How to calculate Planned % and Actual % using weight
‘Schedule % Complete’ in Primavera P6 (represents the planned %) calculates its percentage using
the cost resource. But if you wanted to measure the ‘Schedule % Complete’ by the weight of the
activities, here we will have to use Excel to perform such a task.
This process will be performed using two main tools: Primavera P6 and Excel.
Primavera
1. First of all, from “Project” in the toolbar, choose “Resource Assignments”.
2. Choose “Filter” to filter the resource type as we need only the weight of the activities.
Business Centre, Sharjah
Publishing City Free Zone, Sharjah,
+971 563 444 875
[email protected]
https://planningengineer.net/
Page 1 of 14
Planning Engineer FZE
‫بالنينغ إنجينير م م ح‬
Project Management & Planning Services and Training
‫خدمات وتدريب إدارة المشروعات والتخطيط‬
In case you do not have a weight assigned to your activities, you can create a resource called
“Weight”. From “Enterprise”, Choose “Resources”.
Add a new resource and name it “Weight”, then, choose the resource type as “Nonlabor” and
“Finish”.
After clicking “Finish”, assign the “Weight” resource to all of your activities and choose a suitable
weight for every activity by assigning this weight in the “Budgeted Units”.
Business Centre, Sharjah
Publishing City Free Zone, Sharjah,
+971 563 444 875
[email protected]
https://planningengineer.net/
Page 2 of 14
Planning Engineer FZE
‫بالنينغ إنجينير م م ح‬
Project Management & Planning Services and Training
‫خدمات وتدريب إدارة المشروعات والتخطيط‬
3. In the Resource Assignment, right-click on any column heading, then choose “Columns”,
then “Customize” and make sure that the “Budgeted Units” column is selected.
Business Centre, Sharjah
Publishing City Free Zone, Sharjah,
+971 563 444 875
[email protected]
https://planningengineer.net/
Page 3 of 14
Planning Engineer FZE
‫بالنينغ إنجينير م م ح‬
Project Management & Planning Services and Training
‫خدمات وتدريب إدارة المشروعات والتخطيط‬
4. In the bar chart area, make sure that the displayed units are budgeted units by right-clicking
on any point in the display area. From “Spreadsheet Fields”, choose “Budgeted Units”.
5. Before copying our activities to Excel, we have a final step to do. This step is determining the
timescale of the project. This depends on the minimal periodic reports that we want to
review, do we want to have daily reports? or weekly?
In this article, we will be working on the weekly report. So, right-click on any point in the
display area and choose “Timescale”. In the “Timescale” window, choose “Month/week”
option from “Date Interval” dropdown box. In case you are working on a monthly report,
you will “Quarter/Month” from “Date Interval”.
Business Centre, Sharjah
Publishing City Free Zone, Sharjah,
+971 563 444 875
[email protected]
https://planningengineer.net/
Page 4 of 14
Planning Engineer FZE
‫بالنينغ إنجينير م م ح‬
Project Management & Planning Services and Training
‫خدمات وتدريب إدارة المشروعات والتخطيط‬
Now, choose the WBS levels that you want to show, click on the first WBS row then move down to
the last WBS row (Without clicking on it), click “Shift”, then click on the last WBS row then “Ctrl+C”.
In this screenshot, we want to show the overall progress of the following WBS: Preliminaries,
Surveys and Mapping, Engineering, Procurement, Construction, Testing and commissioning, and
Project Closeout without any further details. So, we collapsed the WBS level to level 2 which includes
these WBS. Let's move on to Excel.
Excel
1. Press “Ctrl+V” to paste the data you copied from Primavera P6.
In the blue box, you can see the WBS of the project as you chose with the corresponding overall
budgeted nonlabor units of each WBS. On the other hand, the red box includes the distribution of
these budgeted nonlabor units over the weeks (the time interval that we chose).
Note that row 2 includes the overall budgeted nonlabor units of the project in the blue box and the
budgeted nonlabor units per week in the red box. This note is essential for the next step.
2. Below the copied data, we will create 2 rows which are: “Weekly Planned Weight” and
“Weekly Planned %”. The “weekly planned weight” will be equal to the cell in row 2 of the
same column, e.g.: the “Weekly Planned Weight” of the week ending on 3-July-22 that lies in
column “F” will be equal to F2.
The “Weekly Planned %” will be equal to the “Weekly Planned Weight” divided by the
overall budgeted nonlabor units (Cell D2).
Let's transform it into an equation, “Weekly Planned %”= F238/$D$2 as shown below.
