177
20.772
Table (10)
MVA
165.699
165.699
Figure (5): 36-bus power system with capacitor banks.
19
PF
90.3 lagging
90.3 lagging
Figure (6): Load flow analysis after installing the capacitor banks.
We conclude that all voltages are within the specifications required in the case of maximum
load.
20
2.3.1.4 Comparison between the three cases:
Table (11) shows the effect on the bus voltage after using each improvement method.
Bus
Number
Bus Type
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Slack Bus
Normal Case
Increase the
voltage of
swing bus by
5%
Changing the tap
changer and change
the swing bus
voltage by 5%
%
89.078
86.527
86.193
86.193
86.132
86.098
86.106
86.202
86.321
86.170
86.393
85.526
86.495
85.558
86.007
85.129
85.116
85.110
85.416
76.747
81.932
82.863
80.874
79.266
77.474
79.511
80.147
79.804
78.101
78.909
78.488
78.444
76.979
76.674
77.168
100.00
%
94.680
92.246
91.926
91.926
91.868
91.838
91.845
91.935
92.049
91.905
92.117
91.292
92.214
91.322
91.763
90.928
90.917
90.911
91.203
83.043
87.870
88.750
86.873
85.379
83.709
85.603
86.192
85.875
84.303
85.036
84.656
84.606
83.260
82.977
83.440
105.000
%
99.474
97.123
96.813
96.813
96.757
96.730
96.736
96.822
96.933
96.793
96.998
96.201
97.092
96.231
96.663
95.859
95.848
95.842
96.124
89.357
93.912
94.748
92.965
91.561
89.990
91.772
92.323
92.026
90.564
91.222
90.891
90.819
89.556
89.290
89.728
105.00
Table (11): Comparison between the three cases.
21
Changing the tap
changer, change the
swing bus voltage
by 5% and adding
capacitor bank
%
105.790
104.143
103.922
103.909
103.929
103.836
103.863
103.935
104.018
103.903
103.933
103.354
104.060
103.430
103.791
103.201
103.202
103.206
103.416
101.811
103.195
103.055
103.288
101.705
101.860
102.475
103.169
102.720
102.856
102.180
102.445
101.027
101.384
101.396
101.214
105.000
2.4 Load Flow Analysis For the 36-Bus System (Minimum Load
Condition):
In this case the network will be studied at its minimum load that the load will be decreased by
70% that we will multiply the real and reactive power by 0.3 at each load, the new data for the
minimum case are shown in table (12).
Bus Number
Normal Case
Bus Type
Minimum Load
1
Load Bus
P (MW)
-
Q (Mvar)
-
P (MW)
-
Q (Mvar)
-
2
Load Bus
-
-
-
-
3
Load Bus
3.000
3.000
0.900
0.900
4
Load Bus
3.570
3.100
1.190
0.930
5
Load Bus
2.610
3.000
0.783
0.900
6
Load Bus
-
-
-
-
7
Load Bus
2.800
2.800
0.840
0.840
8
Load Bus
4.019
3.100
1.206
0.930
9
Load Bus
-
-
-
-
10
Load Bus
3.000
3.000
0.900
0.900
11
Load Bus
16.70
14.70
5.010
4.410
12
Load Bus
3.070
3.070
0.921
0.921
13
Load Bus
14.66
14.68
4.398
4.893
14
Load Bus
3.330
3.270
0.999
0.981
15
Load Bus
-
-
-
-
16
Load Bus
3.800
3.670
1.140
1.101
17
Load Bus
3.800
3.800
1.140
1.140
18
Load Bus
4.000
3.530
1.200
1.059
19
Load Bus
-
-
-
-
20
Load Bus
7.200
7.900
2.16
2.37
21
Load Bus
0.600
0.600
0.18
0.18
22
22
Load Bus
0.230
0.200
0.069
0.06
23
Load Bus
1.390
1.600
0.417
0.48
24
Load Bus
2.400
1.900
0.720
0.570
25
Load Bus
5.600
5.600
1.68
1.68
26
Load Bus
2.980
2.800
0.984
0.934
27
Load Bus
1.000
1.200
0.3
0.36
28
Load Bus
2.700
2.700
0.810
0.810
29
Load Bus
8.350
7.450
2.505
2.235
30
Load Bus
6.130
6.130
1.839
1.839
31
Load Bus
7.350
7.350
2.205
2.205
32
Load Bus
6.670
6.530
2.001
1.959
33
Load Bus
7.600
7.330
2.280
2.199
34
Load Bus
7.600
7.600
2.280
2.280
35
Load Bus
8.000
7.070
2.400
2.121
36
Slack Bus
0.384
1.920
0.1152
0.576
Total Number of buses = 36
144.543
140.6
45.595
42.318
Table (12): New Load values for minimum load condition.
