Subido por Juliana Puente

RAMELIUS RESOURCES LIMITED Assessment 2

Anuncio
Melbourne Metro Tunnel Project Analysis
Maria Juliana Puente Santos
145280
INTRODUCTION
Metro Tunnel Project is the biggest Victorian Government public transport
project that will facilitate Metro’s daily use to the growing population of
Melbourne, with a planning cost of around $11 billion Australian dollars. This
Project will add to Melbourne City’s five new underground metro stations at the
following locations: North Melbourne called Arden Station, Parkville called
Parkville Station, State library called CBD North Station, Town Hall called CBD
South Station, and Anzac called Domain Station Domain Station (City of
Melbourne 2022).
According to Acmena (2022), the new metro tunnel will create a new rail line
from Sunbury in the west of Cranbourne, to Pakenham in the southeast of
Melbourne, covering twenty-nine kilometres, incorporating a new fleet of high
capacity metro trains and a new high capacity signaling system that will
maximize the trains and trams efficiency between Anzac Station (will be located
under St Kilda Road) and the domain interchange. It is expected that the extra
capacity that will be added to the metro rail system in Melbourne will enable
504.000 more passengers to use it during peak periods every week. Also, will
be included other safety features like screen doors in the stations (Victoria Big
Builds 2022).
In figure 1, it is possible to see a map that shows all the Melbourne’s metro
lines, including the new Metro Tunnel, which is shown with a dotted blue line,
and the new underground stations.
Figure 1. Melbourne Metro lines map.
1. INITIATION STAGE
The initiation stage for the Metro Tunnel Project started in 2015 when the
project was announced with the objective of delivering a new pathway through
Melbourne City, connecting the busiest rail lines with a new tunnel under the
city’s CBD, and creating space to run more trains. Also, in this stage was settled
a budget of $11 billion Australian Dollars. (Acmena 2022).
1.1. Success factors
In its initiation stage, a success factor is the successful conclusion of
contracts and deals with the stakeholders that will be involved in the
project’s future along its different stages like the Public-Private Partnership
to project development, de department of Public Transport Victoria,
Melbourne City Council, Victoria State Government, Metro Trains
Melbourne, and the collaborative alliances between them and other
contractors (Acmena 2022).
As the Victoria State Government (2022) declared, the PPP (The Tunnel
and Stations Public Private Partnership) executed a contract with Cross
Yarra Partnership (CYP) in December of 2017, which includes deals with
other contractor companies like Lendlease Engineering, John Holland,
Bouygues Construction and Capella Capital.
1.2. Fail factors
A possible failure factor that could generate more problems in the future like
a budget increment, is that the Victoria State Government had to enter into
amending and settlement deeds with the Cross Yarra Partnership (CYP) in
December 2020 to resolve commercial issues related to the project during
the initiation stage. In this agreement, the Victoria State Government and
CYP settled that they would share the project cost increment, corresponding
to a cost of 1.37 billion Australian Dollars to each. They also included in the
agreement the resolution of the outstanding legal claims that were changed
from the original payment agreement, and the release and settlement of
claims between the parties (Victoria State Government 2022).
1.3. Ethical consideration
It is possible to understand as an ethical consideration the commercial
issues related to the project because they mean that something is not going
well, or they should manage it in a better way.
Also, we can settle as an ethical consideration the way how the Victoria
Government is selecting and hiring The Tunnel and Stations Public Private
Partnership and how was the process of hiring the project’s contractors.
2. PLANNING STAGE
The agent responsible for the development of the Metro Tunnel project during
the planning stage is Rail Projects Victoria (RPV), which develops all the
procurements and the detailed design of the project. Also, this stage is being
developed with the cooperation between different stakeholders, contractors,
and alliances between them (Acmena 2022).
The new Metro Tunnel, due to its magnitude, faces significant system
integration challenges like the high levels of engineering complexity, the
inclusion of new technologies, and construction impacts. To manage the
different system integration challenges, Rail Projects Victoria will need to
guarantee the correct integration of the infrastructure systems that will be done
by different contractors and will need to mitigate other potential risks like delays,
cost increments, and disruptions. That effective integration can only be possible
with a robust requirement management system with the ability to allocate the
project requirements to the different stakeholders and to document every
evidence needed to achieve every requirement (Acmena 2022).
And along this stage, every stakeholder is subject to many rigorous regulatory
requirements to ensure safety conditions over the project life cycle by the Rail
Safety National Law (Acmena 2022).
