CRONOGRAMA VALORADO DE TRABAJOS RUBRO 1 TRANSPORTE DEL ADOQUIN DESDE EL VIVERO AL SITIO DE LA OBRA MANO DE OBRA CALIFICADA PARA EL TENDIDO DE ADOQUIN, CONSTRUCCION DE BERMAS Y 2 REMATE. INCLUYE: CONCRETERA, INVERSION MENSUAL (USD) CANT. PRECIO UNITARIO PRECIO TOTAL 1.00 350.00 350.00000 442.00 2.70 1,193.40000 1,543.40000 1 2 175.00000 175.00000 TIEMPO EN SEMANAS 3 4 2 DIAS 477.36000 477.36000 238.68000 175.00000 175.00000 477.36000 477.36000 238.68000 AVANCE PARCIAL EN % 11.33860% 11.33860% 30.92912% 30.92912% 15.46456% INVERSION ACUMULADA (USD) 175.00000 350.00000 827.36000 1,304.72000 1,543.40000 AVANCE ACUMULADO EN % 11.33860% 22.67721% 53.60632% 84.53544% 100.00000% Porcentaje al 50% del tiempo 33.72332%