Business Centre, Sharjah
Publishing City Free Zone, Sharjah,
+971 563 444 875
[email protected]
https://planningengineer.net/
Page 5 of 14
Planning Engineer FZE
‫بالنينغ إنجينير م م ح‬
Project Management & Planning Services and Training
‫خدمات وتدريب إدارة المشروعات والتخطيط‬
3. Now, we have the weekly planned percentage for every week in the project. However, we
need to calculate the cumulated weekly planned percentage to obtain the “Schedule %
Complete” for any date we choose.
Below the “Weekly Planned Weight” and “Weekly Planned %”, create another two rows
named “Cumm. Planned Weight” and “Cumm. Planned%”. As the equations are already set
in the “Weekly Planned Weight” and “Weekly Planned %”, all we have to do is sum up the
numbers. For the “Cumm. Planned Weight”, the result will be equal to the weekly planned
weight plus the cumulative planned weight of the previous week.
In the below screenshot, the cumulative planned weight of the week ending on 10-Jul-22 is
equal to the weekly planned weight of the week ending on 10-Jul-22 plus the cumulative
planned weight of the week ending on 3-Jul-22.
For the “Cumulated Planned %”, do the same process that we did for “Cumulative Planned
Weight” but using the “Weekly Planned %” and “Cumm. Planned %”.
Business Centre, Sharjah
Publishing City Free Zone, Sharjah,
+971 563 444 875
[email protected]
https://planningengineer.net/
Page 6 of 14
Planning Engineer FZE
‫بالنينغ إنجينير م م ح‬
Project Management & Planning Services and Training
‫خدمات وتدريب إدارة المشروعات والتخطيط‬
4. Finally, we can use a simple HLOOKUP function to get any data we want based on the data
date. The HLOOKUP function works as follows, First, you pick the cell that includes the value
that you aim to look for (in our article, it is the data date). Second, choose the range of data
that Excel will look within it (For us, the range is from row 237 to row 241). Then, you have
to choose the row number that Excel will get its result from when it finds the value you are
looking for, as below, we want the “Cumm. Planned %” which lies in the 5th row in our range.
Finally, Excel will ask you if you want an approximate result or not, choose “False” if you
want an exact result.
Now, let’s move on to calculating the actual % completed using weight.
Business Centre, Sharjah
Publishing City Free Zone, Sharjah,
+971 563 444 875
[email protected]
https://planningengineer.net/
Page 7 of 14
Planning Engineer FZE
‫بالنينغ إنجينير م م ح‬
Project Management & Planning Services and Training
‫خدمات وتدريب إدارة المشروعات والتخطيط‬
Primavera
As we did in the planned %, from “Resource Assignments”, edit “Columns” and switch the “Budgeted
Units” column with “Actual Units”.
Now, choose the exact WBS you chose before while copying the planned nonlabor units, select the
first row, then move down to the last row, press “Shift” and select the last row. Press “Ctrl+C” and
now it is time to paste it into Excel.
Business Centre, Sharjah
Publishing City Free Zone, Sharjah,
+971 563 444 875
[email protected]
https://planningengineer.net/
Page 8 of 14
Planning Engineer FZE
‫بالنينغ إنجينير م م ح‬
Project Management & Planning Services and Training
‫خدمات وتدريب إدارة المشروعات والتخطيط‬
Excel
In Excel, we create 2 sheets, first one is named “From P6”. In this sheet, we paste the actual units
that we copied above.
The second sheet is called “Actual Data”, This sheet consists of two parts as shown below, red and
blue part.
In the red box, you will find the budgeted units of the project as in the “Planned Data” sheet. In the
blue box, you will find the actual units per week. But how can we calculate the actual units per
week?
To calculate the actual units per week, we must follow a certain concept. Every week, the actual
units increase as the project moves forward. So, if we subtract the total actual units as per last week
from the total actual units as per this week, we will get the actual units for this week only.
In the screenshot below, we aim to calculate the actual units for the week of 2 July 2023, We must
subtract the summation of actual units in the previous weeks from the actual units we copied from
Primavera (in the “From P6” sheet).
Below, you will find that the actual units of the whole project for the week ending on 2 Jul 2023 are
equal to the actual units of the whole project (Cell D2 in the sheet named “From P6”) minus the sum
of all actual units before this week.
Once done, drag this equation to the end of the WBS to apply this equation to all your WBS levels.
Business Centre, Sharjah
Publishing City Free Zone, Sharjah,
+971 563 444 875
[email protected]
https://planningengineer.net/
Page 9 of 14
Planning Engineer FZE
‫بالنينغ إنجينير م م ح‬
Project Management & Planning Services and Training
‫خدمات وتدريب إدارة المشروعات والتخطيط‬
Note: When updating the following week, copy the actual units of the last week and paste it “123” to
save the data in the cells, then apply the same equation to get the actual units of the following
week.
