Comisión Federal de Electricidad Tula Branch Gas Pipeline (Hidalgo) point, usually a central power generation plant. The branch to Tula will transport natural gas from the Cempoala-Santa Ana system to the Tula power generation plant in the State of Hidalgo. It will have a capacity of 505 million cubic feet per day (MCFD). Project Details: The project includes the design, engineering, supply, construction, operation and maintenance. The approximate length of the branch is 17 km and 30-inch diameter. The estimated project implementation period is 11 months. Geographic location State of Hidalgo Veracruz Polo Generador Tula Hidalgo Cempoala (PGPB) Hacia Santa Ana (PGPB) Tlaxcala Puebla Relevant Facts: Estimated investment: $50 million U.S. dollars Capacity: 505 MCFD Pre-bid Docs Publication: June 27, 2014 Final Docs Publication: July 24, 2014 Proposals Filing: September 23, 2014 Awarding of Contract: October 9, 2014 COD: September 2015