Subido por Marcos Ortiz

CONSTRUCCIONDE TECHOS METALICOS EN GRANDES BODEGAS

Anuncio
STRUCTURAL STEEL EDUCATIONAL COUNCIL
TECHNICAL INFORMATION & PRODUCT SERVICE
JUNE 2001
Metal Roof Construction On
Large Warehouses
or
Distribution Centers
By
John L. Mayo
President/COO
"Innovative Steel Solutions"
Auburn, California
ACKNOWLEDGMENTS
The authors wish to thank the following members of the Structural Steel Educational
Group:
James J. Putkey
Larry McLean
Verco Manufacturing, Inc.
Disclaimer. The information presented in this publication has been prepared in accordance with
recognized engineering principles and is for general information only. While it is believed to be
accurate, this information should not be used or relied upon for any specific application without
competent professional examination and verification of its accuracy, suitability, and applicability
by a licensed professional engineer, designer, or architect. The publication of the material
contained herein is not intended as a representation or warranty on the part of the Structural
Steel Educational Council or of any other person named herein that this information is suitable for
any general or particular use or of freedom from infringement of any patent or patents. Anyone
making use of this information assumes all liability arising from such use.
Caution must be exercised when relying upon other specifications and codes developed by other
bodies and incorporated by reference herein since such material may be modified or amended
from time to time subsequent to the printing of this publication. The Structural Steel Educational
Council and the authors bear no responsibility for such material other than to refer to it and
incorporate it by reference at the time of the initial printing of this publication.
Metal Roof Construction on Large Warehouses or Distribution Centers, John L. Mayo, Steel Tips, June 2001
1
METAL ROOF CONSTRUCTION ON
LARGE WAREHOUSES OR DISTRIBUTION CENTERS
By John L. Mayo
Table of Contents
Page
Introduction
.................................................................................................... 3
Erection Speed .................................................................................................... 4
Safer Construction
.............................................................................................. 4
Cost Savings
.................................................................................................... 5
1. Diaphragm Capacities ...................................................................... 5
2. Wall Bracing ..................................................................................... 5
3. Panel Chord and Ledgers ................................................................. 6
4. Connections ..................................................................................... 7
Other Factors ...................................................................................................... 8
1. Insulation ........................................................................................... 8
2.
Pre-finished Coatings .......................................................................10
3. Bay Sizes ..........................................................................................10
4. Light Refraction .................................................................................11
5. Special or Extra Loads ......................................................................11
6.
lnsurance ..........................................................................................11
7. Steel is a Recyclable Resource ........................................................11
8. Steel is Insect Proof ..........................................................................11
9. Parapet Requirements ......................................................................11
10. Sprinklers ..........................................................................................11
11. Stability .............................................................................................12
12. Snow Loads ......................................................................................12
13. Acoustical .........................................................................................12
About the Author ...................................................................................................13
Metal Roof Construction on Large Warehouses or Distribution Centers, John L. Mayo, Steel Tips, June 2001
2
INTRODUCTION
If you are currently designing or planning a large warehouse or distribution facility, this
Steel Tips should interest you. Depending on your client's needs, code requirements
and location, you may have a choice between using a plywood roof system or a metal
decking roof system.
The debate to use plywood or metal decking in roof construction has been quite
common in recent years. However, over the past decade the development of the
"hybrid" system utilizing open web steel joists with shop attached wood nailers and field
applied plywood sheathing has become a popular choice. One of the key factors
influencing this choice is the apparent value due to the slightly less initial cost for the
plywood option. But you should look beyond the initial cost and investigate additional
factors to ensure your client is, in fact, receiving the best overall value.
Since the early 90's this hybrid system of open web steel joists combined with plywood
sheathing has gradually taken over from the former popular choice of the glulam beam
and solid wood purlin plywood sheathing system. While this hybrid system appears to
allow fast erection and low cost, it is incumbent on the designer to carefully investigate
all cost facets.
Metal Roof Construction on Large Warehouses or Distribution Centers, John L. Mayo, Steel Tips, June 2001
3
ERECTION SPEED
Metal deck projects such as the recently completed Target Distribution Facilities in
Woodland, California and Albany, Oregon, each close to a million square feet in size,
utilized an innovative new full-bay panelizing system comprised of assembled steel joists
and bridging.