Figure 7 shows the load flow analysis for minimum load condition, after we run the program
the results are obtained from ETAP are shown in tables 13 and 14. Other results are shown in
Appendix E.
Bus Number
Bus Type
1
2
3
4
5
6
7
8
9
10
11
12
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Nominal Voltage
%
Angle
97.186
-1.6
96.393
-1.6
96.300
-1.5
96.185
-1.6
96.283
-1.5
96.278
-1.6
96.278
-1.5
96.298
-1.6
96.337
-1.6
96.294
-1.5
96.450
-1.5
96.215
-1.5
23
PF
77.4
77.3
70.6
95.7
65.4
77.4
69.9
74.7
63.3
70.2
73.2
70.0
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Slack Bus
96.478
96.224
96.363
96.126
96.123
96.121
96.205
93.996
95.150
95.276
94.880
94.502
94.065
94.260
94.698
94.698
94.622
94.334
94.414
94.388
94.055
93.981
94.109
100.00
-1.5
-1.5
-1.5
-1.5
-1.5
-1.5
-1.5
-2.5
-1.9
-1.7
-2.1
-2.5
-2.6
-2.5
-2.1
-2.3
-2.7
-2.4
-2.6
-2.4
-2.6
-2.6
-2.6
0
70.4
70.6
70.7
71.1
69.8
74.0
66.0
67.4
70.7
75.5
65.6
78.4
70.7
70.7
64.0
70.7
74.6
70.7
70.7
71.5
72.0
70.7
74.9
71.2
Table (13)
Summary of total generation, loading and demand are shown in the following table:
Source (Swing Bus)
Total Demand
Total Losses
MW
45.4
45.4
0.642
Mvar
45.228
45.228
3.688
Table (14)
MVA
64.084
64.084
PF
70.84 lagging
70.84 lagging
We have to increase the buses voltage up to 100%, for this case firstly we will increase the
swing bus voltage to 5%.
2.4.1 The Minimum Load Improvement
When the minimum load condition analyzed we noticed that there is a drop voltage in most of
the buses. The calculated voltages shown in the table are not acceptable because of the extra
drop voltage in the networks; and the voltages should be adjusted to Vmax = (100%) Vnominal.
24
This is required in minimum load for better performance of the network, because of the drop
in voltage; we have three methods to increase the voltage on the buses:
1. Increasing the swing bus voltage;
2. Tap changing Transformers;
3. Addition of a shunt capacitor bank to a load bus
Figure (7): Load flow analysis for minimum load condition.
2.4.1.1 Improvement by increasing the swing bus voltage:
For this network we assume that we can increase the voltage on the swing bus up to 5% from
the nominal voltage (220 kV), the new value of the swing bus voltage will be (231 kV), After
25
running the ETAP the load flow results obtained are shown in the tables 15 and 16, other
results are shown in the appendix F, Figure 8 shows the load flow analysis after increasing the
swing bus voltage by 5%.
Bus Number
Bus Type
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Slack Bus
Nominal Voltage
%
Angle
102.281
-1.5
101.512
-1.4
101.422
-1.4
101.311
-1.5
101.406
-1.5
101.401
-1.4
101.401
-1.4
101.420
-1.4
101.458
-1.4
101.417
-1.4
101.568
-1.4
101.340
-1.4
101.595
-1.4
101.349
-1.4
101.484
-1.4
101.254
-1.4
101.251
-1.4
101.250
-1.4
101.331
-1.4
99.196
-2.3
100.310
-1.8
100.431
-1.6
100.048
-1.9
99.684
-2.3
99.262
-2.4
99.450
-2.3
99.873
-2.0
99.800
-2.1
99.522
-2.5
99.678
-2.2
99.599
-2.4
99.573
-2.2
99.253
-2.4
99.182
-2.4
99.305
-2.4
105.00
0
(Table 15)
26
PF
77.4
77.3
70.6
95.7
77.5
77.5
69.9
74.8
-63.3
70.3
73.3
70
70.4
70.8
70.8
71.1
69.9
74.1
66.1
67.4
70.7
75.5
65.6
78.4
70.7
70.7
64.0
70.7
74.6
70.7
70.7
71.5
72.0
70.7
74.9
74.4
Summary of total generation, loading and demand are shown in the following table:
MW
46.279
46.279
0.601
Source (Swing Bus)
Total Demand
Total Losses
Mvar
45.849
45.849
3.455
Table (16)
MVA
65.145
65.145
PF
71.04 lagging
71.04 lagging
The increasing of the swing bus voltage by 5% didn’t achieve the required, so we have to
change the tap changer.