Now, you are all set to create the “Weekly actual units”, “Weekly actual %”, “Cumulative actual
units” and “Cumulative actual %” as we did in the planned nonlabor units section.
Business Centre, Sharjah
Publishing City Free Zone, Sharjah,
+971 563 444 875
[email protected]
https://planningengineer.net/
Page 10 of 14
Planning Engineer FZE
‫بالنينغ إنجينير م م ح‬
Project Management & Planning Services and Training
‫خدمات وتدريب إدارة المشروعات والتخطيط‬
After we managed to organize our data and get the output of the planned & actual % at a given date,
our final step is to represent this data in the form of a chart.
To make a chart we need 3 data types: Date, Planned %, and Actual %.
For the date: we will make a smart equation to allow the data to change automatically once the data
date is changed.
In the below screenshot, you can see several dates that are linked to each other. All the dates below
are linked to the “Data Date”. We aim to represent the planned % and actual % at the “Data Date”
and 4 weeks before the “Data Date”. So, we use the equation “Data Date – 7” to get the date of the
data 7 days ago, and so on till we get the data dates of the previous 4 weeks.
The same concept can be applied to obtain the data dates of the next week by applying the equation
“ Data date + 7”. So, when the next week comes we need only to copy the date”9-Jul-2023” and
paste it using the “123” format in the cell of the “Data Date”.
Now, once the “Data Date” is changed, all the dates will change accordingly.
For the planned %: we will use a “HLOOKUP” equation to get the planned data for the dates we
want. In the HLOOKUP equation, we will search for the date “4-Jun-23” which is located in cell “M4”.
The lookup range will be between the 10th and 19th row in the “planned data - weight” page to get
the cumulative weight %, in our example, the cumulative weight %is located in the 5th row of our
range.
Once done, do the same steps with the other dates.
Business Centre, Sharjah
Publishing City Free Zone, Sharjah,
+971 563 444 875
[email protected]
https://planningengineer.net/
Page 11 of 14
Planning Engineer FZE
‫بالنينغ إنجينير م م ح‬
Project Management & Planning Services and Training
‫خدمات وتدريب إدارة المشروعات والتخطيط‬
For the actual %: we will use a “HLOOKUP” equation to get the actual data for the dates we want. In
the HLOOKUP equation, we will search for the date “4-Jun-23” which is located in cell “M4”. The
lookup range will be between the 10th and 19th row in the “actual data - weight” page to get the
cumulative weight %, in our example, the cumulative weight %is located in the 5th row of our range.
Once done, do the same steps with the other dates.
Now, our data is ready to be represented in a graph:
- Select your data.
- From “Insert”, choose “Recommended Charts”.
- Choose the chart that suits your project/report.
Business Centre, Sharjah
Publishing City Free Zone, Sharjah,
+971 563 444 875
[email protected]
https://planningengineer.net/
Page 12 of 14
Planning Engineer FZE
‫بالنينغ إنجينير م م ح‬
Project Management & Planning Services and Training
‫خدمات وتدريب إدارة المشروعات والتخطيط‬
Do not forget to click on the “Data Labels” and “Data Table” to view more information in your chart.
Artilce & Attachments link: https://planningengineer.net/how-to-How-to-calculate-Planned-%-andActual-%-using-Weight/
Business Centre, Sharjah
Publishing City Free Zone, Sharjah,
+971 563 444 875
[email protected]
https://planningengineer.net/
Page 13 of 14
Planning Engineer FZE
‫بالنينغ إنجينير م م ح‬
Project Management & Planning Services and Training
‫خدمات وتدريب إدارة المشروعات والتخطيط‬
--------------Useful links:
Join our email Newsletter, we send useful free content regularly:
https://planningengineer.net/newsletter/
Our Services https://planningengineer.net/our-services/
Our Courses: https://planningengineer.net/lp-courses/
Free Arabic Basic Course Playlist:
https://youtube.com/playlist?list=PL7qHhNmknL6F5IOHAsNnPVMt1X-fvYe3J
--------------Keep in Touch:
WhatsApp: +201277767728
Email: [email protected]
English YouTube Channel: https://www.youtube.com/c/PlanningengineerNet/videos
Arabic YouTube Channel: https://www.youtube.com/@planningengineer3906
Linked in: https://www.linkedin.com/company/planning-engineer-est/
Facebook Page: https://www.facebook.com/PlanningEngineerDotNet
Facebook Group: https://www.facebook.com/groups/1138400132963230
Twitter: https://twitter.com/PlanningEEst
Instagram: https://www.instagram.com/planningengineerest/
TikTok: https://www.tiktok.com/@planningengineerest
---------------
Business Centre, Sharjah
Publishing City Free Zone, Sharjah,
+971 563 444 875
[email protected]
https://planningengineer.net/
Page 14 of 14
Descargar