PRESUPUESTO DE OBRA PRELIMINAR 13 DIC (1)

Anuncio
PRESUPUESTO DE OBRA NEGRA
Descripción de la obra
OBRA CASA HABITACION UNIFAMILIAR, PROYECTO "ALCAICERIA 250"
PARTIDA
1. DEMOLICION
MANO DE OBRA
TIEMPO
COSTO
1.1. DEMOLICION 1a ETAPA
$360.00
MATERIALES
UND
$/UND
METRAJE
IMPORTE
Demolicion manual y/o mecanica y retiro de escombro generado por la misma
1
$0.00
30
TOTAL DE [PARTIDA]
$10,800.00
$10,800.00
2. CIMENTACION
2.1. LIMPIEZA Y NIVELACION DE TERRENO
$15.00
2.2. TRAZO DE CIMENTACION
2.3. ARMADO DE ZAPATAS
2.4. CIMBRADO DE ZAPATAS
2.5. COLADO DE ZAPATAS
$0.00
$0.00
$0.00
$650.00
1
$0.00
98
$1,470.00
$0.00
$0.00
$0.00
$0.00
71.2
TOTAL DE [PARTIDA]
$46,280.00
$47,750.00
3. INSTALACION HIDRAULICA Y SANITARIA
3.1. CONSTRUCCION DE CISTERNA IN SITU
3.2. CONSTRUCCION DE REGISTROS
$4.00
$1,800.00
1
4
$0.00
2250
$0.00
TOTAL DE [PARTIDA]
$9,000.00
$7,200.00
$16,200.00
$170.00
$170.00
1
1
$0.00
75
$0.00
35
TOTAL DE [PARTIDA]
$12,750.00
$5,950.00
$18,700.00
$370.00
18
$0.00
$18,130.00
4. PISOS
4.1. COLOCACION DE FIRME EN PISO INTERIOR ACABADO CONCRETO PINTADO
4.2. COLOCACION DE FIRME EN PISO EXTERIOR ACABADO ESCOBILLADO
5. CASTILLOS
4.1. CASTLLOS DE 15X20
49
TOTAL DE [PARTIDA]
$18,130.00
6. COLUMNAS
6.1 COLUMNAS 25X25
$520.00
20
$0.00
54
TOTAL DE [PARTIDA]
$28,080.00
$28,080.00
7. MUROS
6.1. MURO INTERIOR DE BLOCK 40X20X15
$160.00
1
$0.00
42
6.2. MURO EXTERIOR COLINDANTE DE BLOCK 40X20X15
$160.00
1
$0.00
25
$4,000.00
6.3. CADENA MURO INTERIOR 15X20
$370.00
1
$0.00
42
$15,540.00
TOTAL DE [PARTIDA]
$6,720.00
$26,260.00
8. TRABES
8.1. TRABECONCRETO ARMADO 25X40
$520.00
1
$0.00
43
TOTAL DE [PARTIDA]
$22,360.00
$22,360.00
9. ESCALERAS
9.1. ESCALERA DE CONCRETO IN SITU (ARMADO, CIMBRADO Y COLADO)
$14,000.00
1
$0.00
1
TOTAL DE [PARTIDA]
$14,000.00
$14,000.00
10. LOSA
10.1. LOSA DE CONCRETO ARMADO H=15 CM
$460.00
1
$0.00
83
TOTAL DE [PARTIDA]
$38,180.00
$38,180.00
11. DEMOLICION
11.1. DEMOLICION 2a ETAPA
$360.00
Demolicion manual y/o mecanica y retiro de escombro generado por la misma
1
$0.00
52
TOTAL DE [PARTIDA]
$18,720.00
$18,720.00
12. REVOQUE EN INTERIORES
12.1. REVOQUE CON ESTUCO BLANCO EN INTERIOR
$110.00
1
$0.00
280
$30,800.00
TOTAL DE [PARTIDA]
$30,800.00
13. LIMPIEZA
13.1. LIMPIEZA GENERAL PARA ENTREGA DE OBRA
$15.00
1
$0.00
98
$1,470.00
TOTAL DE [PARTIDA]
$1,470.00
TOTAL DE OBRA NEGRA
$291,450.00
15% por HONORARIOS
$43,717.50
COSTO TOTAL DE LA OBRA
$335,167.50