Full-bay panelizing has been utilized for decades, but recent
improvements and innovative new ideas have dramatically improved the efficiency of
this process.
The metal deck panelizing system involves spacing out an entire bay of joists on the
ground and installing the complete bridging system (usually "X" bridging). These "lifts"
are typically assembled adjacent to or in the same bay as their final location and may be
stacked. A "crane bay" is established (usually every third bay) that allows the crane to
back across the building and pick the bay in which it is positioned along with the two
adjacent bays.
Crews can prepare enough lifts in advance of the crane to allow erection of as much as
50,000 square feet of framing per day. This method substantially surpasses the plywood
"hybrid" method for speed, safety and value.
SAFER CONSTRUCTION
The metal deck panelizing system enables the bridging to be installed on the ground
prior to hoisting by a crane. All final connections of the framing are made out of lift
baskets. This eliminates the need for workmen to walk the steel frame until the decking
is spread. This also means that no loads are placed on the joist framing until all bridging
is installed, which is in strict accordance with the latest OSHA and Steel Joist Institute
requirements. The wood roof system typically does not install any of the bridging until
after the roof substrate is in place and the joists have been loaded.
Metal Roof Construction on Large Warehouses or Distribution Centers, John L. Mayo, Steel Tips, June 2001
4
COST SAVINGS
1. Diaphragm Capacities
Metal decking diaphragms can resist substantially greater lateral forces than a wood
diaphragm. The maximum shear capacity available with ½" plywood is about 800
pounds per linear foot. The most typical steel roof deck is 1-½" deep Type "B" deck,
which is readily available in even gauges from 16 to 22 gauge. Odd gauges, such as 19
gauge are also available if in large quantities. The maximum shear value for "B" deck
can be as high as 2420 pounds per linear foot, more than three times that of wood.
Typically the weld pattern and gauge is designed in decreasing requirements from the
shear walls or collector lines into the center of the zone where the shears are minimum.
Working out the economics of heavier deck and greater weld pattern gives the owner the
choice of fewer shear walls or interior braced frame elements. As an example, the
Northern California Distribution Facility in Dixon, California is a 300,000 square foot
warehouse originally designed and issued for bids as a plywood "hybrid" system.
An alternate metal deck system was proposed and accepted, which eliminated an
interior braced frame element that had been required with the plywood option. The
ability to provide greater diaphragm capacity allowed distribution of lateral forces out to
the perimeter tilt-up panels without need for interior bracing. Elimination of these interior
brace lines provides savings in the structure costs and also substantial savings with the
deletion of the associated grade beams in the foundation.
The alternate metal deck system not only saved money and time, but also opened up
the interior space as originally desired by the owner.
2. Wall Bracing
It is becoming more common that project conditions allow the use of the metal deck to
provide lateral support for the out-of-plane forces from the concrete tilt-up panels. This
simply means the metal deck can support both the vertical gravity loads and also
laterally brace the perimeter panels. On many projects, calculations can be provided
based on rational analysis that confirms the ability of the metal deck to resist the
combined axial and bending loads. Utilizing this approach allows the elimination of wall
bracing that typically occurs at the ends of the building. This can save substantial costs
in fabrication, erection and a dramatic reduction in the construction schedule.
The evaluation of gauge metal roof deck acting as compression struts or ties to resist
out-of-plane lateral wall forces is based on prescriptions of the Load and Resistance
Factor Design for Cold Formed Steel Structural Members, March 16, 1991, published by
The American Iron and Steel Institute. These prescriptions are included in the 1997
Uniform Building Code.
The metal deck profile and configuration must be fully evaluated for axial and bending
forces. The combined stresses due to bending and axial compression or axial tension
are derived using effective section properties. The calculation of the effective sections
for cold-formed gauge members is an iterative process based upon gross section
profiles and material strength.
