INSPECTION AND TEST PLAN (ITP)
Contract # 092-C48
Name of Contractor
1
2
P&C of TS-8
UNIT/ AREA / LOCATION
4
3
ROAD MARKING AND ROAD REFLETOR INSTALLATION
5
DISCIPLINE
6
ITP #: RCJ-CE-020
Rev #: 0
Page #:
EQUIPMENT DESCRIPTION / TAG NUMBER
CIVIL/ ARCHITECTURAL
7
Activity
#
8
9 Inspection / Test Requirements
Activity Description
Test or Inspection
Stage/Frequency
Performed
10
Reference Document(s)
Code, Spec, Etc
Acceptance Criteria
Method of Verification
(see Legend below)
11
Contr.
QC
R/C
Others
12
Report
Inspection
Request, Hold
Point Release
Reference #
Type of Material,
Manufacturer,
Supplier
IFC Drawings, RC Spec.
Submittal review
Section 02760 pars.
status:
(1.06 A.3,4,7), Part 2
Code 1, 2 or 4
pars. 2.01 to 2.03
R
R
Material
Technical
Submittal (Code
1)
Approved Material
Submittal (Code 1, 2
or 4)
I
I
Inspection
Request,
Delivery Notes
RC Spec. Section
02760 par. 2.05
RC Spec. Section
02760 par. 2.05
I
I
Inspection
Request
Per Road
Location
RC Spec. Section
02760 par. 3.01 to 3.03
RC Spec. Section
02760 par. 3.01 to
3.03
HI
WI
Inspection
Checklist,
Hold Point
Release
Per Road
Location
RC Spec. Section
02760 par. 3.04,
Manufacturer’s
Instruction
RC Spec. Section
02760 par. 3.04,
Manufacturer’s
Instruction
I
I
Inspection
Request
1.
Material Approval
Review Material
Submittals
2.
Material Delivery Handling
& Storage at Site
Visual/
Measurement
Every Material
Delivery
RC Spec. Section
02760 par. 1.10
3.
Pavement Marking
Equipment Conditions
Check
Visual Inspection
Prior to
Pavement
Marking
Application
4.
Pavement Surface
Preparation & Layout
Visual Inspection/
Measurements
5.
Pre-Markings & PreApplication Test
Visual Inspection
INSPECTION AND TEST PLAN (ITP)
Contract # 092-C48
Name of Contractor
1
2
P&C of TS-8
UNIT/ AREA / LOCATION
4
3
ROAD MARKING AND ROAD REFLETOR INSTALLATION
5
DISCIPLINE
6
ITP #: RCJ-CE-020
Rev #: 0
Page #:
EQUIPMENT DESCRIPTION / TAG NUMBER
CIVIL/ ARCHITECTURAL
7
8
Activity
#
6.
7.
13
9 Inspection / Test Requirements
Activity Description
Pavement Marking
Application
Test or Inspection
Stage/Frequency
Performed
Visual Inspection/
Measurement
Installation of Road Markers Visual
(Reflectors)
Measurements
Contractor QC Date & Signature /Stamp No.
14
10
Code, Spec, Etc
Method of Verification
(see Legend below)
11
Reference Document(s)
Contr.
QC
Acceptance Criteria
R/C
Others
12
Report
Inspection
Request, Hold
Point Release
Reference #
Per Road
Locations
IFC drawings, RC Spec.
Section 02760 par.