2.1. Success factors
For the planning stage was possible to identify two success factors:
• The Metro Tunnel Project’s Environment Statement (EES)
assessment that concludes its environmental effect was released in
December 2016 by the Minister for Planning, providing the project
statutory decision to approve this project. (Victoria State Government
2022).
• According to the Victorian Auditor-General’s Office (2019), effective
coordination of the detailed planning and project design was
essential to achieving environmental assessments and planning
approvals.
2.2. Fail factors
As was said by The Victorian Auditor-General’s Office (2022), the
environment Effects Statement (EES) process concluded successfully, and
the project approval assessment was provided by statutory decisionmakers, where this decision includes the approval for the planning scheme
amendments under the Planning and Environment. However, if it weren’t
approved, it would be considered nowadays a major failure factor in the
planning stage, causing a big stagnation, affecting the schedule delaying
every following stage since that point, and producing considerable
increments that could yield management to take decisive choices.
2.3. Ethical consideration
The project’s effects on the environment are an important consideration
because and as it was said below, it is considered a failure factor because
if they are underestimated, they could cause worse damage to the
environment that can also affect the community and may cost lives, money,
and resources in the future.
3. EXECUTION STAGE
Rail Projects Victoria (RPV) is the agent responsible for progressing the Metro
Tunnel project through its construction or execution stage (Acmena 2022).
This stage refers to the early works and construction works that are taking place
since April 2019, between the metropolitan and regional train network from 123 April (Daniel Andrews 2019).
According to Victoria’s Premier declared at that time, most of those works along
Cranbourne and lines like Pakenham, Frankston and Sandringham were going
to happen during holiday periods when fewer people use the rail network
system. And in lines like Glen Waverley, Mernda, Gippsland,
Geelong/Warrnambool, buses were going to replace trains (Daniel Andrews
2019).
3.1. Success factors
A success factor in this stage according to Victorian Auditor-General’s Office
(2019) is the fact that in the early works, there were effectively 'de-risked' some
key elements of the overall project like the fact that the contractors developed
and achieved the land acquisition, the site clearance and demolition, and utility
relocations without any major contingency.
3.2. Fail factors
For the execution stage was possible to identify one major fail factor that
could affect de project development in the coming years:
• The unexpected cost increases for the early works phase:
Because it added considerable tension to the initial budget and the
project-wide contingency funds. Also, the heavy use of the
contingency funds in its early stage represents a project warning
because there are many other phases to complete in the execution
stage, with a lot of complexity and risky construction works ahead
that could increase costs again (Victorian Auditor-General’s Office
2019). According to the New daily (2022), the project has forecasted
to overspend $364 million Australian Dollars in overspend on its
tunnels and stations, and the Victorian Auditor-General’s Office
(2022) the increment of the costs since the project’s early works has
left the contingency budget and the lack of any more contingency
funds can represent a significant budget risk However, that amount
of money has been offset by savings and descoped works in other
areas of the project.
3.3. Ethical consideration
The lack of contingency found due to the unexpected cost of the early works
is an ethical issue related to the project because they should forecast most
of the unexpected costs by having a bigger contingency fund since the
planning stage and don’t have the risk of getting out of the budget and stop
the project.
4. CONTROLLING STAGE
As in the last two stages, also Rail Projects Victoria (RPV) will be the agent
responsible for monitoring and controlling the stage to get all the acceptance
and standards approvals required before handing the infrastructure over to
the rail operator (Acmena 2022).
This stage is to audit the project during and immediately after the execution to
assess the delivery of the Melbourne Metro Tunnel Project (MTP), including the
new tunnels and stations main works against the scope, budget, schedule, and
quality requirements (Victorian Auditor-General’s Office 2022).
4.1. Success factors
There are two remarkable success factors for the controlling stage:
• According to Metro Tunnel (2017), to ensure a correct project
development within every contractor and stakeholder, there is a
system of regular monitoring to measure compliance with complaints
processes to ensure the right project development (Metro Tunnel
2017).
• The capacity to keep continually improving over time, so every
process and practice is always up to change or adapt with time, to
minimise future risks and complaints from project-related works and
activities (Metro Tunnel 2017).
4.2.
Fail factors
In the monitoring stage, we find two main failure factors that Metro Tunnel
should face:
• According to the Victorian Auditor-General’s Office (2019), there is
an electromagnetic interference (EMI) coming from trains could affect
every medical and scientific equipment that could be located near to
the train stations. While Rail Projects Victoria and CYP said they
already have plans to mitigate these EMI risks, they will need to
implement those plans before train testing in June 2023.