Metal Roof Construction on Large Warehouses or Distribution Centers, John L. Mayo, Steel Tips, June 2001
5
The major metal deck manufacturers are equipped to provide automated analysis of
member section properties and associated strut and tie capacities of specific metal deck
profiles and configurations. As an example, the IKEA Distribution Facility is a two
million square foot project in Tejon Ranch, California. By utilizing the combined axial
and bending capacity of the metal roof deck, designers eliminated thousands of costintensive angle braces. At locations where the out-of-plane forces were exceptionally
high, an additional line of joists were added, parallel to the wall to cut the initial deck
span from 8'-0" to 4'-0". The addition of just thirteen joists along one shear wall
eliminated 690 costly wall braces. This not only provided substantial savings back to the
owner, but also cut dramatic time off the fabrication and erection schedule.
3. Panel Chord and Ledgers
Strong consideration should be given to the choice of how the roof joists connect to the
precast panels. A substantial benefit has been established utilizing individual "discrete"
joist seats, wet set in the panels with a relatively small ledger angle between each seat
to pick-up the diaphragm transfer from the metal deck into the panel. This would be
used in lieu of the continuous channels often used in the wood hybrid system. The
continuous channel designs usually use the capacity of the channel to act as the chord
design of the panel. This channel often becomes costly to detail, difficult to produce fast
enough to suit construction schedules and cost intensive to set and field weld together.
The use of individual seats allows much faster production, easier placement into the
panel pours and overall less cost. Reinforcing bars will be required in the panels to suit
chord tie requirements, the cost of which is more than offset by the savings in the
discrete seat method.
Metal Roof Construction on Large Warehouses or Distribution Centers, John L. Mayo, Steel Tips, June 2001
6
4. Connections
A. Framing. There are two standard options of connecting open web framing to
either structural steel framing or to other open web framing. These options are either
two bolts (¾" diameter for longspan and girders or ½" diameter for shortspan joists) or
single pass fillet welds, most typically W fillet weld by 2" long on each side of the
bearing shoe. The Steel Joist Institute sets these standards. On some projects it may
be cost effective for the erector to select the bolted option for all framing connections,
which can provide greater speed and safety of erection. Bolted options do not require
slip critical design or minimum torque levels and can be satisfied with simple snug-tight
soft bolts.
When designating connections on the construction documents, it is best to specify both
options for erector's choice. There will be instances where collector forces will be
required to pass from one element to the next and welding will be necessary at these
locations, since connection holes in shoes are slotted and are unable to provide lateral
transfer. Transfer of lateral forces can be handled through the bearing shoes up to a
maximum of approximately 12 kips for longspan joists and 25 kips for joist-girders.
Forces greater than these should be transferred using "tie-plates" designed appropriately
for the required forces. It is best to categorize these force levels into groupings of
approximately 40 kips in order to provide simplicity in the field without penalizing the
plate designs. All welding should be limited to single pass (5/16" thick) to avoid multipass welding, which may require special inspection requirements. Tie-plates can be
elongated to suit required length of welds to satisfy transfer force.
Bridging is typically bolted "X" bridging. There may be conditions where welded
horizontal bridging is required, such as uplift restraint. The joist manufacturer and
erector, to maximize efficiency, should carefully review and may be able to minimize the
bridging by combining requirements.
B. Decking. Historically, the most common method of connecting metal deck to
steel framing has been by plug welding. Recently, the development and dramatic
improvements in the use of power actuated pinning has provided a more cost effective
and substantially faster option. I.C.B.O. reports are now available for a variety of pinning
options that not only save time and money, but also provide a better quality of production
with less skilled labor. Apprentices are able to install qualified pins at rates of five to
eight times that of plug welding by seasoned ironworkers. It also avoids the unsightly
discoloration of the plug welding from the underside.
The sidelap attachments are done with buttonpunching, screwing or a combination of
clinching and seam welding. The seam welding process should be avoided if possible
due to its multiple step procedure and the high demand on quality control. It may be
best to option for heavier gauge decks with lesser sidelap requirements if possible.
Metal Roof Construction on Large Warehouses or Distribution Centers, John L. Mayo, Steel Tips, June 2001
7
To establish the lowest cost system, it is necessary to make an economic study
considering relative values of deck gauges, labor, equipment and pin costs of various
diaphragm schemes to maximize efficiency.
Typical Roof Deck Profile
Sidelap Attachments
OTHER FACTORS
As in the design of any project there are many factors to consider. What may appear to
be at first a lower cost does not always prove to be the best choice.