2.4.1.2 Improvement by Using Tap-Changing Transformers:
the settings of the transformers tap’s are set as shown in the following table:
Transformer
Tap Settings
T20
0% on the primary Side
Other transformers
-1% on the primary Side
Table (17)
After running the ETAP the load flow results obtained are shown in tables 18 and 19, other
results are shown in the appendix G. If we change the tap of the transformer T20 the buses
voltage will be out of the range
Bus Number
Bus Type
1
2
3
4
5
6
7
8
9
10
11
12
13
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Nominal Voltage
%
Angle
102.275
-1.5
101.505
-1.4
101.415
-1.4
101.304
-1.5
101.399
-1.5
101.393
-1.4
101.394
-1.4
101.414
-1.4
101.451
-1.4
101.410
-1.4
101.561
-1.4
101.332
-1.4
101.588
-1.4
27
PF
77.4
77.3
70.6
95.7
77.5
77.5
69.9
74.8
-63.3
70.3
73.3
70
70.4
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Slack Bus
101.341
101.476
101.246
101.243
101.241
101.323
100.225
101.334
101.453
101.074
100.712
100.292
100.480
100.900
100.827
100.554
100.704
100.631
100.601
100.280
100.209
100.331
105.00
-1.4
-1.4
-1.4
-1.4
-1.4
-1.4
-2.3
-1.8
-1.6
-1.9
-2.3
-2.3
-2.3
-1.9
-2.1
-2.5
-2.2
-2.3
-2.2
-2.3
-2.3
-2.4
0
70.8
70.8
71.1
69.9
74.1
66.1
67.4
70.7
75.5
65.6
78.4
70.7
70.7
64.0
70.7
74.6
70.7
70.7
71.5
72.0
70.7
74.9
71.4
Table (18)
Summary of total generation, loading and demand are shown in the following table:
Source (Swing Bus)
Total Demand
Total Losses
MW
46.374
46.374
0.602
Mvar
45.941
45.941
3.456
Table (19)
MVA
65.279
65.279
PF
71.04 lagging
71.04 lagging
2.5 Load Flow Analysis For the 36-Bus System (Post Fault
Condition):
In this section we will assume that the network is affected by a fault condition in some
locations of the transmission lines of the network, after the fault occurs we will try to optimize
the problem. Line (1-15) one of the most important lines in the network, which is carries max
power as shown in figure (8). It will be assumed that a fault happened at one line of the double
28
line, because of that the resistance and inductance will be multiplied by 2 and we will divide
the admittance by 2.
Figure (8): Load flow analysis for post fault condition (determine the critical transmission
line in the network).
After we change the line 1-15 parameters as follows and run ETAP the load flow results
obtained are shown in tables 20 and 21, other results are shown in the appendix H, Figure 9
shows the load flow analysis for this case.
R= 0.04  new R = 0.08
X= 0.024  new X = 0.048
29
Figure (9): Load flow analysis for post fault condition
Bus Number
Bus Type
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Nominal Voltage
%
105.470
103.774
103.553
103.540
103.504
103.466
103.493
103.566
103.649
103.533
103.609
103.028
103.733
103.100
101.281
30
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Slack Bus
100.675
100.675
100.643
100.895
99.0160
102.807
102.672
102.835
101.308
101.453
102.076
102.771
102.322
101.589
101.828
102.087
101.669
98.6070
98.6070
98.4010
105.000
Table (20)
Summary of total generation, loading and demand are shown in the following table:
Source (Swing Bus)
Total Demand
Total Losses
MW
150.055
150.055
4.477
Mvar
72.944
72.944
21.595
Table (21)
MVA
166.839
166.839
PF
89.94 lagging
89.94 lagging
We conclude that after the fault the voltage of some buses reduced, for this case we will add
capacitor bank at bus 19 with 12 Mvar rating,
2.5.1 The Post Fault Condition Improvement
2.5.1.1 Improvement by Using Capacitor Bank:
After adding a capacitor bank at bus 19 with 12 Mvar rating then running the ETAP the load
flow results obtained are shown in the tables 22 and 23, other results are shown in the
appendix J, Figure 10 shows the load flow analysis after installing the capacitor banks.