3.05, 3.10, 3.12, MOT
Standard,
Manufacturer’s
Instruction
IFC drawings, RC
Spec. Section 02760
par. 3.05, 3.10, 3.12,
Manufacturer’s
Instruction
Per Type of
Roads
IFC drawings,
RC Spec. Section
02760 par. 2.03 B, 3.06,
MOT Standard
Manufacturer’s
Instruction
IFC drawings,
RC Spec. Section
02760 par. 2.03 B,
3.06, MOT Standard
Manufacturer’s
Instruction
13 RC Insp. (Date & Signature.)
Legend : I – Inspection; R – Document Review; T – Test; W - Witness Point; H - Hold Point
HI
HI
13
Others
HI
Inspection
Checklist,
Hold Point
Release
HI
Inspection
Checklist,
Hold Point
Release
ITP Form Completion Instructions
Page 1 of 2
The following refers to numbers shown on the ITP Form
ITP
Form #
1
2
3
4
5
6
7
8
9
10
11
12
13
14
ITP Block
Title
ITP #, Rev #
Page #
Unit / Area /
Location
Discipline
Equipment
Description/
Tag #
Activity #
Activity
Description
Insp. & Test
Requirements
Reference
Documents
Method of
Verification
Report
Reference #
Signatures
Legend
Standard header for ITPs. Contractor Logo and Project Name to be included in block 1.
ITP Title, i.e. description of the main activity covered by the ITP. For example, “Concrete Placement.”
Enter ITP, revision, and page numbers.
Enter the unit, area or location the ITP covers.
Indicate discipline i.e., Civil, Electrical, or Mechanical.
Enter equipment description, and tag numbers (if applicable), placement type, etc.
The activity number shall be a sequential number starting with 1.0, or from the start of an activity to completion.
Enter a brief description of each construction activity to be performed to complete the activity described in block 2. For example
Concrete pre-pour inspection activities.
Identify the inspection & test activity to be performed based on activity identified in block 8. For example, Installation of forms,
Slump test, and indicate stage or frequency
Reference the document that addresses each activity i. e., Code, Standard, Spec., Procedure, Drawing Number, etc., and
identify the acceptance criteria. Ensure when listing “Acceptance Criteria” the actual units required are stated (example:
pressure (psi, Pa), length, depth or height (cm, m), density kg/m3 lb/ft3 etc).
Contractor’s Quality Control, Bechtel and/or Other Project Stakeholders. Refer to Legend #14 below, and page 2 of the
completion instructions for additional information.
Identify inspection/test form number, checklist, and hold point release belonging to each ITP Activity #. Reference the report
number to ensure traceability between the ITP and each inspection/test form, checklist, and the item being inspected or tested.
Signatures by responsible parties signifying that all inspection and tests associated with the ITP have been identified.
Identifies hold & witness points and types of verifications to be performed.
ITP Form Completion Instructions
Page 2 of 2
The Contractor has primary responsibility for performing verification activities for their scope of work.
Inspection and Test Plans are assigned Hold Points, Witness Points and the method of Verification by the Contractor, Royal
Commission/Bechtel, and Other Project Stakeholders. Hold and Witness points are normally assigned when:
a) Verification cannot be performed due to subsequent work processes.
b) The activity has to be verified immediately due to its complexity and importance.
When a Hold Point is identified on the Inspection and Test Plan, the Contractor cannot proceed with the relevant activity until the activity has
been observed. A minimum of 24-hour notification is required in advance of reaching the Hold Point.
When a Witness Point is identified, the Contactor may proceed with the relevant activity if the organization is not present at the appropriate time
and place based on previous notification provided by the Contractor. A minimum of 24-hour notification is required in advance of reaching the
Witness Point. Only if the organization responsible for the inspection fails to respond to the Witness point, or has previously waived the witness
point in writing, the Contractor may proceed.
HOLD POINT AND WITNESS POINT
Hold (H)
Hold Points are designated as “H” plus the verification method.
Witness (W)
Witness Points are designated as “W” plus the verification method.
VERIFICATION METHODS
Review (R)
Inspect (I)
Test (T)
Review is designated as “R”. Review is the act of verifying that documentation is in compliance with project requirements.
Inspect is designated as “I”. Inspection is the act of verifying (such as, examining, measuring, observing, reviewing, recording,
etc.), that activities are in conformance with project requirements.
Test is designated as “T”. Testing is the act of verifying (such as, Compaction, NDE, Hydrostatic, Megger, etc.), to pre-defined
values that activities are in compliance with project requirements.
Note: Hold and Witness points are identified as HR, HI, HT, WR, WI, and WT on the Inspection and Test Plan. R, I, and T may be
indicated by their selves, as appropriate, on the ITP if no Hold or Witness Point is identified.