Some factors that should be taken into account may be:
1.
Insulation
With steel roof deck it is necessary that the insulation be placed on top of the deck as a
substrate for the roofing. This is the best application of insulation since:
•
There is an uninterrupted envelope of insulation without the multiples of gaps
inherent with batt insulation used with wood roofs.
Metal Roof Construction on Large Warehouses or Distribution Centers, John L. Mayo, Steel Tips, June 2001
8
•
All of the steel framing and decking is contained within the insulation at the room
temperature; this insures a minimum of expansion and contraction.
•
The position of the vapor barrier can be maintained at the designed location.
With batt insulation, the vapor barrier quite often occurs in the plywood, resulting
in deterioration of the plywood and/or wood purlins. Unfortunately, this type of
deterioration is not found until substantial failure occurs in the substrate with
cases of rotting framing falling to the ground that had been hidden by the
insulation.
•
Another drawback to batt insulation is the long-term maintenance costs for
periodical re-attachment, a non-issue for the metal deck system.
Metal Roof Construction on Large Warehouses or Distribution Centers, John L. Mayo, Steel Tips, June 2001
9
2.
Pre-finished Coatings
There are a variety of optional coatings available:
Galvanized:
Painted:
G40
Light coating of galvanizing at slightly less cost.
Suitable for larger projects only due to longer lead time
for special coil.
(Relative cost = .97)
G60
Standard and most common coating. This product is
readily available from all manufacturers.
(Relative cost = 1.00)
G90
Heavy coating of galvanizing only used for special
conditions. Suitable for larger projects only due to long
lead time for special coil.
(Relative cost = 1.03)
Single coat of grey paint over cold rolled. This is a primer only.
Coating is subject to discoloration and stains.
Field touch-up or final painting required if exposed.
(Relative cost = .92)
Single coat of white paint over cold rolled. This is not considered a
finished coating and is subject to discoloration and stains.
Field touch-up or final painting required if exposed.
(Relative cost = .94)
Single coat of white paint over galvanized. This is not considered
a finished coating but will not discolor or stain.
Field touch-up or final painting required if exposed.
(Relative cost = 1.10)
Double coat of paint over galvanized. This would be considered a
final coating and would require special handling including
shipping "softeners" to avoid scratching and marks. This is
the most expensive option and should be carefully
analyzed for economics. Field touch-up may be required.
(Relative cost = 1.20)
3. Bay Sizes
Inherently, plywood roofs are designed based on the standard 8'-0" plywood module.
Quite often this is modified to 8'-01/8" to allow for expansion and contraction. This
limitation tends to result in bay sizes in a multiple of 8'-0" with the 1/8" increment a
nuisance to contend with. Since steel decking is custom rolled to length to fit the
particular job, and the steel roof framing of open-web girders and joists are custom
fabricated to fit, there are no limitations as to bay widths or lengths with steel roofs. For
example, if a project would benefit with dimensions based on clear between columns, it
can be simply done.
Metal Roof Construction on Large Warehouses or Distribution Centers, John L. Mayo, Steel Tips, June 2001
10
4. Light Refraction
A big advantage of metal decking over wood sheathing is the ability of the metal decking
to provide substantially greater light refraction capabilities. A combination of skylights
with either the galvanized or painted finish can provide sufficient light during daylight
hours to turn off interior lighting. This power saving option was recently utilized at the
Nestle's Distribution Facility in Lathrop, California during the recent and ongoing power
crisis.
5. Special or Extra Loads
If the project requires, the roof-framing module for steel roof decking can be easily
modified bay-to-bay to accommodate special or extra roof loads such as mechanical
equipment or roof screens.
6. Insurance
Depending on the occupancy and insurance requirements, use of a steel roof deck over
steel framing may show substantial insurance coverage savings.
7. Steel is a Recyclable Resource
Steel is recyclable and the quality is consistent.
8. Steel is Insect Proof
Wood is subject to infestation from insects and microscopic organisms, which is of
special concern in any biotech application. Steel is insect proof.
9. Parapet Requirements
With steel roof decking, the requirement for extended parapets may be eliminated.