• Rail Projects Victoria needs to make a diligently manage of the
coming Metro Rail Project’s emerging risks to stay keep within the
approved budget of $12.58 billion Australian Dollars and to achieve
the planned opening date in September 2024 (Victorian AuditorGeneral’s Office 2022).
4.3. Ethical consideration
As an ethical consideration, Rail Projects Victoria should find the best to sort
Metro Tunnel Project contingencies without affecting other businesses, the
community, and the surrounding environment.
5. CLOSING STAGE
6. This stage supports the transition from the construction stage the project
closure ready start the operation of the tunnels and stations to receive public
transport users. This stage also includes the engagement with local businesses
that will be located nearby, residents, roads, and public transport users to aware
them about the operation of the new tunnels and stations (Metro Tunnel 2017).
6.1. Success factors
Has been identified two success factors:
• According to Victoria Big Builds (2022), Metro Tunnel is on track to
be completed by 2025.
• A periodically participation public engagement activities directed to
the different stakeholders involved, specially those ones who will be
involved after the closing stage, promoting public interaction (Metro
Tunnel 2017).
6.2. Fail factors
In the last stage, only was identified the risk that the Victorian Liberals would
win the elections, who said they will renegotiate project’s contract, that as a
consequence, will produce years of delays in the coming milestones,
incrementing costs by billions of dollars, stopping the currently running trains
from running more often, and dealing with new contracts (Loneragan 2018).
But other risks can be inferred in this stage, like a weak public engagement
with the project and a tight budget to deal with operation stakeholders.
6.3.
Ethical consideration
The transparency in the engagement process should be as clear as possible
to show the community the truth about the benefits the Tunnel will provide
as well as the possible issues it could cause, letting them have their own
opinion without being influenced by any other with certain interests.
REFERENCES
•
•
•
•
•
•
•
•
•
Acmena 2022, Melbourne Metro Tunnel, Acmena, retrieved 3 December
2022,
<https://www.acmena.com.au/case-studies/melbourne-metrotunnel/>.
City of Melbourne 2022, Metro Tunnel, City of Melbourne, retrieved 5
December
2022,
<https://www.melbourne.vic.gov.au/parking-andtransport/transport-planning-projects/metro-tunnel/Pages/metrotunnel.aspx>.
Daniel Andrews 2019. Melbourne’s New Tunnel Hits Another Milestone,
Premier
of
Victoria.
Retrieved
4
December
2022,
<https://www.premier.vic.gov.au/melbournes-new-tunnel-hits-anothermilestone/>.
Loneragan, D. 2018, Melbourne’s Metro Tunnel to be finished a year
early,
Railxpress,
retrieved
4
December
2022,
<https://www.railexpress.com.au/melbournes-metro-tunnel-to-befinished-a-yearearly/#:~:text=The%20newly%20released%20tunnels%20and%20stati
ons%20publicprivate%20partnership,to%20be%20finished%20by%20the%20close%
20of%202025>.
Metro Tunnel 2017, Community and Stakeholder Engagement
Management Framework, Metro Tunnel, Retrieved 3 December 2022,
<https://metrotunnel.vic.gov.au/__data/assets/pdf_file/0013/104530/MT
-FRAMEWORK-201700306-Community-and-StakeholderEngagement-Management-Framework.PDF>.
The New Daily 2022, Melbourne Metro Tunnel’s budget blowout, the
New
Daily,
retrieved
3
December
2022,
<
https://thenewdaily.com.au/news/state/vic/melbourne/2022/06/22/melb
ourne-metro-tunnels-budget-blowout/>.
Victoria State Government 2022, Planning: Melbourne Metro Rail
Project, Victoria State Government, retrieved 3 December 2022,
<https://www.planning.vic.gov.au/environment-assessment/browseprojects/projects/melbourne-metro-rail>.
Victoria’s Big Builds 2022, About the Metro Tunnel Project, Victoria’s Big
Builds,
retrieved
4
December
2022,
<https://bigbuild.vic.gov.au/projects/metro-tunnel/about>.
Victorian Auditor-General’s Office 2019, Melbourne Metro Tunnel
Project—Phase 1: Early Works, Victorian Auditor-General’s Office,
retrieved
4
December
2022,
•
<https://www.audit.vic.gov.au/report/melbourne-metro-tunnel-projectphase-1-early-works?section=>.
Victorian Auditor-General’s Office 2022, Melbourne Metro Tunnel project
Phase 2: Main works, Victorian Auditor-General’s Office, retrieved 4
December
2022,
<https://www.audit.vic.gov.au/report/melbournemetro-tunnel-project-phase-2-main-works?section=34129--appendix-asubmissions-and-comments&show-sections=1>.
Descargar