31
Bus Number
Bus Type
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Load Bus
Slack Bus
Nominal Voltage
%
106.343
104.664
104.445
104.432
104.397
104.359
104.386
104.458
104.540
104.425
104.499
103.924
104.623
103.997
102.804
102.208
102.208
102.175
102.733
101.055
103.745
103.597
103.787
102.268
102.437
103.039
103.732
103.283
102.565
102.796
103.063
102.642
100.293
100.300
100.080
105.000
Table (21)
Summary of total generation, loading and demand are shown in the following table:
Source (Swing Bus)
Total Demand
Total Losses
MW
150.445
150.445
4.19
Mvar
57.651
57.651
20.371
Table (22)
32
MVA
161.111
161.111
PF
93.38 lagging
93.38 lagging
Figure (10): Load flow analysis for post fault condition after adding capacitor bank.
33
CHAPTER THREE
CONCLUSION
34
CHAPTER THREE
CONCLUSION
3.1
Conclusion:
Power flow analysis is an essential step for operational purposes to evaluate various operating
states of an existing system. Also it is necessary for enhancement and development projects. In
this research Load flow study using ETAP software is carried out to analyze the system under
various conditions. By using ETAP load flow program, it is found that the 36-bus network
experiences many technical problems including: poor power factor, low voltage levels and
power losses. And the aim of this load flow studies is to determining the system voltage under
various conditions, and to use proper methods that used to maintain the problem of under
voltage. And they are useful to determine if system voltages remain within specific limits
under various conditions, and whether equipment such as transformers and transmission lines
are overloaded. It is used to identify the need for additional generation, placement of shunt
capacitors or reactors to maintain the system voltages within the limits.
35
BIBLIOGRAPHY
[1]: Gonen, T. (2013). Modern power system analysis. CRC Press.
[2]: Turan, G. (1998). Electric power transmission system engineering.
[3]: Glover, J. D. D., & Sarma, M. S. (2001). Power system analysis and design. Brooks/Cole
Publishing Co.
[4]: Afolabi, O. A., Ali, W. H., Cofie, P., Fuller, J., Obiomon, P., & Kolawole, E. S. (2015).
Analysis of the load flow problem in power system planning studies. Energy and Power
Engineering, 7(10), 509.
36
Appendices
Appendix (A): Normal Case
A.1 Input Data
Bus Input Data:
37
Branch Connections:
38
2-Winding Transformer Input Data:
A.2 Load Flow Solution
39
40
A.3 Branch Losses
41
Appendix (B): Maximum Load Condition (Swing Bus)
B.1 Load Flow Solution (Swing Bus)
42
43
B.2 Branch Losses (Swing Bus)
44
Appendix (C): Maximum Load Condition (Tap Changing Transformer)
C.1 Load Flow Solution (Tap Changing Transformer)
45
46
C.2 Branch Losses (Tap Changing Transformer)
47
Appendix (D): Maximum Load Condition (Capacitor Bank)
D.1 Load Flow Solution (Capacitor Bank)
48
49
D.2 Branch Losses (Capacitor Bank)
50
Appendix (E): Minimum Load Condition
E.1 Load Flow Solution
51
52
E.2 Branch Losses
53
Appendix (F): Minimum Load Condition (Swing Bus)
F.1 Load Flow Solution (Swing Bus)
54
55
F.2 Branch Losses (Swing Bus)
56
Appendix (G): Minimum Load Condition (Tap changing Transformer)
G.1 Load Flow Solution (Tap changing Transformer)
57
58
G.2 Branch Losses (Tap changing Transformer)
59
Appendix (H): Post Fault Condition
H.1 Load Flow Solution
60
61
H.2 Branch Losses
62
Appendix (J): Post Fault Condition (Capacitor Bank)
J.1 Load Flow Solution (capacitor bank)
63
64
J.2 Branch Losses (Capacitor Bank)
65
Descargar