Under Factory Mutual requirements parapets may be required if a wood roof deck is
used.
10. Sprinklers
Where ceilings occur and all materials above the ceiling including the metal roof deck
are incombustible, sprinkling the attic space may possibly be eliminated with the
resulting substantial savings.
Metal Roof Construction on Large Warehouses or Distribution Centers, John L. Mayo, Steel Tips, June 2001
11
11. Stability
Steel roof deck is stable throughout its life without long-term deflection or shrinkage.
This means the design capabilities, both vertical and horizontal have not deteriorated
over time.
12. Snow Loads
If the project is located where snow loads govern, usually the steel deck will carry the
extra load without change in gauge, whereas most often, the wood roof decking must be
increased at additional costs.
13. Acoustical
If the project needs or would benefit from some acoustical treatment to reduce noise,
this can easily be accommodated with steel deck simply by use of perforated acoustical
roof deck of the same gauge and profile without losing any diaphragm shear capacity.
After the deck is laid, the roofer installs strips of pre-cut batt insulation, as furnished by
the deck manufacturer, in the ribs before installing the flat insulation panels as part of the
roofing. Noise reduction coefficient of up to .80 may be obtained.
Acoustical
Vertical Webs Perforated With 5/32" Diameter Holes Staggered 7/16" C/C
Insulation Strips in Low Flutes Field Installed
Absorption Coefficients
125
250
500
1000
2000
4000
Noise Reduction
Coefficient
.60
.99
.92
.79
.43
.23
.80
Reprinted with permission from Verco Manufacturing Co., Inc.
Every project involves unique issues and challenges. The designer should consider all
aspects of cost, safety and speed when choosing a system. What can often appear to
be cost effective in the short term, may not be the best overall value.
If you have any questions or need further information please feel free to call the
Structural Steel Educational Council.
Metal Roof Construction on Large Warehouses or Distribution Centers, John L. Mayo, Steel Tips, June 2001
12
ABOUT THE AUTHOR
John L. Mayo is a Civil Engineering graduate from the University of Maine and began
working in the steel joist and metal deck industry in 1980 with Mclean Steel of Hayward,
California. John spent 13 years with Mclean Steel as a detailer, project manager and
Vice-President before starting his own firm with partner Don Jeffrey in 1993 called JD2
Inc.
JD2, Inc. has offices in Sacramento, San Francisco, San Diego and Los Angeles. They
are a steel construction subcontractor specializing in design-build projects providing
complete steel packages, including erection. They have developed many connections
and methods that are now considered industry standards and are currently pioneering
the first commercial use of a Special Truss Moment Frame (STMF) system called TruFrame.
JD2, Inc. can be visited on their Website at jd2inc.com.
Metal Roof Construction on Large Warehouses or Distribution Centers, John L. Mayo, Steel Tips, June 2001
13
STRUCTURAL STEEL EDUCATIONAL COUNCIL
P.O. Box 6190
Moraga, CA 94570
Tel. (925) 631-1313
Fax. (925) 631-1112
Fred Boettler, Administrator
Steel tips may be viewed and downloaded at www.aisc.org
S P O N S O R S
Adams & Smith
Four Star Erectors
PDM Strocal, Inc.
Bannister Steel, Inc.
Gayle Manufacturing
Plas-Tal Manufacturing Co.
Baresel Corp
The Herrick Corporation
Reno Iron Works
Bethlehem Steel Corporation
Hoertig Iron Works
SME Industries
Bickerton Industries, Inc.
Junior Steel Co.
Shollenbarger-Borello, Inc.
Bostrum Bergen
McLean Steel Inc.
Templeton Steel Fabrication
California Erectors
Martin Iron Works, Inc.
Verco Manufacturing, Inc.
Eagle Iron Construction
Nelson Stud Welding Co.
Vulcraft Sales Corp.
Trade Arbed
Oregon Steel Mills
Western Steel & Metals, Inc.
Eandi Metal Works
The local structural steel industry (above sponsors) stands ready to assist you in determining the most
economical solution for your products. Our assistance can range from budget prices and estimated
tonnage to cost comparisons, fabrication details and delivery schedules.
Funding for this publication provided by the California Iron Workers Administrative Trust.
Descargar