Maintenance Work Instruction PV-P-PRM-001-0 Code: Revision # Issue Date Next Revision Date Page E4131 1YR TNK225 VIS INSP RUN 0 2023-05-11 TBD 1 of 4 E4131 YEARLY TNK225 VIS INSP RUN Assigned Dept: 135 (PM6;CBM) Frequency: 1 YR PV area: 4131 This work is covered by: □ An open work permit Main Work Center: 10RL-TAB (PRPDM) Shutdown Required: NO Open Permit #: ____________ □ A new work permit Permit Board #: ____________ Time to Complete: 6 hours SAFETY INSTRUCTIONS & INFORMATION ** Complete an FLRA ** • • • • • • Complete a proper walk around before entering any work area when conducting the workplace exam. Note all hazards and conditions fixed on the workplace examination template. Report all hazards that could not be fixed to your immediate supervisor. Exercise your ‘Stop Work’ Authority if conditions are not suitable for working. Do NOT conduct a task or operate equipment you are not trained and proven competent on. Review any JSA’s with all personnel involved with this job. Acceptance: I have reviewed the work permit and carried out the required risk assessment. I have received the necessary training and have been deemed competent to accomplish safely and correctly the required tasks associated with this work instruction. Accepted by: __________________Signature: ______________ Date:(yyyy-mm-dd) ____________ Maintenance Work Instruction Code: Revision # Issue Date Next Revision Date Page PV-P-PRM-001-0 E4131 1YR TNK225 VIS INSP RUN 0 2023-05-11 TBD 2 of 4 Documents and References: PV-P-PRM-101-X_Process Plant Work Permit_revX_PVDC_date PV-P-PR-031-X_Process Plant Field Level Risk Assessment_revX_PVDC_date PV-P-PRO-xxx-0_Process Plant Job Hazard Analysis_revX_PVDC_date Document Register Register identification Type Location Retention period Process Plant MWI Register Copy/filing cabinet Maintenance Planning office Livelink Electronic IT server RCMCost Electronic IT server Permanent. Latest version is kept. Permanent: All versions are kept. Permanent Latest version is kept Revision History Revision Date (yyyy-mm-dd) Description of changes and/or modifications Maintenance Work Instruction PV-P-PRM-001-0 Code: Revision # Issue Date Next Revision Date Page E4131 1YR TNK225 VIS INSP RUN 0 2023-05-11 TBD 3 of 4 Task Details PV3-4131-TNK0225 (TANK - CIL 2) Task Description Inspeccionaar visualmente el tanque paracumplir con los requisitos de la API. Realizar esta actividad con el procedimiento de inspección visual de PVDC. Visually inspect the tank to meet API requirements. Carry out this activity with the PVDC visual inspection procedure. OK Not Not OK Complete □ □ □ Observations Maintenance Work Instruction PV-P-PRM-001-0 Line Ref # Code: Revision # Issue Date Next Revision Date Page E4131 1YR TNK225 VIS INSP RUN 0 2023-05-11 TBD 4 of 4 Observations - Notes - Comments Spares, PPE & Special Tools Spares description Times used in this PM PPE & Special Tools Times used in this PM Work Instruction - Final Comments Additional Resources: Actual Hours: Date: Sign off: ____________________________________